Upload
trinhkien
View
231
Download
4
Embed Size (px)
Citation preview
Operating Committee June 18, 2015
Connecticut River Valley
Project Update
2 2
The Problem The most recent ISO-NE NH/VT 2023 Needs Assessment (completed fall of 2014) identified the following reliability deficiencies: • High voltages near the Hartford 115kV
substation for a single element outage event.
• Overloads on the Coolidge to Ascutney, 115kV, K31 line during N-1-1 contingency events.
• High and low voltages near the Hartford 115kV substation during N-1-1 events.
• Voltage collapse in the Connecticut River Valley during N-1-1 contingency events.
• Breaker Failure at Hartford substation results in loss of 46kV service at Chelsea and Hartford.
Line Overload
Affected Area
3 3
The Solution • Transmission Line – Reconductor the existing, 15 mile, Coolidge to Ascutney,115
kV line known as the K31 line. – Addresses thermal overload – Replaces existing conductor with 1351.5 ACSS (Aluminum Conductor Steel
Supported) – allows operation at a higher temperature – 1351.5 ACSS has nearly identical cross section as VELCO’s standard 1272
ACSR (Aluminum Conductor Steel Reinforced) – Allows VELCO to use its standard 115 kV line design standard – Requires reconductoring of several GMP subtransmission lines – Numerous alternatives considered
4 4
The Solution (continued)
• Voltage Control – Installation of a Static VAr Compensator (SVC), at the Ascutney 115 kV substation. – SVC is a transmission apparatus that uses power electronics technology to
regulate or control system voltage.
– The SVC will have a capacity range of +50 MVAr power injection capability to -25 MVAr power absorption capability.
– Addresses the voltage violations and voltage collapse concerns. – Evaluated and considered alternatives including Statcom, SC, SVC-
TSC/TSR, and SVC-TCR/FC
5 5
Ascutney Substation Details
• The installation of a third bay at the Ascutney, 115kV substation will be needed to accommodate the Static VAr Compensator
6 6
The Solution (continued)
• Chelsea Substation Upgrade – Rebuild the Chelsea 115 kV substation from a
straight bus configuration to a three-breaker ring substation
– Allows continued service to the 46 kV system following a transmission outage event that can cause voltage collapse
– VELCO, Green Mountain Power and Washington Electric Cooperative intend to
replace their respective 46kV oil breakers
– Maintenance on the transformer bushing will be performed and an oil containment system will be installed for the transformer
– Security package and a generator will be installed
– Alternatives under review
7 7
Chelsea Substation
• Preliminary Chelsea Substation General Arrangement
8 8
The Solution (continued)
• Harford Substation - Reduce the existing 25 MVAr capacitor bank at Harford substation to a 12.5 MVAr bank and add a new 12.5 MVAr capacitor bank to the Hartford-Wilder K26 line terminal at Harford substation. – Addresses high voltage concerns following a transmission outage event
– Allows improved operational flexibility
– VELCO and Green Mountain Power will replace their respective 46kV oil
breakers
– An oil containment system will be installed for the transformer
9 9
Harford Substation
• Preliminary Hartford Substation General Arrangement
10 10
Project Status • Ongoing stakeholder communication
– Public outreach meetings (Weathersfield, Cavendish, Chelsea and Hartford). – Meetings with Select Boards (Weathersfied and Chelsea) and Planning Commissions (Windsor) – One-on-One meetings with landowners – Meetings with the Vermont Public Service Department – Presentation to the VELCO Board of Directors – Presentation to the VELCO Operating Committee
• ISO-NE completed the alternative evaluation and issued a letter pursuant to
Section I.3.9 of the ISO Tariff stating that no significant adverse effect has been identified regarding the project.
• VELCO currently anticipates filing the 45 Day package in July 2015.
• VELCO currently anticipates filing a Petition with the Public Service Board seeking a Certificate of Public Good during Q3 2015.
• Preliminary estimate is $137.6 Million - effort to refine estimate is currently underway
11 11
Project Schedule
• Subject to Public Service Board approval, VELCO expects to begin substation construction in summer 2016, and line construction from fall 2016 to winter 2017 (access work will start in the summer or fall of 2016)
• Expected Commissioning Dates: – Hartford Capacitor Banks – December 2016 – Ascutney Bay Addition – March 2017 – Chelsea Rebuild – June 2017 – Ascutney SVC – December 2017