Upload
lyliem
View
215
Download
0
Embed Size (px)
Citation preview
Conquering the Challenges in Geothermal Utilization —
the EDC Experience
Resource Management Division, Technical Services Sector
30th UNU-GTP Anniversary Workshop
Reykjavík, Iceland
26-27 August 2008
EC Angcoy Jr., EH Alcober, FXM Sta. Ana, AC Cabel Jr.,LF Bayrante, RCM Malate, MS Ogena
Title
INTRODUCTION
TECHNOLOGIES/EXPERTISE
Tracer Tests
Scale Inhibition
Solids Mitigating Measures
On-line Steam Purity Monitoring
SUMMARY and FUTURE OUTLOOK
Presentation Outline
INTRODUCTION
BBGGPPFF
115500 MMWWee
LLGGPPFF
770088 MMWWee
NNNNGGPPFF
4499 MMWWee
SSNNGGPPFF
119922 MMWWee
MMGGPPFF
110044 MMWWee
1976
2007
~1,200 MWe60% of Total Installed Geothermal Power Plant Capacity in the Philippines
Tracer Tests
Field Date Tracers Used Objective
MGPF 2003 1,6 NDS / 2,6 NDS Brine returns from Matingao and Kullay sectors
LGPF 2003 1,5 NDS/1,6 NDS / 2,6 NDSDefine flow paths of inflowing cooler peripheral
waters and brine injected in Mahanagdong sector.
LGPF 2003 1,5 NDS Condensate returns injected in Upper Mahiao sector
SNGPF 2005 1,5 NDS / 1,6 NDS Brine returns injected in Palinpinon-II sector
LGPF 2006 1,6 NDS Brine returns injected in Upper Mahiao sector
LGPF 2006 1,5 NDS / Tritium Brine returns injected in Tongonan-1 sector
LGPF 2007 1,5 NDS/2,6 NDS/2,7 NDS Brine returns injected in Malitbog sector
Objectives:
Determine flow paths and impact of geothermal fluids injections (mandated by law)
Aid in reservoir simulation
Tracer Test Results
Data reduction using UNU-GTP Icebox package and Anduril software
Provides information to formulate injection strategies
B
Brine injection
optimized
Condensate injection
transferred
GGrroouunnddwwaatteerr
iinnffllooww
Brine injection
optimized
BBrriinnee
RReettuurrnnss
BBrriinnee
rreettuurrnnss
((11,,55 NNDDSS))
((11,,66 NNDDSS))
((22,,66 NNDDSS))
Herras et al., 2005
417D
Dacillo and Herras, 2008
Calcite Inhibition System
TOP VALVE
MASTER
VALVE
WING VALVE
SIDE VALVE
Mixing
Tank
Feed
Tank
PUMP
SYSTEM
Capillary
Tubing
Alternative to costly/risky/periodic mechanical clearing due to calcite blockages.
Lesser decline in total mass flow of production well: 4 kg/s/month (without CIS) vs <0.5 kg/s/month (with CIS).
Siega et al., 2005
Silica Scaling Studies
Chemical tank
2-phaseline
header
Mini-
separator
Mini-
silencer
Open
pipe
Steamline
Thermal Pond
SP-2
SP-3
Brineline
Mini-
silencer
SP-4
0.68 MPa
163°C
Chemical tank
2-phaseline
header
Mini-
separator
Mini-
silencer
Open
pipe
Steamline
Thermal Pond
SP-2
SP-3
Brineline
Mini-
silencer
SP-4
0.68 MPa
163°C
Botong Silica Inhibition Set-up(BGPF)
Panopio et al., 2008
Malitbog Silica Inhibition Set-up(LGPF)
Alcober et al., 2005
Solids Mitigating Measures
WH Washing
Modified Solids Trap
BRANCHLINE
CATCH POT
INVERTED
U-PIPE
BLEED LINE
TO SILENCER
INSPECTION
FLANGE
SOLIDS
CLEAN STEAM
SILENCER
WH Solids Removal System
Reduced suspended solids in steamby 80-100%
Reduced thinning rates by 60-99%
Villa et al., 2007
On-line Steam Purity Monitoring
Accurate and continuous real-time steam purity data.
Prevents scaling and erosion / corrosion in turbine blades.
Prevents plant shutdown / tripping due to brine carry-over.
Monitors separator and drainpot efficiency.
Meets contract obligations with BOT partner on steam purity.
STEAM PIPELINE
DEGASSER
CONDENSER
FLAME PHOTOMETER
NCG OUT
STEAM CONDENSATE
SAMPLE
ISK PROBE
DRAIN
STEAM PIPELINE
DEGASSER
CONDENSER
FLAME PHOTOMETER
NCG OUT
STEAM CONDENSATE
SAMPLE
ISK PROBE
DRAIN
Condensed steam is isokinetically-sampled
Sodium (Na) in condensed steam generates a certain wavelengthonce burned in low temperature.
On-line SPM Display
1.0 ppm
0.5 ppm
0.0 ppm
CONTRACT LIMIT = 0.56 ppm
CALIBRATION:
MP: 1430H
TCP: 1445H
DAILY AVE. = 0.05 ppm
Alarm system: 0.40 ppm Na (high alarm); 0.56 ppm Na (high-high alarm)
0.56 ppm Na limit equivalent to 1 ppm Cl limit
Annual savings of ~USD 400-900 M from manual sampling and analysis Additional savings from minimized shutdowns, increased efficiency
Summary and Future Outlook
Developed practices and technologies (Tracer Tests, Scale Inhibition, Solids Mitigating Measures, On-line SPM) aided the integrated reservoir management of EDC for ~3 decades.
Acid inhibition system in LGPF starts in 2008 (MG9D, 3 MW) potential development of EDC wells with
acidic discharges
Widen installed capacity by putting up new power plants and bidding for state-owned geothermal assets
Expand international cooperation in geothermal services, consultancy and drilling projects
Projects (+310 MWe, to 2015)
Nasulo (20 MWe)
Cotabato (50 MWe)
So. Leyte (50-80 MWe)
Rangas (40 MWe)
Kayabon (40 MWe)
Dauin (40 MWe)
Tanawon (50 MWe)
Erlindo C. Angcoy Jr.GeochemistResource Management DepartmentLeyte Geothermal Production FieldEnergy Development Corporation
e-mail address:
Takk Fyrir !!!
THANK YOU