Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Connecting Hydro Power in Africa -
The Need for Transmission and
Distribution Grid Interconnectivity
and Capacity
Nishan Rathanlall | Sector Unit Manager
Africa Utility Week, CTICC, 17-19 May 2016
1.Energy in Africa and the Electricity
Market/Value Chain.
2.Hydro Power Potential locations across
Africa versus potential Grid Plans/Power
Flows.
3.Why Grid Connectivity and
Interconnectivity.
4.The need for Generation Capacity.
5.Africa Power Pools creating
Interconnectivity and Capacity.
6.T&D Sector Trends
Index
1
Energy in Africa
3
“In Africa power is inaccessible,
unaffordable and unreliable for most
people – this traps people in poverty –
today 25 African counties face an energy
crisis”
World Bank Africa Energy Unit 2012
Energy in Africa – Access to Electricity
4
2012 was the UN year of universal access to
energy for Africa
Some of our African countries have an electricity
access rate below 20 percent
In South Africa it is 85 percent with universal
access planned for 2025
Power & Energy Sector Market
5
Inbound Logistics
Generation Transmission & Distribution
Reticulation
Primary Energy
Hydro Power Potential locations versus Power Flow plans
across Africa
2
Why Connectivity and Interconnectivity?
Transmission and Distribution Grid/Network Connectivity is important for the
development of Hydro Power projects (clean energy) on the continent.
Interconnectivity = Power Pools.
Not all jurisdictions have access to natural resources for power generation e.g.
coal, gas, hydro etc. Also the MW potential of Generation Capacity is sometimes
larger than the offtake capability of a country, so the need to export to other counties
where there is an offtake capability or higher load growth projections/potential.
Ability to trade energy across the regions in a pool.
Access to funding – the risk profiles are different in each region and therefore
certain countries with a lower risk profile can attract lower costs of funding with less
risk mitigation.
Ability to manage Environmental requirements – some regions have a
concentration risk e.g. coal in SA. Another region may not have that risk hence
resulting in the ability to utilise the regions energy resources more effectively. 2
Regional interconnections are drivers of economic growth and hence job
creation. The associated Transmission Grid projects its self, create jobs in the
regions i.e. Consulting, Engineering, Construction etc.
It attracts investment – Having access to electricity and being able to connect
faster, allows investors to have faster payback periods.
Results in the ability of one region to meet its daily energy deficit if connected
to a interconnected pool.
Increases security of supply.
The access to Generation sources results in the ability of a region/country to
meet its electricity universal access targets towards getting people connected
to the grid.
Technically, interconnecting Transmission networks increases stability under
light loaded situations. Increased Fault Levels assist with Quality of Supply with
regards to voltage fluctuations etc.
Why Connectivity and Interconnectivity cont.
3
Why Connectivity and Interconnectivity cont.
4
Interconnectivity will help with managing the
variability/intermittency aspect of Renewable sources like Wind
and PV.
Being able to dispatch more controlled resources like Hydro and
Pump Storage schemes becomes a reality with Interconnected
systems,
Interconnectivity will assist in reducing the marginal cost of
generation.
Interconnectivity will assist if the load forecasts in any country are
underestimated. Generation from other countries could make up for
this instead of having to load shed.
The need for Grid Connection Capacity
In any Hydro Power Development whether large, medium or small scale, it is
essential to study/determine the Transmission or Distribution Grid Capacity
Availability as one of the first steps.
It is essential to work with the Electricity Utility Engineers/Planners to determine
this capacity.
It will be required that the existing countries or Power Pool’s Grid Code Planning
and connection requirements are met.
Its recommended that Utility Planning Engineers carry out studies on all/most parts of
their networks points, giving a Generation Capacity outlook so that developers
have information on existing and potential Transmission Capacity. E.g. the Eskom
Generation Connection Capacity Assessment (GCCA) reports/updates.
The above does not mean that new capacity with new network development does not
get considered. This only means that there will be a lead time to create network
capacity.
It can take up to 10 years or more depending on the challenges to create new
Transmission lines. 5
The need for Planning Studies within Africa Power Pools
Require medium to long term integrated Energy/Generation and
Transmission Development plans supported by good load/demand
forecasting.
This can be achieved by Power Pools:
o SAPP – Southern African Power Pool
o East African Power Pool
o West African Power Pool
o Central African Power Pool.
o COMELEC
6
Africa Power Pools - Diagram
7
T&D Major Sector Trends
9
• Huge Capital requirements over next 10 years predicted in SA and Africa e.g.
approx. R170billion planned at some point in the Eskom Transmission Development
Plan for new works.
• Africa Transmission Development could be valued much higher than the Eskom
amount above.
• Drivers:
o Economic Growth and Reliability enhancement (Grid Codes and Aging assets)
o Transfer of Bulk Electricity from new Generation nodes in Africa to Load
centres.
o Other African Countries in general have an under-developed Electricity network
– 8-20% of people in Africa (SAPP) have access to electricity.
• Some Bottlenecks:
o Lack of Funding
o Co-operation between countries.
o Lack of Regulatory Frameworks, Planning directives and policies for cross
border trade of power.
o Power Pools can solve these and most power pools seem to be achieving this
goals.
o Difficulty to build Transmission lines through certain regions.