  ASSIGNMENT ON CONSTRUCTION CONRACTS & CONTRACTING NCP 23 Submitted By : SUJITHLAL SOMAN Reg. No :

Construction Contract Conctracting

Embed Size (px)

Citation preview

Page 1: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 1/25

 

 ASSIGNMENT ON CONSTRUCTION CONRACTS &

CONTRACTING NCP 23

Submitted By : SUJITHLAL SOMAN

Reg. No :

Page 2: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 2/25

ASSIGNMENT

NICMAR/CODE OFFFICE

1.  Course No : NCP 23 

2.  Course title : Construction Contracts & Contracting

3.  Assignment No :

4.  Date of dispatch :

5.  Last date of receipt of  

Assignment at CODE office :

Assignment

Contract administration and monitoring is the most important area of 

construction management. Contract administration process should start right from

the day work is assigned to the company. Discuss any project contract currently in

 progress with your company and how administration and monitoring is being

done. Draw the organization chart for this activity and explain all the function

carried out. Do you think the system is achieving results? Discuss.

Page 3: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 3/25

INTRODUCTION 

Contract management is the process that enables both parties to a contract to

meet their obligations in order to deliver the objectives required from the contract.

It also involves building a good working relationship between customer and

 provider. It continues throughout the life of a contract and involves managing

 proactively to anticipate future needs as well as reacting to situations that arise.

The central aim of contract management is to obtain the services as agreed

in the contract and achieve value for money. This means optimising the efficiency,

effectiveness and economy of the service or relationship described by the contract,

 balancing costs against risks and actively managing the customer  –  provider 

relationship. Contract management may also involve aiming for continuous

improvement in performance over the life of the contract.

Page 4: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 4/25

  The company has got approval from the OHS and the blank tabulated form

is given below:

CONTRACT MANAGEMENT

Document 1h: Contract OHS System Approval for Labour HireLast Update:

Owner:

Labour hire consists of contractors engaged directly or through labour hire

agencies to carry out work under similar arrangements to normal staff. The

contractor will be supervised directly by University staff. This does not include

contractor managed work teams which fit under the other classifications of 

contract management. This document when completed is to be kept with the

current version of the Contractor‟s Health and Safety Plan and forms part of the

contract documentation.

Contract Major Minor Businessservices

EventMgt

Lightdelivery

Heavydelivery

Contractstaff 

Off-siteVenuehire

LongL/M/H

hazard

Medium L/M/Hhazard

OngoingL/M/Hhazard

ShortL/M/H

hazard

In general, contractors in this group must be treated in the same manner as staff members as

regards induction, supervision and other OHS requirements. The University is described as the

“Host Employer”. 

Page 5: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 5/25

Contract Details:

Contract Name. Contract Number:

Company Name:

 Name of Contact Person:

Contact details:

Position: Date:

 Name and Contact Details of Deakin Representative:

Contract

Characteristics

Class Notes

Type of Contract?

CT 1 -9

CT 1: Labour 

hire contract

staff 

The type of contract is an important factor in determining the

types of OHS controls required

Type of Engagement?

E 1 - 4

E1: Long term project or service contract (more than 2 weeks)

E2: Medium term project or event (up to 2 weeks)

E3: Ongoing but intermittent

E4: Short term (few hours), one-off or annual

Hazard level?

L/M/H

Low: Serious injury is unlikely

Medium: Serious injury is possible

High: Serious injury is likely if not well managed

(Serious injury is any injury that involves lost time or hospital

treatment)

Page 6: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 6/25

Element

(see Table 1:OHS Control Measures for Labour Hire) 

Date

Received

Satisfactory/

Unsatisfactory /

Not Applicable

Contract for Labour Hire

Labour Hire Contractor insurances

Labour Hire Contractor OHS Management System

Labour Hire Contractor has established systems and procedures for managing OHS

hazards

Labour Hire Contractor and contractor employees hold all necessary qualifications and

 permits.

Labour hire employee has a good understanding of the hazards and risks associated with

the contract

(University responsibility) Plant and equipment used by the contractor is appropriately

licensed or registered and is maintained on a regular basis

The Labour Hire Contractor is recommended for inclusion on the Approved Contractor 

List (Panel) for (describe type of contract) 

Hazard Disclosure and Labour Hire Job Description

(University responsibility) Project Risk Assessment

The University will be required to develop (if required) and use Job Safety Assessments

and/or Safe Working Method Statements

The labour hire employee will operate under University Permit and Isolation procedures

and have been made familiar with them

The labour hire employee have completed the General University Induction

The labour hire employee will complete a Local Site Induction before commencing

work 

The labour hire employee has received copies of the Site Safety Rules

Deakin staff will be required to supervise the contractor 

The labour hire employee will follow University sign in/sign out procedures

The labour hire employee will be monitored (indicate how frequently and whether

randomly or by agreement)

Page 7: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 7/25

Element

(see Table 1:OHS Control Measures for Labour Hire) 

Date

Received

Satisfactory/

Unsatisfactory /

Not Applicable

The performance of the labour hire employee will be formally evaluated (indicate

when)

Comments

Authorisation Signature Date

Local supervisor 

Contract Manager 

Contractor Representative

Element Date Yes / No

The Contractor is approved for inclusion on the Approved Contractor List

The Contract meets the University OHS contractor management requirements

Authorisation Signature Date

Dean / Head of School /

Director 

Page 8: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 8/25

Table 1:OHS Control Measures for Labour Hire

OHS Control

Measures

Notes

Resources and Tools

All the forms are intended for adaption as

required

Contract OHS

Management

Contracts cannot transfer 

responsibility for OHS to the

contractor 

For use of the Contract Manager:

(1a) Contract OHS Management System

Guidelines 

(1b) Contract OHS Management System

Template for Labour Hire  (This

document)

WorkSafe Victoria: Host Employers:

Managing the safety of labour hire

workers 

Written contractOHS requirements must be

included in the contract.

For use of the Contract Manager:

(2) Model Contract Clauses 

Hazard Management

Project Risk 

Assessment

Required for all contracts that

involve a medium to high hazardlevel. An initial risk assessment

should be carried by the Contract

Manager to identify issues. The risk 

assessment must be discussed with

the labour hire employee

For use of the Contract Manager and

Contractor:

(3a) Contract OHS Risk Assessment  for 

construction and related works

(3a) Contract OHS Risk Assessment  for 

maintenance and related works

Page 9: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 9/25

OHS Control

MeasuresNotes

Resources and Tools

All the forms are intended for adaption as

required

OHS Management

System

Large labour hire contractors willhave an established OHS

Management System.

For use of the Contract Manager:

(4a) OHS Guidelines for Contractor 

Selection 

(4c) Tender OHS Management System

Evaluation 

For completion by the contractor:

(4b) Tender OHS Management System

Questionnaire 

WorkSafe Victoria: Labour Hire Agency

health and safety „health check‟ 

Proof of WorkCover 

and insurance coverage Normally required for all contracts

Hazard Disclosure

Statement

The Hazard Disclosure Statement is

a formal advice to the Contractor 

about hazards known to Deakin

University that may affect the

safety of the contractor 

The Labour Hire Provider may

require the University to complete a

Labour Hire Description or OHS

Management System assessment

For use of the Contract Manager:

(6) OHS Hazard Disclosure Statement 

(6b) Labour Hire Job Description 

WorkSafe Victoria: Assessment of host

employer‟s system for managing OHS 

Job Safety Assessments

In major works where there are

activities with a medium to high

hazard level

For use of the Contract Manager or local

supervisor:

(10a) Guidelines for Job Safety Assessments 

(10b) Job Safety Assessment Template 

(10c) Safe Working Method Statement

Template 

Safe Work Method

Statements

In major works where there are

activities with a medium to highhazard level

University‟s Permit and

Isolation procedures

The labour hire employee must be

familiar with these procedures.Local procedure

Labour Hire employee

Certificates

Where work requires that the

operator has certification (e.g.

forklift driver),

The Contract Manager must verify their 

currency

Page 10: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 10/25

OHS Control

MeasuresNotes

Resources and Tools

All the forms are intended for adaption as

required

Local induction

This induction is required and

would be the same as a similar 

University staff member 

The induction checklist chosen will

depend upon the nature of the work 

This is the normal induction process for casual and contracted staff 

For use of the Contract Manager:

(15a) Contractor OHS Induction Checklist -

Maintenance and Service contracts 

(15b) Contractor OHS Induction Checklist -

Office based labour hire, casual staff,

temporary staff contracts 

(15c) Contractor OHS Induction Checklist -

Venue hire contracts 

(15d) Contractor OHS Induction Checklist -

Laboratory and workshop based

contractors and temporary staff  

(15e) Contractor OHS Induction Checklist  –  

Labour Hire Selection, Induction and

Training Record 

Site induction

Site Safety Rules

Booklet

Site Safety Rules provided as a

 booklet to the Labour Hire

employee

Local arrangements

Supervision and Monitoring

The University is

responsible for 

supervision

Required The supervisor nominated in this document

Sign in and Sign out

 procedures Normal University arrangements

Requirements for the contractor:

(21a) Site Sign In / Out Template 

Monitoring the

 performance of the

contract

Direct responsibility of the

University supervisor 

Page 11: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 11/25

OHS Control

MeasuresNotes

Resources and Tools

All the forms are intended for adaption as

required

Evaluating contractor 

 performance

Where a labour hire contractor hasan ongoing relationship with the

University, the contractor‟s OHS

 performance must be periodically

reviewed.

For use of the Contract Manager:

(23a)  Non Conformance Report Form 

(23b) Post / Annual Contractor Evaluation

Form 

Based on the above data and elements of consideration I do have submitted a

labour contract that happened in a company.

Page 12: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 12/25

 

Name of Project

Completing Water Supply System for the upcoming project Aditya

Aluminum, at Lapanga, Sambalpur, Orissa.

Scope of Work 

Complete Design and Engineering, Manufacture, Supply, Transport,

Handling, Erection, Testing and commissioning including Performance Guarantee

Test for Water Supply System and related Substation, pipe Line, WBM Road for 

supply of Raw Water from Hirakud Reservoir to Aditya Aluminium Smelter &

Captive Power Plant at Lapanga, District Sambalpur, Orissa.

Important details of the contract:

 Name of the company : Aditya Aluminium,(A Division of HINDALCO Industries Ltd.)

Lapanga, Sambalpur, Orissa

 Name of contractor : Not to Display

Type of Contract

The contract is of Lump sum Fixed Price type turnkey contract. The above

contract includes complete design, engineering, supply, erection, testing and

commissioning of equipment. In case any item is missed out or omitted from the

list of technical specification for completion of the job as per contract provision it

is also deemed to be in scope of the supplier without any cost implication to the

company.

Page 13: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 13/25

Price of the contract 

The contract price is payable by the company to the supplier in consideration of 

all the supplies to be made and all services to be provided by the suppliers

according to the terms of the contract shall be:

(i)  Supply of equipment including Not to Display

Commissioning spares, packing

Forwarding, transit Insurance

(ii)  Design, Engineering, Unloading, Not to Display

Storage, Handling, Erection andCommissioning including all civil

Work etc. with supervision and

insurance for storage and erection

of the “water Supply System”

in Complete

The above prices are exclusive of Transport, Excise Duty with education

cess, Sales Tax, Entry Tax, but inclusive of work Contract Tax and other Taxes

and duties as applicable to the scope of the contract.

Page 14: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 14/25

Price Variation

In this contract the aforesaid contract price shall remain firm throughout the

entire contract period and shall not be subject to any escalation on the any account

whatsoever expect for any statutory variation (Increase or decrease) in taxes and

duties and the price of the MS spirally welded pipe for main water supply. The

 price of the MS pipe are based on 11th

jan,2010 if any variation in the in price by

the SAIL shall be applied on the supply price of the pipe with its correspondence

impact on taxes and duties and shall be paid.

Similarly for intake well & pipe line laying system the depth/lengthvariation are applicable at mutually agreed unit rates. In case of any variation

(increased and decreased) in account , the total contract price shall be increased or 

decreased and the advances/payments already paid and/or due for payment shall be

adjusted accordingly.

Page 15: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 15/25

Time of Completion

The program of delivery, installation and commissioning of the

“Equipment” will be effective from the effective date and will be according to the

schedule of 24 months from the effective date.

For construction of the raw water pipe line land corridor will be provided by

Aditya Aluminiumin phases within 8 month of the date of LOI. Incase of any

delay in providing land corridor due to any reason attributable to Aditya

Amuminium, the contract period shall be extended correspondingly without any

financial impact to the company.

Similarly for the construction of intake well and channel inside the Hirakud

Reservoir, in case any delay in the construction due to change in stipulation of 

government of the Orissa and central government or Dam authority etc. the

contract period will also be extended correspondingly without levying and LD.

Page 16: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 16/25

Payment terms

The payment of the contract price will be made by the company in

accordance with the following terms on receipt of invoices and other related

documents:

For supplies

1.  10% contact value as advance with LOI against of BG

2.  5% of contract value against the submission & approval of GA drawings.

3.  60% of contract along with 100% taxes &duties on pro-rata as per approved

 billing schedule against lawful invoice.

4.  10% of contract value against achievement of milestone.

5.  5% of contract value after issuing of commissioning certificate against

 performance bank guarantee of equivalent amount.

6.  10% of contract value against issue of final acceptance certificate (FAC).

i.e. after completion of defect liability period of 12 month from date of 

commissioning certificate.

For Civil, Erection, Testing & Commissioning1.  10% contact value as mobilization advance against of BG of equivalent.

2.  5% of contract value against the submission & approval of GA drawings.

3.  60% of contract along with 100% taxes &duties on pro-rata as per approved

 billing schedule against lawful invoice.

4.  10% of contract value against achievement of erection milestone.

5. 

5% of contract value after issuing of commissioning certificate against performance bank guarantee of equivalent amount.

6.  10% of contract value against issue of final acceptance certificate (FAC).

i.e. after completion of defect liability period of 12 month from date of 

commissioning certificate.

Page 17: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 17/25

 

Quality inspection and testing during manufacturing

The company will be entitled at all reasonable times to witness the

inspection, examination and testing of the equipment and erection & construction

work at workshop of supplier.

For this the contract should give one week prior notice to company for 

testing.

The supplier should provide such assistance, labour, material, electricity,

fuels, apparatus and instrument etc. for carry out test. If, after inspecting,

examination, or testing any part of the equipment and erection & construction

work, the company should decide that such part is defective or not in accordance

with the terms and specification for the contract, then it may reject such part by

giving to supplier seven working days written notice of such defect.

The company will bear all the costs and expenses for deputing its inspector.

Page 18: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 18/25

 

Warranty

The supplier warrant that all material and all services provided by the

supplier should new, free from defect in workmanship and material or design and

fit purpose for which they are supplied.

The supplier warranty shall be effective for 18 month from last date of 

receipt of supplies or 12 month from the date of successful commissioning.

During the warranty period if there are any failure, the supplier, on it option,

repair. Make good, replace, or modify with all possible speed without any

additional cost to company.

If supplier does not commence the correction activities the company may, at

its option, correct the defect at the suppler expenses. In such case the warranty

 period will extended to 12 month from the date on which such replacement or 

repair is completed.

Page 19: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 19/25

 

Project Management, Co-Ordination, Monitoring and Supervision

The supplier should depute at their own expense duly qualified supervisors

to site to supervise the erection and construction work and putting in to operation

at site.

The supplier should provide supervisory services for project management,

installation and commissioning also bear all the cost against the facilities provided

to its supervisors.

All the work should be complete on or before time if any site supervisor 

deputed at site for work is not able to complete the work on time or at any guilty

of serious misconduct, the supplier should remove or replace such persons at

supplier expense so as not to cause any interruption in carrying out the erection &

construction work or any delay in specified time schedule for the work.

The supplier should provide adequate on the job training to operating andmaintenance staff of the company at site during the erection & commissioning

without charging any additional cost to the company.

Liaison and co-ordination for processing of all statutory clearances with

State Government Authority at Bhubaneswar or at District Level or with the DAM

Authorities shall be carried by the supplier.

Page 20: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 20/25

 

Liquidated damages (LD) for delays and shortfall in performance

In the event of delay in completion of supply and commissioning of the

water supply system, beyond the completion period as per schedule, the supplier 

shall pay LD @ 0.5% of the contract price per week of delay subjected to a

maximum of 5% of the contract prices for both supply and erection order value.

The payments of deduction of liquidated damages shall in no way relieve

the supplier from completing the supplies and works and discharging all its other 

obligations under the contract provided however that the above mentioned

liquidated damages are the supplier only obligation to financially compensate the

company in case of delay completion of the facility and/or failure to achieve the

 performance guarantees.

Page 21: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 21/25

 

The important point from contract point of view to be monitored/ resolved

1.  The company should furnish all the pertinent data and information‟s

available to it without charges and within a reasonable time and should give

such assistance as should reasonably required by the supplier for carrying

out the supplier obligations under the contract as per schedule.

2.  The supplier , in carrying out its responsibilities, shall comply with the

legislation, laws, by-laws, rules, regulations of the Govt. of India, the State

of Orissa and other local authorities as may be applicable including those

relating to environment, labour and safety.

3.  The company should make timely payment to the suppliers for all amounts

due to the suppliers under the contract in accordingly with the terms and provisions of the contract.

4.  The Engineer-in-charge (EIC) carryout such duties in issuing certificates,

decision, instructions and order as per contract to be carried out by the

supplier. EIC shall have the full authority to act on behalf of the company

for all purpose in connection with the contract and shall be supplier primary

 point of contact with company in relation to the execution of the work. Thesupplier shall proceed with the works in accordance with decision,

instruction and order given by EIC subject to and in accordance with the

contract, including provision for variation hereof.

5.  Liaison and co-ordination for processing of all statutory clearances with

State Government Authority at Bhubaneswar or at District Level or with the

DAM Authorities shall be carried by the supplier.

Page 22: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 22/25

6.  During the contractual period, the supplier shall indemnify the company to

co-ordinate and ensure to take care of all the Local, socio, economic,

cultural, education and political requirement of various non profitable

organizations, association, institution including district and local

administration if any form time to time as a part of their contractual and

social obligation with due consultation and approval from the company.

7.  The supplier shall also get approved by the company the list of its vendors

engaged for the purpose of the contract.

8.  The supplier shall make its own arrangement for land, supply of water,

electricity or any other facilities required for fabrication, erection, and

commissioning of the work.

9.  The supplier shall indemnify to the company that they will create as

environment of awareness and physical being that is conducive to a safe and

healthy workplace, in accordance with all federal, state, local and corporate

regulation and contractual obligations. The supplier shall provide safety

 programs that are effective in identifying and reducing hazards in the work  place and impart training to their employees to develop safe work practices

that efficiently produce quality products in a safe manner with an objective

to have an injury free workplace and zero accident.

10. The supplier shall use liberal factors of safety throughout the design and

shall follow all other relevant IS and also international codes, wherever 

applicable.

Page 23: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 23/25

 

The Consultant

The Consultant will be totally responsible for all the engineering of Projects

going on at all the branches. He will be involved in each activities from initial

idea, generation of layout drawings with all infrastructure requirements, Detail

working drawings, estimates, and site execution up to hand over.

The consultants would be responsible for preparation of drawings and

documentation within their various disciplines with regard the Services. Site-visits

would be made by the consultants at specified milestones, or as may be required.

The Group Head (CEO & COO):

The group head‟s role would be the monitoring of the designer‟s output andactivities, and taking responsibility for all the work that is generated by the group.

Project In charge (Sr. V.P.):

Interaction with contractors to detail out their requirements, obtaining

signoffs and overseeing the tendering and negotiating process. Subsequently,

during the execution stage, he monitors the project for cost, quality, and schedulesand local administration.

The Project Manager (GM):

The project manager audits the project during the drawing/design stage, for 

conformance to the stipulated process, and for adherence to agreed schedules.

Subsequently, during the execution stage, he monitors the project for cost, quality,

and schedules.

Page 24: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 24/25

 

The Site In Charge(Manager/ Sr. Manager):

The site in charge is responsible for achieving quality on site, interpreting

the drawings and documentation on site, and raising reports on quality and

scheduling.

Assistant Site In charge (Asst. Manager/ Engineer):

The role of a Assistant site In Charge is the day to day monitoring of site

activities. Monitoring of day to day schedules and raw material quality fall within

the scope of duties. He is responsible for Co-ordination between Vendors and the

generation of daily and weekly status reports.

Page 25: Construction Contract Conctracting

7/28/2019 Construction Contract Conctracting

http://slidepdf.com/reader/full/construction-contract-conctracting 25/25

 

Recommendations & Conclusion

1.  In this contract there is no provision and any point hasn‟t made about

change of the scheme for drawl of water from the reservoir and change in

the price of the contract according to that change.

2.  The contract doesn‟t have the provision of the penalty as per contract the

contract can‟t leave work there is provision of the liquidity damage

maximum of 5 % of the contract value. The contract has to complete the

work and if there is any defect in the work the contractor has to rectify it on

his own expenses within the guarantee period in case of any delay of 

contract due to unsatisfactory work the company will suffer the loss by

unavailability of the water at plant area.

References:

-   NICMAR publication lesson books on Construction Contract

Management