Conf12 Wallner

Embed Size (px)

Citation preview

  • 7/27/2019 Conf12 Wallner

    1/36

    Gas-Insulated-Substations

    SF6 gas handling

    EPAs 2012 Workshop on SF6-emission reduction strategies

    Atlanta, Georgia; April 17-18, 2012

    Copyright Siemens AG

    Energy Sector Power Transmission High Voltage SubstationsPeter GlaubitzChristian Wallner

  • 7/27/2019 Conf12 Wallner

    2/36

    Introduction

    SF6 in a lifecycle process CO2-footprint reduction of GIS

    Handling of SF6

    Regulations on SF6

    Conclusion

    Page 2Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

  • 7/27/2019 Conf12 Wallner

    3/36

    Power Transmission

    Page 3Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    High Voltage Substations are the backbone of the Transmission System

  • 7/27/2019 Conf12 Wallner

    4/36

    Requirements for

    -

    High system reliability

    ,

    Compact space saving solutions Innovative solutions (devices, switchgears)

    Low li e cycle costs

    Reliable and competent partners (operator, manufacturer)

    Smart and Power grid adaptation Environmental-sustainability

    Page 4Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

  • 7/27/2019 Conf12 Wallner

    5/36

    SF6 is colorlessly, odorless and a

    6

    SF6 is 5x heavier than air, is not toxic and

    SF6

    is no hazardous material

    SF6 has no eco-toxic potential

    SF6 has no impact for the ozonosphere

    SF6 is a potent greenhouse gas (GWP* 22,800** x CO2)

    Page 5Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    6 as exce en eec rca c arac ers cs

    * Global Warming Potential; ** according to EU-F-Gas regulation

  • 7/27/2019 Conf12 Wallner

    6/36

    SF6-emissions

    l g

    Herstellungroducing SF6 EntwicklungPr fungManufacturingProduktion

    DevelopmentTests Commissioning

    indust

    ri

    rocessi

    SF6 is used in a closed cycle

    UseecommissioningRecycling of SF6for reusedividual

    cessing

    in

    pr

    Page 6Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    =

  • 7/27/2019 Conf12 Wallner

    7/36

    SF6

    6

    Emission

    SF6-handling losses SF6-leakage

    +

    Technical recommendation in e.g. Definition in IEC-standards,

    Cigr SF6-Handling Guide No. 276 like IEEE C37.122, IEC 62271-203,Cigr SF6-Tightness Guide No. 430

    Page 7Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

  • 7/27/2019 Conf12 Wallner

    8/36

    -

    [%]

    8D2

    80

    90

    100

    Size of building

    Space requirement

    Packing volume

    example: the development of the

    Siemens GIS 145 kV

    40

    50

    60

    8D8 8DN9

    8DN8

    0

    10

    20

    68 70 72 74 76 78 80 82 84 86 88 90 92 94 96 98

    source: Siemens

    2010

    The developments within the last decades have led to smaller gas

    compartments of the switchgear and thus to considerably less used

    year

    Page 8Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    amount of SF6 at the same performance data.

  • 7/27/2019 Conf12 Wallner

    9/36

    6

    -- 68%68%

    -- 77%77%

    -- 75%75%

    8D.5 8DQ1

    420 kV

    8D.5 8DQ1

    420 kV

    8D.6 8DN8

    145 kV

    8D.6 8DN8

    145 kV

    8D.4 8DN9

    245 kV

    8D.4 8DN9

    245 kV

    type of GIS

    A significant reduction of SF6 was reached by using modern development

    Siemens GIS, Cable bay with double busbar system including 2 BBSiemens GIS, Cable bay with double busbar system including 2 BB DS, 1 line DS, 1 CB, 3 ESDS, 1 line DS, 1 CB, 3 ES

    Page 9Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    introduction of the GIS-technology in 1968

  • 7/27/2019 Conf12 Wallner

    10/36

    Reduction of SF6-emissions in the factory

    Test object is inside

    Test box is equippedwith inspection

    All connections are

    gastight Operation of rupture

    disc will allow SF6 toemitt in the test box

    SF6 will be collectedin a closed cycle aftertestin

    Page 10Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    Internal arc testing without SF6-emission

  • 7/27/2019 Conf12 Wallner

    11/36

    -

    The componentes ng mus assure

    very low SF6emission by usingstate-of-the-art-handling equipmentin the factories

    Page 11Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    Internal tightness of components

  • 7/27/2019 Conf12 Wallner

    12/36

    -6

    - - - -

    equipment

    regularly checks and trainedstaffs

    Page 12Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    Achieving low SF6 emission during production

  • 7/27/2019 Conf12 Wallner

    13/36

    -6

    Environmentally respondsiblebehavior and state-of-the-artequpmen s ea s o ow 6-emission in the factory

    Page 13Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    Source: GIS Factory Berlin

  • 7/27/2019 Conf12 Wallner

    14/36

    Optimized gas work needs

    1 mbar SF6- SF6- measurement SF - collectin devicemaintenance

    unit

    device

    %- SF6,dew-point temperature,

    for measurement of gas

    6-

    Source: DILO

    Page 14Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

  • 7/27/2019 Conf12 Wallner

    15/36

    SF6 Recollection

    Gas flows through theinstrument into recovery bag(SF6-recollecting pipe)

    No emission!

    Page 15Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    Source: DILO, GAS-WIKA-Siemens

  • 7/27/2019 Conf12 Wallner

    16/36

    6

    Use of strong and big maintenance units - should be able to recoveru u

    Minimum Residual pressure to be achieved < 20mbar - according to IEC62271-303-

    compartments it's not always possible.

    Page 16Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

  • 7/27/2019 Conf12 Wallner

    17/36

    6

    10kg]

    SFSF66--residual quantity (emission) dependence on the SFresidual quantit y (emission) dependence on the SF66 rated filling pressure /rated filling pressure /

    compartment size / SFcompartment size / SF66 residual pressureresidual pressure

    7

    8

    9

    residualqua

    ntity

    [

    420 kV-circuit breaker, 3-pole- volume: approx. 7000 l

    - working pressure: 6,6 bar abs.

    420 kV-disconnector, 3-pole

    - volume: approx. 870 l

    - working pressure: 4,8bar abs.

    4

    5

    6SF6

    - SF6-amount: approx. 300 kg

    - SF6-density: 43 g/l

    - SF6-amount: approx. 27 kg

    - SF6-density: 26,7 g/l

    1

    2

    3

    With State-of-the-art-handling equipment SF6 recovery of each gas compartment

    0 20 40 60 80 100 120 140 160 180 200

    SF6 residual press ure [m bar]Source: Cigr-Guide no. 276; Application of table 25

    Page 17Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    very ow pressure - m ar s poss e, us securng osses o a easless than 2% during maintenance and end of life.

  • 7/27/2019 Conf12 Wallner

    18/36

    Gas-tightness

    Gas-tightness essential for the functionality static and dynamic solutions

    IEC 62271-203 High-voltage switchgear and controlgear Part 203: Gas-insulatedmetal-enclosed switchgear for rated voltages above 52 kV (09/2011)

    required leakage rate

  • 7/27/2019 Conf12 Wallner

    19/36

    Type testing on SF6-tightness according to

    Nowadays SF6-tightness can be confirmed (integral measuringprocess with state-of-the-art measurement devices) in the range of

  • 7/27/2019 Conf12 Wallner

    20/36

    State-of-the-art

    n

    145 kV145 kV

    1968

    Number ofinstalled bays

    evoluti

    Theimagecannotbedisplayed.Your computer may nothaveenough memory to open theimage,or theimagemay havebeen corrupted.Restartyour computer,and then open thefi leagain.Ifthered x stillappears,you may haveto del etetheimageand then insertitagain.

    Todays

    experience

    GI

    2012.- No generic life limitation- Issues of aging and deteriorationGas leakages

    Theimagecannotbedisplayed.Your computer may nothaveenough memory to open theimage,or theimagemay havebeen corrupted.Restartyour computer,and then open thefil eagain.Ifthered x stillappears,you may haveto deletetheimageand then insertitagain.

    Originallyexpectedlife-time

    Secondary systems Corrosion

    FirstInstallation

    0 5040302010

    Page 20Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    Continuous development assures the sustainable performance

  • 7/27/2019 Conf12 Wallner

    21/36

    In the Past State-of-the-art-technology

    6

    Short maintenance intervals (frequentopening of gas compartments) 2 openings during life time: once after 25years of service, once during end-of-lifeprocedure after 40-50 years.

    Limited SF6-handling instruction Detailed explained SF6-handling instructionand regulations

    SF6-maintenance units with a minimum High power SF6-maintenance units with6- - 6-

    Insensitive SF6-leakage detectors Sensitive SF6-leakage detectors to findsmallest leaks

    - -

    collecting the used gas

    gas are now offeredFundamental tests and implementation ofnew production processes

    Using Helium for leakage detection wherepossible (e.g. housing leakage test)

    Page 21Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    Since the implementation is a continuous improvement

  • 7/27/2019 Conf12 Wallner

    22/36

    SF6 History 2005 Implementation

    Based on the previous voluntary commitment(1996)

    Agreed with and recognized by the GermanGovernment in 2005

    Sco e: Switch ear and Com onents >1 kV

    Quantified and dedicated targets for 2020 bylifecycles and responsibilities

    Annual monitorin of activit data andemissions according to IPCC 2006Guidelines for verification

    Mission:SF6-emissions should be avoided wherever possib le.

    The specific quantity of SF6 used to fulfill functions is

    Page 22Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    .

  • 7/27/2019 Conf12 Wallner

    23/36

    6

    1.200.000 1,1Bestand (kg) Emissionsrate (%)

    1.050.000

    1.100.000

    1.150.000

    0,8

    0,9

    1

    850.000

    900.000

    950.000

    . .

    inkg

    0,5

    0,6

    0,7

    in%

    700.000

    750.000

    800.000

    0,2

    0,3

    0,4

    600.000

    650.000

    2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010

    0

    ,

    Page 23Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    Emission on electric power equipment 2000 - 2010

    - . .

  • 7/27/2019 Conf12 Wallner

    24/36

    SF6-emissions

    l g

    Herstellungroducing SF6 EntwicklungPr fungManufacturingProduktionDevelopment

    Tests Commissioning

    indus

    tri

    roces

    si

    SF6 is used in a closed cycle

    UseecommissioningRecycling of SF6for reusedividual

    cessing

    in

    p

    r

    The EU-F-Gas regulation concentrates

    Page 24Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    =

    on the individual processing

  • 7/27/2019 Conf12 Wallner

    25/36

    EU-F-Gas regulation 842/2006

    *

    Regulation (EC) No 842/2006 of the European Parliamentand of the Council on fluorinated greenhouse gases

    SF6 is considered in limited products only

    The use of SF6 in electric power

    equipment is permitted

    Certain measures to be carried out bymanufacturers and users have been

    Amendments have been released to

    Page 25Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    *California Air Resources Board

  • 7/27/2019 Conf12 Wallner

    26/36

    European F-Gas-regulation 842/2006 -

    6

    (EC) 305/2008 definitions, minimum

    Article 5 Trainin andRegulation (EC)

    (EC) 1493/2007 defini tions, format

    requirement on certification of staffcertification.on certainfluorinated

    greenhouse* of reporting

    (EC) 1494/2007 defini tions, formArticle 7 Labelling

    o a e s

    Page 26Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    *) certain fl uorinated greenhouse gases means hydrofluorocarbons (HFCs), perfluorocarbons (PFCs) and sulphur hexafluoride (SF6)

  • 7/27/2019 Conf12 Wallner

    27/36

    European F-Gas-regulation 842/2006, article 2

    Definitions for SF6-handling

    Recovery

    Collection and storage of SF6 from electric power equipment or containers

    in practice: taking out SF6 from equipment and putting it into a container Recycling

    Reuse o recovered F6 ollowing a basic cleaning process in practice: recycling of SF6 on site Reclamation

    * 6performance in practice: used SF6 is reprocessed (e.g. SF6-production plant)

    Destruction

    Transformation or destruction into one or more stable substances which are notfluorinated GHG in practice: burning of SF6

    * - IEC 60376 S ecification of technical rade sulfur hexafluoride SF for use in electrical e ui ment

    Page 27Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    - IEC 60480 Guidelines for the checking and treatment of sulfu r hexafluoride (SF6) taken from electrical equipment and specification for its re-use

  • 7/27/2019 Conf12 Wallner

    28/36

    European F-Gas-regulation 842/2006, article 5

    *

    Commission regulation No. 305/2008 establishing minimum requirements and

    the conditions for mutual recognition for the certification of personnel recovering

    certain fluorinated GHG from HV switchgear

    Process and responsibilities

    IndividualIndividualTrainingnotsubectto

    Evaluation

    bod / Proof of Certification

    certificatecertificate

    conditions of

    regulation)

    Examination

    (content defined)

    competenceo y ssues

    certifications

    Evaluation body andCertification body have

    to be independent

    Page 28Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    *) regulation refers to HV switchgear only

  • 7/27/2019 Conf12 Wallner

    29/36

    European F-Gas-regulation 842/2006, article 6

    The reporting is a must to do in case of

    SF6 > 1 t SF6 > 1 tcountry A country BImport Export

    EuropeanUnion

    or bottles or bottles

    The reporting is not necessary for

    import /import /import /import /

    exportexport

    exporexporinside EUinside EU

    countriescountries

    equipmentequipment < 1 t per< 1 t peryear andyear and

    companycompany

    Page 29Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    In some countries additional voluntary commitments regarding reporting exist

  • 7/27/2019 Conf12 Wallner

    30/36

    European F-Gas-regulation 842/2006, article 7

    Standards required SF6-weight already in the past: declaration ofweight of gas according toIEEE C37.122 or IEC 62271-203

    additional label*NEW

    *

    The label shall be placed clearly, indelibly andadjacent to the service point of the equipment

    Weight of SF6 filling 99 kg

    Page 30Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    between the different manufactures

  • 7/27/2019 Conf12 Wallner

    31/36

    Review required 5 years after implementation (7/067/11)

    epor o e comm ss on pu s e on ep em er ,

    includes 26 substances, one is SF6

    positive results regarding our electrical power applications

    strong reduction of F-gas-emission demanded in general

    No modification for electrical power equipment, very small adjustments

    -,

    Other branches/ substances strongly affected

    Draft of modified EU-F-Gas-regulation

    will be available autumn 2012 (planned by EU-commission)

    Final decision by the EU Parliament

    Scheduled until beginning of 2014

    Page 31Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    Link: http://ec.europa.eu/clima/policies/f-gas/index_en.htm

  • 7/27/2019 Conf12 Wallner

    32/36

    SF RECYCLING6GUIDE

    No. 234

    Avoid SF6handlinglosses due to state-of-the-art handling

    2003SF6 HANDLING

    GUIDE

    Guarantee of SF6 tightness due to state-of--

    .

    2005 SF6 TIGHTNESSGUIDE

    2012

    Cigr SC B3 delivers and bundles

    all technical and environmentally

    No. 430

    Page 32Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    aspects on SF62010

  • 7/27/2019 Conf12 Wallner

    33/36

    6

    WG B3.17 Residual life concepts applied to HV GIS

    (Finished, will be published in 6/2012) WG B3.25 SF anal sis for AIS1/GIS and MTS2 Condition Assessment

    WG B3.30 Guide to minimize the use of SF6 during routine testing

    1 Air Insulated Switchgear2 Mixed Technology Switchgear

    Page 33Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    Brochures can be downloaded on http://www.e-cigre.org/

  • 7/27/2019 Conf12 Wallner

    34/36

    - ommon spec ca ons or 6- nsua e an air-insulated high-voltage switchgear and controlgear

    IEC 62271-200 Standard of medium-voltage SF6-GIS

    - - Revision published in 9/2011

    IEC 62271-3031 Use and handling of SF6

    IEC 603762 Specification for new SF6-gas IEC 604802 Checking and treatment of sulfur hexafluoride (SF6) taken from electric equipment IEEE C37.122 Gas Insulated Substations IEEE C37.122 IEEE Guide for Sul hur Hexaflouride

    ASTM D2472-00 SF6-gas1 Revision in progress: IEC 62271-42 Maintenance of the standardscheduled until 2014.

    Page 34Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    Target: 1 standard only, SF6-Gas mixtures to be included, recommendation on monitoring

  • 7/27/2019 Conf12 Wallner

    35/36

    Implementation of adequate maintenance

    strategy for aged equipment

    Evaluation of each SF6-leakage for

    systematical or individual failure

    Gas tight equipment and low SF6

    -emission

    reduce life-cycle costs

    Residual Life of equipment goes in line with

    ow6-emss on

    For end-of-life procedures, SF6 has to be

    Page 35Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

  • 7/27/2019 Conf12 Wallner

    36/36

    Thank you for your attention!

    GIS Lead-Factory Berlin, Germany

    Page 36Copyright Siemens AG

    Energy Sector - Power Transmission - High Voltage SubstationsChristian Wallner

    r. r s an a ner

    Tel. +49 9131 7 33811

    eMail [email protected]

    e er au z

    Tel. +49 9131 7 35010

    eMail [email protected]