Upload
tosin-yusuf
View
63
Download
1
Tags:
Embed Size (px)
Citation preview
General Principles of English Law
(GPEL)
Contract Lecture 3:
Discharge and Remedies
Theresa Lynch (Law School: Room 118)
Contract Law: GPEL
Contract Law Elements GPEL module:
The essential features in the formation of a contract (offer,
acceptance, consideration, intention to create legal relations and
privity). Dr. Sanders has covered these elements of contract law
with you in Lectures 1 and 2 on Contract Law).
Over the next three weeks the remaining contract lectures will
focus on:
The different types of contractual terms and their
significance;
Defects and vitiating factors
Discharging a contract (through performance, agreement
and frustration.
The available remedies following breach of contract.
Change to Lecture Schedule
You will attend a Seminar 3 in either week
9/10 on discharging contracts and remedies
for breach of contract.
NB. The supervision sheet for Seminar 3 is now on
WebCT.
Therefore today‟s lecture (so as to ensure
that you have been lectured on the seminar
topic before you have the seminar), will be on
discharge and remedies.
New Lecture Schedule
So your new lecture schedule is:
Contract Lecture (3): Week 8 (wk/b 15th
November 2011) Discharge and Remedies
Contract Lecture (4): Week 9 (wk/b 21st
November 2011) Terms/Content of a
Contract
Contract Lecture (5): Week 10 (wk/b 15th
November 2011) Defects and vitiating
factors.
NB. TIMES AND VENUES OF LECTURES DO
NOT CHANGE
Lecture Overview
A contract establishes the rights and duties of
the parties and where successfully completed
the parties will be considered to have
discharged their responsibilities.
However, this is not the only way in which the
contract may be discharged and this lecture
will discuss these other ways.
This lecture will also importantly, identify the
remedies available when a party has
breached a contract.
Lecture Overview Contd.
This lecture will be split into two halves:
1. Discharging a Contract
2. Remedies for Breach of Contract
Learning Outcomes
Following this lecture you should be able to:
List and discuss the ways in which a contract
may be discharged;
Identify the remedies available for breach of
contract; and
Have an understanding of the implications of
the equitable remedies available for breach of
contract.
Part 1
Discharging a Contract There are 4 ways in which a contract may be
discharged:
1. Agreement
2. Performance
3. Frustration
4. Breach
1. Agreement
Both parties agree to end the agreement.
The parties may agree between themselves
that they no longer wish to continue with the
contract, and therefore release each other
from their obligations.
As this is in effect a new contract, and varying
a contract requires formalities to make it valid,
the elements of agreement and consideration
are necessary.
2. Performance Normally, for a contract to be discharged by
performance complete performance of all
obligations is required.
The most obvious form of discharge is
through the parties‟ completion of their
obligations (the contract performed).
Where complete performance has not been
achieved, the courts have developed rules on
what implications such a situation will have
for the parties.
Cutter v. Powell [1975] 6 Term Rep 320
Jamaica, Kingston Harbour.
Cutter v. Powell [1975] 6 Term Rep 320
Captain Powell engaged Cutter as part of his crew in a voyage from
Jamaica to Liverpool.
The contract stipulated that the contract was only fulfilled when the
entire contract was performed and payment was only due when the
voyage was completed.
Mr Cutter died 19 days before the vessel arrived in Liverpool and his
widow claimed for his owed wages.
It was held that the claim must be denied as it was a condition of the
contract that payment would be made on completion of the voyage, and
this had not been complied with.
Cutter v Powell established that for a contract to be discharged by
performance – complete performance of all obligations is required.
General Rule on Performance: Exceptions The general rule is that for a contract to be discharged
by performance complete performance of all obligations
is required (Cutter v Powell).
However, there are exceptions to this general rule. These are:
a. where contract is divisible.
b. where “substantial performance” has been carried
out. Hoenig v Isaacs [1952] 2 All ER 176
c. where the performance of the obligation in question
has been prevented by the other party to the
contract. Planché v Colburn [1824-34] All ER 94
d. where the other party has accepted part
performance instead.
a. Where the contract is divisible
This means that the contract is broken into smaller units.
Example
A contract for the shipment of cargo was agreed at a price of £5 per
ton. Not all of the cargo was delivered; therefore the owners
claimed a breach. Further, they asserted that they were not obliged
to pay an amount as the entire contract has not been completed.
It was held in Ritchie v Atkinson [1808] 10 East that there was a
breach, but as this was divisible contract payment was due on the
basis of the number of tons of cargo actually delivered.
b. Substantial Performance
If, on the other hand, a substantial proportion of
the contract has been completed, the innocent
party has an obligation to pay, taking into account
the short comings of the contract.
This was demonstrated in Hoeing v Isaacs [1952]
2 All ER 176.
Hoeing v Isaacs [1952] 2 All ER 176.
Problems with a book shelf/cupboard that
was left unfinished/not in working order.
Hoeing v Isaacs [1952] 2 All ER 176.
In this case a contract was established for the decorating and
furnishing of a flat for a fee of £750.The work was done but it
contained some defects ( book shelf/cupboard was left unfinished/not
in working order).
The cost of putting right the defects was no more than £55. The
defendant claimed that the contract was an entire contract and that
since the plaintiff had not fully completed the work he was not entitled
to any payment.
However, the Court of Appeal held that since the defect was very
minor, there had been substantial performance of the contract. The
defendant was therefore bound to pay the contract price less the cost
of rectifying the defect.
This result in this case is fair because to uphold the defendant‟s
argument would have resulted in the defendant retaining the benefit of
the plaintiff‟s work without paying anything for it.
c. One Party Prevents the Other from
Completing Performance
There is also a claim for partial or substantial performance
of the contract if the full and complete performance of the
contract was prevented through the other party‟s actions.
In Planche v Colburn [1831] 5 C & P 58, a book was
commissioned (for a fee of £100) and the author had
partially completed this when the contract was cancelled. It
was held that £50 was to be paid to the claimant for the
work already completed (known as quantum meruit
assessment).
d. Part Performance
There may exist in situations where a contract is not fully
completed, and the other party voluntarily accepts the
partial performance.
It must be noted at this stage that the acceptance must
undertaken voluntarily for it to be valid.
In the case of Sumpter v Hedges [1898] 1 QB 673, it
was decided that where the innocent party has no choice
but to accept the part performance the party in breach is
not entitled to payment for the work completed on the
contract.
The acceptance of the partial performance discharges
the party from any further obligation under the contract
and the innocent party must pay an appropriate
proportion of the price.
3. Frustration Where subsequent events outside the parties‟ control
render the performance of contract impossible or futile,
the contract is said to have been “frustrated”.
Frustration has been found to discharge a contract on
three main grounds. These are:
a. impossibility of performance (destruction of subject
matter of contract ),
b. supervening Illegality (change in the law) or,
c. Frustration of Purpose (purpose of contract no
longer available).
a. Impossibility In a situation where the subject matter of the contract has ceased to
exist before the contract has been performed, and its neither party‟s
fault that this has occurred, then the courts consider this to be
frustration. For example, in Taylor v Caldwell [1861-73] All ER Rep
24:
T and C had entered into a contract on 27th May 1861 where C had
agreed to let T have the use of the Surrey Gardens and music Hall
at a rate of £100 per day. This hire was to take place for four days
for the purpose of giving a series of grand concerts. The contract
was established, but before the first performance the Music hall was
destroyed by fire and therefore the contracts could not take place.
Taylor claimed damages for the money spent on the advertising and
preparation for the concerts.
The decision of the High Court was „... the Music Hall having ceased
to exist, without fault of either party, both parties are excused, the
plaintiff from taking the gardens and paying the money, the
defendants from performing their promise to give the use of the Hall
and Gardens and other things‟.
b. Supervening Illegality If the parties have agreed a contract, but before the contract is due
to be performed it subsequently becomes illegal, then the contract
is frustrated.
This was the case in Fibrosa Spolka Akcyjna v Fairbairn Lawson
Combe Barbour [1943] involving the outbreak of hostilities between
England and Germany.
Here Fairbairn based in England could not legally supply good to
Fibrosa, based in Poland, as Germany had occupied Poland in
1939 and England had declared war on Germany. There was a
provision preventing British companies from supplying, inter alia,
machinery to an enemy-occupied country, and consequently the
contract was frustrated. Any attempt to deliver the goods under the
contract would result in supervening illegality.
c. Frustration of Purpose If parties contract for a specific event, and for some reason this event does not
take place, the contract will be frustrated. For example In Krell v Henry [1900-
03] All ER Rep 20:
K left instructions with his solicitor to rent out his suite of chambers located
at 56a Pall Mall. On 17 June 1902 H responded to an advertisement for the
hire of the flat) from which it was possible to view the procession of the
King‟s coronation). H agreed to take the suite, and paid a deposit, but the
King became ill before the coronation and hence the procession was
cancelled. Henry refused to pay the balance due and K began an action to
recover the sum. It was argued by K that the contract could still continue as
the flat was still in existence, and H could still have the use of it for the days
for the days identified in the contract.
The Court of Appeal held that the contract was frustrated. It took a broader
view that the entire purpose of hiring the flat was to view the coronation
(evidenced from the price paid to hire the premises). The King‟s illness was
the fault of neither party but its effect was to make the contract radically
different from what was agreed. Hence the contract was frustrated.
When Does the Frustration Rule Not
Apply?
If event should have been foreseeable when
contract made;
If the party causes the frustrating event;
When an alternative method of performance
is still possible;
If the contract is simply „too expensive‟ to
perform.
The Effect of the Frustration Rule The effect of frustration result in the parties
being discharged from any further
performance in the contract and any money
paid is returned (at the discretion of the
court).
It should be noted at the that this known as a
doctrine of last resort and will therefore only
be used where the parties have not made
their own arrangement for a frustrating event.
The courts have encouraged the parties to
make provisions in the contract on the basis
of such eventualities.
The Effect of the Frustration Rule Contd. If no provisions are contained in the contract, assistance has
been provided through the Law Reform (Frustrated
Contracts) Act 1943. This statute provides that:
Any money paid is recoverable;
Any money to be paid in the future ceases to be payable;
A party who received a valuable benefit from other party‟s
performance before the frustrating event may have to pay
for that benefit.
These provisions do not apply if the parties make their own
provisions for the effect of frustration.
4. Breach
Any breach will allow an innocent party to
claim damages; BUT not every breach is
capable of resulting in discharge of contract.
This will depend upon the type of contractual
term that has been breached.
Next weeks lecture is on terms/content of a
contract but it is useful to set out two of the
main terms at this stage also.
Terms of a contract: Conditions and
Warranties
Conditions are important terms of a contract
often described as a term that „goes to the
heart of a contract‟ (ie. that the term could be
said to be what the contract is all about).
Warranties are lesser or subsidiary terms of a
contract distinct from the vital terms which are
the conditions.
Typically breach of a condition will result in
the discharge of a contract, but only if the
injured party wishes to do so.
On the other hand, one cannot discharge a
contract for breach of a warranty.
Anticipatory Breach
An anticipatory breach occurs where one
party indicates before performance is due
that they do not intend to perform their
obligations. In this type of situation the other
party may cancel the contract and sue for
damages at this point or wait until it is time for
performance then cancel and sue.
Overview: Discharging a Contract 1. Agreement
2. Performance
Exceptions
a. where contract is divisible.
b. where substantial performance has been carried out.
c. where the performance of the obligation in question has been prevented by
the other party to the contract.
d. where the other party has accepted part performance instead.
3. Frustration
Types of Frustration
a. impossibility of performance (destruction of subject matter of contract ),
b. supervening Illegality (change in the law) or,
c. Frustration of Purpose (purpose of contract no longer available).
When does the Frustration Rule not apply?
The Effects of Frustration
4. Breach
Terms of a Contract
Anticipatory Breach
Part 2
Remedies for Breach of Contract
In the next part of this lecture we will be looking
at remedies for breach of contract. The lecture
will focus on:
1. Damages
2. Measure of Damages
3. Equitable Remedies for Breach of Contract
1. Damages
Damages are monetary compensation for
loss or damage arising from breach. The aim
is not to punish, but to compensate.
Damages are intended to put the innocent
party, so far as money can do it, in the
position in which he would have been in if the
contract had been performed. This includes
loss of profits which the innocent party would
have made if the contract had been
performed.
2. Measure of Damages
Limitations on the Damages Recoverable
a. Remoteness of Damage
b. Duty to Mitigate
c. Penalty Damage
d. Non Pecuniary Losses
a. Remoteness of Damages
Whether the resulting damage should be attributed to
a party is determined by a remoteness test; that is
the court will determine whether the possibility of
such damages occurring were reasonably
foreseeable by the person causing the damage.
Usual damage: might reasonably anticipate/in the
natural course of things – likely to be liable
Non-usual damage: circumstances not necessarily
known to other party – unlikely to be liable (too
remote)
Remoteness of Damages Contd.
Hadley v Baxendale [1843-60] All ER Rep 461
H owned a flourmill and in May the mill was stopped due to a
breakdown of the crankshaft (the only one it had). H was to send the
crankshaft to a third party for it to be replaced, B informed H that
delivery would be made the following day. However, delivery was
delayed seven days and this led to a loss of profits that H attempted to
recover. B argued that it had no knowledge that H would have sent
the only crankshaft and hence a delay would have completely stopped
production.
The court concluded that there had been a breach of contract, but
damages should be based on what may fairly and reasonably be
considered arising naturally from the breach. A complete cessation of
work due to the delay would have not been reasonably foreseeable by
B.
Remoteness of Damages Contd. As H sent its only crankshaft to be delivered by B, it
had an obligation to inform B of this fact and a delay
would have prevented any work being completed. B
would then have realised the consequences of any
delay – that is a total loss of business and
consequent loss of profits. This legal reasoning was
continued in: Victoria Laundry v. Newman Industries
[1949] 2 KB 528
In this latter case a delay in delivering an industrial
boiler for commercial launderers would allow
damages to be claimed for the subsequent lost
profits, but this did not extend to possible lucrative
contracts that could have been won had the boiler
been delivered as expected.
b. Duty to Mitigate
Duty to mitigate: injured party has duty to take all
reasonable steps to minimise their loss.
Where an innocent party has failed to mitigate
his/her losses following breach they may be
awarded nominal damages.
The award of nominal damages essentially reflects
that the claimant has „won‟ the case, but he/she
may not have acted reasonably in the
circumstances (see Brace v Calder [1895] 2 QB
253).
c. Penalty Damages
Liquidated damages occur when there is a provision
in contract stating in advance what damages will
have to be paid if a breach occurs.
Only enforced if genuine pre-estimate of loss.
Where the amount agreed is exorbitant and not a
genuine pre-estimate of the anticipated loss, the
courts will treat the agreement as a penalty and will
refuse to enforce it (see Dunlop Pneumatic Tyre
Company v New Garage and Motor Company [1915]
AC 79).
d. Non Pecuniary Loss Non pecuniary losses – for example,
damages for mental distress, hurt feelings,
disappointment, loss of reputation or loss of
amenity.
The General Rule
The traditional view of the courts when
determining the level of damages applicable
in such cases has been to ignore any injured
feelings or loss of enjoyment suffered (see
Addis v Gramophone [1909] AC 488). This is
due to the problem inherent in quantifying
such damages and the potential opening of
the floodgates for claimants.
Non Pecuniary Loss Contd. The Exceptions
There are 2 main exceptions to the general rule.
1. Damages for distress may be awarded where the
distress arises from physical inconvenience
caused by the breach of contract (e.g. see Watts v
Morrow [1991] 1 WLR 1421.
2. Damages for non-monetary losses such as mental
distress may be recovered in cases where the
main object of the contract was to provide
pleasure, relaxation and enjoyment. This is the
case, for example, with a contract for the provision
of a relaxing holiday.
Non Pecuniary Loss Contd
Although damages are awarded for non-
monetary losses in the case of these
exceptions, the amounts awarded as usually
very modest. The courts have stated that they
are not keen to see huge US-style awards for
non-monetary losses on this side of the
Atlantic
Jarvis v Swan Tours [1972] 3 WLR 954
Holiday to Switzerland. The whole purpose
of the contract was for pleasure, relaxation
and enjoyment.
Jarvis v Swan Tours [1972] 3 WLR 954
The plaintiff booked a winter holiday which
the defendants promised in their brochure
would be like a “house party”, with special
entertainment and proper facilities for skiing.
In fact the facilities were inadequate. In the
second week the “house party” consisted of
the claimant alone. The court awarded him
damages for the cost of the holiday and in
addition for the disappointment suffered and
the loss of entertainment he had been
promised in the brochure.
Mental Distress: Farley v Skinner [2001] UKHL 49;
[2002] 2 AC 732.
Aircraft Noise. House located 15miles from Gatwick
Airport. Surveyor asked whether house would be
affected by aircraft noise.
Farley v Skinner [2001] UKHL 49; [2002] 2 AC
732. In this case the claimant employed the defendant to survey a „gracious
country residence‟ which he wished to purchase. The House was
situated some 15 miles from Gatwick airport. Given its proximity to the
airport the claimant expressly asked the defendant to report on
whether or not aircraft noise was likely to be a problem.
The defendant stated that the noise was unlikely to be a problem,
„although some planes will inevitably cross the area, depending on the
direction of the wind positioning of the flight paths‟. The claimant
purchased the house. After he had spent more than £100,000 on
improvements to it, he discovered that the aircraft noise was a problem
and interfered with his enjoyment of the house.
The trial judge found that the defendant was in breach of contract and
awarded the claimant £10,000 for the distress and inconvenience
caused to him by the aircraft noise (the noise from the aircraft did not
affect the value of the property).
The House of Lords upheld the award (notwithstanding the fact that
the award was, in their view on the high side).
House of Lords Decision in Farley v Skinner [2001]
UKHL 49; [2002] 2 AC 732. Their Lordships did not engage in a radical overhaul of
this area of law. They accepted the traditional starting
point, namely that the law of contract does not
compensate a claimant for mere disappointment or
annoyance suffered as a result of the defendant‟s
breach of contract.
Prior to Farley v. Skinner the courts had recognised
that damages for mental distress could be awarded
firstly where the breach of contract caused physical
inconvenience and distress to the claimant (Watts v
Morrow). Secondly where the predominant object of the
contract was to obtain some mental satisfaction (Jarvis
v Swan Tours).
What the House of Lords did however was to expand
the scope of the exceptions to the general rule.
House of Lords Decision in Farley v Skinner [2001] UKHL
49; [2002] 2 AC 732. Contd.
The House of Lords expanded the scope of
liability in two respects.
1. They dispensed with the „predominant
object‟ test in the second exception. It
sufficed that the term broken was one was
which was known by both parties to be an
important term of the contract: whether the
contract as a whole was one to provide
peace of mind or not was not the decisive
factor.
House of Lords Decision in Farley v Skinner [2001]
UKHL 49; [2002] 2 AC 732. Contd. The claimant in Farley v. Skinner had specifically
asked the surveyor to report on the level of aircraft
noise. As Lord Clyde observed, it was „the specific
provision relating to the peacefulness of the property
in respect of the aircraft noise which makes the
present case out of the ordinary‟. In the absence of a
specific question to the surveyor, it would appear that
a surveyor will not ordinarily be liable to a house
purchaser for the disappointment or distress which he
suffers in the event that the House suffers from a
defect.
The elimination of the „predominant object test‟ may
result in a gradual but controlled expansion of the
ambit of liability for mental distress damages.
House of Lords Decision in Farley v Skinner
[2001] UKHL 49; [2002] 2 AC 732. Contd.
2. It was established in Farley that the claimant
can recover damages on the ground that the
defendant‟s breach of contract resulted in
inconvenience and discomfort for the plaintiff.
The Lords adopted a very broad view of
inconvenience and it was held that the noise
from the aeroplanes caused the claimant to
suffer „real discomfort‟, in that it interfered with
the enjoyment of his property.
House of Lords Decision in Farley v Skinner [2001]
UKHL 49; [2002] 2 AC 732. Contd
A finding that the noise interfered with the claimants use
of the property seems rather marginal in that no other
house owner appeared to suffer in the same way.
But the fact was that the noise did interfere with the
claimants: „quite reflective breakfast‟, „morning stroll in
the garden‟ and pre dinner drinks on the terrace all spoilt
by the noise.
There is a definitional problem here because it may not
always be easy to distinguish between inconvenience
which (which falls within the scope of this category) and
disappointment (which does not).
House of Lords Decision in Farley v Skinner
[2001] UKHL 49; [2002] 2 AC 732. Contd
It may be that the difference is that inconvenience affects the
senses. Lord Scott stated:
“If the cause is no more than disappointment that the contractual
obligation has been broken damages are not recoverable even if
the disappointment has led to a complete mental breakdown.
But if the cause of the inconvenience is discomfort or,sensory
(sight, touch, hearing smell etc) experience, damages can,
subject to the remoteness rules, be recovered.”
NB. For further discussion of Farley v Skinner see: E.McKendrick (2011) Contract
Law. (This forms part of the recommended reading for seminar 3 and you can
find the relevant extract on WebCT after the lecture.
3. Equitable Remedies for Breach of
Contract Equitable remedies are discretionary – this means
that the court is not obliged to grant them, but can
do so at its discretion if counsel makes a convincing
argument. The party claiming the equitable remedy
must show that:
Damages would not be an adequate remedy; and
They acted completely honestly. There is an
equitable maxim, or rule, that he who comes to
equity must come with clean hands.
Equitable Remedies for Breach of
Contract Contd. Equitable remedies for breach include:
a. Rescission – the court sets aside contract and
restores parties to pre-contractual position.
b. Specific performance – the court orders the
breaching party to perform their contractual
obligations. If the party continues to refuse after the
court order, it will be guilty of the criminal offence of
contempt of court.
c. Injunction – the court directs a party to refrain from
doing something that would act as a breach of the
contract (see: Warner Bros v Nelson [1937] 1 KB
209).
Overview: Remedies for Breach of Contract
1. Damages
2. Measure of Damages
Limitations on the Damages Recoverable
a. Remoteness of damage
b. Duty to Mitigate
c. Penalty Damages
d. Non Pecuniary Losses
3. Equitable Remedies for Breach of Contract
a. Rescission
b. Specific Performance
c. Injunction
Next Lecture:
Contract Lecture (4): Week 9 (wk/b 21st
November 2011): Terms/Content of a
Contract
Either: Tuesday (10-12: AW WG5); or,
Friday (4-6: Howarth 101).