Consolidation program SPS Main Power Converters (Dipole & Quadrupole ) . K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012 . Outlines. SPS consolidation overview Transformers Thyristor bridges Electronics and CIS Powering tests Conclusions. Overview. - PowerPoint PPT Presentation
Citation preview
Consolidation programSPS Main Power Converters
(Dipole & Quadrupole)
K. Kahle / Q. King / G. Le Godec (TE-EPC)IEFC Workshop, 9 March 2012
o SPS consolidation overviewo Transformerso Thyristor bridgeso Electronics and CISo Powering testso Conclusions
2
Outlines
3
Consolidation overview
Overview
SPS Dipole Circuit
Power system ratings: 25 kV/6kA/150 MW 12 converters connected in series 2 active spares.
18 kV
+15°
-15°
+15°
-15°
4
OverviewSp
ares
2 converters
1 active spare
18 kV
+15°
-15°
+15°
-15°
5
Overview
SPS Quadrupole Circuit
Power system ratings: 4.8 kV/2.2 kA/ 10.6 MW 2 converters + 1 active spare
6
History of SPS powering1975: SPS Main Power System was put into service,
1981: Transformer upgrade for collider mode (voltage increase),
1993: Change of the regulation control electronics
1998: Replacement of the command and interlocking system (CIS)
1998-2000: Filter capacitors replacement (PCB elimination),
2002: New Earth Protection and Discharge System (Crowbar),
The consolidation program shall continue to maintain the excellent availability of the machine
Overview
SPS powering consolidation: A large project!
18 kV
+15°
-15°
+15°
-15°
7
Overview
18kV cablesQty 20 km
LS1 EN/EL
Transformers
Qty = 68LS1
TE/EPC
ThyristorsQty = 68
LS1TE/EPC
Electronics and CIS
LS1-2TE/EPC
8
Overview
Strategy: For the case of major problem, we shall be able to
return to the previous situation.
Transformers: Full compatibility between old and new transformers (dimensions of the pits and power connections),
Thyristor bridges: Full compatibility between old and new thyristor bridges (no modification of existing converter racks),
18 kV cables: Keep the ability to reconnect the old cables. Feasibility study underway (EN/EL).
9
Transformers
For SMD and SMQ
Transformers
10
Oil Transformers … reasons to change Ageing (≈30 years of operation):
High maintenance costs and urgent need of consolidation:o Corrosion,o Oil leakages.
PCB traces Oil treatment in 2008-2009 to conform to French/Swiss
regulation, However, traces of PCB remain (within the legal limit <50ppm),
The oil transformers will be replaced by cast-resin transformers during LS1: 60 transformers in 30 enclosures (6 MCHF).
Transformers
11
Transformers
Existing oil transformers
12
Transformers…
Transformers
4 pre-series transformers already in operation in 2011,4 additional transformers installed for the operation in 2012,
Transformers
13
Preparations in 2012… The SAX area will be required for the storage of the new cast-resin
transformers in 2012-2013,
The old oil transformers need to be stored on platform with oil retention (b.951) until 2016.
Clear out of all equipment is required
Presently, the SAX area is managed by GS. We would like to take the responsibility for this area as it was designed to store oil transformers.
Transformers
14
Preparations in 2012… Access road around BA2 to be rebuild (budget 55 kCHF covered by
GS),
Transformers
15
Installation in 2013… Installation of 60 transformers by TE-EPC (January - December
2013), The installation per converter (4 transformers) takes 10 days, The pre-tests without power take 4 days,
The support of the following groups is required: EN/HE for transport and crane, EN/EL for the control cabling and earthing system,
Planning proposal
The coordination and the planning of all co-activities is required with the support of the SPS coordination team.
BA1 January 2013
BA2 February – March
BA3 April – May
BA4 June
BA5 September
BA6 October
16
Thyristor bridges
For SMD and SMQ
Thyristors
17
Thyristors … reasons to change Expected lifetime of all components is reached:
Increasing problems with reliability of operation (water leaks, issues with electrical contacts, thyristor firing circuits etc…)
The old bridges will be replaced during LS1: 68 thyristor bridges in
17 power converters (1 MCHF).
Thyristors
18
Thyristors
Thyristors: existing water-cooled power
bridges
19
Thyristors…
Thyristors
Integration into the existing racks
20
Thyristors…
Thyristors
Two parallel bridges
Replaced by one single bridge
Thyristors
21
Preparations in 2012… Delivery of prototypes (Dipoles & Quadrupoles) in July 2012,
Mechanical validation in a spare converter (outside SPS),
Installation of 2 thyristor bridges in BA2 spare converter in September for validation with the SPS,
Operation with this spare converter until end of 2012,
Delivery of all bridges in 2013.
Thyristors
22
Installation in 2013… Installation of 68 bridges by TE-EPC from January to December
2013, The installation per power converter takes 6 days, The pre-tests without power take 2 days,
No co-activities with other groups
Planning proposal BA1 January 2013
BA2 February – March
BA3 April – May
BA4 June
BA5 September
BA6 October
23
Electronics and CIS
Electronics and CIS
24
Electronics… reasons to change Increasing problems with reliability of operation (connectors,
contacts, etc…),
Modern diagnostics tools are needed to optimize performances and post mortem analysis,
The consolidation of Electronics is a long term project and will be completed in LS2.
Electronics
25
Electronics…
Electronics
Electronics designed by S. Van Der Meer
26
Electronics
AnalogueVoltage
Regulation
Powerpart
AnalogueCurrent
Regulation
FunctionGeneration
DAC
MUGEF in 2012
I ref Vref
I meas
V meas
AnalogueVoltage
Regulation
Powerpart
AnalogueCurrent
Regulation
Func.Gen.
DAC
MUGEF after LS1
I ref
Vref
I meas
V meas
ADC
DigitalCurrent
Regulation
Analogue regulation can be reactivated in minutes
First step: integration of Current Regulation in the Mugef in LS1.
27
The new MUGEF software will provide many benefits including post-mortem logging, asynchronous starting and stopping of the SPS mains (no need for a special supercycle) and digital regulation of current.
Digital regulation in the new MUGEF software uses the same regulation library (Libreg) as the FGCs in the LHC, POPS and Booster.
Digital regulation will improve the tracking of the reference, management of current and voltage reference limits and monitoring of the regulation error.
Electronics
28
Command and Interlock System (CIS)CIS
HMI (BA3)
Master PLC (BA3)
Local PLC’s (all BA’s)
Local PLC’s (all BA’s)
Local PLC’s (all BA’s)…
Modernization of the CIS system
Reprogramming of new PVSS for CIS was not yet successful.
We had to return to the
old HP workstation
First phase
Second phase
29
Powering tests
Powering tests
Powering tests
30
System tests at the end of LS1By the end of LS1, all 18 kV cables, all transformers, all thyristors, part of the regulation system will have been replaced: comprehensive tests of the entire system are required before physics can re-start.
Power tests of the entire system: SPS ring closed at the end of February 2014, First beam in the SPS beginning of June 2014, Requirement EPC: 2 months of powering tests in March-April 2014,
31
Conclusions
Conclusions
32
Manufacturing of transformers and thyristor bridges underway,
Pre-series transformers have been validated in operation,
Pre-series thyristor bridges will be validated in operation in September,
Some preparations still need to be done in 2012 (SAX area, civil eng. BA2),
In case of major problems, we can always return to the previous situation,
Power test period is required,
All old transformers and thyristor bridges will be kept for at least 1-2 years as a backup,
Proposal to transfer the management of the SAX area to EPC,
Conclusions