33

remedies in contract

Embed Size (px)

Citation preview

Slide 1

AN ASSIGNMENT ON

by- Sugandh GandotraLaw Of Contract Remedies in Contract

CONSEQUENCES OF BREACH OF CONTRACT

Remedies in Contract Remoteness of damages Two rules in remoteness of damagesMeasure of damagesSection 73 of ICA,1872 Duty to mitigate the loss Liquidated damages Penalty Section 74 of ICA,1872 Quantum merit Section 75 of ICA,1872Conclusion.

CONTENTS:

REMEDIES IN CONTRACT A remedy is a means given by law for the enforcement of a right Following are the remedies

[1] Damages. [2] Suit upon quantum merit. [3] Suit for specific performance.[4] Suit for injunction.

When a contract is broken by one party, the other party may sue to treat the contract as rescinded and refuse further performance . In such a case , he is absolved of all his obligations under the contract.

The court may give rescission due to 1)contract is voidable.2)contract is unlawful

The court may refuse to rescind (END) if 1)Plaintiff has ratified (confirmed )the contract.2)Parties cannot be restored to the original position.3)The third party has acquired for value.4)When only a part is sought to be rescinded.(sec 27 of specific relief act 1937)RESCISSION:

Damages are a monetary compensation allowed to the injured party by the court for the loss or injury suffered by him by the breach of the contract.

The objective of awarding damages for the breach of contract is to put the injured party in the same position as if he had not been injured.

The fundamental basis is awarding damages for the pecuniary loss.2. DAMAGES

After the introduction of the topic now we shall discuss about section 73, 74 and 75 of the Indian Contract Act,1872 in detail

CONSEQUENCES FOR LOSS OR DAMAGE CAUSED BY BREACH OF CONTRACT-When a contract has been broken the party who suffers by such breach is entitled to receive, from the party who has broken the contract , compensation for any loss or damage caused to him thereby , which naturally arose in the usual course of things from such breach , or which the parties knew , when they made contract , to be likely to result from the breach of it.Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of breach Section 73:According to INDIAN CONTRACT ACT 1872:

COMPENSATION FOR FAILURE TO DISCHARGE OBLIGATION RESEMBLING THOSE CREATED BY CONTRACT-When an obligation resembling those created by contract has been incurred and has not been discharged , any person injured by the failure to discharge it is entitled to receive the same compensation from the party in default, as if such person had contracted to discharge it and had broken his contract. Explanation- in estimating the loss or damage arising from a breach of contract, the means which existed of remedying the inconvenience caused by the non-performance of the contract must be taken into account.

COMPENSATION FOR FAILURE TO DISCHARGE OBLIGATION RESEMBLING THOSE CREATED BY CONTRACT-

When an obligation resembling those created by contract has been incurred and has not been discharged , any person injured by the failure to discharge it is entitled to receive the same compensation from the party in default, as if such person had contracted to discharge it and had broken his contract.

Explanation- in estimating the loss or damage arising from a breach of contract, the means which existed of remedying the inconvenience caused by the non-performance of the contract must be taken into account.

In action for damages for the breach of contract there arises two problems :

REMOTENESS OF DAMAGE The leading case that decided that damage would be remote or proximate Hadley v. Baxendale(1854)9 Ex. 341,at 354Para 1 of sec 73 of ICA,1872 explains the same. There were two parts laid in this case : On the breach of contract such damages can be recovered if, damage arises in the usual course of things or More loss arises from special circumstances

Hence ,It is the rule of reasonable foresight.

Cases under first rule

Delay in carriage of goods meant for saleWilson v. Lancashire and Yorkshire Railway Koufos v. C. Czarnikow Ltd. Collard v. South Eastern Rly.

Compensation for mental anguish Ghaziabad Development Authority v. Union of India

When monetary compensation is not adequate relief Sandeep Cement (P) Ltd. v. Union of India

Breach of promise to marryPrema v. Mustak Ahmed Laxminarayan v. Sumitra

Claim by stranded passengers Hobbs v. L & S.W. Ry. Le Blanche v. L & N.W. Ry.

Damages for pre-contract and wasted expenditure Anglia Television Ltd. V. Reed Cullinane v. British Manufacturing Ltd.

Cases under second rule :

Simpson v. London & North Western Railway Co.Dominion of India v. All India Reporter Ltd. Union of India v. Hari Mohan Ghosh British Columbia Saw Mill Co. Ltd.Horne v. Midland Railway Co.Smeed v. Foord Diamond v. Campbell-JonesPilkington v. wood

MEASURE OF DAMAGE :Once it is known that the consequence of breach of contract is proximate the next step is to know that the problem is the assessment of compensation for the breach of contractDamages are compensatory in nature .

Case : State of Kerala v. K. BhaskaranDamages are ascertained as on date of breach of contract . Thus,If the buyer makes the breach of contract , the seller can claim damages as arising on the date of breach of contract and it is not necessary that the seller should resell the goods on that date If the seller makes a breach of contract , the buyer can claim damages as arising on the date of breach of contract, and it is not necessary that the buyer should re-purchase the goods on that date If the plaintiff makes a delay in reselling the goods after the breach of contract , he does so at his own risk.

Actual re-sale by the seller not necessary

Proper measure of damages is the diff. b/w the contract price and the market price

On the date of breach of contract irrespective of the fact that the seller does not again sell the goods on that day , but sells the same on a subsequent date and actual loss to him is different from the difference in the prices on the date of breach of contract

Damages when goods have fixed market price

The market price for certain goods may be fixed one and not subject to any fluctuation , then can the seller recover the damages from the buyer on the basis of being deprived of the profit which he would have made, had the buyer taken the goods

Loss Of Profit On a Sub-Contract:When the seller does not supply the goods to the buyer and the buyer is not able to earn certain amount of profit which he could have made by supplying the goods further under a sub- contract , the buyer is not entitled to recover the loss of expected profit but his right is only to recover the difference b/w the contract price and market price only

Damages in case of delivered by installments:In this the measure of damage is between the C.P and M.P of a particular installment ,on the final date of performance of that installment

DUTY TO MITIGATE THE LOSS:

When the plaintiff sues for the breach of a contract, he owes the duty of taking all reasonable steps to mitigate the loss consequent upon the breach and cannot claim as damages any sum which is due to his own neglect .

The burden of proof is on the plaintiff.

If the concerned party fails to take steps to mitigate the loss he is debarred from claiming any part of compensation for such loss that could have been mitigated .

Cases :

Jamal v. Moola Dawood sons & Co.

M.Nanjappa v. Muthuswamy It was held that it would have taken 3 months for plaintiff to secure similar employment in Bangalore & if not then it was at his own fault. He was held entitled to recover damages equivalent to his salary for 3 months

Ravindra Kumar v. U.P. State of Handloom Corp. Ltd.

Liquidated damages n Penalty

The parties at the time of making the contract agree to the amount of compensation payable in the event of the breach of contract .

The amount of compensation payable may either be liquidated or penalty.

If the compensation to be paid is genuine pre-estimate of the prospective damages it is Liquidated Damages .

If the compensation agreed to be paid in the event of breach of contract is excessive and highly disproportionate to the likely loss , the amount then fixed is Penalty.

Cases

Dunlop pneumatic Tyre Co. v. New Garage n Motor Co. Ltd.

Dunlopsued its tyre retailer, New Garage, for breaching an agreement to not resell Dunlop tyres at a price lower than that listed in the contract. The agreement then said if that did happen, New Garage would pay 5 per tyre by way of liquidated damages and not as a penalty.

Judgment: It was held that the sum of compensation payable on the breach was the genuine pre-estimate of damages, therefore liquidated damages.

Ford Motor V. Armstrong:

Defendant, who was a retail dealer of the car and car parts manufactured by the plaintiff company, agreed not to sell any car or its parts below the companys list price and if that did happen the amount of damages payable will be $250.

It was held that since parties must have known that actual likely loss was much more than they agreed, but had still preferred to fix that, the damages payable must be limited to the agreed amount only.

NOMINAL DAMAGES:In the absence of any concrete material to show the extent of damages suffered by the plaintiff , resort will have to the maxim of Nominal Damages

In case of Ashby v. White ,The High court held that ,Nominal Damage might be awarded where the fact of the loss was shown but necessary evidence as to its amount was not given.

Hence in law , damage would always entitle the plaintiff to a judgment even if without loss but done because it is an injury.

COMPENSATION FOR BREACH OF CONTRACT Where PENALTY STIPULATED FOR:

When a contract has been broken , if a sum is named in the contract as the amount to be paid in case of such breach , or if the contract contains any other stipulation by the way of penalty , the party complaining of the breach is entitled , whether or not actual loss or damage is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.Explanation a stipulation for increased interest from the date of default may be a stipulation by way of penalty SECTION 74:According to INDIAN CONTRACT ACT 1872:

Exception When a person enters into a bail-bond , recognizance or other instrument of the same nature , or under the provisions of any law , or under the orders of the Central Government or of any State Government , gives any bond for the performance of any public duty or act in which the public are interested , he shall be liable , upon breach of the condition of any such instrument , to pay the whole sum mentioned therein.

Explanation A person who enters into a contract , with Government does not necessarily thereby undertake any public duty, or promise to do an act in which the public are interested

CASES:Aditya Mass Communication Private Ltd. V. A.P.S.R.T.C Hyderabad M/s Ganga Maruthi v. NagarajState Of Gujarat v. M.K Patel &Co.K.P Subbarama Sastri v. K.S. RaghavanT.K. Sundaram v. Co-operative Sugars Ltd.Delhi Development Authority v. Grithapna Co-op. group Housing Society Ltd.Hanuman Cotton mills v. Tata Aircraft Ltd.Dharam Chand Soni v. Sunil Ranjan

FORFIETURE OF THE EARNEST MONEY:

This could be explained in case of State of Bihar v. Bhawani Industries Ltd.

NO Forfeiture OF ADVANCE IF CONTRACT BECOMES FRUSTRATED:

It is well settled that where the performance of the contract becomes impossible within the meaning of Section 56 of ICA,1872 forfeiture of any advance paid would be improper

CASES:Thiriveedhi v. Gidipudi Venkata Subba Rao Balasaheb Dayandeo Naik v. Appa Saheb Dattaraya Pawar

Quantum meruit:When a person agrees to complete some work for a lump sum , non-completion of the work does not entitle him to any remuneration even for the part of the work done .But the law recognizes an important exception to this rule by way of an action for Quantum Meruit .

Essentials for an action of Quantum Meruit are:One of the parties makes a breach of contract , or prevents the performance of it by the other side.The party injured by the breach of contract who has already performed a part of it, elects to be discharged from further performance of conntract and brings an action for recompense for the value of the work he has already done.

CASES:

Puran Lal v. State of U.P. De Bernardy v. harding

Planche v. colburn

Cravan-Ellis v. Cannon Ltd.

Associated cement Co. v. Union Of India

According to INDIAN CONTRACT ACT 1872:Section 75;PARTY RIGHTFULLLY RESCINDING CONTRACT, ENTITLED TO COMPENSATION-

A person who rightfully rescinds a contract is entitled to compensation for any damage which he has sustained through the non-fulfillment of the contract