Upload
immortalmarx
View
218
Download
0
Embed Size (px)
Citation preview
7/28/2019 Construction Contract Terminology
http://slidepdf.com/reader/full/construction-contract-terminology 1/6
Construction Contract Terminology
http://www.contract-laws.com/terminology.html#conflicts
Abandonment - Can have different meanings. One type of abandonment is contract abandonment,
where the parties both have conducted themselves in such a way that the original contract is nolonger valid. Both parties may mutually agree to do this, or it can become part of a claim.
Another type of abandonment is where a contractor fails to perform the work on a project by eithernot starting the project in a reasonable amount of time, or not completing the work, or failing toresume work in a reasonable amount of time. Abandonment of a construction project without legalexcuse is a cause for sidciplinary action under B&P sect.1707.
Arbitration a form of alternative dispute resolution (ADR), is for the resolution of disputes outside
the courts, where a third party reviews the case and imposes a decision that is legally binding for bothsides. Arbitration is most commonly used for the resolution of commercial disputes, particularly inconstruction disputes imposed by contract terms.
Arbitration can be either voluntary or mandatory and can be either binding or non-binding. Non-
binding arbitration is, on the surface, similar to mediation. However, the principal distinction is thatwhereas a mediator will try to help the parties find a middle ground on which to compromise, the(non-binding) arbitrator remains totally removed from the settlement process and will only give adetermination of liability and, if appropriate, an indication of the quantum of damages payable.
Bid Protests & Disputes - In public contracting, there are specific procedures dictated by
California Public Contract Code. to handle bid protests. The procedures are very specific as are thetimelines in which to formalize a protest. The procedure is often complicated.
Breach - One of the parties in a contract that does not fullfill their obligatory promise has breached.
There are different levels of breaches such as minor, material, fundamental, anticipatory. The reasons
can be where one of the parties makes it impossible for the other party perform their obligation, oneof the parties refuses to perform their obligations, one of the parties is unable to or will be unable toperform their obligation. Not every failure to perform amounts to a breach because there are anumber of excuses for non performance.
Bonds & Surety A lot of people like to sum up a surety bond as insurance, but in reality, surety
bonds are a financial guarantee. They are a part of the insurance industry but they serve as a financialguarantee for the obligee (or person requiring the bond).
Every contractor is required to get a bond in California. many projects require a bond of some form.Common construction bonds are bid bonds, performance bonds and payment bonds. Other bonds maybe obtained for special situations such as bonding around a mechanic's lien.
Cardinal change - A cardinal change is where ordered changes exceed the general scope of thecontract. It is a deviation so far outside the scope of work that it invalidates the terms of the originalcontract. Abandonment and cardinal change are often used interchangeably, but have beendistinguished by the California Supreme Court. calling the two doctrines“fundamentally different.” According to the court, under an abandonment claim, the contractor is entitled to recover its total cost
(less payments received) for work both before and after the contract was abandoned. In contrast,under a cardinal change claim, the contractor is only entitled to breach of contract damages for theadditional work constituting a cardinal change. While the court rejected a public contractor’s right tobring an abandonment claim, it purported not to address a contractor’s right to bring a cardinalchange claim.
7/28/2019 Construction Contract Terminology
http://slidepdf.com/reader/full/construction-contract-terminology 2/6
Change orders - a procedure that is defined in the contract to provide for modifications of the
contract scope of work. Change orders can increase the cost of the work, reduce the cost of the work,or have no cost impact. Along with the cost factor is an amount of time that the project schedule maychange due to the change order.
Changed conditions - A term that identifies anything that is different than at the time of the bid.
In many cases it has to do with the site conditions that were undetected prior to construction, but mayalso include factors that have changed since construction commenced. The importance of a changedcondition is the impact it may have on the cost of the work or the delay in the schedule.
Conflicting Terms - Within a contract, terms that are in conflict with other parts of the same
contract. This is a common, yet serious problem when contracts are created from pieces of othercontracts taken out of context. Terms and conditions often affect other provisions of a contract inseveral areas.
Consequential damages - are damages that do not flow directly and immediately from an act
but rather flow from the results of the act; damages that are indirect consequences of a breach of contract.
Differing site conditions - Where the construction site is not what it was understood to be at
the time of bidding. An example is when a contractor encounters subsurface or latent physicalconditions differing materially from those indicated in the contract documents. It typically will be"reasonably unforeseeable on the basis of all the information available to the contractor at the time of bidding.
Default - failure to perform specific terms of a contract obligation. Often used interchangeably with
material breach, but often specifically identified within contract terms.
Defects - Subsurface deficiencies, construction deficiencies, material deficiencies, design
deficiencies, all can cause defects in the finished construction project.
Delays - Based on the project schedule and the critical path, delays are anything that extends the
project schedule completion date. This can be applied to interim milestones as well as final completiondate.
Design Delegation Clause. The contract may specify who is responsible for the design. If the
construction contract specifically requires a contractor to provide design services and specify designand performance criteria, a contractor is to procure those design services from a licensed designprofessional.
Exculpatory clauses part of an agreement which relieves one party from liability. It is a provision
in a contract which is intended to protect one party from being sued for their wrongdoing ornegligence.
Flow-down Usually the Owner wishes to impose the same obligations on the contractor's
subcontractors, flow-down clauses are common in construction subcontracts. However the scope of
7/28/2019 Construction Contract Terminology
http://slidepdf.com/reader/full/construction-contract-terminology 3/6
responsibility is often disputed by subcontractors due to limited involvement in a prject. Flow-downpayment clauses may include pay-when-paid and pay-if-paid clauses.
Incorporation by Reference The construction contract itself typically does not explicitly
address every detail of the parties' agreement. Therefor, it is common to permit parties to incorporateother documents into the construction contract by reference.
Indemnification is a contractual promise in which one party agrees to protect another party from
financial loss.
In most cases, indemnification applies only to situations in which the loss is caused by negligencerather than by an intentional act of malice. Since most businesses are required to provide this kind of security for a wide variety of situations, not just construction contracts, indemnification is one of themore common contract terms.
Liquidated Damages Liquidated damages clauses are another common feature of construction
contracts, especially contracts in which time is of the essence. Liquidated damages clauses inconstruction contracts require that the contractor must compensate the owner for every dayconstruction extends beyond the end date specified in the contract.
Miller Act - The Miller Act (1935) is a federal law that requires contractors performing public work
projects (addition or general repairing of any governmental building or public works facilities) toproduce a performance bond as well as a labor and material payment bond in any contracts thatexceed $100,000. Since government construction projects are unable to protect themselves from non-payment with a traditional lien, the Miller Act was created to protect the subcontractors as well as thesuppliers when dealing with projects owned by the federal government.
No Contract - Exactly what the words mean. That there is no contract between the parties. At least
one requirement necessary to constitute a contract does not exist. A basic contract consists of an offerfor goods or services, an acceptance of that offer by the other party, and consideration for the goodsor services. There must be a mutually agreed to understanding of the intent of the obligation.
No Damage for Delay Clause. An exculpatory clause commonly included in construction
contracts. However, when the delay is not reasonably contemplated by the parties at the time of contract formation, a "no damage for delay" clause may not deny the contractor recovery foradditional costs.
Notice clause. In order to be paid for additional costs incurred in performance, a contractor must
provide the owner with adequate notice of such claims. Whether notice is adequate will generallydepend on whether the timing and substance of the notice conform to the notice requirements in thecontract.
Payment is the primary concern of most parties to a construction contract. The contract should
clearly define the manner in which payment is made, and address progress payments, retention, timefor payment, and final payment.
AIA Document A201-1997, Article 9 deals with payment. Article 9.2.1 requires the contractor tosubmit a schedule of values to assist the architect in evaluating the contractor's applications forpayment. After receiving the contractor's applications for payment, the architect issues a certificate for
7/28/2019 Construction Contract Terminology
http://slidepdf.com/reader/full/construction-contract-terminology 4/6
payment to the owner pursuant to Article 9.4. By the certificate for payment, the architect certifies tothe owner that, to the best of the architect's knowledge, information, and belief, the work is inaccordance with the construction contract. Other contracts may have different procedures, so it isimportant to understand the specific terms of each contract.
Pay if Paid, Pay When Paid Clauses. These clauses, are common, but are not enforceable
under California Law. A clear schedule of values and a definite payment procedure should be adhered
to by the contractor in order to preserve its rights to payment.
Payment disputes - one of the parties believes that the payment procedures were not followed,
or that the amount of money owed on a particular payment is not what was agreed to.
Private Works Projects that do not fall into the definition as public works of Federal projects are
typically private works. Every type of project that is funded from private money is considered a privateworks project. There are some hybrid types of projects that involve contracts between privatecompanies, but are ultimately funded from public source.
Public Works Construction projects that derive their funding from the public. This includes
municipalities, counties, regional agencies, water and wastewater districts, public schools, stateinfrastructure such as highways, and any project that is funded with money collected by a government
entity from the public. There are state laws specifically for public works projects which all public worksprojects must follow.
Federal projects are public works projects that derive their funding from federal sources. The FederalGovernment has specific laws that govern Federal projects.
Prevailing wages Prevailing wage may include both wages and benefits. It encompasses the
compensation for a worker given for performed labor.
The Davis-Bacon Act all federal government construction contracts, and most contracts for federallyassisted construction over $2,000, must include provisions for paying workers on-site no less than thelocally prevailing wages and benefits paid on similar projects.
Retention is a portion of the contract price paid into an escrow account before substantialcompletion of the work, and is beneficial to both the owner and the contractor. For the owner,retention ensures that the project is completed, protecting against default by the contractor. And forthe contractor, retention protects against default by the owner.
The final payment is distinct from, the progress payments. In addition to the requirement that thework conform to the contract, the owner typically attaches certain conditions to the contractor'sreceipt of the final payment.
Right to Stop Work The right to stop work is not the same as the right to terminate. While
termination is permanent, a work stoppage lasts only until the cause of the delay is resolved.
Every construction contract should address the conditions under which each party has the right to stopwork and who should bear the costs for the work stoppage or delay.
In order for the contractor to stop work for nonpayment, it must follow the specified procedures in thecontract. The contract time may be extended until payment is made and the contract price may beincreased to include the contractor's reasonable costs incurred in stopping work.
Schedule (Project) All construction projects have a schedule. Small projects may have only an
informal schedule, but large projects have a comprehensive schedule that a contractor and owner takeseriously. When progress does not keep in sync with the schedule or additional time is required due to
7/28/2019 Construction Contract Terminology
http://slidepdf.com/reader/full/construction-contract-terminology 5/6
delays or changes to the work, the the schedule often changes, and the critical path (CPM) may beaffected, which in turn may trigger delay damage claims or liquidated damage charges.
Schedule of values - Not to be confused with a project schedule, a schedule of values is an
assigned 'value' to various phases of work, or percentage of completion. This schedule is important forallocating progress payments to contractors in amounts that have been agreed to by way of theschedule of values.
Scope of Work The contractor involved in a construction project has a scope of work. The scope
of the work is defined by the construction contract between the owner and the contractor.Subcontractors scope of work is contractually defined, but by a different contract. (Between theGeneral and the Sub) And each subcontractor has a specific scope of work based on the trade.
It is very important to have the scope of work very explicitly defined because contractor orsubcontractor is not obliged to perform work that is beyond the contractual scope of work.
The scope of work becomes important when the owner issues a change order, requiring that thecontractor or subcontractor to perform tasks that are outside the original scope of work, or are amodification to the scope of work.
Any changed or extra work ordered by the owner which exceeds the scope of the contract work may incertain circumstances be considered a cardinal change. A cardinal change may be considered a breachof contract, and may allow the contractor to stop work until the parties reach an agreement regardingthe work beyond the contractual scope of work.
Site Inspection Clause. A site inspection clause requires the contractor to inspect the work site to
verify the accuracy of the owner's description of the site. If the construction contract contains such aclause, the contractor must comply with its duty to inspect before it may recoverfor differing site conditions.
Stop Notice gives the claimant a lien against undisbursed construction funds in the possession of either the owner or the lender. For private works of improvement, the Mechanic's Lien and Stop Noticegives the claimant a lien against undisbursed construction funds in the possession of either the owneror the lender.
For private works of improvement, the Mechanic's Lien and Stop Notice are cumulative remedieswhich can be simultaneously pursued along with a suit for breach of contract on the underlying debt.Generally, a Mechanic's Lien cannot be filed on a publicly owned parcel of real property. On Californiapublic works projects, the Stop Notice and payment bond claims are cumulative remedies.
Termination for Cause or for Convenience. A construction contract can be terminated for cause or
for convenience. A termination for cause occurs when one party stops work because of a deficiency inperformance by the other party. Because the contract is terminated as a result of a party's own poorperformance, the law typically provides the terminated party with little recourse in the event of atermination for cause. A termination for convenience, by contrast, occurs when the owner stops workfor reasons other than a deficiency in performance by the contractor. Because a termination for
convenience is not the result of poor performance by the contractor, the law may provide theaggrieved contractor with significant rights against the breaching owner.
7/28/2019 Construction Contract Terminology
http://slidepdf.com/reader/full/construction-contract-terminology 6/6
Unenforceable - A valid contract where there is no legal remedy if there is a breach. A contract
may be unenforceable when certain statutory requirements have not been met. For example, an oralcontract to buy land would not be enforceable because the Statute of Frauds requires such anagreement to be in writing. Similarly, statutes of limitations, which limit the length of time availablefor legal action, may apply to contracts of certain types and render them unenforceable after a certainperiod of time. Parts of a contract may be unenforceable, while other parts of the same contract areenforceable.
Waiver of Consequential Damages Clause. Construction contracts also frequently include a
mutual waiver of consequential damages clause, whereby both parties agree to waive allconsequential damage claims relating to the contract. Consequential damage waivers may amount tono damage for delay clauses when costs arising from delays are characterized as consequential.
Warranties Warranties can be either express or implied. Contractors will be held to any express
warranties made in the construction contract. The express warranty typically lasts one year from thedate of substantial performance but may be some other time frame as specified in the contract.Implied warranties are those that are understood to be in effect, even if there is nothing in writing. Acontractor's failure to fulfill an express warranty to repair or replace defective materials mayconstitute abandonment.