Contoh Penawaran Proyek

Embed Size (px)

DESCRIPTION

PEMBANGUNAN LABORATORIUM IPA SMPN BIB

Citation preview

  • AAABBAAABBBg

    R E K A P I T U L A S I

    PEKERJAAN : PEMBANGUNAN LABORATORIUM IPA SEKOLAH MENENGAH PERTAMA

    SEKOLAH : SMP NEGERI BOLAANG ITANG BARATTAHUN ANGGARAN: 2011LOKASI : KEC. BOLAANG ITANG BARAT KAB. BOLAANG MONGONDOW UTARA

    NO JENIS PEKERJAAN

    I PEKERJAAN PERSIAPAN 4,250,000.00 II PEKERJAAN TANAH DAN PASIR 6,915,895.55 III PEKERJAAN PASANGAN PONDASI DAN BETON 60,939,373.39 IV PEKERJAAN DINDING DAN PLESTERAN 34,153,401.50 V. PEKERJAAN FINISHING LANTAI 15,902,700.00 VI. PEKERJAAN PINTU & JENDELA 10,716,464.25 VII. PEKERJAAN KUNCI DAN PENGGANTUNG 2,214,250.00 VIII. PEKERJAAN KUDA-KUDA, RANGKA ATAP DAN P 46,350,537.65 IX. PEKERJAAN PENGECATAN 7,078,278.45 X. PEKERJAAN INSTALASI LISTRIK DAN ARMATUR 3,130,680.00 XI. PEKERJAAN MEUBELAIR 47,000,000.00 XII. PEKERJAAN LAIN-LAIN 250,000.00

    - Real Cost 238,901,580.79 - PPN 10% 23,890,158.08

    - JUMLAH 262,791,738.87

    - DIBULATKAN 262,791,000.00

    Terbilang : xxxxxxxxxxxxxxxxxxxxx

    Boroko, 04 Oktober 2011

    Mengetahui, Dibuat Oleh,KONTRAKTOR PELAKSANA KONTRAKTOR PELAKSANA

    xxxxxxxxxxxxxx xxxxxxxxxxxxxx

    JUMLAH HARGA

    (RP)

  • xxxxxxxxxxxxx xxxxxxxxxxxxxxxDirektur Pimpinan Teknik

  • DAFTAR HARGA SATUAN JADIPEKERJAAN : PEMBANGUNAN LABORATORIUM IPA

    SEKOLAH MENENGAH PERTAMASEKOLAH : SMP NEGERI BOLAANG ITANG BARATTAHUN ANGGARAN : 2011LOKASI : KEC. BOLAANG ITANG BARAT KAB. BOLAANG MONGONDOW UTARA

    NO URAIAN PEKERJAAN

    1. Pembersihan Lokasi Ls 250,000.00 2. Pengukuran dan Pasangan Bouwplank Ls 500,000.00 3. Pembuatan Direksi Keet, Gudang Sementara, Air Kerja, P3K Ls 2,000,000.00 4. Pembuatan Papan Nama Proyek Ls 500,000.00 5. Administrasi dan Dokumentasi Ls 1,000,000.00 6. Galian Tanah Pondasi M3 22,200.00 7. Urugan Tanah M3 61,875.00 8. Urugan Pasir dibawah Pondasi dan Lantai M3 111,550.00 9. Urugan Tanah Kembali M3 10,645.00

    10. Pasangan Batu Kosong / Aanstamping M3 235,470.00 11. Pas. Pondasi Jalur Batu Kali camp. 1Pc : 5 Psr M3 536,025.00 12. Pek. Cor Beton Bertulang Sloof 20/25 M3 2,719,422.40 13. Pek. Cor Beton Bertulang Sloof 15/12 M3 4,425,682.71 14. Pek. Cor Beton Bertulang Kolom 20/25 M3 3,182,832.40 15. Pek. Cor Beton Bertulang Kolom 15/15 M3 4,412,009.04 16. Pek. Cor Beton Bertulang Ringbalk 15/12 M3 5,247,157.71 17. Pek. Rabat Beton Tumbuk ad. 1 : 3 : 5 M3 502,225.00 18. Pek. Cor Beton Bertulang Meja Lab tebal 10 cm M3 4,418,225.00 19. Pas. Tembok Batu Bata Trasram camp. 1 Pc : 3 Psr M2 87,537.50 20. Pasang Tembok Batu Bata camp. 1 Pc : 5 Psr M2 82,175.00 21. Plesteran Tembok Trasram dan Beton camp. 1 Pc : 3 Psr M2 30,675.00 22. Plesteran Tembok Biasa camp. 1 Pc : 5 Psr M2 28,275.00 23. Acian Semen M2 14,100.00 24. Pas. Keramik 40 x 40 cm untuk lantai bangunan M2 106,018.00 25. Pas. Kusen Pintu/Jendela Kayu Klas. II M3 3,946,500.00 26. Pas. Daun Pintu Panil Kayu Klas. II M2 301,500.00 27. Pas. Bingkai Daun Jendela M2 247,200.00 28. Pas. Jalusi Ventilasi M2 283,925.00 29. Pas. Kaca 5 mm M2 76,930.00 30. Pas. Angkur Kusen Ls 250,000.00

    FILE SAMPEL JASA DOKUMEN TENDER ONLINE DI : http://dokumentender.blogspot.com/ *** File Ini Tidak Dapat Di Edit

    SATUAN

    HARGA SATUAN

    (Rp.)

  • 31. Pas. Kunci Tanam 2 Slaag Untuk Pintu Panil Kayu Bh 80,930.00 32. Pas. Engsel Pintu Panil Kayu @ Buah Bh 28,430.00

    NO URAIAN PEKERJAAN

    33. Pas. Engsel Jendela @ 2 Buah Bh 19,805.00 34. Pas. Grendel Jendela Bh 18,430.00 35. Pas. Kait Angin Jendela Bh 18,930.00 36. Pek. Kuda-kuda & Rangka Atap Kayu Klas. II M3 3,422,100.00 37. Pek. Gording Kayu M3 2,863,600.00 38. Pek. Atap Genteng Metal M2 57,005.00 39. Pek. Nok Genteng Metal M' 40,800.00 40. Pas. Rangka Plafond M2 54,200.00 41. Pas. Plafond Tripleks 4 mm M2 27,082.50 42. Pek. Profil Kayu M' 11,160.00 43. Pas. Listplank Kayu M' 29,695.00 44. Pek. Pengecatan Dinding M2 10,805.00 45. Pek. Pengecatan Plafond M2 10,805.00 46. Pek. Pengecatan Kusen, Daun Pintu Panil & Jendela M2 33,210.00 47. Pemasangan Instalasi Titik Lampu Ttk 194,860.00 48. Pemasangan Instalasi Titik Stop Kontak 200 VA Ttk 194,860.00 49. Pemasangan Stop Kontak 200 VA ex Broco Bh 22,500.00 50. Pas. Lampu SL 18 Watt Bh 45,000.00 51. Pas. Saklar Tunggal Bh 15,000.00 52. Pas. Saklar Ganda Bh 25,000.00 53. Meja Serbaguna Bh 750,000.00 54. Meja Kursi Bh 600,000.00 55. Meja Demonstrasi Bh 800,000.00 56. Kursi Siswa Bh 300,000.00 57. Kursi Bunder Tinggi Bh 450,000.00 58. Kursi Kerja Bh 400,000.00 59. Lemari Kaca Geser Bh 1,750,000.00 60. Lemari Alat Peraga Bh 1,350,000.00

    SATUAN

    HARGA SATUAN

    (Rp.)

  • NO URAIAN PEKERJAAN

    61. Lemari Kertas Kerja Bh 1,000,000.00 62. Lemari Gantung P3K Bh 950,000.00 63. Lemari Asam Bh 900,000.00 64. Papan Tulis Gantung Bh 200,000.00 65. Kotak Sampah Bh 75,000.00 66. Pek. Pembersihan dan Perapihan Sisa-sisa Material Ls 250,000.00

    Boroko, 04 Oktober 2011

    Mengetahui, Dibuat Oleh,KONTRAKTOR PELAKSANA KONTRAKTOR PELAKSANA

    xxxxxxxxxxxxxx xxxxxxxxxxxxxx

    xxxxxxxxxxxxx xxxxxxxxxxxxxxxDirektur Pimpinan Teknik

    SATUAN

    HARGA SATUAN

    (Rp.)

  • : KEC. BOLAANG ITANG BARAT KAB. BOLAANG MONGONDOW UTARA

    FILE SAMPEL JASA DOKUMEN TENDER ONLINE DI : http://dokumentender.blogspot.com/ *** File Ini Tidak Dapat Di Edit

  • DAFTAR KUANTITAS DAN HARGAPEKERJAAN : PEMBANGUNAN LABORATORIUM IPA

    SEKOLAH MENENGAH PERTAMASEKOLAH : SMP NEGERI BOLAANG ITANG BARATTAHUN ANGGARAN : 2011LOKASI : KEC. BOLAANG ITANG BARAT KAB. BOLAANG MONGONDOW UTARA

    NO JEIS PEKERJAAN VOLUME SATUAN

    I. PEKERJAAN PERSIAPAN1. Pembersihan Lokasi 1.00 Ls 250,000.00 250,000.00 2. Pengukuran dan Pasangan Bouwplank 1.00 Ls 500,000.00 500,000.00 3. Pembuatan Direksi Keet, Gudang Sementara, Air Kerj 1.00 Ls 2,000,000.00 2,000,000.00 4. Pembuatan Papan Nama Proyek 1.00 Ls 500,000.00 500,000.00 5. Administrasi dan Dokumentasi 1.00 Ls 1,000,000.00 1,000,000.00

    Jumlah 4,250,000.00

    II. PEKERJAAN TANAH DAN PASIR1. Galian Tanah Pondasi 29.64 M3 22,200.00 658,008.00 2. Urugan Tanah 60.00 M3 61,875.00 3,712,500.00 3. Urugan Pasir dibawah Pondasi dan Lantai 21.97 M3 111,550.00 2,450,753.50 4. Urugan Tanah Kembali 8.89 M3 10,645.00 94,634.05

    Jumlah 6,915,895.55

    III. PEKERJAAN PASANGAN PONDASI DAN BETON1. Pasangan Batu Kosong / Aanstamping 7.41 M3 235,470.00 1,744,832.70 2. Pas. Pondasi Jalur Batu Kali camp. 1Pc : 5 Psr 39.67 M3 536,025.00 21,264,111.75 3. Pek. Cor Beton Bertulang Sloof 20/25 2.85 M3 2,719,422.40 7,750,353.83 4. Pek. Cor Beton Bertulang Sloof 15/12 0.34 M3 4,425,682.71 1,504,732.12 5. Pek. Cor Beton Bertulang Kolom 20/25 3.03 M3 3,182,832.40 9,643,982.16 6. Pek. Cor Beton Bertulang Kolom 15/15 0.64 M3 4,412,009.04 2,823,685.79 7. Pek. Cor Beton Bertulang Ringbalk 15/12 1.79 M3 5,247,157.71 9,392,412.30 8. Pek. Rabat Beton Tumbuk ad. 1 : 3 : 5 7.50 M3 502,225.00 3,766,687.50 9. Pek. Cor Beton Bertulang Meja Lab tebal 10 cm 0.69 M3 4,418,225.00 3,048,575.25

    Jumlah 60,939,373.39

    IV. PEKERJAAN DINDING DAN PLESTERAN1. Pas. Tembok Batu Bata Trasram camp. 1 Pc : 3 Psr 10.76 M2 87,537.50 941,903.50 2. Pasang Tembok Batu Bata camp. 1 Pc : 5 Psr 183.80 M2 82,175.00 15,103,765.00 3. Plesteran Tembok Trasram dan Beton camp. 1 Pc : 3 56.52 M2 30,675.00 1,733,751.00 4. Plesteran Tembok Biasa camp. 1 Pc : 5 Psr 367.60 M2 28,275.00 10,393,890.00 5. Acian Semen 424.12 M2 14,100.00 5,980,092.00

    Jumlah 34,153,401.50 -

    V. PEKERJAAN FINISHING LANTAI - 1. Pas. Keramik 40 x 40 cm untuk lantai bangunan 150.00 M2 106,018.00 15,902,700.00

    Jumlah 15,902,700.00

    FILE SAMPEL JASA DOKUMEN TENDER ONLINE DI : http://dokumentender.blogspot.com/ *** File Ini Tidak Dapat Di Edit

    HARGA SATUAN

    (Rp.)

    JUMLAH HARGA

    (Rp.)

  • NO JEIS PEKERJAAN VOLUME SATUAN

    VI. PEKERJAAN PINTU & JENDELA1. Pas. Kusen Pintu/Jendela Kayu Klas. II 1.06 M3 3,946,500.00 4,183,290.00 2. Pas. Daun Pintu Panil Kayu Klas. II 6.15 M2 301,500.00 1,854,225.00 3. Pas. Bingkai Daun Jendela 3.66 M2 247,200.00 904,752.00 4. Pas. Jalusi Ventilasi 9.73 M2 283,925.00 2,762,590.25 5. Pas. Kaca 5 mm 9.90 M2 76,930.00 761,607.00 6. Pas. Angkur Kusen 1.00 Ls 250,000.00 250,000.00

    Jumlah 10,716,464.25 -

    VII. PEKERJAAN KUNCI DAN PENGGANTUNG1. Pas. Kunci Tanam 2 Slaag Untuk Pintu Panil Kayu 3.00 Bh 80,930.00 242,790.00 2. Pas. Engsel Pintu Panil Kayu @ Buah 12.00 Bh 28,430.00 341,160.00 3. Pas. Engsel Jendela @ 2 Buah 34.00 Bh 19,805.00 673,370.00 4. Pas. Grendel Jendela 17.00 Bh 18,430.00 313,310.00 5. Pas. Kait Angin Jendela 34.00 Bh 18,930.00 643,620.00

    Jumlah 2,214,250.00

    VIII. PEKERJAAN KUDA-KUDA, RANGKA ATAP DAN PLAFOND1. Pek. Kuda-kuda & Rangka Atap Kayu Klas. II 1.81 M3 3,422,100.00 6,194,001.00 2. Pek. Gording Kayu 2.34 M3 2,863,600.00 6,700,824.00 3. Pek. Atap Genteng Metal 200.43 M2 57,005.00 11,425,512.15 4. Pek. Nok Genteng Metal 42.90 M' 40,800.00 1,750,320.00 5. Pas. Rangka Plafond 204.00 M2 54,200.00 11,056,800.00 6. Pas. Plafond Tripleks 4 mm 204.00 M2 27,082.50 5,524,830.00 7. Pek. Profil Kayu 172.00 M' 11,160.00 1,919,520.00 8. Pas. Listplank Kayu 59.90 M' 29,695.00 1,778,730.50

    Jumlah 46,350,537.65

    IX. PEKERJAAN PENGECATAN1. Pek. Pengecatan Dinding 237.51 M2 10,805.00 2,566,295.55 2. Pek. Pengecatan Plafond 204.00 M2 10,805.00 2,204,220.00 3. Pek. Pengecatan Kusen, Daun Pintu Panil & Jendela 69.49 M2 33,210.00 2,307,762.90

    Jumlah 7,078,278.45

    X. PEKERJAAN INSTALASI LISTRIK DAN ARMATURE1. Pemasangan Instalasi Titik Lampu 10.00 Ttk 194,860.00 1,948,600.00 2. Pemasangan Instalasi Titik Stop Kontak 200 VA 3.00 Ttk 194,860.00 584,580.00 3. Pemasangan Stop Kontak 200 VA ex Broco 3.00 Bh 22,500.00 67,500.00 4. Pas. Lampu SL 18 Watt 10.00 Bh 45,000.00 450,000.00 5. Pas. Saklar Tunggal 2.00 Bh 15,000.00 30,000.00 6. Pas. Saklar Ganda 2.00 Bh 25,000.00 50,000.00

    Jumlah 3,130,680.00

    HARGA SATUAN

    (Rp.)

    JUMLAH HARGA

    (Rp.)

  • NO JEIS PEKERJAAN VOLUME SATUAN

    XI. PEKERJAAN MEUBELAIR1. Meja Serbaguna 20.00 Bh 750,000.00 15,000,000.00 2. Meja Kursi 2.00 Bh 600,000.00 1,200,000.00 3. Meja Demonstrasi 1.00 Bh 800,000.00 800,000.00 4. Kursi Siswa 2.00 Bh 300,000.00 600,000.00 5. Kursi Bunder Tinggi 40.00 Bh 450,000.00 18,000,000.00 6. Kursi Kerja 4.00 Bh 400,000.00 1,600,000.00 7. Lemari Kaca Geser 3.00 Bh 1,750,000.00 5,250,000.00 8. Lemari Alat Peraga 1.00 Bh 1,350,000.00 1,350,000.00 9. Lemari Kertas Kerja 1.00 Bh 1,000,000.00 1,000,000.00

    10. Lemari Gantung P3K 1.00 Bh 950,000.00 950,000.00 11. Lemari Asam 1.00 Bh 900,000.00 900,000.00 12. Papan Tulis Gantung 1.00 Bh 200,000.00 200,000.00 13. Kotak Sampah 2.00 Bh 75,000.00 150,000.00

    Jumlah 47,000,000.00

    XII. PEKERJAAN LAIN-LAIN1. Pek. Pembersihan dan Perapihan Sisa-sisa Material 1.00 Ls 250,000.00 250,000.00

    Jumlah 250,000.00

    Boroko, 04 Oktober 2011

    Mengetahui, Dibuat Oleh,KONTRAKTOR PELAKSANA KONTRAKTOR PELAKSANA

    xxxxxxxxxxxxxx xxxxxxxxxxxxxx

    xxxxxxxxxxxxx xxxxxxxxxxxxxxxDirektur Pimpinan Teknik

    HARGA SATUAN

    (Rp.)

    JUMLAH HARGA

    (Rp.)

  • PEMBANGUNAN RKB SMP NEGERI 3 SATAP BONE DESA SOGITIA KEC. BONE

    26 26 26 26

    4,250,000.00 26

    117,911,370.44 26 #REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!

    40,000 20000 40,000 20000 40,000 20000 17,000 20000 4,000 20000 40,000 20000 40,000 17000 40,000 40000 40,000 40000 45,000 40000 40,000 40000 40,000 45000 25,000 40000 451,000 40000

    25000 45,100 4000 45,000 40000

  • 113,721,452.85

    45,000 40000

  • = #REF!

  • R E K A P I T U L A S I

    KEGIATAN : PENGADAAN SARANA DAN PRASARANA PUSKESMAS PEKERJAAN : REVITALISASI PUSKESMAS PERAWATAN KWANDANGLOKASI : KECAMATAN KWANDANG KABUPATEN GORONTALO UTARASUMBER DANA : DAK/DAUTAHUN ANGGARAN : 2009

    NO JENIS PEKERJAAN HARGA (Rp)

    A. PEKERJAAN PERSIAPAN 14,850,000.00

    B. PEMBANGUNAN GEDUNG RAWAT JALAN #REF!

    C. PEMBANGUNAN GEDUNG RAWAT INAP #REF!

    D. PEKERJAAN KORIDOR PENGHUBUNG 12,000,000.00

    E. PEKERJAAN LAIN - LAIN 4,500,000.00

    A. SUB TOTAL #REF!

    B. PPN 10 % #REF!

    C. IMB 13,410,000.00

    ( A + B + C) TOTAL #REF!

    DIBULATKAN #REF!

    Terbilang : " Satu Milyar Enam Ratus Satu Juta Enam Ratus Ribu Rupiah "

    Kwandang, 23 Maret 2009Mengetahui

    PT. PERDANA PUTRA BAJATAMA Dibuat Oleh

    ABDUL RASYID ABAS xxxxxxxxxxxxxDirektur Pimpinan Teknik

  • RENCANA ANGGARAN BIAYA (RAB)

    KEGIATAN : PENGADAAN SARANA DAN PRASARANA PUSKESMAS PEKERJAAN : REVITALISASI PUSKESMAS PERAWATAN KWANDANGLOKASI : KECAMATAN KWANDANG KABUPATEN GORONTALO UTARASUMBER DANA : DAK/DAUTAHUN ANGGARA: 2009

    NO URAIAN PEKERJAAN SATUAN VOL HARGA JUMLAHSATUAN HARGA( Rp.) ( Rp. )

    A. PEKERJAAN PERSIAPAN 14,850,000.00 1 Pekerjaan Pembuatan Papan Nama Proyek Ls 1.00 500,000.00 500,000.00 2 Pembersihan awal Ls 1.00 1,000,000.00 1,000,000.00 3 Pembongkaran Bangunan Lama Ls 1.00 6,000,000.00 6,000,000.00 4 Biaya administrasi / dokumentasi Ls 1.00 1,500,000.00 1,500,000.00 5 Pekerjaan Penyediaan Air Kerja Ls 1.00 2,000,000.00 2,000,000.00 6 Biaya Pemindahan/Pasang Meteran PLN Lama Ls 1.00 350,000.00 350,000.00 7 Direksi Keet Ls 1.00 3,000,000.00 3,500,000.00

    B. PEMBANGUNAN GEDUNG RAWAT JALAN #REF!I PEKERJAAN TANAH DAN URUGAN1 Galian tanah untuk pondasi M 103.68 #REF! #REF!2 Urugan tanah kembali M 34.56 #REF! #REF!3 Pekerjaan Timbunan lantai M 79.65 #REF! #REF!4 Urugan pasir dibawah Pondasi dan lantai M 23.90 #REF! #REF!

    II PEKERJAAN PONDASI 1 Pasangan batu kosong / aanstamping M 13.30 #REF! #REF!2 Pas. pondasi batu kali camp 1 : 4 M 61.66 #REF! #REF!

    ==

    III PEKERJAAN BETON =1 Pekerjaan Cor Lantai Kerja 1 : 3 : 5 M 12.39 #REF! #REF!2 Pekerjaan Beton Pondasi Tapak M 7.88 #REF! #REF!3 Pek. Lantai Beton Bertulang 1:2:3 M 18.72 #REF! #REF!4 Pek. Beton Sloof 20/25 M 6.20 #REF! #REF!5 Pek. Beton Kolom K1 30/30 M 5.26 #REF! #REF!6 Pek. Beton Kolom K2 20/30 M 0.46 #REF! #REF!7 Pek. Beton Kolom K3 20/20 M 2.34 #REF! #REF!8 Pek. Beton Kolom K4 11/20 M 0.10 #REF! #REF!9 Pek. Beton Kolom Praktis 12/12 M 3.57 #REF! #REF!10 Pek. Beton Balok B1 25/40 M 10.80 #REF! #REF!11 Pek. Beton Balok B2 20/30 M 0.24 #REF! #REF!12 Pek. Beton Balok B3 15/20 M 2.55 #REF! #REF!13 Pek. Beton Balok Ring 15/20 M 5.58 #REF! #REF!14 Pek. Beton Balok Bordes 25/20 M 0.25 #REF! #REF!15 Pek. Beton Balok Latei 12/15 M 2.84 #REF! #REF!16 Pek. Lisplank Beton M 31.53 #REF! #REF!17 Pek. Tangga/Bordes Beton M 1.33 #REF! #REF!18 Pekerjaan Beton Plat Level M 1.72 #REF! #REF!19 Pekerjaan Beton Plat Meja M 0.12 #REF! #REF!

    ==

    IV PEKERJAAN PAS. DINDING DAN PLESTERAN =1 Pas. Tembok bt. Bata trasram camp. 1Pc : 3Ps M 67.89 #REF! #REF!2 Pas. Tembok bt. Bata camp. 1Pc : 5Ps M 583.69 #REF! #REF!3 Plesteran tembok trasram camp. 1Pc : 3Ps M 135.78 #REF! #REF!4 Plesteran tembok biasa camp. 1Pc : 5Ps M 1,109.01 #REF! #REF!

  • NO URAIAN PEKERJAAN SATUAN VOL HARGA JUMLAHSATUAN HARGA( Rp.) ( Rp. )

    5 Pekerjaan Acian M 1,244.79 #REF! #REF!6 Pek. Papan Nama Stainless Steel Ls 1.00 1,000,000.00 1,000,000.00

    =

    V PEKERJAAN PINTU JENDELA DAN VENTILASI =1 Pek. Kusen pintu dan jendela Aluminium M' 741.64 #REF! #REF!2 Pek. Bingkai Jendela Aluminium M' 582.88 #REF! #REF!3 Pas. Pintu Panel Aluminium/Kaca M 31.74 #REF! #REF!4 Pas. Sekat Multipleks 5 mm M 31.50 #REF! #REF!5 Pas. Pintu PVC Set 5.00 #REF! #REF!6 Pas. Kaca polos t = 4,5 mm M 73.15 #REF! #REF!7 Pas. Railling Stainless Balkon M' 22.00 375,000.00 8,250,000.00

    =###

    VI PEKERJAAN ATAP =1 Pekerjaan Kuda-Kuda Kayu Kelas II M 6.79 #REF! #REF!2 Pekerjaan Rangka Atap Kayu Kelas II M 172.90 #REF! #REF!3 Pekerjaan Atap Genteng Sakura Roof M 172.90 #REF! #REF!4 Pekerjaan Nok Genteng Sakura Roof M' 64.74 #REF! #REF!5 Pekerjaan Lisplank Kayu M' 9.00 #REF! #REF!

    ==

    VII PEKERJAAN PLAFOND =1 Pekerjaan Pasangan rangka Plafond M 409.94 #REF! #REF!2 Pekerjaan Plafond Tripleks 3 mm M 409.94 #REF! #REF!3 Pekerjaan Lis Plafon Sp. 3 M' 388.00 #REF! #REF!

    ==

    VIII PEKERJAAN KERAMIK =1 Pas. Keramik 40 x 40 cm polos M 324.20 #REF! #REF!2 Pas. Keramik 20 x 20 cm KM/WC M 9.50 #REF! #REF!3 Pas. Keramik Dinding 20 x 25 cm KM/WC/Meja Beton M 27.90 #REF! #REF!

    =IX PEKERJAAN GANTUNGAN DAN KUNCI =1 Pas. Engsel Pintu Psg 22.00 #REF! #REF!2 Pas. Engsel Jendela Psg 150.00 #REF! #REF!3 Pas. Kunci 3 Lever Bh 22.00 #REF! #REF!4 Pas. Grendel Tanam Bh 150.00 #REF! #REF!5 Pas. Hak Angin Psg 150.00 #REF! #REF!6 Pas. Ekspagnyolet Stainless Psg 10.00 #REF! #REF!7 Pas. Door Closer Psg 22.00 #REF! #REF!

    ==

    X PEKERJAAN PERLENGKAPAN DALAM =Pekerjaan Instalasi Listrik =

    1 Pasang MCB 6 grup Bh 6.00 #REF! #REF!2 Penyambungan Kabel Listrik Ls 1.00 350,000.00 350,000.00 3 Pasangan Lampu Pijar 25 Watt Unit 6.00 #REF! #REF!4 Pasangan Lampu SL Philips 18 Watt + Downlight Unit 18.00 #REF! #REF!5 Pasangan Lampu SL Philips 18 Watt Unit 25.00 #REF! #REF!6 Lampu TL Armateur 2 x 36 Watt Unit 26.00 #REF! #REF!7 Pasangan Saklar Doubel Unit 24.00 #REF! #REF!8 Pasangan Saklar Tunggal Unit 10.00 #REF! #REF!9 Pasangan Stop Kontak Unit 38.00 #REF! #REF!10 Pasangan Instalasi Titik Lampu Ttk 75.00 #REF! #REF!

    Pekerjaan Sanitasi Dan Instalasi Air =1 Pasangan Floor Drain Bh 5.00 #REF! #REF!2 Pasangan Pipa VE 0,5" (Air Bersih) M1 102.00 #REF! #REF!3 Pasangan Pipa VE 2" (Air Kotor) M1 94.00 #REF! #REF!4 Pasangan Pipa VE 3" (Air Hujan) M1 211.50 #REF! #REF!5 Pasangan Pipa VE 4" (Air Kotor) M1 40.00 #REF! #REF!6 Pasangan Kran Air Bh 11.00 #REF! #REF!7 Pasangan Kloset Duduk Bh 5.00 #REF! #REF!

  • NO URAIAN PEKERJAAN SATUAN VOL HARGA JUMLAHSATUAN HARGA( Rp.) ( Rp. )

    8 Pasangan Wastafel Bh 6.00 #REF! #REF!9 Pasang Septic tank dan peresapan Unit 1.00 #REF! #REF!10 Pasang Saluran Air Hujan M' 58.00 #REF! #REF!

    =XI PEKERJAAN PENGECATAN =1 Pek. Pengecatan Tembok Dan Plafond M 1,654.73 #REF! #REF!2 Pek. Pengecatan Lisplank Kayu M 4.50 #REF! #REF!3 Pek. Pengecatan Waterproofing Lisplank Beton M 192.20 #REF! #REF!

    =

    C. PEMBANGUNAN GEDUNG RAWAT INAP #REF!

    I PEKERJAAN TANAH DAN URUGAN1 Galian tanah untuk pondasi M 120.62 #REF! #REF!2 Urugan tanah kembali M 40.21 #REF! #REF!3 Pekerjaan Timbunan lantai M 135.90 #REF! #REF!4 Urugan pasir dibawah Pondasi dan lantai M 36.36 #REF! #REF!

    II PEKERJAAN PONDASI 1 Pasangan batu kosong / aanstamping M 20.27 #REF! #REF!2 Pas. pondasi batu kali camp 1 : 4 M 94.85 #REF! #REF!

    ==

    III PEKERJAAN BETON 1 Pekerjaan Cor Lantai Kerja 1 : 3 : 5 M 21.14 #REF! #REF!2 Pekerjaan Beton Pondasi Tapak M 2.63 #REF! #REF!3 Pekerjaan Sloef Beton 15/20 M 5.91 #REF! #REF!4 Pekerjaan Sloef Beton 20/30 M 0.96 #REF! #REF!5 Pekerjaan Kolom K1 40/40 M 2.78 #REF! #REF!6 Pekerjaan Kolom K3 25/25 M 2.74 #REF! #REF!7 Pekerjaan Kolom K2 30/30 M 0.66 #REF! #REF!8 Pekerjaan Kolom Praktis 12/12 M 2.05 #REF! #REF!9 Pekerjaan Balok Latei 12/15 M 2.21 #REF! #REF!10 Pekerjaan Ring Balok 15/20 M 5.37 #REF! #REF!11 Pekerjaan Ring Balok 20/30 M 1.08 #REF! #REF!12 Pekerjaan Beton Plat Level M 1.19 #REF! #REF!13 Pekerjaan Beton Plat Meja M 0.21 #REF! #REF!14 Pekerjaan Lisplank Beton M 21.39 #REF! #REF!

    ==

    IV PEKERJAAN PAS. DINDING DAN PLESTERAN =1 Pas. Tembok bt. Bata trasram camp. 1Pc : 3Ps M 118.77 #REF! #REF!2 Pas. Tembok bt. Bata camp. 1Pc : 5Ps M 454.67 #REF! #REF!3 Plesteran tembok trasram camp. 1Pc : 3Ps M 237.54 #REF! #REF!4 Plesteran tembok biasa camp. 1Pc : 5Ps M 863.86 #REF! #REF!5 Pekerjaan Acian M 1,101.40 #REF! #REF!6 Pekerjaan Profil Semen M' 86.92 #REF! #REF!

    =

    V PEKERJAAN PINTU JENDELA DAN VENTILASI =1 Pek. Kusen pintu dan jendela Aluminium M' 293.08 #REF! #REF!2 Pek. Bingkai Jendela Aluminium M' 202.70 #REF! #REF!3 Pas. Pintu Panel Aluminium/Kaca M 31.74 #REF! #REF!4 Pas. Pintu PVC Set 6.00 #REF! #REF!5 Pas. Kaca polos t = 4,5 mm M 28.24 #REF! #REF!

    =###

    VI PEKERJAAN ATAP =1 Pekerjaan Kuda-Kuda Kayu Kelas II M 8.15 #REF! #REF!2 Pekerjaan Rangka Atap Kayu Kelas II M 421.78 #REF! #REF!3 Pekerjaan Atap Genteng Sakura Roof M 421.78 #REF! #REF!4 Pekerjaan Nok Genteng Sakura Roof M' 60.47 #REF! #REF!

  • NO URAIAN PEKERJAAN SATUAN VOL HARGA JUMLAHSATUAN HARGA( Rp.) ( Rp. )

    ==

    VII PEKERJAAN PLAFOND =1 Pekerjaan Pasangan rangka Plafond M 384.00 #REF! #REF!2 Pekerjaan Plafond Tripleks 3 mm M 384.00 #REF! #REF!3 Pekerjaan Lis Plafon Sp. 3 M' 361.00 #REF! #REF!

    ==

    VIII PEKERJAAN KERAMIK =1 Pas. Keramik 40 x 40 cm polos M 253.00 #REF! #REF!2 Pas. Keramik 20 x 20 cm KM/WC M 16.50 #REF! #REF!3 Pas. Keramik Dinding 20 x 25 cm KM/WC/Meja Beton M 15.00 #REF! #REF!

    =IX PEKERJAAN GANTUNGAN DAN KUNCI =1 Pas. Engsel Pintu Psg 18.00 #REF! #REF!2 Pas. Engsel Jendela Psg 80.00 #REF! #REF!3 Pas. Kunci 3 Lever Bh 4.00 #REF! #REF!4 Pas. Kunci 2 Lever Bh 10.00 #REF! #REF!5 Pas. Grendel Tanam Bh 80.00 #REF! #REF!6 Pas. Hak Angin Psg 80.00 #REF! #REF!7 Pas. Ekspagnyolet Stainless Psg 8.00 #REF! #REF!8 Pas. Door Closer Psg 17.00 #REF! #REF!

    ==

    X PEKERJAAN PERLENGKAPAN DALAM =Pekerjaan Instalasi Listrik =

    1 Pasang MCB 5 grup Bh 5.00 #REF! #REF!2 Pasangan Lampu Pijar 25 Watt Unit 8.00 #REF! #REF!3 Pasangan Lampu SL Philips 18 Watt Unit 17.00 #REF! #REF!4 Lampu TL Armateur 2 x 36 Watt Unit 26.00 #REF! #REF!5 Pasangan Saklar Doubel Unit 16.00 #REF! #REF!6 Pasangan Saklar Tunggal Unit 7.00 #REF! #REF!7 Pasangan Stop Kontak Unit 29.00 #REF! #REF!8 Pasangan Instalasi Titik Lampu Ttk 51.00 #REF! #REF!

    Pekerjaan Sanitasi Dan Instalasi Air =1 Pasangan Floor Drain Bh 6.00 #REF! #REF!2 Pasangan Pipa VE 0,5" (Air Bersih) M1 65.00 #REF! #REF!3 Pasangan Pipa VE 2" (Air Kotor) M1 40.00 #REF! #REF!4 Pasangan Pipa VE 4" (Air Kotor) M1 23.00 #REF! #REF!5 Pasangan Pipa VE 3" (Air Hujan) M1 122.85 #REF! #REF!6 Pasangan Kran Air Bh 9.00 #REF! #REF!7 Pasangan Shower Bh 2.00 #REF! #REF!8 Pasangan Kran Shower Bh 2.00 #REF! #REF!9 Pasangan Kloset Jongkok Bh 4.00 #REF! #REF!10 Pasangan Kloset Duduk Bh 2.00 #REF! #REF!11 Pasangan Wastafel Bh 4.00 #REF! #REF!12 Pasangan Kitchen Zink Bh 1.00 #REF! #REF!13 Pasangan Bak Fiberglass Bh 4.00 #REF! #REF!14 Pasang Septic tank dan peresapan Unit 3.00 #REF! #REF!15 Pasang Saluran Air Hujan M' 66.00 #REF! #REF!

    =XI PEKERJAAN PENGECATAN =1 Pek. Pengecatan Tembok Dan Plafond M 1,485.40 #REF! #REF!2 Pek. Pengecatan Waterproofing Lisplank Beton M 130.38 #REF! #REF!

    D. PEKERJAAN KORIDOR PENGHUBUNG 12,000,000.00 1 Selasar Rangka Stainless Steel Atap Polykarbonat Ls 1.00 12,000,000.00 12,000,000.00

    E. PEKERJAAN LAIN - LAIN 4,500,000.00 1 Pembersihan Akhir Ls 1.00 1,000,000.00 1,000,000.00 2 Asbuilt Drawing Ls 1.00 3,500,000.00 3,500,000.00

    =

  • NO URAIAN PEKERJAAN SATUAN VOL HARGA JUMLAHSATUAN HARGA( Rp.) ( Rp. )

    Boroko, 04 Oktober 2011KONTRAKTOR PELAKSANA #REF!

    xxxxxxxxxxxxxx

    #REF! xxxxxxxxxxxxx0 Pimpinan Teknik

  • HITUNG BESI Panjang J Jumlah Bh J Bh HitTELAPAK BESI 12 2.6 7.666667 19.93333 2 39.86667 35.39203

    BESI 16 1 6 6 2 12 18.9388854.33091

    KOLOM 30 x 30BESI 12 11.11111 4 44.44444 39.456BESI 12 20 4 80 49.32BESI 8 1.25 75.07407 93.84259 37.02653

    125.8025BEKISTING 11.11111 0.3 0.3 0.3 0.3 13.33333 3.333333

    KOLOM 20 x 20BESI 12 16 4 64 56.81664BESI 12 25 2 50 30.825BESI 8 0.85 107.6667 91.51667 36.10882

    123.7505BEKISTING 16 0.25 0.25 0.25 0.25 16 8

    BALOK LATEY 11/15BESI 12 55.55556 4 222.2222 137BESI 8 0.85 371.3704 315.6648 124.5487

    261.5487BEKISTING 55.55556 0.12 0.12 0.15 0.15 30 15

    SLOOF 20 x 25BESI 12 20 6 120 106.5312BESI 8 0.95 134.3333 127.6167 50.35243

    156.8836BEKISTING 20 0.2 0.2 0.25 0.25 18 4.500

    SLOOF 15 x 12BESI 12 55.55556 4 222.2222 197.28BESI 8 0.59 371.3704 219.1085 86.45146

    283.7315BEKISTING 55.55556 0.15 0.15 0.12 0.12 30 7.500

    KOLOM PRAKTIS 15/15BESI 12 44.44444 4 177.7778 157.824BESI 8 0.59 297.2963 175.4048 69.20772

    227.0317BEKISTING 44.44444 0.15 0.15 0.15 0.15 26.66667 6.667

    BALOK 15 x 30BESI 10 33.33333 4 133.3333 82.2BESI 8 0.65 334.3333 217.3167 85.74446

    167.9445

  • BEKISTING 33.33333 0.15 0.15 0.2 0.2 23.33333 5.833333

    BALOK 15 x 20BESI 10 33.33333 4 133.3333 118.368BESI 8 0.75 223.2222 167.4167 66.05592

    184.4239BEKISTING 33.33333 0.15 0.15 0.2 0.2 23.33333 11.66667

    BALOK 15 x 20BESI 10 33.33333 4 133.3333 118.368BESI 10 33.33333 2 66.66667 41.1BESI 8 0.75 223.2222 167.4167 66.05592

    225.5239BEKISTING 33.33333 0.15 0.15 0.2 0.2 23.33333 5.833333

    BALOK 15 x 15BESI 10 44.44444 4 177.7778 157.824BESI 8 0.65 297.2963 193.2426 76.2458

    234.0698BEKISTING 44.44444 0.15 0.15 0.15 0.15 26.66667 6.666667

    PRAKTIS 12/12BESI 10 69.44444 4 277.7778 171.25BESI 8 0.53 463.963 245.9004 97.02245

    268.2725BEKISTING 69.44444 0.12 0.12 0.12 0.12 33.33333 16.66667

    BESI 12 26.66667 6 160 142.0416BESI 8 0.85 178.7778 151.9611 59.95778

    201.9994BEKISTING 26.66667 0.15 0.15 0.25 0.25 21.33333 10.66667

    RING BALOKBESI 12 60.60606 4 242.4242 215.2145BESI 8 0.65 405.0404 263.2763 103.8783

    319.0928BEKISTING 60.60606 0.12 0.11 0.15 0.15 32.12121 8.030303

    BALOK LATEI 12 x 12BESI 12 69.44444 4 277.7778 171.25BESI 8 0.49 695.4444 340.7678 134.4533

    4.430483BEKISTING 69.44444 0.12 0.12 0.12 0.12 33.33333 0.483092

    BALOK LATEI 1,8 x 1BESI 12 0.555556 4 2.222222 1.37BESI 8 0.49 6.555556 3.212222 1.267414

    4.747346

  • BEKISTING 0.555556 1.8 1.8 1 1 0.388889 0.7

    BALOK LATEI 12 x 12BESI 12 55.55556 4 222.2222 137BESI 8 0.49 556.5556 272.7122 107.6013

    4.402824BEKISTING 55.55556 0.12 0.12 0.12 0.12 26.66667 0.48

    RING BALOK 15 x 15BESI 12 44.44444 5 222.2222 197.28BESI 8 0.61 297.2963 181.3507 71.55375

    268.8337BEKISTING 44.44444 0.12 0.12 0.12 0.12 21.33333 10.66667

  • 0.48

  • 0.48

    0.48

  • DAFTAR HARGA SATUAN BAHANPEKERJAAN : PEMBANGUNAN LABORATORIUM IPA

    SEKOLAH MENENGAH PERTAMASEKOLAH : SMP NEGERI BOLAANG ITANG BARATTAHUN ANGGARAN : 2011LOKASI : KEC. BOLAANG ITANG BARAT KAB. BOLAANG MONGONDOW UTARA

    NO. U R A I A N SATUAN KET.

    1. Kayu Klas II M3 2,000,000.00 2. Kayu Kls. III M3 1,850,000.00 3. Kayu Terentang M3 1,850,000.00 4. Balok Kayu Borneo M3 1,850,000.00 5. Dolken Kayu Galam 8 - 10/4 m Btg 25,000.00 6. Kayu Kamper, Papan M3 2,000,000.00 7. Batu Belah / Batu Gunung M3 120,000.00 8. Batu Bata Bh 600.00 9. Koral Beton M3 85,000.00

    10. Pasir Pasang M3 100,000.00 11. Pasir Beton M3 100,000.00 12. Pasir Urug M3 80,000.00 13. Tanah Urug M3 40,000.00 14. Semen Kg 1,250.00 15. Semen Warna Kg 3,500.00 16. Keramik 40 x 40 Dos 9,600.00 6.25 17. Keramik 30 x 30 Dos 4,050.00 11.11 18. Besi Beton Kg 9,000.00 19. Kawat Beton Kg 17,000.00 20. Besi Strip Kg 12,500.00 21. Minyak Bekisting Lt 17,500.00 22. Genteng Metal Lbr 35,000.00 23. Nok Genteng Metal Bh 15,000.00 24. Seng Gelombang Lbr 40,000.00 25. Seng Plat Lbr 60,000.00 26. Tripleks 4 mm Lbr 42,500.00 27. Plywood Tebal 9 mm Lbr 75,000.00 28. Kaca 5 mm M2 60,000.00 29. Kayu Profil M' 4,500.00 30. Paku Biasa 2" - 5" Kg 17,000.00 31. Paku Biasa 1/2' - 1 " Kg 17,000.00 32. Paku Tripleks Kg 22,500.00 33. Paku Seng Kg 22,500.00

    FILE SAMPEL JASA DOKUMEN TENDER ONLINE DI : http://dokumentender.blogspot.com/ *** File Ini Tidak

    Dapat Di Edit

    HARGA SATUAN

    (Rp.)

  • 34. Kunci Tanam Biasa Bh 70,000.00 35. Engsel Pintu Bh 17,500.00 36. Engsel Jendela Bh 12,500.00 37. Grendel Bh 7,500.00 38. Kait Angin Bh 8,000.00

  • NO. U R A I A N SATUAN KET.

    39. Cat Meni Kg 32,500.00 40. Plamir Kg 10,000.00 41. Cat Dinding Dasar Kg 9,000.00 42. Cat Dinding Penutup Kg 12,500.00 43. Cat Kayu Dasar Kg 21,000.00 44. Cat Kayu Penutup Kg 32,500.00 45. Cat Atap Seng Kg 32,500.00 46. Kawat NYYM 3 x 2.5 mm M' 5,500.00 47. Pipa Instalasi 1/2" Ujg 12,000.00 48. Klem PVC 1/2" Lot 2,500.00 49. T.Dos PVC Bh 1,500.00 50. Bok PVC Bh 1,500.00 51. Isolatip Bh 8,000.00 52. Stop Kontak 200 VA ex Broco Bh 22,500.00 53. Lampu SL 18 Watt Bh 45,000.00 54. Saklar Tunggal Bh 15,000.00 55. Saklar Ganda Bh 25,000.00 56. Meja Serbaguna Bh 750,000.00 57. Meja Kursi Bh 600,000.00 58. Meja Demonstrasi Bh 800,000.00 59. Kursi Siswa Bh 300,000.00 60. Kursi Bunder Tinggi Bh 450,000.00 61. Kursi Kerja Bh 400,000.00 62. Lemari Kaca Geser Bh 1,750,000.00 63. Lemari Alat Peraga Bh 1,350,000.00 64. Lemari Kertas Kerja Bh 1,000,000.00 65. Lemari Gantung P3K Bh 950,000.00 66. Lemari Asam Bh 900,000.00 67. Papan Tulis Gantung Bh 200,000.00 68. Kotak Sampah Bh 75,000.00

    Boroko, 04 Oktober 2011 -

    Mengetahui, Dibuat Oleh, KONTRAKTOR PELAKSANA KONTRAKTOR PELAKSANA

    xxxxxxxxxxxxxx xxxxxxxxxxxxxx

    xxxxxxxxxxxxx xxxxxxxxxxxxxxxDirektur Pimpinan Teknik

    HARGA SATUAN

    (Rp.)

  • DAFTAR HARGA SATUAN UPAH

    PEKERJAAN : PEMBANGUNAN LABORATORIUM IPA SEKOLAH MENENGAH PERTAMA

    SEKOLAH : SMP NEGERI BOLAANG ITANG BARATTAHUN ANGGARAN : 2011LOKASI : KEC. BOLAANG ITANG BARAT KAB. BOLAANG MONGONDOW UTARA

    NO. U R A I A N SATUAN KET.

    1 Pekerja O/H 50,000.00 7,142.86 / Jam

    2 Tukang O/H 60,000.00 8,571.43 / Jam

    3 Kepala Tukang O/H 75,000.00 ### / Jam

    4 Mandor O/H 55,000.00 7,857.14 / Jam

    Boroko, 04 Oktober 2011

    Mengetahui, Dibuat Oleh,KONTRAKTOR PELAKSANA KONTRAKTOR PELAKSANA

    xxxxxxxxxxxxxx xxxxxxxxxxxxxx

    xxxxxxxxxxxxx xxxxxxxxxxxxxxxDirektur Pimpinan Teknik

    HARGA

    (Rp.)

  • DAFTAR HARGA SATUAN PERALATAN

    PEKERJAAN : PEMBANGUNAN LABORATORIUM IPA SEKOLAH MENENGAH PERTAMA

    SEKOLAH : SMP NEGERI BOLAANG ITANG BARATTAHUN ANGGARAN : 2011LOKASI : KEC. BOLAANG ITANG BARAT KAB. BOLAANG MONGONDOW UTARA

    NO. U R A I A N SATUAN KET.

    1 Beton Mollen Hari 250,000.00

    2 Dump Truck Hari 450,000.00

    3 Stamper Hari 100,000.00

    Boroko, 04 Oktober 2011

    Mengetahui, Dibuat Oleh,KONTRAKTOR PELAKSANA KONTRAKTOR PELAKSANA

    xxxxxxxxxxxxxx xxxxxxxxxxxxxx

    xxxxxxxxxxxxx xxxxxxxxxxxxxxxDirektur Pimpinan Teknik

    HARGA

    (Rp.)

  • DAFTAR ANALISA

    PEKERJAAN : PEMBANGUNAN LABORATORIUM IPA SEKOLAH MENENGAH PERTAMA

    SEKOLAH : SMP NEGERI BOLAANG ITANG BARATTAHUN ANGGARAN : 2011LOKASI : KEC. BOLAANG ITANG BARAT KAB. BOLAANG MONGONDOW UTARA

    NO URAIAN PEKERJAAN SAT HARGA JUMLAH

    PEKERJAAN TANAH

    Galian Tanah Satuan : M3Tenaga

    - Pekerja 0.400 Oh 50,000.00 20,000.00 - Tukang - Oh - - Kepala Tukang - Oh - - Mandor 0.040 Oh 55,000.00 2,200.00

    Jumlah Harga Satuan Bahan + Upah 22,200.00 Total 22,200.00

    Urugan Tanah Kembali Satuan : M3Tenaga

    - Pekerja 0.192 Oh 50,000.00 9,600.00 - Tukang - Oh - - Kepala Tukang - Oh - - Mandor 0.019 Oh 55,000.00 1,045.00

    Jumlah Harga Satuan Bahan + Upah 10,645.00 Total 10,645.00

    Urugan Tanah Satuan : M3Bahan

    - Tanah Urug 1.200 M3 40,000.00 48,000.00 Tenaga -

    - Pekerja 0.250 Oh 50,000.00 12,500.00 - Tukang - Oh - - Kepala Tukang - Oh - - Mandor 0.025 Oh 55,000.00 1,375.00

    Jumlah Harga Satuan Bahan + Upah 61,875.00 Total 61,875.00

    Urugan Pasir Satuan : M3Bahan

    - Pasir Urug 1.200 M3 80,000.00 96,000.00 Tenaga -

    - Pekerja 0.300 Oh 50,000.00 15,000.00 - Tukang - Oh - - Kepala Tukang - Oh - - Mandor 0.010 Oh 55,000.00 550.00

    Jumlah Harga Satuan Bahan + Upah 111,550.00

    FILE SAMPEL JASA DOKUMEN TENDER ONLINE DI : http://dokumentender.blogspot.com/ *** File Ini

    Tidak Dapat Di Edit

    KOEFISIEN

  • Total 111,550.00

  • PEKERJAAN PONDASI

    Pas. Pondasi Batu Kali 1 Pc : 5 Ps Satuan : M3Bahan

    - Batu Belah 15/20 1.100 M3 120,000.00 132,000.00 - Semen Portland 136.000 Kg 1,250.00 170,000.00 - Pasir Pasang 0.544 M3 100,000.00 54,400.00

    Tenaga - - Pekerja 1.500 Oh 50,000.00 75,000.00 - Tukang 1.600 Oh 60,000.00 96,000.00 - Kepala Tukang 0.060 Oh 75,000.00 4,500.00 - Mandor 0.075 Oh 55,000.00 4,125.00

    Jumlah Harga Satuan Bahan + Upah 536,025.00 Total 536,025.00

    Pas. Pondasi Batu Kosong Satuan : M3Bahan

    - Batu Belah 15/20 1.200 M3 120,000.00 144,000.00 - Pasir Urug 0.300 M3 80,000.00 24,000.00

    Tenaga - - Pekerja 0.780 Oh 50,000.00 39,000.00 - Tukang 0.390 Oh 60,000.00 23,400.00 - Kepala Tukang 0.039 Oh 75,000.00 2,925.00 - Mandor 0.039 Oh 55,000.00 2,145.00

    Jumlah Harga Satuan Bahan + Upah 235,470.00 Total 235,470.00

    PEKERJAAN BETON

    Cor Beton Bertulang 1 Pc : 2 Ps : 3 Kr Satuan : M3Bahan

    - Semen Portland 232.000 Kg 1,250.00 290,000.00 - Pasir Beton 0.520 M3 100,000.00 52,000.00 - Koral Beton 0.780 M3 85,000.00 66,300.00

    Tenaga - - Pekerja 1.650 Oh 50,000.00 82,500.00 - Tukang 0.250 Oh 60,000.00 15,000.00 - Kepala Tukang 0.025 Oh 75,000.00 1,875.00 - Mandor 0.080 Oh 55,000.00 4,400.00

    Jumlah Harga Satuan Bahan + Upah 512,075.00 Total 512,075.00

    Cor Beton Tumbuk 1 Pc : 3 Ps : 5 Kr Satuan : M3Bahan

    - Semen Portland 218.000 Kg 1,250.00 272,500.00 - Pasir Beton 0.520 M3 100,000.00 52,000.00 - Koral Beton 0.870 M3 85,000.00 73,950.00

    Tenaga - - Pekerja 1.650 Oh 50,000.00 82,500.00 - Tukang 0.250 Oh 60,000.00 15,000.00 - Kepala Tukang 0.025 Oh 75,000.00 1,875.00 - Mandor 0.080 Oh 55,000.00 4,400.00

    Jumlah Harga Satuan Bahan + Upah 502,225.00 Total 502,225.00

  • Pembesian Dengan Besi Polos atau Besi Ulir Satuan : KgBahan

    - Besi Beton (polos/ulir) 1.050 Kg 9,000.00 9,450.00 - Kawat Beton 0.015 Kg 17,000.00 255.00

    Tenaga - - Pekerja 0.007 Oh 50,000.00 350.00 - Tukang 0.007 Oh 60,000.00 420.00 - Kepala Tukang 0.0007 Oh 75,000.00 52.50 - Mandor 0.0003 Oh 55,000.00 16.50

    Jumlah Harga Satuan Bahan + Upah 10,544.00 Total 10,544.00

    Pasangan Bekisting Untuk Sloof Satuan : M2Bahan

    - Kayu Terentang 0.045 M3 1,850,000.00 83,250.00 - Paku Biasa 2" - 5" 0.300 Kg 17,000.00 5,100.00 - Minyak Bekisting 0.100 Lt 17,500.00 1,750.00

    Tenaga - - Pekerja 0.300 Oh 50,000.00 15,000.00 - Tukang 0.260 Oh 60,000.00 15,600.00 - Kepala Tukang 0.026 Oh 75,000.00 1,950.00 - Mandor 0.005 Oh 55,000.00 275.00

    Jumlah Harga Satuan Bahan + Upah 122,925.00 Total 122,925.00

    Pasangan Bekisting Untuk Kolom Satuan : M2Bahan

    - Kayu Terentang 0.040 M3 1,850,000.00 74,000.00 - Paku Biasa 2" - 5" 0.400 Kg 17,000.00 6,800.00 - Minyak Bekisting 0.200 Lt 17,500.00 3,500.00 - Balok Kayu Borneo 0.015 M3 1,850,000.00 27,750.00 - Plywood Tebal 9 mm 0.350 Lbr 75,000.00 26,250.00 - 2.000 Btg 25,000.00 50,000.00

    Tenaga - - Pekerja 0.300 Oh 50,000.00 15,000.00 - Tukang 0.330 Oh 60,000.00 19,800.00 - Kepala Tukang 0.033 Oh 75,000.00 2,475.00 - Mandor 0.006 Oh 55,000.00 330.00

    Jumlah Harga Satuan Bahan + Upah 225,905.00 Total 225,905.00

    Pasangan Bekisting Untuk Balok Satuan : M2Bahan

    - Kayu Terentang 0.040 M3 1,850,000.00 74,000.00 - Paku Biasa 2" - 5" 0.400 Kg 17,000.00 6,800.00 - Minyak Bekisting 0.200 Lt 17,500.00 3,500.00 - Balok Kayu Borneo 0.018 M3 1,850,000.00 33,300.00 - Plywood Tebal 9 mm 0.350 Lbr 75,000.00 26,250.00 - 2.000 Btg 25,000.00 50,000.00

    Tenaga - - Pekerja 0.320 Oh 50,000.00 16,000.00 - Tukang 0.330 Oh 60,000.00 19,800.00 - Kepala Tukang 0.033 Oh 75,000.00 2,475.00 - Mandor 0.006 Oh 55,000.00 330.00

    Jumlah Harga Satuan Bahan + Upah 232,455.00 Total 232,455.00

    Dolken Kayu Galam 8 - 10/4 m

    Dolken Kayu Galam 8 - 10/4 m

  • Pek. Cor Beton Bertulang Sloof 20/25 Satuan : M3

    Cor Beton Bertulang 1 Pc : 2 Ps : 3 Kr 1.000 M3 512,075.00 512,075.00 Pembesian Dengan Besi Polos atau Besi 156.884 Kg 10,544.00 1,654,184.90 Pasangan Bekisting Untuk Sloof 4.500 M2 122,925.00 553,162.50

    Total 2,719,422.40

    Pek. Cor Beton Bertulang Sloof 15/12 Satuan : M3

    Cor Beton Bertulang 1 Pc : 2 Ps : 3 Kr 1.000 M3 512,075.00 512,075.00 Pembesian Dengan Besi Polos atau Besi 283.732 Kg 10,544.00 2,991,670.21 Pasangan Bekisting Untuk Sloof 7.500 M2 122,925.00 921,937.50

    Total 4,425,682.71

    Pek. Cor Beton Bertulang Kolom 20/25 Satuan : M3

    Cor Beton Bertulang 1 Pc : 2 Ps : 3 Kr 1.000 M3 512,075.00 512,075.00 Pembesian Dengan Besi Polos atau Besi 156.884 Kg 10,544.00 1,654,184.90 Pasangan Bekisting Untuk Kolom 4.500 M2 225,905.00 1,016,572.50

    Total 3,182,832.40

    Pek. Cor Beton Bertulang Kolom 15/15 Satuan : M3

    Cor Beton Bertulang 1 Pc : 2 Ps : 3 Kr 1.000 M3 512,075.00 512,075.00 Pembesian Dengan Besi Polos atau Besi 227.032 Kg 10,544.00 2,393,825.41 Pasangan Bekisting Untuk Kolom 6.667 M2 225,905.00 1,506,108.64

    Total 4,412,009.04

    Pek. Cor Beton Bertulang Ringbalk 15/12 Satuan : M3

    Cor Beton Bertulang 1 Pc : 2 Ps : 3 Kr 1.000 M3 512,075.00 512,075.00 Pembesian Dengan Besi Polos atau Besi 283.732 Kg 10,544.00 2,991,670.21 Pasangan Bekisting Untuk Balok 7.500 M2 232,455.00 1,743,412.50

    Total 5,247,157.71

    Pek. Cor Beton Bertulang Meja Lab tebal 10 cm Satuan : M3

    Cor Beton Bertulang 1 Pc : 2 Ps : 3 Kr 1.000 M3 512,075.00 512,075.00 Pembesian Dengan Besi Polos atau Besi 150.000 Kg 10,544.00 1,581,600.00 Pasangan Bekisting Untuk Balok 10.000 M2 232,455.00 2,324,550.00

    Total 4,418,225.00

  • Pasang Batu Merah Tebal 1/2 Bata 1 Pc : 3 Ps Satuan : M2Bahan

    - Bata Merah 5 x 11 x 22 70.000 Bh 600.00 42,000.00 - Semen Portland 14.370 Kg 1,250.00 17,962.50 - Pasir Pasang 0.040 M3 100,000.00 4,000.00

    Tenaga - - Pekerja 0.320 Oh 50,000.00 16,000.00 - Tukang 0.100 Oh 60,000.00 6,000.00 - Kepala Tukang 0.010 Oh 75,000.00 750.00 - Mandor 0.015 Oh 55,000.00 825.00

    Jumlah Harga Satuan Bahan + Upah 87,537.50 Total 87,537.50

    Pasang Batu Merah Tebal 1/2 Bata 1 Pc : 5 Ps Satuan : M2Bahan

    - Bata Merah 5 x 11 x 22 70.000 Bh 600.00 42,000.00 - Semen Portland 9.680 Kg 1,250.00 12,100.00 - Pasir Pasang 0.045 M3 100,000.00 4,500.00

    Tenaga - - - Pekerja 0.320 Oh 50,000.00 16,000.00 - Tukang 0.100 Oh 60,000.00 6,000.00 - Kepala Tukang 0.010 Oh 75,000.00 750.00 - Mandor 0.015 Oh 55,000.00 825.00

    Jumlah Harga Satuan Bahan + Upah 82,175.00 Total 82,175.00

    Plesteran 1 Pc : 3 Ps, tebal 15 mm Satuan : M2Bahan

    - Semen Portland 6.480 Kg 1,250.00 8,100.00 - Pasir Pasang 0.019 M3 100,000.00 1,900.00

    Tenaga - - Pekerja 0.200 Oh 50,000.00 10,000.00 - Tukang 0.150 Oh 60,000.00 9,000.00 - Kepala Tukang 0.015 Oh 75,000.00 1,125.00 - Mandor 0.010 Oh 55,000.00 550.00

    Jumlah Harga Satuan Bahan + Upah 30,675.00 Total 30,675.00

    Plesteran 1 Pc : 5 Ps, tebal 15 mm Satuan : M2Bahan

    - Semen Portland 4.320 Kg 1,250.00 5,400.00 - Pasir Pasang 0.022 M3 100,000.00 2,200.00

    Tenaga - - - Pekerja 0.200 Oh 50,000.00 10,000.00 - Tukang 0.150 Oh 60,000.00 9,000.00 - Kepala Tukang 0.015 Oh 75,000.00 1,125.00 - Mandor 0.010 Oh 55,000.00 550.00

    Jumlah Harga Satuan Bahan + Upah 28,275.00 Total 28,275.00

  • Acian Semen Satuan : M2Bahan

    - Semen Portland 2.250 Kg 1,250.00 2,812.5 Tenaga -

    - Pekerja 0.150 Oh 50,000.00 7,500.0 - Tukang 0.050 Oh 60,000.00 3,000.0 - Kepala Tukang 0.005 Oh 75,000.00 375.0 - Mandor 0.0075 Oh 55,000.00 412.5

    Jumlah Harga Satuan Bahan + Upah 14,100.0 Total 14,100.0

    PEKERJAAN KUNCI DAN KACA

    Pas. Kunci Tanam Biasa Satuan : BhBahan

    - Kunci Tanam Biasa 1.000 Bh 70,000.00 70,000.00 Tenaga -

    - Pekerja 0.015 Oh 50,000.00 750.00 - Tukang 0.150 Oh 60,000.00 9,000.00 - Kepala Tukang 0.015 Oh 75,000.00 1,125.00 - Mandor 0.001 Oh 55,000.00 55.00

    Jumlah Harga Satuan Bahan + Upah 80,930.00 Total 80,930.00

    Pas. Engsel Pintu Satuan : BhBahan

    - Engsel Pintu 1.000 Bh 17,500.00 17,500.00 Tenaga -

    - Pekerja 0.015 Oh 50,000.00 750.00 - Tukang 0.150 Oh 60,000.00 9,000.00 - Kepala Tukang 0.015 Oh 75,000.00 1,125.00 - Mandor 0.001 Oh 55,000.00 55.00

    Jumlah Harga Satuan Bahan + Upah 28,430.00 Total 28,430.00

    Pas. Engsel Jendela Kupu-kupu Satuan : BhBahan

    - Engsel Jendela 1.000 Bh 12,500.00 12,500.00 Tenaga -

    - Pekerja 0.010 Oh 50,000.00 500.00 - Tukang 0.100 Oh 60,000.00 6,000.00 - Kepala Tukang 0.010 Oh 75,000.00 750.00 - Mandor 0.001 Oh 55,000.00 55.00

    Jumlah Harga Satuan Bahan + Upah 19,805.00 Total 19,805.00

    Pas. Grendel Satuan : BhBahan

    - Grendel 1.000 Bh 7,500.00 7,500.00 Tenaga -

    - Pekerja 0.015 Oh 50,000.00 750.00 - Tukang 0.150 Oh 60,000.00 9,000.00 - Kepala Tukang 0.015 Oh 75,000.00 1,125.00 - Mandor 0.001 Oh 55,000.00 55.00

    Jumlah Harga Satuan Bahan + Upah 18,430.00 Total 18,430.00

  • Pas. Kait Angin Satuan : BhBahan

    - Kait Angin 1.000 Bh 8,000.00 8,000.00 Tenaga -

    - Pekerja 0.015 Oh 50,000.00 750.00 - Tukang 0.150 Oh 60,000.00 9,000.00 - Kepala Tukang 0.015 Oh 75,000.00 1,125.00 - Mandor 0.001 Oh 55,000.00 55.00

    Jumlah Harga Satuan Bahan + Upah 18,930.00 Total 18,930.00

    Pas. Kaca, tebal 5 mm Satuan : M2Bahan

    - Kaca 5 mm 1.100 M2 60,000.00 66,000.00 Tenaga -

    - Pekerja 0.015 Oh 50,000.00 750.00 - Tukang 0.150 Oh 60,000.00 9,000.00 - Kepala Tukang 0.015 Oh 75,000.00 1,125.00 - Mandor 0.001 Oh 55,000.00 55.00

    Jumlah Harga Satuan Bahan + Upah 76,930.00 Total 76,930.00

    PEKERJAAN PENUTUP LANTAI DAN DINDING

    Pas. Lantai Keramik ukuran 40 x40 cm Satuan : M2Bahan

    - Keramik 40 x 40 cm 6.930 Bh 9,600.00 66,528.00 - Semen Portland 9.800 Kg 1,250.00 12,250.00 - Pasir Pasang 0.022 M3 100,000.00 2,200.00 - Semen Warna 1.300 Kg 3,500.00 4,550.00

    Tenaga - - Pekerja 0.250 Oh 50,000.00 12,500.00 - Tukang 0.120 Oh 60,000.00 7,200.00 - Kepala Tukang 0.001 Oh 75,000.00 75.00 - Mandor 0.013 Oh 55,000.00 715.00

    Jumlah Harga Satuan Bahan + Upah 106,018.00 Total 106,018.00

    Pas. Lantai Keramik 30 x 30 cm Satuan : M2Bahan

    - Keramik 30 x 30 cm 11.870 Bh 4,050.00 48,073.50 - Semen Portland 10.000 Kg 1,250.00 12,500.00 - Pasir Pasang 0.022 M3 100,000.00 2,200.00 - Semen Warna 1.500 Kg 3,500.00 5,250.00

    Tenaga - - - Pekerja 0.260 Oh 50,000.00 13,000.00 - Tukang 0.125 Oh 60,000.00 7,500.00 - Kepala Tukang 0.001 Oh 75,000.00 75.00 - Mandor 0.013 Oh 55,000.00 715.00

    Jumlah Harga Satuan Bahan + Upah 89,313.50 Total 89,313.50

  • PEKERJAAN KAYU

    Pas. Kusen Pintu & Jendela Satuan : M3Bahan

    - Kayu Kls. II 1.200 M3 2,000,000.00 2,400,000.00 Tenaga -

    - Pekerja 6.000 Oh 50,000.00 300,000.00 - Tukang 18.000 Oh 60,000.00 1,080,000.00 - Kepala Tukang 2.000 Oh 75,000.00 150,000.00 - Mandor 0.300 Oh 55,000.00 16,500.00

    Jumlah Harga Satuan Bahan + Upah 3,946,500.00 Total 3,946,500.00

    Pas. Pintu Panel Satuan : M2Bahan

    - Kayu Kls. II 0.040 M3 2,000,000.00 80,000.00 Tenaga -

    - Pekerja 1.000 Oh 50,000.00 50,000.00 - Tukang 2.500 Oh 60,000.00 150,000.00 - Kepala Tukang 0.250 Oh 75,000.00 18,750.00 - Mandor 0.050 Oh 55,000.00 2,750.00

    Jumlah Harga Satuan Bahan + Upah 301,500.00 Total 301,500.00

    Pas. Pintu & Jendela Kaca Kayu klas. II Satuan : M2Bahan

    - Kayu Kls. II 0.035 M3 2,000,000.00 70,000.00 Tenaga -

    - Pekerja 0.800 Oh 50,000.00 40,000.00 - Tukang 2.000 Oh 60,000.00 120,000.00 - Kepala Tukang 0.200 Oh 75,000.00 15,000.00 - Mandor 0.040 Oh 55,000.00 2,200.00

    Jumlah Harga Satuan Bahan + Upah 247,200.00 Total 247,200.00

    Pas. Konstruksi Kida-Kuda Kayu Kls. II Satuan : M3Bahan

    - Kayu Kls. II 1.100 M3 2,000,000.00 2,200,000.00 - Besi Strip 15.000 Kg 12,500.00 187,500.00 - Paku Biasa 2" - 5" 0.800 Kg 17,000.00 13,600.00

    Tenaga - - Pekerja 4.000 Oh 50,000.00 200,000.00 - Tukang 12.000 Oh 60,000.00 720,000.00 - Kepala Tukang 1.200 Oh 75,000.00 90,000.00 - Mandor 0.200 Oh 55,000.00 11,000.00

    Jumlah Harga Satuan Bahan + Upah 3,422,100.00 Total 3,422,100.00

    Pas. Gording Satuan : M3Bahan

    - Kayu Kls. II 1.100 M3 2,000,000.00 2,200,000.00 - Paku Biasa 2" - 5" 3.000 Kg 17,000.00 51,000.00

    Tenaga - - Pekerja 2.400 Oh 50,000.00 120,000.00 - Tukang 7.200 Oh 60,000.00 432,000.00 - Kepala Tukang 0.720 Oh 75,000.00 54,000.00 - Mandor 0.120 Oh 55,000.00 6,600.00

    Jumlah Harga Satuan Bahan + Upah 2,863,600.00 Total 2,863,600.00

  • Pas. Kaso + Reng Satuan : M2Bahan

    - Kayu Kls. II 0.012 M3 2,000,000.00 24,000.00 - Paku Biasa 2" - 5" 0.150 Kg 17,000.00 2,550.00

    Tenaga - - Pekerja 0.100 Oh 50,000.00 5,000.00 - Tukang 0.100 Oh 60,000.00 6,000.00 - Kepala Tukang 0.010 Oh 75,000.00 750.00 - Mandor 0.005 Oh 55,000.00 275.00

    Jumlah Harga Satuan Bahan + Upah 38,575.00 Total 38,575.00

    Pas. Lisplang Kayu Satuan : M1Bahan

    - Kayu Kls. III 0.009 M3 1,850,000.00 16,650.00 - Paku Biasa 2" - 5" 0.060 Kg 17,000.00 1,020.00

    Tenaga - - Pekerja 0.100 Oh 50,000.00 5,000.00 - Tukang 0.100 Oh 60,000.00 6,000.00 - Kepala Tukang 0.010 Oh 75,000.00 750.00 - Mandor 0.005 Oh 55,000.00 275.00

    Jumlah Harga Satuan Bahan + Upah 29,695.00 Total 29,695.00

    Pas. List Plafond Kayu Profil Satuan : M1Bahan

    - List Kayu Profil 1.100 M' 4,500.00 4,950.00 - Paku Biasa 2" - 5" 0.010 Kg 17,000.00 170.00

    Tenaga - - Pekerja 0.050 Oh 50,000.00 2,500.00 - Tukang 0.050 Oh 60,000.00 3,000.00 - Kepala Tukang 0.005 Oh 75,000.00 375.00 - Mandor 0.003 Oh 55,000.00 165.00

    Jumlah Harga Satuan Bahan + Upah 11,160.00 Total 11,160.00

    Pas. Jalusi Kaca Mati Kusen Kayu Kamper Satuan : M2Bahan

    - Kayu Kamper, Papan 0.060 M3 2,000,000.00 120,000.00 - Paku Biasa 1/2' - 1 " 0.150 Kg 17,000.00 2,550.00

    Tenaga - - Pekerja 0.500 Oh 50,000.00 25,000.00 - Tukang 2.000 Oh 60,000.00 120,000.00 - Kepala Tukang 0.200 Oh 75,000.00 15,000.00 - Mandor 0.025 Oh 55,000.00 1,375.00

    Jumlah Harga Satuan Bahan + Upah 283,925.00 Total 283,925.00

  • PEKERJAAN PENUTUP ATAP

    Pas. Atap Genteng Metal Satuan : M2Bahan

    - Genteng Metal 1.020 Lbr 35,000.00 35,700.00 - Paku Seng 0.200 Kg 22,500.00 4,500.00

    Tenaga - - Pekerja 0.200 Oh 50,000.00 10,000.00 - Tukang 0.100 Oh 60,000.00 6,000.00 - Kepala Tukang 0.010 Oh 75,000.00 750.00 - Mandor 0.001 Oh 55,000.00 55.00

    Jumlah Harga Satuan Bahan + Upah 57,005.00 Total 57,005.00

    Pas. Nok Genteng Metal Satuan : M1Bahan

    - Nok Genteng Metal 1.100 Bh 15,000.00 16,500.00 - Paku Seng 0.050 Kg 22,500.00 1,125.00

    Tenaga - - Pekerja 0.250 Oh 50,000.00 12,500.00 - Tukang 0.150 Oh 60,000.00 9,000.00 - Kepala Tukang 0.015 Oh 75,000.00 1,125.00 - Mandor 0.010 Oh 55,000.00 550.00

    Jumlah Harga Satuan Bahan + Upah 40,800.00 Total 40,800.00

    Pas. Atap Seng Gelombang Satuan : M2Bahan

    - Seng Gelombang 3' x 6" Bjls 0.700 Lbr 40,000.00 28,000.00 - Paku Seng 0.020 Kg 22,500.00 450.00

    Tenaga - - Pekerja 0.120 Oh 50,000.00 6,000.00 - Tukang 0.060 Oh 60,000.00 3,600.00 - Kepala Tukang 0.006 Oh 75,000.00 450.00 - Mandor 0.006 Oh 55,000.00 330.00

    Jumlah Harga Satuan Bahan + Upah 38,830.00 Total 38,830.00

    Pas. Nok Seng Gelombang Satuan : M2Bahan

    - Seng Plat 3" x 6" Bjls 30 0.300 Lbr 60,000.00 18,000.00 - Paku Seng 0.040 Kg 22,500.00 900.00

    Tenaga - - Pekerja 0.150 Oh 50,000.00 7,500.00 - Tukang 0.070 Oh 60,000.00 4,200.00 - Kepala Tukang 0.008 Oh 75,000.00 600.00 - Mandor 0.006 Oh 55,000.00 330.00

    Jumlah Harga Satuan Bahan + Upah 31,530.00 Total 31,530.00

  • PEKERJAAN LANGIT-LANGIT

    Rangka Plafond Kayu Klas II Satuan : M2Bahan

    - Kayu Klas II 0.012 M3 2,000,000.00 24,000.00 - Paku 0.100 Kg 17,000.00 1,700.00

    Tenaga - - Pekerja 0.150 Oh 50,000.00 7,500.00 - Tukang 0.250 Oh 60,000.00 15,000.00 - Kepala Tukang 0.025 Oh 75,000.00 1,875.00 - Mandor 0.075 Oh 55,000.00 4,125.00

    Jumlah Harga Satuan Bahan + Upah 54,200.00 Total 54,200.00

    Plafond Tripleks (60x120) cm, tebal 4 mm Satuan : M2Bahan

    - Tripleks 4 mm 0.375 Lbr 42,500.00 15,937.50 - Paku 0.030 Kg 22,500.00 675.00

    Tenaga - - Pekerja 0.070 Oh 50,000.00 3,500.00 - Tukang 0.100 Oh 60,000.00 6,000.00 - Kepala Tukang 0.010 Oh 75,000.00 750.00 - Mandor 0.004 Oh 55,000.00 220.00

    Jumlah Harga Satuan Bahan + Upah 27,082.50 Total 27,082.50

    PEKERJAAN PENGECATAN

    Pengecatan Bidang Kayu Baru (1 lapis plamir 1 lapis cat dasar, Satuan : M2Bahan

    - Cat Meni 0.200 Kg 32,500.00 6,500.00 - Plamir 0.150 Kg 10,000.00 1,500.00 - Cat Dasar 0.170 Kg 21,000.00 3,570.00 - Cat Penutup 3 x 0.350 Kg 32,500.00 11,375.00

    Tenaga - - Pekerja 0.070 Oh 50,000.00 3,500.00 - Tukang 0.105 Oh 60,000.00 6,300.00 - Kepala Tukang 0.004 Oh 75,000.00 300.00 - Mandor 0.003 Oh 55,000.00 165.00

    Jumlah Harga Satuan Bahan + Upah 33,210.00 Total 33,210.00

    Pengecatan Atap Seng Satuan : M2Bahan

    - Cat Atap Seng 0.260 Kg 32,500.00 8,450.00 Tenaga -

    - Pekerja 0.070 Oh 50,000.00 3,500.00 - Tukang 0.009 Oh 60,000.00 540.00 - Kepala Tukang 0.006 Oh 75,000.00 450.00 - Mandor 0.003 Oh 55,000.00 165.00

    Jumlah Harga Satuan Bahan + Upah 13,105.00 Total 13,105.00

  • Pengecatan Tembok Baru (1 lapis plamir 1 lapis cat dasar, 2 la Satuan : M2Bahan

    - Plamir 0.200 Kg 10,000.00 2,000.00 - Cat Dasar 0.100 Kg 9,000.00 900.00 - Cat Penutup 3 x 0.260 Kg 12,500.00 3,250.00

    Tenaga - - Pekerja 0.070 Oh 50,000.00 3,500.00 - Tukang 0.009 Oh 60,000.00 540.00 - Kepala Tukang 0.006 Oh 75,000.00 450.00 - Mandor 0.003 Oh 55,000.00 165.00

    Jumlah Harga Satuan Bahan + Upah 10,805.00 Total 10,805.00

    PEKERJAAN SALURAN

    Pasangan Saluran Pinggir Bangunan Satuan : M1Bahan

    - Pas. Batu Bata 1 : 3 0.220 M2 87,537.50 19,258.25 - Plesteran 1 : 3 2.200 M2 30,675.00 67,485.00 - Pasir Urug 0.030 M3 111,550.00 3,346.50

    Tenaga - - Pekerja 0.120 Oh 50,000.00 6,000.00 - Tukang 0.250 Oh 60,000.00 15,000.00 - Kepala Tukang 0.049 Oh 75,000.00 3,675.00 - Mandor 0.012 Oh 55,000.00 660.00

    Jumlah Harga Satuan Bahan + Upah 115,424.75 Total 115,424.75

    PEKERJAAN INSTALASI LISTRIK

    Pemasangan Instalasi Titik Lampu & Stop Kontak Satuan : TtkBahan

    - Kawat NYYM 3 x 2.5 mm 12.0000 M' 5,500.00 66,000.00 - Pipa Instalasi 5/8" 2.0000 Ujg 12,000.00 24,000.00 - Klem PVC 1/2" 0.5000 Lot 2,500.00 1,250.00 - T.Dos PVC 4.0000 Bh 1,500.00 6,000.00 - Bok PVC 2.0000 Bh 1,500.00 3,000.00 - Isolatip 2.0000 Bh 8,000.00 16,000.00

    Tenaga - - Pekerja 0.070 Oh 50,000.00 3,500.00 - Tukang 0.750 Oh 60,000.00 45,000.00 - Kepala Tukang 0.400 Oh 75,000.00 30,000.00 - Mandor 0.002 Oh 55,000.00 110.00

    Jumlah Harga Satuan Bahan + Upah 194,860.00 Total 194,860.00

    Boroko, 04 Oktober 2011

    Mengetahui, Dibuat Oleh,KONTRAKTOR PELAKSANA KONTRAKTOR PELAKSANA

    xxxxxxxxxxxxxx xxxxxxxxxxxxxx

    xxxxxxxxxxxxx xxxxxxxxxxxxxxxDirektur Pimpinan Teknik

  • ANALISA TEKNIKPEKERJAAN : PEMBANGUNAN LABORATORIUM IPA

    0 SEKOLAH MENENGAH PERTAMASEKOLAH : SMP NEGERI BOLAANG ITANG BARATTAHUN ANGGARAN : 2011LOKASI : KEC. BOLAANG ITANG BARAT KAB. BOLAANG MONGONDOW UTARA

    * Pekerjaan Persiapan 7.00 Hari 1.00 Minggu

    * Galian Tanah Pondasi- Volume Pekerjaan = 29.64 - Tenaga yang dibutuhkan

    - Pekerja = 4.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 10.00

    - Waktu yang dibutuhkan 29.64 = 2.96 Hari 10.00

    - Dibulatkan = 2.96 Hari 0.42 Minggu

    * Urugan Tanah Kembali- Volume Pekerjaan = 8.89 - Tenaga yang dibutuhkan

    - Pekerja = 4.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 20.83

    - Waktu yang dibutuhkan 8.89 = 0.43 Hari 20.83

    - Dibulatkan = 0.43 Hari 0.06 Minggu

    * Urugan Pasir dibawah Pondasi dan Lantai- Volume Pekerjaan = 21.97 - Kebutuhan bahan

    - Pasir Urug = 26.36

    - Tenaga yang dibutuhkan

    - Pekerja = 4.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 13.33

    - Waktu yang dibutuhkan 21.97 = 1.65 Hari 13.33

    - Dibulatkan = 1.65 Hari 0.24 Minggu

    FILE SAMPEL JASA DOKUMEN TENDER ONLINE DI : http://dokumentender.blogspot.com/ *** File Ini

    Tidak Dapat Di Edit

    M3

    M3/ Hari

    M3

    M3/ Hari

    M3

    M3

    M3/ Hari

  • * Urugan Tanah- Volume Pekerjaan = 60.00 - Kebutuhan bahan

    - Tanah Urug = 72.00

    - Tenaga yang dibutuhkan

    - Pekerja = 4.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 16.00

    - Waktu yang dibutuhkan 60.00 = 3.75 Hari 16.00

    - Dibulatkan = 3.75 Hari 0.54 Minggu

    * Pasangan batu kosong- Volume Pekerjaan = 7.41 - Kebutuhan bahan

    - Batu Belah = 8.89 - Pasir Urug = 2.22

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 20.51

    - Waktu yang dibutuhkan 7.41 = 0.36 Hari 20.51

    - Dibulatkan = 0.36 Hari 0.05 Minggu

    * Pas. Pondasi Jalur Batu Kali camp. 1Pc : 5 Psr- Volume Pekerjaan = 39.67 - Kebutuhan bahan

    - Semen = 5,395.12 Kg- Pasir = 21.58 - Batu = 43.64

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 5.00

    - Waktu yang dibutuhkan 39.67 = 7.93 Hari 5.00

    - Dibulatkan = 7.93 Hari 1.13 Minggu

    M3

    M3

    M3/ Hari

    M3

    M3

    M3/ Hari

    M3

    M3M3

    M3/ Hari

  • * Pekerjaan Beton Bertulang- Volume Pekerjaan = 16.84 - Kebutuhan bahan

    - Semen Kg- Pasir- Kerikil- Besi Beton Kg- Kawat Beton- Kayu Bekisting Kg- Paku Lt- Minyak Bekisting

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 2.00

    - Waktu yang dibutuhkan 16.84 = 8.42 Hari 2.00

    - Dibulatkan = 8.42 Hari 1.20 Minggu

    * Pas. Tembok Batu Bata Trasram camp. 1 Pc : 3 Psr- Volume Pekerjaan = 10.76 M2- Kebutuhan bahan

    - Semen = 154.62 Kg- Pasir = 0.43 - Batu Bata = 753.20 Bh

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 80.00

    - Waktu yang dibutuhkan 10.76 = 0.13 Hari 80.00

    - Dibulatkan = 0.13 Hari 0.02 Minggu

    M3

    M3M3

    M3

    M3/ Hari

    M3

    M2/ Hari

  • * Pasang Tembok Batu Bata camp. 1 Pc : 5 Psr- Volume Pekerjaan = 183.80 - Kebutuhan bahan

    - Semen = 1,779.18 Kg- Pasir = 8.27 - Batu Bata = 12,866.00 Bh

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 80.00

    - Waktu yang dibutuhkan 183.80 = 2.30 Hari 80.00

    - Dibulatkan = 2.30 Hari 0.33 Minggu

    * Plesteran Tembok Trasram dan Beton camp. 1 Pc : 3 Psr- Volume Pekerjaan = 56.52 - Kebutuhan bahan

    - Semen = 366.25 Kg- Pasir = 1.07

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 53.33

    - Waktu yang dibutuhkan 56.52 = 1.06 Hari 53.33

    - Dibulatkan = 1.06 Hari 0.15 Minggu

    * Plesteran Tembok Biasa camp. 1 Pc : 5 Psr- Volume Pekerjaan = 367.60 - Kebutuhan bahan

    - Semen = 1,588.03 Kg- Pasir = 8.09

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 53.33

    - Waktu yang dibutuhkan 367.60 = 6.89 Hari 53.33

    - Dibulatkan = 6.89 Hari 0.98 Minggu

    M2

    M3

    M2/ Hari

    M2

    M3

    M2/ Hari

    M2

    M3

    M2/ Hari

  • * Acian Semen- Volume Pekerjaan = 424.12 - Kebutuhan bahan

    - Semen = 954.27 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 160.00

    - Waktu yang dibutuhkan 424.12 = 2.65 Hari 160.00

    - Dibulatkan = 2.65 Hari 0.38 Minggu

    * Pas. Keramik 40 x 40 cm untuk lantai bangunan- Volume Pekerjaan = 150.00 - Kebutuhan bahan

    - Semen = 1,470.00 Kg- Keramik = 1,039.50 Bh- Pasir Pasang = 3.30 M3- Semen Warna = 195.00 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 66.67

    - Waktu yang dibutuhkan 150.00 = 2.25 Hari 66.67

    - Dibulatkan = 2.25 Hari 0.32 Minggu

    * Pas. Kusen Pintu/Jendela Kayu Klas. II- Volume Pekerjaan = 1.06 - Kebutuhan bahan

    - Kayu Kls. II = 1.27

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 0.44

    - Waktu yang dibutuhkan 1.06 = 2.39 Hari 0.44

    - Dibulatkan = 2.39 Hari 0.34 Minggu

    M2

    M2/ Hari

    M2

    M2/ Hari

    M3

    M3

    M3/ Hari

  • * Pas. Daun Pintu Panil Kayu Klas. II- Volume Pekerjaan = 6.15 - Kebutuhan bahan

    - Kayu Kls. II = 0.25

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 3.20

    - Waktu yang dibutuhkan 6.15 = 1.92 Hari 3.20

    - Dibulatkan = 1.92 Hari 0.27 Minggu

    * Pas. Bingkai Daun Jendela- Volume Pekerjaan = 3.66 - Kebutuhan bahan

    - Kayu Kls. II = 0.13

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 4.00

    - Waktu yang dibutuhkan 3.66 = 0.92 Hari 4.00

    - Dibulatkan = 0.92 Hari 0.13 Minggu

    * Pas. Jalusi Ventilasi- Volume Pekerjaan = 9.73 - Kebutuhan bahan

    - Kayu Kamper, Papan = 0.58 - Paku Biasa 1/2' - 1 " = 1.46 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 4.00

    - Waktu yang dibutuhkan 9.73 = 2.43 Hari 4.00

    - Dibulatkan = 2.43 Hari 0.35 Minggu

    M2

    M3

    M2/ Hari

    M2

    M3

    M2/ Hari

    M2

    M3

    M2/ Hari

  • * Pas. Kaca 5 mm- Volume Pekerjaan = 9.90 - Kebutuhan bahan

    - Kaca 5 mm = 10.89

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 53.33

    - Waktu yang dibutuhkan 9.90 = 0.19 Hari 53.33

    - Dibulatkan = 0.19 Hari 0.03 Minggu

    * Pas. Kunci Tanam 2 Slaag Untuk Pintu Panil Kayu- Volume Pekerjaan = 3.00 Bh- Kebutuhan bahan

    - Kunci Tanam = 3.00 Bh

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 53.33

    - Waktu yang dibutuhkan 3.00 = 0.06 Hari 53.33

    - Dibulatkan = 0.06 Hari 0.01 Minggu

    * Pas. Engsel Pintu Panil Kayu @ Buah- Volume Pekerjaan = 12.00 Bh- Kebutuhan bahan

    - Engsel Pintu = 12.00 Bh

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 53.33

    - Waktu yang dibutuhkan 12.00 = 0.23 Hari 53.33

    - Dibulatkan = 0.23 Hari 0.03 Minggu

    M2

    M2

    M2/ Hari

    Bh/ Hari

    Bh/ Hari

  • * Pas. Engsel Jendela @ 2 Buah- Volume Pekerjaan = 34.00 Bh- Kebutuhan bahan

    - Engsel Jendela = 34.00 Bh

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 80.00

    - Waktu yang dibutuhkan 34.00 = 0.43 Hari 80.00

    - Dibulatkan = 0.43 Hari 0.06 Minggu

    * Pas. Grendel Jendela- Volume Pekerjaan = 17.00 Bh- Kebutuhan bahan

    - Grendel Jendela = 17.00 Bh

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 53.33

    - Waktu yang dibutuhkan 17.00 = 0.32 Hari 53.33

    - Dibulatkan = 0.32 Hari 0.05 Minggu

    * Pas. Kait Angin Jendela- Volume Pekerjaan = 34.00 Bh- Kebutuhan bahan

    - Kait Angin Jendela = 34.00 Bh

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 53.33

    - Waktu yang dibutuhkan 34.00 = 0.64 Hari 53.33

    - Dibulatkan = 0.64 Hari 0.09 Minggu

    Bh/ Hari

    Bh/ Hari

    Bh/ Hari

  • * Pek. Kuda-kuda & Rangka Atap Kayu Klas. II- Volume Pekerjaan = 1.81 - Kebutuhan bahan

    - Kayu Kls. II = 1.99 - Besi Strip = 27.15 Kg- Paku Biasa 2" - 5" = 1.45 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 0.67

    - Waktu yang dibutuhkan 1.81 = 2.72 Hari 0.67

    - Dibulatkan = 2.72 Hari 0.39 Minggu

    * Pek. Gording Kayu- Volume Pekerjaan = 2.34 - Kebutuhan bahan

    - Kayu Kls. II = 2.57 - Paku Biasa 2" - 5" = 7.02 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 1.11

    - Waktu yang dibutuhkan 2.34 = 2.11 Hari 1.11

    - Dibulatkan = 2.11 Hari 0.30 Minggu

    * Pek. Atap Genteng Metal- Volume Pekerjaan = 200.43 - Kebutuhan bahan

    - Genteng Metal = 204.44 Lbr- Paku Seng = 40.09 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 80.00

    - Waktu yang dibutuhkan 200.43 = 2.51 Hari 80.00

    - Dibulatkan = 2.51 Hari 0.36 Minggu

    M3

    M3

    M3/ Hari

    M3

    M3

    M3/ Hari

    M2

    M2/ Hari

  • * Pek. Nok Genteng Metal- Volume Pekerjaan = 42.90 M'- Kebutuhan bahan

    - Nok Genteng Metal = 47.19 Lbr- Paku Seng = 2.15 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 53.33

    - Waktu yang dibutuhkan 42.90 = 0.80 Hari 53.33

    - Dibulatkan = 0.80 Hari 0.11 Minggu

    * Pas. Rangka Plafond - Volume Pekerjaan = 204.00 - Kebutuhan bahan

    - Kayu Kls. II = 2.45 - Paku = 20.40 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 32.00

    - Waktu yang dibutuhkan 204.00 = 6.38 Hari 32.00

    - Dibulatkan = 6.38 Hari 0.91 Minggu

    * Pek. Profil Kayu- Volume Pekerjaan = 172.00 M'- Kebutuhan bahan

    - List Kayu Profil = 189.20 M'- Paku Biasa 2" - 5" = 1.72 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 160.00

    - Waktu yang dibutuhkan 172.00 = 1.08 Hari 160.00

    - Dibulatkan = 1.08 Hari 0.15 Minggu

    M'/ Hari

    M2

    M3

    M2/ Hari

    M2/ Hari

  • * Pas. Listplank Kayu- Volume Pekerjaan = 59.90 M'- Kebutuhan bahan

    - Kayu Kls III = 0.54 - Paku Biasa 2" - 5" = 3.59 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 80.00

    - Waktu yang dibutuhkan 59.90 = 0.75 Hari 80.00

    - Dibulatkan = 0.75 Hari 0.11 Minggu

    * Pek. Pengecatan Dinding dan Plafond- Volume Pekerjaan = 441.51 - Kebutuhan bahan

    - Plamir = 88.30 Kg- Cat Dasar = 44.15 Kg- Cat Penutup 3 x 114.79 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 60.00

    - Waktu yang dibutuhkan 441.51 = 7.36 Hari 60.00

    - Dibulatkan = 7.36 Hari 1.05 Minggu

    * Pek. Pengecatan Kusen, Daun Pintu Panil & Jendela- Volume Pekerjaan = 69.49 - Kebutuhan bahan

    - Cat Meni = 13.90 Kg- Plamir = 10.42 Kg- Cat Dasar = 11.81 Kg- Cat Penutup 3 x = 24.32 Kg

    - Tenaga yang dibutuhkan- Pekerja = 4.00 Org - Tukang = 8.00 Org - Kepala Tukang = 1.00 Org - Mandor = 1.00 Org

    - Kapasitas rata - rata 1 regu = 60.00

    - Waktu yang dibutuhkan 69.49 = 1.16 Hari 60.00

    - Dibulatkan = 1.16 Hari 0.17 Minggu

    M3

    M2/ Hari