125
Lassonde Mineral Engineering Program University of Toronto Capstone Final Report: MIN467 Submitted to: David Eden From: Giancarlo Volpe, Pearl Barrett, Tsun Yu Lam, Faraz Chattha Date: Thursday April 7, 2015 Subject: Grum Project - Faro

Conceptual Mine Design, Grum YT

Embed Size (px)

Citation preview

Page 1: Conceptual Mine Design, Grum YT

Lassonde Mineral Engineering Program

University of Toronto

Capstone Final Report: MIN467

Submitted to: David Eden

From: Giancarlo Volpe, Pearl Barrett, Tsun Yu Lam, Faraz Chattha

Date: Thursday April 7, 2015

Subject: Grum Project - Faro

Page 2: Conceptual Mine Design, Grum YT

2

Executive Summary

Northwestern Canada is home to the Grum Deposit, located in central Yukon. Approximately 200 km

north of its capital, Whitehorse, the deposit makes up one of 7 deposits in the 35 kilometer long Anvil

Range. In previous work a preliminary pit design was constructed using basic economic assumptions.

This was complemented through a detailed investigation of the geotechnical properties of the rock

which were used to assess the stability of the pit slopes.

At this stage of the design, more realistic parameters, including costs and a detailed ramp design, have

allowed for the construction of a detailed pit design. The ramp was based on a Cat 785C haulage truck,

selected at this stage of design, with a grade of 10%. Switchbacks weren’t incorporated to promote

safety and prevent significant changes in the pit economics.

A detailed preliminary design of the site’s waste rock dump (WRD) and tailings storage facility (TSF) have

been constructed. Both designs have assumed a conservative slope geometry and knowing this, a

numerical model was developed to design both facilities. The acidic properties of the waste and slurry

material draw concerns for the possibility of acid mine drainage (AMD). A wet cover on the TSF was

therefore decided to limit this generation in the generally humid climate of the Faro area.

Additionally, a basic water balance was conducted for both waste facilities. The results suggest the

tailings facility may require additional pumping to provide adequate water for the wet cover.

Consequently, the water balance also suggests the possibility of further optimization to the TSF design.

Leading to the start of production, Benny Resource Group (BRG) will obtain all required permits, licenses

and approvals. The primary stakeholders consist of the Faro community and the Kaska people, both

affected environmental changes. As such, a preliminary Impact Benefit Agreement is also included to

outline the positive impacts the project may have on the community, while a risk matrix was used to

assess various negative impacts. It is important for BRG to prevent another Faro Mine disaster and

foster mutual respect with the communities. The site layout is designed to reflect such considerations

BRG will implement progressive reclamation and obtain all permits required for mine closure, in

compliance with the government of Yukon. Furthermore, consultation with First Nations and community

stakeholders on all phases of mine closure will be essential. The main environmental concern for closure

will be the occurrence of AMD, and as a result engineered covers will be employed on the WRD, a water

cover for the TSF, while the pit will be flooded to limit AMD. The estimated reclamation cost is between

$7 and $15 Million.

The current economic study of the design suggests a Net Present Value of $156.1 Million is attainable

with a 4.8 year payback period, a mine life of 20 years, and 2 additional years of pre-stripping.

Additionally specific smelters have been considered to begin a preliminary look into appropriate metal

markets, and the associated costs have been weighed. The current state of this study suggests that the

project should be brought to the next stage. In this case, baselines studies, further site investigation and

detailed metallurgical testing should be considered as next steps.

Page 3: Conceptual Mine Design, Grum YT

3

Signatures of Authors

The following signatures verify the group of graduating personnel known as “Benny Resource

Group,” have written and reviewed the contents of this document.

Pearl Barrett

Giancarlo Volpe

Faraz Chattha

Tsun Yu Lam

Page 4: Conceptual Mine Design, Grum YT

4

Table of Contents

Executive Summary ................................................................................................................................................................ 2

Signatures of Authors ............................................................................................................................................................ 3

1 Background .................................................................................................................................................................... 13

2 Previous Analyses ........................................................................................................................................................ 13

2.1 Rock Mass Properties ....................................................................................................................................... 13

2.2 Geotechnical Domains ...................................................................................................................................... 14

2.3 Slope Stability Analysis .................................................................................................................................... 15

3 Detailed Pit Design ...................................................................................................................................................... 16

3.1 Ramp Design ........................................................................................................................................................ 16

3.1.1 Ramp Width ................................................................................................................................................ 17

3.1.2 Ramp Section Design ............................................................................................................................... 18

3.1.3 Ramp Maintenance .................................................................................................................................. 19

3.2 Pit Slope Geometry ............................................................................................................................................ 19

4 Production Scheduling ............................................................................................................................................... 20

5 Preliminary Processing Design .............................................................................................................................. 24

6 Tailings Storage Facility Design ............................................................................................................................. 25

6.1 Selection of an Appropriate Cover System .............................................................................................. 25

6.2 Design of the Dam Geometry ......................................................................................................................... 26

6.3 Considerations for Dam Construction ....................................................................................................... 28

7 Design of the Waste Rock Dump ............................................................................................................................ 29

8 Site Layout ...................................................................................................................................................................... 31

8.1 Background ........................................................................................................................................................... 31

8.2 Placement Methodology .................................................................................................................................. 31

8.3 Tailings Storage Facility .................................................................................................................................. 32

8.4 Additional Site Requirements ....................................................................................................................... 34

8.4.1 Processing Mill ........................................................................................................................................... 34

8.4.2 Explosives Storage and Handling ....................................................................................................... 34

8.4.3 Technical Departments .......................................................................................................................... 34

Page 5: Conceptual Mine Design, Grum YT

5

8.4.4 Environmental Systems ......................................................................................................................... 35

9 Water Balance of the Mine Site .............................................................................................................................. 35

9.1 Water Balance of the Waste Rock Dump .................................................................................................. 35

9.2 Water Balance of the Tailings Storage Facility ...................................................................................... 37

10 Operations Planning .............................................................................................................................................. 39

10.1 Equipment Selection and Pricing Model ................................................................................................... 39

10.1.1 Daily Ore and Waste Production ........................................................................................................ 40

10.1.2 Daily Productive Hours .......................................................................................................................... 41

10.1.3 Required Hourly Production Rate ..................................................................................................... 41

10.1.4 Potential Truck and Shovel Models ................................................................................................... 42

10.1.5 Properties of Trucking Routes ............................................................................................................ 42

10.1.6 Time Spent on Travelling to and from Dump and Mill .............................................................. 43

10.1.7 Loading Time .............................................................................................................................................. 43

10.1.8 Truck Cycle Time ...................................................................................................................................... 44

10.1.9 Number of Required Shovels ............................................................................................................... 44

10.1.10 Additional Equipment and Support Fleet .................................................................................. 46

10.2 Benchmarking...................................................................................................................................................... 46

10.2.1 ARCTIC (NovaCopper Inc.) ................................................................................................................... 46

10.3 Meadowbank (Agnico-Eagle Mines Ltd.) .................................................................................................. 47

11 Environmental and Social Impact Assessment ........................................................................................... 47

11.1 Required Legal Documents ............................................................................................................................ 47

11.2 Valued Ecosystem Components ................................................................................................................... 48

11.2.1 Atmospheric Systems.............................................................................................................................. 48

11.2.2 Water Systems ........................................................................................................................................... 49

11.2.3 Terrestrial Environment ....................................................................................................................... 50

11.2.4 Natural Heritage System ........................................................................................................................ 51

11.2.5 Socio-Economic Factors ......................................................................................................................... 51

11.3 Assessment of Impacts ..................................................................................................................................... 52

11.4 Impact Benefit Agreement .............................................................................................................................. 53

12 Mine Closure ............................................................................................................................................................. 54

12.1 Introduction ......................................................................................................................................................... 54

Page 6: Conceptual Mine Design, Grum YT

6

12.2 Regulatory Requirements ............................................................................................................................... 55

12.2.1 Permits .......................................................................................................................................................... 55

12.3 Environmental Studies ..................................................................................................................................... 55

12.3.1 Environmental Baseline Studies ........................................................................................................ 56

12.4 Objectives and Environmental Issues ........................................................................................................ 56

12.4.1 Acid Mine Generation ............................................................................................................................. 57

12.5 Environmental Management ......................................................................................................................... 57

12.5.1 Waste Rock Dump .................................................................................................................................... 57

12.5.2 Tailings Dam ............................................................................................................................................... 58

12.5.3 Pit Lake ......................................................................................................................................................... 58

12.6 Site Monitoring .................................................................................................................................................... 59

12.6.1 Water ............................................................................................................................................................. 59

12.6.2 Air .................................................................................................................................................................... 59

12.6.3 Acid Mine Drainage .................................................................................................................................. 59

12.7 Community Relations ....................................................................................................................................... 60

12.8 Closure Costs ........................................................................................................................................................ 60

13 Detailed Economic Analysis ................................................................................................................................ 61

13.1 Revenues: $6,163,000,000 ............................................................................................................................. 64

13.1.1 Price ............................................................................................................................................................... 64

13.1.2 Variable Grades and Contained Metal over LOM ......................................................................... 65

13.1.3 Variable Rock Type, Recoveries, and Recoverable Metal over LOM ................................... 66

13.1.4 Smelter Terms ............................................................................................................................................ 67

13.2 Operating Costs: $2,902,000,000 ................................................................................................................ 67

13.2.1 Mining Operating Cost: $1,171,500,000 from $3.01/tonne mined ..................................... 67

13.2.2 Processing Cost: $741,200,000 from $14.05/tonne milled .................................................... 68

13.2.3 Freight Cost: $326,700,000 from $74.50/dmt ............................................................................. 68

13.3 Capital Cost: $534,200,000 ............................................................................................................................ 71

13.3.1 Processing Equipment Capital Cost: $108,400,000.................................................................... 71

13.3.2 Mining Equipment Capital Cost: $86,900,000 .............................................................................. 71

13.3.3 Capital Pre-strip Cost: $115,500,000 ............................................................................................... 72

13.3.4 Closure Cost: $15,000,000 .................................................................................................................... 72

13.3.5 Sustaining Capital: $145,300,000 ...................................................................................................... 72

Page 7: Conceptual Mine Design, Grum YT

7

13.4 Taxes: $911,700,000 at a 30% tax rate ..................................................................................................... 72

14 Conclusions & Recommendations .................................................................................................................... 72

15 References .................................................................................................................................................................. 73

16 Appendices ................................................................................................................................................................ 77

16.1 Ramp Design Considerations ........................................................................................................................ 77

16.2 Re-sloped Pit Calculations .............................................................................................................................. 79

16.3 Equipment Unit Costs ....................................................................................................................................... 80

16.4 Provided Metallurgical Recovery Data ...................................................................................................... 81

16.5 Initial Tailings Volumes ................................................................................................................................... 82

16.6 TSF Volume Calculations: Volume of a Truncated Pyramid ............................................................. 83

16.7 Summary of the Annual Rate of Rise of Tailings Deposition ............................................................ 84

16.8 Soil Classification of the Overburden Material ...................................................................................... 85

16.9 TSF Option Comparison ................................................................................................................................... 86

16.10 WRD Option Comparison ........................................................................................................................... 88

16.11 Detailed Water Balance ............................................................................................................................... 90

16.12 Suggested Water Pumping Schedule to Maintain the Water Cover .......................................... 92

16.13 Measurement of Truck Routes ................................................................................................................. 93

16.14 Rimpull and Retardation Curves ............................................................................................................. 96

16.15 Travel Times ................................................................................................................................................. 102

16.16 Loading Times.............................................................................................................................................. 103

16.17 Number of Trucks Required per Shovel............................................................................................ 105

16.18 Environmental and Social Impact Assessment .............................................................................. 108

16.19 Closure Costs ................................................................................................................................................ 121

16.20 Contained Process Metals ....................................................................................................................... 122

16.21 Mill Recoveries Used for Economics ................................................................................................... 123

16.22 Sustaining Capital ....................................................................................................................................... 124

16.23 Depreciation and Tax Calculations ...................................................................................................... 125

Page 8: Conceptual Mine Design, Grum YT

8

List of Tables

Table 2-1 Recommended Bench Face Angles for slopes governed by Wedge failure ................................ 16

Table 2-2 Overall pit slope safety factors for each sector, at different water saturations ........................ 16

Table 3-1 Purpose of each layer in designing a ramp ................................................................................. 19

Table 3-2 Adjusted Pit Slope Parameters ................................................................................................... 20

Table 5-1 Summary of Contained Metals before processing, Recovered Metals and Average Metal

Grades ......................................................................................................................................................... 24

Table 5-2 Results of the Preliminary Mass Balance for Froth Floatation ................................................... 25

Table 6-1 Summary of Key Parameters of the Final TSF Design ................................................................. 28

Table 6-2 Estimates for required Material needed to construct the Final TSF design ............................... 28

Table 7-1 Summary of Total Waste Rock Volume Determination with Suggested Volume Adjustment

Factors [8] ................................................................................................................................................... 30

Table 7-2 Summary of Final WRD Design Parameters ................................................................................ 30

Table 9-1 Key Coefficients used in Conducting the Mine Water Balance [9] ............................................. 35

Table 9-2 Summary of the WRD Water Balance ......................................................................................... 36

Table 9-3 Summary of the water movement contributions for water movement of each stream in the

TSF water balance ....................................................................................................................................... 38

Table 9-4 Summary of water contributions for water movement of each stream after incorporating

additional pumping ..................................................................................................................................... 39

Table 10-1 Summary of chosen loading and haulage fleet ......................................................................... 39

Table 10-2 A summary of mining rates near the end of mine life. ............................................................. 41

Table 10-3 A summary of net productive hours calculation. ...................................................................... 41

Table 10-4 The distances, grades and rolling resistances involved in the haulage routes for ore and

waste. .......................................................................................................................................................... 43

Table 10-5 Number of trucks and shovel s expected throughout the mine life ........................................ 46

Table 10-6 Number of additional and support equipment expected ........................................................ 46

Table 10-7 A comparison of preliminary equipment fleets of Grum and NovaCopper’s ARCTIC .............. 46

Table 10-8 A comparison of loading and haulage fleets between Grum and Agnico Eagle’s Meadowbank

.................................................................................................................................................................... 47

Table 11-1 Permits for various Mine Activities ........................................................................................... 48

Table 11-2 Summary of Key Impacts, Causes, and Mitigation Strategies ................................................... 52

Page 9: Conceptual Mine Design, Grum YT

9

Table 12-1 Permits Required for Mine Closure .......................................................................................... 55

Table 12-2 Environmental Baseline Studies ................................................................................................ 56

Table 12-3 Estimated Closure Costs ............................................................................................................ 61

Table 13-1 – Performance metrics .............................................................................................................. 61

Table 13-2 - Summary of financial results .................................................................................................. 61

Table 13-3 - The forecast prices used for the model .................................................................................. 64

Table 13-4 - The long term price forecasts and the average, consensus price from three banks .............. 65

Table 13-5 - The recoveries of each metal for each rock type.................................................................... 66

Table 13-6 - Smelter terms used, adapted from Prices and Revenues [40] ............................................... 67

Table 13-7 – The total capital costs associated with the total mining equipment fleet ............................ 71

Table 16-1 Summary of Associated Unit Costs for Selected Machinery ..................................................... 80

Table 16-2 Preliminary Recovery Data Provided for the Grum Deposit ..................................................... 81

Table 16-3 Table Showing the process in Calculating Annual Tailings Volumes......................................... 82

Table 16-4 Table Showing Summary of Tailings Rate of Rise for the final TSF design. Notice the given

Storage Length and Width used in the design. ........................................................................................... 84

Table 16-5 Summary of the Soil Classification of the Grum Overburden Material, including Key Findings

.................................................................................................................................................................... 85

Table 16-6 Economic Indicators TSF Option Comparison ........................................................................... 86

Table 16-7Environmental Indicators TSF Option Comparison .................................................................... 87

Table 16-8 Social Indicators TSF Option Comparison ................................................................................. 87

Table 16-9 Economic Indicators WRD Option Comparison ........................................................................ 88

Table 16-10 Environmental Indicators WRD Option Comparison .............................................................. 89

Table 16-11 Social Indicators WRD Option Comparison ............................................................................. 89

Table 16-12 Summary of the reported Detailed Water Balance ................................................................ 90

Table 16-13 Summary of the Recommended Pumping Schedule and resulting Water Balance (note the

negative values require pumping of water out of the dam)....................................................................... 92

Table 16-14 - Travel times for various road segments on the route of a CAT 777G ................................ 102

Table 16-15 -Travel times for various road segments on the route of a CAT 785D ................................. 102

Table 16-16 - Travel times for various road segments on the route of a CAT 789D ................................ 102

Table 16-17 -The time involved in a load, haul, dump, return cycle of a CAT 777D................................. 103

Table 16-18 - The time involved in a load, haul, dump, return cycle of a CAT 785D ................................ 104

Page 10: Conceptual Mine Design, Grum YT

10

Table 16-19 -The time involved in a load, haul, dump, return cycle of a CAT 789D................................. 105

Table 16-20 - The number of CAT 777G trucks required for each type of shovel .................................... 105

Table 16-21 - The number of CAT 785D trucks required for each type of shovel .................................... 106

Table 16-22 - The number of CAT 789D trucks required for each type of shovel .................................... 107

Table 16-23 Yukon Air Quality and Particulate Matter Standards ............................................................ 108

Table 16-24: Yukon water quality standards to monitor and follow, the bolded items are pertinent to the

Grum Site. ................................................................................................................................................. 110

Table 16-25: Risk assessment criteria for event severity .......................................................................... 111

Table 16-26: Risk assessment criteria for event probability ..................................................................... 112

Table 16-27: Risk Matrix ........................................................................................................................... 112

Table 16-28: Impact assessment: Pit development and mining ............................................................... 113

Table 16-29: Impact assessment: Waste rock dump ................................................................................ 116

Table 16-30: Impact assessment: Tailings storage facility ........................................................................ 116

Table 16-31: Impact assessment: Waste Management ............................................................................ 117

Table 16-32: Impact assessment: General operational ............................................................................ 118

Table 16-33: Impact assessment: Closure and remediation ..................................................................... 118

Table 16-34: Impact assessment: Natural disasters ................................................................................. 120

Table 16-35 Unit Costs of Items Needed for Closure ................................................................................ 121

Table 16-36 - The effective recoveries and recoverable metal of ore sent to the mill for each year of mine

production................................................................................................................................................. 123

Table 16-37 - The effective recoveries and recoverable metal of ore sent from the stockpile ............... 124

Table 16-38 - The calculated sustaining capital to be allotted annually over the LOM ........................... 124

Table 16-39 - Depreciation (at 20%) and tax (at 30%) calculations .......................................................... 125

List of Figures

Figure 2-1 Conservative Mohr Coulomb Criterion for Joint Strength, assuming no cohesion ................... 14

Figure 2-2 Simplified outline of the proposed Grum Pit, divided into 10 sectors with 8 unique

orientations ................................................................................................................................................. 15

Figure 2-3 Visualization of the Pit's Geotechnical Domains ....................................................................... 15

Figure 3-1 Two-Way Traffic Ramp Design ................................................................................................... 17

Page 11: Conceptual Mine Design, Grum YT

11

Figure 3-2 Ramp design for pushback 27. Note that the ramp exit is towards the southeast part of the

pit, making the haulage distance to WRD shorter. Thus increasing productivity. ..................................... 18

Figure 3-3 Construction Layers of the Ramp Surface ................................................................................. 19

Figure 3-4 Pit Wall Geometry for Sectors 8, 10, 9&1 .................................................................................. 20

Figure 4-1 - The production schedule needed to meet a 3.2 Mt mill capacity. The first year could be

ramped over the preceding two years, as indicated by the arrow. ............................................................ 21

Figure 4-2 -The production schedule with an initial ramp up. Further smoothing of production can be

achieved by distributing higher production in the end of mine life to earlier periods. ............................. 21

Figure 4-3 - A production schedule with low deviation; note that production is not divided into “Ore

Mined” and “Waste Mined”, but “Processed Ore” and “Waste Dump or Stockpile”. “Ore Mined” could

be processed in the mill or stored in stockpile, and “Processed Ore” could from the mine or stockpile. . 22

Figure 4-4 -The tonnage of waste associated with every 80, 000 tonnes of ore, over 766 intervals. ........ 23

Figure 4-5 - A schedule with balanced milling and production rates, using stockpiles. ............................. 23

Figure 6-1 Simplified Cross Section through the Final TSF Dam Design ..................................................... 26

Figure 6-2 Simplified Representation (in Plan View) of the Final TSF Dam Design (not to scale) .............. 27

Figure 8-1 Site layout with main geographically significant structures ...................................................... 31

Figure 8-2 Tailings Facility Site Options ...................................................................................................... 33

Figure 8-3 Waste Rock Dump Site Options ................................................................................................. 34

Figure 9-1 Visual Interpretation of the Yearly WRD Water Balance ........................................................... 37

Figure 9-2 Simplified Interpretation of the TSF Water Balance including Annual Average Volumes of

Water contributing to each Stream ............................................................................................................ 37

Figure 10-1 Toromont pass match chart for determining truck model based on milling rate and

recommended shovel models based on truck model [12] ......................................................................... 42

Figure 10-2 Capital cost associated with each shovel truck pairing ........................................................... 45

Figure 10-3 Efficiency of each shovel truck pairing .................................................................................... 45

Figure 11-1 Yukon Drainage Basins [20] ..................................................................................................... 49

Figure 12-1 A schematic cross-section of the cover over WRD .................................................................. 58

Figure 13-1 - The production schedule and resulting cash flow model for the current pit design and

operation..................................................................................................................................................... 63

Figure 13-2 - Sensitivities of prices and operating costs............................................................................. 64

Figure 13-3 - The average annual Pb and Zn grades over the LOM ............................................................ 65

Figure 13-4 - The average annual Au and Ag grades over the LOM ........................................................... 66

Page 12: Conceptual Mine Design, Grum YT

12

Figure 13-5 - The variation in lead and zinc recoveries over the scheduled mine life ............................... 66

Figure 13-6 - The variation in gold and silver recoveries over the scheduled mine life ............................. 67

Figure 13-7 - The interpolated unit cost of Grum, at 8800 tpd and a strip ratio of 6. ................................ 68

Figure 13-8 - Interpolated processing unit cost for two concentrates at a milling rate of 8800 tpd ......... 68

Figure 13-9 - The route and distance from Faro to Trail [41] ..................................................................... 69

Figure 13-10 - The Korea Zinc Onsan smelter, located close to a port [44] ............................................... 70

Figure 13-11 - An aerial photograph of the port town Skagway is shown on the left and the shortest

route from Faro to Skagway is shown on the right [45] ............................................................................. 70

Figure 13-12 - Interpolated processing capital cost for two concentrates at a milling rate of 8800 tpd ... 71

Figure 16-1 Haulage Truck Specifications- Cat 785C [49] ........................................................................... 77

Figure 16-2 Ramp Design for the first push back at Whittle Pit 6 .............................................................. 78

Figure 16-3 Ramp Design for the second push back at Whittle Pit 9 ......................................................... 78

Figure 16-4 Ramp Design for the third push back at Whittle Pit 18 ........................................................... 79

Figure 16-5 Diagram showing the Meanings of each constant in the Truncated Pyramid Volume

Calculation .................................................................................................................................................. 83

Figure 16-6 – An overview of the mine site layout for context, with dimensions of paths superimposed.

For a clearer depiction of measurements, refer to subsequent figures. .................................................... 93

Figure 16-7 - View of horizontal projection distances of equipment travel paths; due to the high degree

of segmentation in the pit, dimensions are overlapping and difficult to read. A magnified view could be

found in Figure 16-6. ................................................................................................................................... 94

Figure 16-8 - A magnified view of the horizontal projection lengths of the pit ramp. ............................... 95

Figure 16-9 - Rimpull curve of the CAT 777G, with appropriate speeds determined for loaded travel on

effective grades of 3%, 4%, and 13%. ......................................................................................................... 96

Figure 16-10 - Retardation curve of an empty CAT 777G on effective grades of 0% and 7%. ................... 97

Figure 16-11 - Rimpull curve of the CAT 785D, with appropriate speeds determined for loaded travel on

effective grades of 3%, 4%, and 13%. ......................................................................................................... 98

Figure 16-12 - Retardation curve of an empty CAT 785D on effective grades of 0% and 7%. ................... 99

Figure 16-13 - Rimpull curve of the CAT 789D, with appropriate speeds determined for loaded travel on

effective grades of 3%, 4%, and 13%. ....................................................................................................... 100

Figure 16-14 - Retardation curve of an empty CAT 789D on effective grades of 0% and 7%. ................ 101

Figure 16-15 - Annual contained lead and zinc processed ....................................................................... 122

Figure 16-16 - Annual contained silver and gold processed ..................................................................... 122

Page 13: Conceptual Mine Design, Grum YT

13

1 Background

Northwestern Canada is home to the Grum Deposit, located in central Yukon and 200 km northeast of

the capital, Whitehorse. In addition, the site is 15 km from the town of Faro. It is understood that the

deposit is host to rich lead and zinc bearing minerals, such as galena and sphalerite, while trace amounts

of lead and silver are also expected to provide economic benefit. A basic look at the processing of these

metals is given in Section 5.

The Anvil Range district, of which the deposit is part of, contains a string of 7 deposits distributed over a

strike interval of 35 km, roughly parallel to, and 3 to 6 km to the north‐east of the major Vangorda fault

zone. The galena and sphalerite bearing massive sulfide ore includes pyritic, barytic, carbonatic and

pyrrhotitic variants, with common post depositional breccia textures. The massive sulfides are fringed

laterally and below by quartzose and graphitic disseminated sulfide mineralization, which may be

banded and/or spectacularly brecciated. The ore lenses are typically elongated. Tills in this area are from

the McConnell glaciation, and are believed to be good construction material at this stage.

2 Previous Analyses

The Grum deposit has been intercepted by two exploration drill holes reaching 218.5 and 132.2 meters

in length. These boreholes struck the orebody at 250/70 and 300/70 (trend/plunge) at UTM coordinates

of 5910.87 East, 2467.40 North and 6754.40 East, 2941.30 North. The resulting drill logs yielded both

geotechnical and qualitative geological information that can be used to get an early assessment of the

ground conditions of the Grum area. This data was complemented by a 205 meter exploration tunnel in

which fractures were mapped from its entrance, of which the exact location was unknown.

Analysis on the Grum pit design had been done previously using this data, including an attempt to

quantify the site’s rock mass properties. Following from this the potential pit area was divided into

several geotechnical domains, from which starting pit slope angles were calculated using various

numerical modeling tools. These 3 aspects will be summarized in the following Section.

2.1 Rock Mass Properties

Generally the Grum site can be divided into two main rock types, quartzite and phyllite, for which

laboratory test results were provided. From this the data provided from the boreholes allowed for the

calculation and determination a distribution rock mass quality (RQD) values where it was found that 70%

of the borehole lengths were of a value of 70 or greater. This suggested a moderate to strong rock mass.

As a result the use of both the Q and RMR76 systems were warranted, and a list of known joint sets was

compiled. Examining the joint sets present, it was found that phyllite contained 2 minor sets and 2 major

sets, while quartzite contained 2 major sets and 1 minor set (labeled Minor Set 1). The following 4 sets

were discovered:

Page 14: Conceptual Mine Design, Grum YT

14

● Major Set 1 – Dip: 79 Dip Direction: 043 ● Major Set 2 – Dip: 44 Dip Direction: 317 ● Minor Set 1 – Dip: 72 Dip Direction: 149 ● Minor Set 2 – Dip: 20 Dip Direction: 206

Typical RMR values of 63.5 and 67.5 for phyllite and quartz respectively and typical Q values of 0.24 and 0.31, suggested a similar quality of rock mass for each rock type. However it was clear that phyllite is the weaker of the two.

Lab test data on discontinuities for shear and normal stresses, a Mohr Coulomb strength criterion was

generated for joints in each rock type. The results of this concluded that the joint in the phyllite rock

mass is much weaker, as displayed in Figure 2-1 Conservative Mohr Coulomb Criterion for Joint

Strength, assuming no cohesion. For this reason, and its overall dominance at the mine site, all rock

mass analyses utilized the strength properties of the phyllite.

τ= σn tan(40) for Quartzite

τ= σn tan(29) for Phyllite

Figure 2-1 Conservative Mohr Coulomb Criterion for Joint Strength, assuming no cohesion

A similar procedure was carried out using the Generalized Hoek-Brown failure criterion, and similarly the

phyllite was found to be weaker, however it was evident that the controlling factor for failure was due

to joint properties. Additionally, the properties of the overburden material was analysed and a Mohr

Coulomb failure criterion was generated and appeared as such:

Evidently the overburden material is much weaker and is shown to reduce the slope angles of the pit in

early years of development.

2.2 Geotechnical Domains

Using the data from geotechnical analysis, a preliminary pit was produced, with assumed 45 degree

slopes, to determine the shape of the pit. This pit was discretized based on the orientation of each

slope. This resulted in 10 sectors with 8 distinct orientations, as shown in Figure 2-2.

Page 15: Conceptual Mine Design, Grum YT

15

Figure 2-2 Simplified outline of the proposed Grum Pit, divided into 10 sectors with 8 unique orientations

The pit was then divided into two geotechnical domains: rock and overburden. As seen in Figure 2-3, the

rock is composed primarily phyllite, with lesser amounts of quartzite and other minerals. Thus the rock

mass was modelled as one domain with the properties of phyllite, with properties previously discussed

in Section 2.1. As previously discussed overburden is a glacial till consisting of weaker, weathered

material and therefore its strength would govern its failure and is dominant in the southern portion of

the pit.

Figure 2-3 Visualization of the Pit's Geotechnical Domains

2.3 Slope Stability Analysis

A bench height 12 meters was chosen for the convenience of re-blocking the model from 6 m x 7.6 m x

7.6 m to 12 m x 7.6 m x7.6 m. This height corresponds to the shovel reach. Bench width was determined

to be 6.9 m, based on the relation proposed by K. Esmaeili [1]:

Bench width = 0.2*bench height + 4.5m

Page 16: Conceptual Mine Design, Grum YT

16

When ensuring the stability of the pit it was found that the majority of cases resulted in possible wedge

failures. Using Swedge, the probability of failure (PoF) was determined for each sector, dictated by

wedge failure at different pit slopes ranging from 65 to 85 degrees. A sensitivity analysis was also

performed with water filling 50% to 100% of the discontinuities. The resulting chosen bench face angles

are displayed in Table 2-1.

Table 2-1 Recommended Bench Face Angles for slopes governed by Wedge failure

Alternatively toppling failure was the driving factor for two faces on the northern side of the pit oriented

at 225° and 335°. Bench face angles of 80° can be acceptable, with safety factors close to or above one

at 50% saturation. It is recommended that the water pressure in these slopes is closely monitored with

pumping programs in place to control the water level.

Lastly the overall slopes used in the preliminary design were generated and checked using Rocscience

Slide software. The result is shown in Table 2-2, differentiating between host rock and overburden (OVB)

overall slope angles (OSA).

Table 2-2 Overall pit slope safety factors for each sector, at different water saturations

3 Detailed Pit Design

Following from previous work, a detailed pit could be constructed. In open pit planning, roads play a

crucial role and therefore will be incorporated early in the planning process as they can significantly

alter pit slope angles. They can also affect the economics of reserves. The overall slope angles

determined in the scoping study had not accounted for roads, therefore ignored unplanned stripping

and reserve sterilization. The next section will outline ramp specifications and its effect on the pit.

3.1 Ramp Design

The ramp will consist of two lanes; one lane for uphill traffic carrying material and the other lane for

empty downhill traffic. The two-way traffic system will be efficient and will eliminate costs for designing

two separate one-way traffic ramps. According to Couzens, 1979, the roadway of a two-way traffic ramp

should have a width greater than four times the truck width. For safety purposes, a berm, with a repose

angle of 35 and height equal to truck’s tire radius, will also be added along the sides of the ramp to

Page 17: Conceptual Mine Design, Grum YT

17

enhance road safety and will be added to the total roadway width. The grade of the ramp will be 10%.

The ramp curve radius is 150 m, widening the curves enough to ensure safety and reduce difficulties in

turning.

3.1.1 Ramp Width

As mentioned previously, the ramp width has to be greater than four times the width of the operating

haulage truck. Since the bench width is 6.9 m, and the Grum Pit is a small open pit (small pits normally

have bench heights of 12 m) [2], Benny Resource Group (BRG) ensured that there was enough space for

efficient and safe haulage operations. Therefore, BRG has selected the CAT 785C haulage trucks.

According to the 1965 AASHO Manual for Rural Highway Design-Mine Haulage Road [3] the space

adjacent to each lane, both right and left, should equal to one-half the width of the haulage truck. The

ramp design is shown in Figure 3-1 below. The full specification of the CAT 785C is shown in Appendix

Section 16.1.

Figure 3-1 Two-Way Traffic Ramp Design

Once the dimensions of the ramp were finalized, they were inputted into GEOVIA GEMS (GEMS) to

generate a ramp design for each pushback: 6, 9, 18 and 27. Figure 3-2 displays ramp design for pushback

27. The ramp design for pushbacks 6, 9, and 18 can be found in Appendix Section 16.1.

Page 18: Conceptual Mine Design, Grum YT

18

Figure 3-2 Ramp design for pushback 27. Note that the ramp exit is towards the southeast part of the pit, making the haulage distance to Waste Rock Dump shorter. Thus increasing productivity.

Since the Grum Pit is located in Yukon, the roads can expect to become icy and wet, therefore,

switchbacks were avoided during designing. As a result, a spiral ramp was designed because of the

following reasons:

Safe to operate on, especially in weather conditions like rain, ice etc.

Reduce tire wear

Unlike the switchback, the overall slope of the pit changes within a small degree (discussed in

the subsequent section)

Enhance visibility for drivers

Efficient fleet operations and increased productivity

BRG created the ramp, with iterations, to exit towards the west side of the pit, for all pushbacks, where

the dump sites are located for optimum productivity.

3.1.2 Ramp Section Design

One of our main targets is to maintain low costs during the life of the mine. Poorly constructed and

maintained roads incur extra and large haulage costs and can become a safety hazard. Therefore, a good

ramp design is necessary. The ramp will be comprised of four different layers discussed in Table 3-1

(occurring in the order presented, from top to bottom).

Page 19: Conceptual Mine Design, Grum YT

19

Table 3-1 Purpose of each layer in designing a ramp

Figure 3-3 shows the section of the ramp. The material for each layer is dependent on both economic

and operating factors. Operating factors, for instance, are contingent on material’s ability to distribute

estimated loads from haulage trucks.

Figure 3-3 Construction Layers of the Ramp Surface

3.1.3 Ramp Maintenance

Deterioration of the roads can generate extra costs, which can place a dent in the economics of the

operation. A damaged road can reduce the life of equipment significantly, thus incurring extra capital

costs. Therefore to ensure the operation runs as planned, the following objectives will be met:

Drivers will be recommended to drive on different areas of the lane to prevent formation of ruts on roads due load concentration

Snow and ice will need to be immediately removed using a motor grader

Spillage of material from loaded trucks will be prevented as they will cause unnecessary bumps, causing tire wear

Maintain ramp grade and slope and smooth depressed surfaces

3.2 Pit Slope Geometry

By adding the ramp, the overall slope angle of the pit changes. When constructing the ramp, the aim

was to ensure that ramp was designed as intended without significantly changing the economics. The

ramp changed the overall slope angle of the walls on the west side of the pit to an insignificant degree

Page 20: Conceptual Mine Design, Grum YT

20

and therefore the change was neglected. The walls on the east side of the pit, however, had their overall

slopes change significantly after the construction of the ramp. These changes are summarized in Table

3-2 and are visualized in Figure 3-4 with calculations shown in Appendix Section 16.2. After calculating

the new overall slope angles, they were re-entered into Whittle to determine the new economics of the

operation (discussed in Section 13).

Table 3-2 Adjusted Pit Slope Parameters

Figure 3-4 Pit Wall Geometry for Sectors 8, 10, 9&1

4 Production Scheduling

Using the pit design, as described in Section 3, the production schedule produced is shown in Figure 4-1.

Page 21: Conceptual Mine Design, Grum YT

21

Figure 4-1 - The production schedule needed to meet a 3.2 Mt mill capacity. The first year could be ramped over the preceding two years, as indicated by the arrow.

Following this exact schedule would be unreasonable due to high fluctuation in mining rates, especially

in the first year. Assuming the first year could have prestripping over earlier years, the resulting

production would yield Figure 4-2.

Figure 4-2 -The production schedule with an initial ramp up. Further smoothing of production can be achieved by distributing higher production in the end of mine life to earlier periods.

Although the deviation of production has been reduced, there is still a significant difference between

the higher beginning and ending rates, with the lower rates at the middle of the mine life. To reduce

variation of production rates further, the production of years 12 to 17 could be distributed to the years 4

to 11. The resulting production theoretically has a balanced production rate of 27 Mt per year, as shown

in Figure 4-3.

0

10000000

20000000

30000000

40000000

50000000

60000000

70000000

-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Production Schedule

Ore Waste

0

10000000

20000000

30000000

40000000

50000000

60000000

70000000

-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Production Schedule with Ramp Up

Ore Waste

Page 22: Conceptual Mine Design, Grum YT

22

Figure 4-3 - A production schedule with low deviation; note that production is not divided into “Ore Mined” and “Waste Mined”, but “Processed Ore” and “Waste Dump or Stockpile”. “Ore Mined” could be processed in the mill or stored in stockpile, and

“Processed Ore” could come from the mine or stockpile.

However, forwarding production earlier does not mean only waste is forwarded, but ore associated with

that waste. For this reason, stockpiles would be required as more ore would be mined than the mill

would be capable of handling during early mine life. Later in the mine life, ore extraction would not

meet the milling capacity, so stockpiles would be consumed to do so.

To determine the tonnage and grade of the stockpiles, the ore that follows the forwarded production

needs to be determined. A Whittle schedule was made with a smaller milling limit, to determine how

the amount of waste and the grade changes per unit of ore over the mine life. This was accomplished by

producing a schedule with a smaller milling limit, which would show how much waste needed to be

extracted for a certain tonnage of ore.

Due to Whittle’s hardcoded limits of 999 periods and seven minutes per iteration, the smallest unit of

ore used was one fortieth of the target milling rate, at 0.08 Mt/period. The resulting schedule

represented how much waste is required to extract every 0.08 Mt of ore. The resulting breakdown is

shown in Figure 4-4.

0

5000000

10000000

15000000

20000000

25000000

30000000

-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Theorectical Balanced Production Schedule

Processed Ore Waste Dump or Stockpile

Page 23: Conceptual Mine Design, Grum YT

23

Figure 4-4 -The tonnage of waste associated with every 80, 000 tonnes of ore, over 766 intervals.

The appropriate tonnages of ore and waste mined, as shown in Figure 4-4, can be matched with the

target production, as in Figure 4-3. The intervals of waste and ore were integrated to best match the

target production of each year. In the years which the tonnage of ore mined exceeds mill capacity, ore

would be stockpiled. Meanwhile, in years which ore production does not meet mill capacity, the

stockpile would be processed. The resulting schedule is shown in Figure 4-5, in terms of:

Stockpiled ore: Ore that has been mined and is stockpiled due to exceeding mill capacity.

Processed mined ore: Ore that is processed after extraction

Processed stockpile ore: Ore sent to the mill from stockpiles

Mined Waste: Waste rock without economic value, sent to waste rock dump (WRD)

Figure 4-5 - A schedule with balanced milling and production rates, using stockpiles.

0

500000

1000000

1500000

2000000

2500000

3000000

3500000

4000000

2

33

64

95

12

6

15

7

18

8

21

9

25

0

28

1

31

2

34

3

37

4

40

5

43

6

46

7

49

8

52

9

56

0

59

1

62

2

65

3

68

4

71

5

74

6

Waste Associated with every 80000 Mt of Ore

Ore Waste

0

5000000

10000000

15000000

20000000

25000000

-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Balanced Production Schedule with Stockpiles

Stockpile Processed Ore Mined and Processed

Ore Stockpiled Waste

Page 24: Conceptual Mine Design, Grum YT

24

5 Preliminary Processing Design

Before an appropriate Tailings Storage Facility (TSF) design could be constructed it was essential that a

preliminary design of the ore processing was considered. For the purposes of this study a high level

approach was taken due to a lack of geochemical data and laboratory testing which could more

accurately represent the results of processing.

To obtain a good sense of the required processing method the amounts of metal contained in the

extracted ore was compared. From these results, seen in Table 5-1, it is clear that the focus will be

placed on the concentration of lead and zinc.

Table 5-1 Summary of Contained Metals before processing, Recovered Metals and Average Metal Grades

One such method includes the use of lead – zinc froth floatation, which would produce two separate

concentrates, one lead and one zinc, with the gold and silver reporting as pollutants in both streams.

From here the concentrates would be sold to the smelter company. It has been suggested that such a

process has the potential to generate a concentrate containing a lead grade of 60%, while zinc could

reach a grade of 56% [4].

Some preliminary metallurgical lab data was provided for the site (see Appendices, Section 16.4). This

data appeared to match the recovery range of 80 to 90%, common for lead and zinc floatation [4]. As a

result it was decided that this data would be sufficient for use in a preliminary processing mass balance.

However note that it is recommended that future lab tests are carried out in the future for more

accurate results.

Using the recovered metal data produced from these assumptions, and the material data generated for

the pit using Whittle, average tailings grades were found using the following equation:

𝑀𝑒𝑡𝑎𝑙 𝐺𝑟𝑎𝑑𝑒 𝑜𝑓 𝑇𝑎𝑖𝑙𝑖𝑛𝑔𝑠 = (𝑀𝑒𝑡𝑎𝑙 𝐼𝑛𝑝𝑢𝑡 − 𝑀𝑒𝑡𝑎𝑙 𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑒𝑑)

100 ×(𝑂𝑟𝑒 𝐼𝑛𝑝𝑢𝑡 − 𝑀𝑒𝑡𝑎𝑙 𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑒𝑑)

From this it was found that tailings will have an estimated grade of 0.41% lead and 0.26% zinc. A

preliminary mass balance was then completed assuming 1 tonne of feed, and the results of which can be

seen in Table 5-2 below.

Metal Total Input (Metric Tonnes) Recovered (Metric Tonnes) Input Grade

Lead (%) 113557353 99940258 2.056

Zinc (%) 180277921 158668979 3.264

Gold (g) 35424963 21251519 0.641

Silver (g) 1933521098 995616297 35.003

Page 25: Conceptual Mine Design, Grum YT

25

Table 5-2 Results of the Preliminary Mass Balance for Froth Floatation

The results of Table 5-2 were calculated assuming the mass balance for each stream follows the

processing mass balance equation written as:

𝐹𝑒𝑒𝑑(𝑖𝑛𝑝𝑢𝑡 𝑔𝑟𝑎𝑑𝑒) = 𝐶𝑜𝑛𝑐𝑒𝑛𝑡𝑟𝑎𝑡𝑒(𝑐𝑜𝑛𝑐𝑒𝑛𝑡𝑟𝑎𝑡𝑒 𝑔𝑟𝑎𝑑𝑒) + 𝑇𝑎𝑖𝑙𝑖𝑛𝑔𝑠(𝑡𝑎𝑖𝑙𝑖𝑛𝑔𝑠 𝑔𝑟𝑎𝑑𝑒)

In addition it has been assumed that if the overall processing is considered an average mass balance can

be taken between the two streams. This was done to gain a sense of the overall amount of materials

reporting to the TSF, which is around 96% of every ton of ore processed, as seen in Table 5-2. It is

important to note that this method of estimation represents a very rough estimate of the overall

processing mass balance. As such, careful metallurgical testing should be conducted in order to produce

an accurate processing mass balance which accounts for the 2 separate concentrate streams and other

factors, such as the mass balances of individual crushers, grinders, and floatation cells required in the

circuit. However, for this level of study the current analysis is sufficient to conduct further estimates for

tailings management purposes.

6 Tailings Storage Facility Design

At this stage it has been suggested that the specifics regarding the stability of the impoundment are not

essential, and can be determined in later design stages. Instead this level of design will focus on the

appropriate geometry necessary to store the tailings material. In doing this, it allows for the estimation

of a possible design footprint and therefore an appropriate site layout. This document will cover the

technical details involved in finding a preliminary dam geometry while the process of site layout and

selection will be covered in its own document.

6.1 Selection of an Appropriate Cover System

The site has been marked as a massive sulfide deposit, which is capable of producing acidic effluent, and

therefore appropriate measures must be taken to inhibit acid mine drainage (AMD). Due to this a

proposed tailings storage design should be able to keep acid generation to a minimum, and mitigate the

release of potentially harmful effluent to the environment.

Given that the Faro area sees a regular amount of precipitation (approximately 316 mm annually), and it

can considered a humid climate, prevention of AMD using dry tailings throughout the mine life could

prove difficult [5]. As a result, the abundant amount of nearby water sources suggests that a designed

water cover could provide an effective strategy to combat AMD throughout the mine life. Therefore the

preferred method of tailings impoundment in humid climates, a wet cover system, will be employed [6].

Concentrate Grade Amount Reporting to Conc. Tailings Grade Amount Reporting to Tailings Input Grade

Pb 60% 5% 0.41% 95% 3.305%

Zn 56% 3% 0.26% 97% 2.075%

Avg Mass Balance 4% 96%

Page 26: Conceptual Mine Design, Grum YT

26

Typical water covers provide protection against AMD using a relatively thin layer of water that prohibits

oxygen ingress to the acid generating tailings [6]. A water cover thickness of 2 m has been selected for a

conservative approach. This has been done in response to the heightened social sensitivity to the

spillage of effluent as a result of the nearby Faro site; the Faro mine is currently a major remediation

project for contamination due to old mine workings. By using a thicker water cover this should

significantly reduce the possibility for acid generation from the tailings. More details on the community

and the effects of the Faro site are covered in Sections 8 and 11, Site Layout and Environmental and

Social Impact Assessment, respectively.

6.2 Design of the Dam Geometry

After the cover system was selected a numerical model was generated to determine the overall

geometry of the required tailings dam. In doing this, the first fundamental assumption was that the

generated tailings, when first deposited as a slurry, would have a moisture content of 40%, by weight of

solids, which is within the range suggested by McPhail – 30 to 50% – for freshly placed tailings [5]. Also

as part of the preliminary design stage a conservative dam geometry has been suggested in advance,

utilizing a crest width of 8 m, a berm width of 15 m and slope of 1:2.5, height to width, on the

downstream face. The beach of the impoundment will also assume a gradient of 1:2.5. This produced

the final design geometry presented in Figure 6-1, below.

Figure 6-1 Simplified Cross Section through the Final TSF Dam Design

In order to reach this final design the numerical model took into account the previous geometrical

assumptions along with the water content of the tailings to attempt to find an appropriate dam

configuration to accommodate the tailings. For this to work an initial estimate of the amount of tailings

volume (including water) produced per year was generated. This was done by using the ore tonnages

sent to the mill, obtained from Whittle Analyses, and applying the assumed 40% water content and

average ore density of 2.64 ton/m3, found from earlier lab testing. The results of this can be seen in

Appendix Section 16.5. Note that the values are presented in yearly amounts, which is important for

determining the mine’s water balance, covered in Section 9.

Knowing the volume of material going into the TSF each year, the geometry can be used to predict the

annual height of the tailings. This was done by utilizing the expression for the volume of a truncated

Page 27: Conceptual Mine Design, Grum YT

27

pyramid (explained in Appendix Section 16.6), presented by Bronstein et al. [6]. The truncated pyramid

shape could be used to represent the geometry of capacity of the TSF. In this case it is assumed that the

shape of the tailings as it fills the dam will be that of the truncated pyramid when it is inverted, or

flipped on its head.

With the tailings volume accounted for, the numerical model uses this equation in determining the

height of the tailings, and its annual rate of rise, shown in Appendix Section 16.7. The model does this by

taking the storage width and length, graphically shown in Figure 16-5, as well as the desired dam height

as inputs. Geometry is then used to calculate the overall length and width of the TSF, assuming a

rectangular shape. Furthermore, the model is able to determine the number of slopes and berms the

downstream slope will require, as visually shown in Figure 6-1.

After initially constructing the model it was found that the mountainous landscape in the vicinity of the

Grum deposit provided significant challenges for the previous assumptions. An additional model was

created to account for the change in gradient of the area the TSF was placed. However results showed

that this change would cause large losses in dam capacity, requiring larger amounts of space than the

prior model. As a compromise the first model was adjusted by assuming a natural slope can take the

place of one of the downstream slopes, as shown at the top of Figure 6-2. This eliminated the need for a

downstream slope on one end of the dam, reducing its overall length, and assumes that the natural

slope could be re-graded to the necessary 1:2.5 height to width ratio.

Figure 6-2 Simplified Representation (in plan view) of the Final TSF Dam Design (not to scale)

The downside of this assumption is that it would require that the base of the TSF is leveled, which may

require a large amount of material. Therefore for a preliminary phase this design should represent a

Page 28: Conceptual Mine Design, Grum YT

28

conservative approach and different strategies may be used to reduce the cost and size of this design.

The final design parameters are summarized in

Table 6-1.

Table 6-1 Summary of Key Parameters of the Final TSF Design

6.3 Considerations for Dam Construction

A final estimate of the volume of construction material necessary to construct the final dam design was

calculated on a yearly basis. These values can be seen in Table 6-2. This was estimated by using the

product of the estimated final volume of building material and the ratio of yearly tailings volume to the

final tailings volume; the latter is shown as the approximate dam completion. The purpose of this

exercise was to get a “ball-park” estimate of how much material will be needed to construct it. This

result could then be used to see if additional material will be required for construction, and can have

ramifications on the final cost estimates, however this was done as a point to move on from for future

studies.

Table 6-2 Estimates for required Material needed to construct the Final TSF design

Due to the foreseen high level of public scrutiny and the large consequences of failure, a downstream

method of deposition and dam creation will be used. This appears to be most conservative as the new

materials are placed on older dam materials, rather than on top of the tailings. Downstream deposition

Dam Area 2.2 km2

Length 1733 m

Width 1266 m

Final Dam Capacity 5.31E+07 m3

Total Tailings Held 3.75E+07 m3

Free Board 11.87 m

Summary of Final TSF Dimensions

End of Production Year Tailings Capacity Needed (m3) Approx. Dam Completion Additional Dam Material Needed (m3/year)

1 1.20E+05 0% 1.38E+05

2 7.77E+05 2% 7.58E+05

3 2.57E+06 6% 2.07E+06

4 4.90E+06 12% 2.69E+06

5 6.99E+06 17% 2.41E+06

6 8.85E+06 21% 2.14E+06

7 1.12E+07 27% 2.76E+06

8 1.36E+07 33% 2.76E+06

9 1.60E+07 39% 2.76E+06

10 1.84E+07 45% 2.76E+06

11 2.08E+07 50% 2.76E+06

12 2.32E+07 56% 2.76E+06

13 2.56E+07 62% 2.76E+06

14 2.80E+07 68% 2.76E+06

15 3.04E+07 74% 2.76E+06

16 3.28E+07 79% 2.76E+06

17 3.51E+07 85% 2.76E+06

18 3.75E+07 91% 2.76E+06

19 3.99E+07 97% 2.76E+06

20 4.13E+07 100% 1.59E+06

Total (m3) 3.98E+08 4.76E+07

Page 29: Conceptual Mine Design, Grum YT

29

allows for better control over the engineering properties of the dam structure and as such should

produce a more stable design.

Additionally, note that there is a need for an impervious core material, likely clay or compacted local till

material, which is not shown in Figure 6-1. This would be done in order to manage the amount of flow

out of the toe of the dam, which could lead to potential instability in the design.

It was also previously stated that the area sees regular precipitation throughout the year and as a result

designed spillways should be placed on the abutments of the dam, where the dam makes contact with

the natural slope. These spillways should reduce the chances of overtopping if a flood event occurs,

which is critical in ensuring the continued stability of the design. Additionally, should discharge through

the spillways be necessary, a form of water diversion, should be created around the dam so that water

can be lead to the water treatment facility. From here any excess water can be released safely to the

environment, however the specifics of the design of these diversions is left to later studies.

Lastly preliminary data was collected for the Grum area’s overburden material and was analysed; this

data and results are tabulated in Appendix Section 16.8. The findings of this analysis found that

according to the ASTM soil classification scheme the material is an SC-Clayey Sand. This represents good

quality building material, characteristic of glacial tills, however some uncertainties in the lab test results

suggests more detailed testing is required; this is further explained in Appendix Section 16.8. For

seepage purposes this material has a permeability ranging from 5.5x10-9 to 5.5x10-6 m/s [7]. This data

therefore suggests that natural liner material obtainable from the local area will have a permeability of

5.5x10-9 m/s at best. For this reason the water balance, discussed in Section 9, will utilize this value.

7 Design of the Waste Rock Dump

Following the TSF design, the disposal of unprocessed material will also be an important factor in the

mine design of this location. Just like the tailings, the waste rock can also be considered as Potentially

Acid Generating (PAG), and as a result a low permeability mat material will need to be placed on the

selected site of the WRD. Additionally it was decided that only one dump would be necessary as any

Non-PAG material will be assumed to be used immediately for dam construction at this stage of design.

Considering this, a similar approach was used to design the WRD as the TSF design. In this case the

overall waste rock generated over the life of mine was considered from the whittle model. This was

done because it allows for the overall footprint of the design to determined using a numerical model;

yearly waste values are also not sensitive to the yearly water balance.

The numerical model used takes on the assumption that the slopes of the WRD will take on the same

geometry as the downstream face of the TSF, as suggested prior to starting the design. This conservative

assumption will allow for a focus on the selection of an appropriate site rather than its overall stability.

Just as the TSF, the selection of an appropriate site is covered in the Section 8.

Page 30: Conceptual Mine Design, Grum YT

30

From here the amount of waste volume was estimated by applying both a bulking factor, due to the

mechanical handling of material, and a compaction factor, assuming efforts will be made to

mechanically compact the waste [8]. The calculation of the Final waste rock volume, using the previously

assumed density of 2.64 ton/m3, can be seen in .

Table 7-1.

Table 7-1 Summary of Total Waste Rock Volume Determination with Suggested Volume Adjustment Factors [8]

By specifying the length and width of the rectangular WRD, the numerical model finds the height of the

dump required to accommodate the volume of waste. By testing different variations of the WRDs, a final

design was found, and its geometry is summarized in Table 7-2. The method by which these geometries

were chosen are further discussed in Section 8.

Table 7-2 Summary of Final WRD Design Parameters

Similar to the TSF, water runoff from the WRD should also be diverted to a water treatment facility from

which water can be safely released to the environment. As a result of this the diversion of runoff water

would also be done through the use of appropriate ditches following the perimeter of the facility and

would direct it to the site’s water treatment facility. This process would occur until the end of

production, where an appropriate dry covering system will be used; this is further described in Section

12.

Total Waste Rock 3.5E+08 Metric Tonnes

Avg Feed Density 2.64 Ton/m^3

Bulking Factor 1.15

Compaction Factor 0.95

Volume of Waste 1.5E+08 m3

Overall Dimensions Value Units

Length 1500 m

Width 1500 m

Dump Height 109 m

Slope Parameters Value Units

# of Berms 10 Berms

# of Slopes 11 Slopes

Top Dimensions Value Units

Length 654 m

Width 654 m

Page 31: Conceptual Mine Design, Grum YT

31

8 Site Layout

Figure 8-1 Site layout with main geographically significant structures

8.1 Background

The mine site evolves around the pit and the material excavated from it. The tailings pond and the waste

rock dump are the most significant components of the mine site next to the open pit. Both require a

large amount of space and are permanent installations on the landscape. The tailings storage facility

(TSF) and waste rock dump (WRD) generate acid mine drainage due to the presence of sulphides in the

ore. This presents certain requirements for site choice for these structures. Both the TSF and WRD

require an impermeable liner to ensure a layer of water remains on the tailings to slow acid generation

and so the bleed water running off the waste rock does not flow into the nearby streams. Design of TSF

and WRD were seen in Section 6 and Section 7, respectively, and an environmental risk matrix in Section

11.3. Emphasis was given to impacts of placement on water systems and the community.

8.2 Placement Methodology

When determining placement, a minimum distance of 150 m from streams and public roads is used as a

buffer zone and stream diversion is considered if necessary. The TSF and WRD are designed to hold the

waste produced from the mine and mill. An iterative process of selecting the site and calculating the

height, length and width to meet capacity is the main methodology to physically determine the best

sites. For these sites, economic, environmental and social effects of the design are used to compare

each alternative to find the most acceptable solution. Appendix Section 16.18 shows the economic,

environmental and social considerations and indicators when comparing the options for the site of the

tailings facility and waste rock dump.

Page 32: Conceptual Mine Design, Grum YT

32

Other less geographically significant features present on the mine site include:

Ore mill including ore stockpile

Water treatment plant

Topsoil stockpile

Site admin office, metallurgical testing lab and parking

Septic field and waste management facility

Garden nursery, operation beginning within last 5 years of life

Maintenance garage

Access roads and power corridors

Explosives magazine

The site for each of the above features depends on the structure they cater to. The mill will be located

between the pit and the TSF, the site office and parking will be located at the entrance of the mine site,

roads will go where needed, the maintenance garage near the exit of the ultimate pit ramp, etc. The

explosives magazine will also be located away from the buildings, pit and waste facilities; the blast

radius of a fully stocked magazine will determine the distance. Figure 8-1 shows the complete site

layout.

8.3 Tailings Storage Facility

The TSF was placed first to ensure it was away from homes, infrastructure and streams with the use of

the natural landscape to confine at least part of the structure. The options were chosen based on

capacity and then compared against the other options for economic, environmental effects outlined in

Appendix Section 16.9. The chosen site uses a south dipping mountain side to create a confining slope.

The facility is placed within one watershed with potential to expand without diverting the streams

leading to the productive Vangorda Creek. Due to the slurry nature of the Grum tailings, the tails will be

piped to the site from the mill. The site selection considers pipe and access road crossings over streams.

Figure 8-2 shows the three site options for the TSF. TSF one was the chosen option and it is located

North-East of the pit.

Page 33: Conceptual Mine Design, Grum YT

33

Figure 8-2 Tailings Facility Site Options

After the TSF site was determined, three potential sites were compared for the waste rock dump. With

similar constraints as the tailings facility but solid rather than slurry, three geometries were determined.

Again due to the Acid Mine Drainage caused by the sulphides in the waste, water was a concern. The

chosen site avoids stream diversion has the possibility to expand. The dimensions of the dump also bring

down the height which is a concern for the tourism community trying to show off beautiful terrain.

Figure 8-3 details the three potential sites and Appendix Section 16.10 outlines the economic,

environmental and social comparison of the potential WRD sites. After placing the WRD on the chosen

site, geometry and distance from open pit allowed the dump to move inward, away from the road and

closer to the pit. Specifics associated with the WRD design were found in Section 7.

Page 34: Conceptual Mine Design, Grum YT

34

Figure 8-3 Waste Rock Dump Site Options

8.4 Additional Site Requirements

8.4.1 Processing Mill

The processing mill will contain crushers, grinders and two flotation circuits for zinc and lead. The mill is

located just north of the pit. The placement avoids truck and pipe crossings, with each other and/or

streams. The mill was also placed directly upstream of the pump pond where, if a mill breach occurred,

the effluent would travel.

8.4.2 Explosives Storage and Handling

A contract will be entered into with a recognized supplier of mining explosives, to establish his own

facilities in the south west of the waste rock facility, well away from the local population and mine

activities, and to supply emulsion as needed.

8.4.3 Technical Departments

The site admin office, engineering department, metallurgical testing lab, revegetation nursery, septic

field and human waste treatment facility will be located at the entrance of the mine site surrounded by

existing vegetation. These buildings will be surrounded with parking to provide easy access and distance

from haul trucks.

Page 35: Conceptual Mine Design, Grum YT

35

8.4.4 Environmental Systems

The water treatment plant and topsoil stockpile are located east of the pit between the small pump

pond and tailings facility. The pipe leading from the mill to the water treatment plant must travel below

the road surface to bring the reusable water to the plant. A pipe runs from the tailings facility to the

water treatment plant providing a safe discharge of extra water. The topsoil pile will be covered during

operation and used for progressive remediation efforts around the mine site.

9 Water Balance of the Mine Site

Having looked at the major causes for concern when dealing with the contamination of water, the water

balance can provide a key tool for managing the water flow around the mine site. As previously

mentioned the TSF alone can account for up to 80% of all water movements at a mine site, and as a

result it, and the WRD, will be the focus of this exercise [9]. Table 9-1 tabulates the key coefficients, as

suggested by McPhail, which were used in estimating the mine water balance for both the TSF and WRD.

Table 9-1 Key Coefficients used in Conducting the Mine Water Balance [9]

9.1 Water Balance of the Waste Rock Dump

Starting with the simpler of the two designs, the PAG materials in the WRD provides a challenge for

maintaining good water quality in the nearby environment. This balance then aims at determining the

appropriate amount of water a water treatment plant can expect to process on a yearly basis due to the

WRD.

The key source of water that will reach the WRD is assumed to be due to precipitation. Before

continuing note that in this area of the Yukon around a third of the annual precipitation is received as

snow. However for the purposes of this preliminary analysis it will be treated as rain in all cases.

Factor Low High Comments

Pond Area 10% 30% of Beach Area

Pond 100% 100%

Dry Tailings & Beach 50% 60% Average used for WRD

Pond Rate 80% 100%Low is in the Summer; High in Winter Months.

Assumed 100% for the TSF.

Wet Beach Rate 60% 80% of Pond Evap Rate

Damp Beach Rate 40% 60% of Pond Evap Rate

Dry Beach Rate 0% 20%of Pond Rate (Depends on Rate of Rise of Pond).

Average used for WRD.

Seepage Rate

Moisture Content 30% 50% Recommended Range for Newly Placed Tails

Interstitial Water AllowanceSubtract from m, above (will reduce over time

due to desication; does not affect seepage)

Remaining Water Change 50:50 between evaporation & seepage

Amount 30% 50% of the water pumped onto the dam (including

50%

Underdrainage & Decant Water

15%

Infiltration

Equals permiability of Tailings or the Foundation (whichever is lower) and can incorporate

representative pond depth.

Seepage

Runoff

Evaporation

Page 36: Conceptual Mine Design, Grum YT

36

Knowing the amount of annual rainfall in the area is 316 mm per year, and that the WRD will be 1500 m

by 1500 m (even at the end of the first year of production) a quick estimate of annual volume can be [5].

From here an average runoff coefficient of 55% for dry tailings and beaches can be used to determine

how much of the precipitation will stay in the tailings [9]. Additionally an annual amount of evaporation

can be estimated by applying an average evaporation coefficient of 10% for dry beaches alongside the

300 mm mean annual evaporation rate for bodies of water in this area of Canada [10]. The result of this

is 252 thousand m3 of net retained water (shown as Net Water Balance in Table 9-2) within the WRD

annually. In addition the result shows that 391 thousand m3 of runoff water is produced, which must be

treated each year. Furthermore the annual average results are summarized and visually depicted in

Figure 9-1.

Table 9-2 Summary of the WRD Water Balance

When examining these results the constant values across all years can be attributed to the fact that the

facility is expected to reach its maximum outer dimensions after the first year of production.

Additionally the basic nature of this study does not account for the variable wetness of the WRD, which

could affect the evaporation rate, as suggested by McPhail [9].

End of Production Year Precipitation (m3) Runoff (m3) Evaporation (m3) Net Water Balance

1 7.11E+05 3.91E+05 6.75E+04 2.52E+05

2 7.11E+05 3.91E+05 6.75E+04 2.52E+05

3 7.11E+05 3.91E+05 6.75E+04 2.52E+05

4 7.11E+05 3.91E+05 6.75E+04 2.52E+05

5 7.11E+05 3.91E+05 6.75E+04 2.52E+05

6 7.11E+05 3.91E+05 6.75E+04 2.52E+05

7 7.11E+05 3.91E+05 6.75E+04 2.52E+05

8 7.11E+05 3.91E+05 6.75E+04 2.52E+05

9 7.11E+05 3.91E+05 6.75E+04 2.52E+05

10 7.11E+05 3.91E+05 6.75E+04 2.52E+05

11 7.11E+05 3.91E+05 6.75E+04 2.52E+05

12 7.11E+05 3.91E+05 6.75E+04 2.52E+05

13 7.11E+05 3.91E+05 6.75E+04 2.52E+05

14 7.11E+05 3.91E+05 6.75E+04 2.52E+05

15 7.11E+05 3.91E+05 6.75E+04 2.52E+05

16 7.11E+05 3.91E+05 6.75E+04 2.52E+05

17 7.11E+05 3.91E+05 6.75E+04 2.52E+05

18 7.11E+05 3.91E+05 6.75E+04 2.52E+05

19 7.11E+05 3.91E+05 6.75E+04 2.52E+05

20 7.11E+05 3.91E+05 6.75E+04 2.52E+05

Total Over LOM 1.42E+07 7.82E+06 1.35E+06 5.05E+06

Page 37: Conceptual Mine Design, Grum YT

37

Figure 9-1 Visual Interpretation of the Yearly WRD Water Balance

9.2 Water Balance of the Tailings Storage Facility

Continuing from the WRD water balance the TSF balance uses the water added through the tailings as a

starting point. These tailings (40% water by mass) are then deposited, and approximately 15%

(subtracted from the 40%) by mass of the tailings becomes trapped in the voids. The remaining 25% is

free as bleed water and floats above the tailings contributing to the required water cover. The water

cover is then susceptible to losses, due to seepage and evaporation, and further gains from precipitation

[9]. This process is visually depicted in Figure 9-2 below.

Figure 9-2 Simplified Interpretation of the TSF Water Balance including Annual Average Volumes of Water contributing to each Stream

When considering the tailings water balance the net water balance will be considered as the amount of

water contributing to the 2 m thick water cover each year; this is represented by the light blue in Figure

9-2. The initial tailings water can be easily calculated, and was mentioned previously in Appendix Section

16.5 as the total water added. In addition an interstitial, or trapped water volume can be calculated

from the tailings using 15% water by mass of tailings [9]. Precipitation is then calculated using the rate of

Page 38: Conceptual Mine Design, Grum YT

38

316 mm per year, but using the pond area and a factor of 5, as the catchment area is cited as being

upwards of 5 times the pond area in valley locations in many cases [9]. For evaporation the lake

evaporation rate of 300 mm per year was used with the pond area and an evaporation coefficient of

100% [10].

Seepage was estimated by using the assumed minimum permeability of nearby materials equal to

5.5x10-9 m/s (or 0.17 m/year), as explained in Section 6.3. The amount of seepage water per year was

then solved by the product of the catchment area and the yearly permeability. This and other values can

be seen in the full water balance in Appendix Section 16.11. The final water balance is then found using

the following equation:

𝑁𝑒𝑡 𝑊𝑎𝑡𝑒𝑟 𝐵𝑎𝑙𝑎𝑛𝑐𝑒 = 𝑇𝑎𝑖𝑙𝑖𝑛𝑔𝑠 𝑊𝑎𝑡𝑒𝑟 − 𝐼𝑛𝑡𝑒𝑟𝑠𝑡𝑖𝑡𝑖𝑎𝑙 𝑊𝑎𝑡𝑒𝑟 + 𝑅𝑎𝑖𝑛𝑓𝑎𝑙𝑙 − 𝑆𝑒𝑒𝑝𝑎𝑔𝑒 − 𝐸𝑣𝑎𝑝𝑜𝑟𝑎𝑡𝑖𝑜𝑛

Going through the water balance it is seen that the total water movements across the life of mine sum

to 84.2 million m3 of water. In order to obtain a better picture of where this water is going the

contributions of each stream was calculated and was tabulated in Table 9-3. Also average values for

each stream were calculated and presented graphically in Figure 9-2.

Table 9-3 Summary of the water movement contributions for water movement of each stream in the TSF water balance

As seen here it is seen that the largest contributor to water losses over the mine life is due to seepage,

accounting for 16%. Due to this it is likely that this water will have to be drained to the water treatment

facility, contributing an average value of 0.745 Million m3 of water annually. Combining this value with

that of the WRD amounts to 1.132 Million m3 of water that must be processed, and released to the

environment, by the water treatment plant every year. As a result some form of water holding pond

may be needed to accommodate the rate of processing and a similar dam geometry can be assumed for

it at this stage, however the specifics of this will be left to future studies.

In addition if the amount of water needed to ensure the water cover remains 2 m thick is considered it is

found that there is a deficit of water after the first year of production. This was found by working the

computed water balance back into the TSF model described in Section 6.2. By doing this it was found

that a pumping schedule, tabulated in Appendix Section 16.12, could be added into the water balance to

ensure a 2 m cover is maintained. Table 9-4, akin to Table 9-3, was created in order to fully realize the

Precipitation 30%

Evaporation 6%

Tailings Water 24%

Seepage 16%

Bleed Water 15%

Trapped (Interstitial) Water 9%

Total Water Balance 100%

Water Balance Contributions

Page 39: Conceptual Mine Design, Grum YT

39

impact of supplementary pumping, shown below. Note that this is now a breakdown of 104 Million m3

in total water volume movement.

Table 9-4 Summary of water contributions for water movement of each stream after incorporating additional pumping

The pumping schedule sees that an additional 0.855 Mm3 of water is added over top of the tailings in the

first year, while all subsequent years require water to be pumped out. Now accounting for 19% of total

water movements across the mine site this can be seen as a large cost to this design. However by

analysing the new TSF design the incorporation of the water balance increases the final freeboard to just

shy of 22 m. As such this presents the possibility for future modifications to the TSF, or the possibility of

allowing for excess water to accumulate in later years to reduce the need for pumping.

10 Operations Planning

10.1 Equipment Selection and Pricing Model

The mining equipment fleet selected and its change over the mine life is shown in Table 10-1. Details on

selection methodology are detailed in the following sub-sections.

Table 10-1 Summary of chosen loading and haulage fleet

Years into Production -2 -1 1 to 17 18

Haul Trucks CAT 785D 150 ton 7 13 21 8 Shovels CAT 6040 22 m3 1 1 1 1 Front End Loaders CAT 994F 7.7 m3 1 1 1 1 Track Dozer CAT D9T 13.5 m3 1 2 2 1 Wheel Dozer CAT 854K 7.9 m3 1 1 1 1 Motor Grader CAT 24M 16’ blade 1 2 2 1 Articulated Truck CAT 735B 24 m3 1 1 1 1 Vibratory Compactor CAT CS-64 112 kW 1 1 1 1 Tool Carrier CAT IT 38H 2.5 m3 1 1 1 1 Diesel Drill --- 4.5’’ to 8.5’’ 2 4 6 1 Secondary Drill --- 4.5’’ to 5.5’’ 1 1 1 1

Precipitation 24%

Evaporation 5%

Tailings Water 19%

Seepage 13%

Bleed Water 12%

Trapped (Interstitial) Water 7%

Supplementary Pumping/Drainage 19%

Total Water Balance 100%

Wate Balance Contributions with Supplementary Pumping

Page 40: Conceptual Mine Design, Grum YT

40

The equipment selection model used selects the model and quantity of equipment best suited to the

geometry of the mine site, available work hours, the target milling rate, and expected strip ratio at a

certain point in the mine’s production life. The process of selection is listed as follows:

1. Calculate daily production

𝐷𝑎𝑖𝑙𝑦 𝑊𝑎𝑠𝑡𝑒 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 = 𝐷𝑎𝑖𝑙𝑦 𝑂𝑟𝑒 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 ∗ 𝑆𝑡𝑟𝑖𝑝 𝑅𝑎𝑡𝑖𝑜

2. Determine effective number of working hours per day

𝐷𝑎𝑖𝑙𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑒 𝐻𝑜𝑢𝑟𝑠 = (𝐷𝑎𝑖𝑙𝑦 𝑆𝑐ℎ𝑒𝑑𝑢𝑙𝑒𝑑 𝐻𝑜𝑢𝑟𝑠 − 𝐵𝑟𝑒𝑎𝑘𝑠) ∗ 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦

3. Calculate the effective hourly production

𝐻𝑜𝑢𝑟𝑙𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 = 𝐷𝑎𝑖𝑙𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 ∗𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑒 𝐻𝑜𝑢𝑟𝑠

𝑆𝑐ℎ𝑒𝑑𝑢𝑙𝑒𝑑 𝐻𝑜𝑢𝑟𝑠

4. Select potential trucks and shovels from pass match chart

5. Determine the lengths and grades of truck routes (bassed on section on Site Layout)

6. Determine the load time for a truck and shovel pairing

𝐿𝑜𝑎𝑑 𝑇𝑖𝑚𝑒 = 𝐹𝑖𝑟𝑠𝑡 𝑃𝑎𝑠𝑠 + 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑃𝑎𝑠𝑠𝑒𝑠 ∗ 𝑃𝑎𝑠𝑠 𝑇𝑖𝑚𝑒 + 𝑆𝑝𝑜𝑡 𝑇𝑖𝑚𝑒

7. Determine the cycle time for a truck

𝑇𝑟𝑢𝑐𝑘 𝐶𝑦𝑐𝑙𝑒 𝑇𝑖𝑚𝑒 = 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 + 𝑇𝑟𝑎𝑣𝑒𝑙 𝑡𝑜 𝐷𝑢𝑚𝑝 𝑆𝑖𝑡𝑒 + 𝐷𝑢𝑚𝑝𝑖𝑛𝑔 + 𝑇𝑟𝑎𝑣𝑒𝑙 𝑡𝑜 𝑃𝑖𝑡

8. Determine the number of shovels required

𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑆ℎ𝑜𝑣𝑒𝑙𝑠 = 𝑅𝑂𝑈𝑁𝐷𝑈𝑃 (𝑇𝑟𝑢𝑐𝑘 𝐶𝑦𝑐𝑙𝑒 𝑇𝑖𝑚𝑒

𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑇𝑟𝑢𝑐𝑘𝑠 ∗ 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 𝑇𝑖𝑚𝑒)

9. Compare different truck and shovel pairings by cost and efficiency

𝑆ℎ𝑜𝑣𝑒𝑙 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 =𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑇𝑟𝑢𝑐𝑘𝑠 ∗ 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 𝑇𝑖𝑚𝑒

𝑇𝑟𝑢𝑐𝑘 𝐶𝑦𝑐𝑙𝑒 𝑇𝑖𝑚𝑒 ∗ 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑆ℎ𝑜𝑣𝑒𝑙𝑠

This model was used with recommendations from Andrew Moebus, sales support staff of Toromont.

10.1.1 Daily Ore and Waste Production

The product of a daily milling rate and expected strip ratio is the expected daily waste production rate as

shown:

𝐷𝑎𝑖𝑙𝑦 𝑊𝑎𝑠𝑡𝑒 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 = 𝐷𝑎𝑖𝑙𝑦 𝑂𝑟𝑒 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 ∗ 𝑆𝑡𝑟𝑖𝑝 𝑅𝑎𝑡𝑖𝑜

For an open pit mine in the arctic, it was assumed 5 days are lost to holidays and other work

interruptions every year [11]. Targeting a yearly milling rate of 3.2 Mt of ore per year and assuming 360

Page 41: Conceptual Mine Design, Grum YT

41

effective working days per year, about 8889 tpd of ore can be expected per day. To determine the total

size of the fleet, the conditions with the highest production rate. Based a production-balanced mine

schedule with stockpiles (refer to section “Production Schedule”), strip ratio reaches approximately

7.43, producing an expected waste production of about 65000 tpd of waste, as in Table 10-2.

Table 10-2 A summary of mining rates near the end of mine life.

Material Movement Units

Strip Ratio Waste/ore 7.43

Ore Per Day Tonnes 8889

Waste Per Day Tonnes 65132

10.1.2 Daily Productive Hours

Assume a number of working hours scheduled per day; the daily productive hours can be estimated

based on an estimated efficiency and time used for shift changes and breaks.

It was assumed that a schedule can designed for a 24 hour day, with 4 hours lost to breaks and shift

changes [11]. Of the remaining 20 workings hours, assume 90% efficient use [11], resulting in 18 hours

of productivity per day, as summarized in Table 10-3.

Table 10-3 A summary of net productive hours calculation.

Scheduling and Availability

Daily Scheduled Hours hrs 24

Shift changes, lunches and Breaks hrs 4

Gross Scheduled hours hrs 20

Efficiency % 90

Daily Productive Hours hrs 18

𝐷𝑎𝑖𝑙𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑒 𝐻𝑜𝑢𝑟𝑠 = (𝐷𝑎𝑖𝑙𝑦 𝑆𝑐ℎ𝑒𝑑𝑢𝑙𝑒𝑑 𝐻𝑜𝑢𝑟𝑠 − 𝐵𝑟𝑒𝑎𝑘𝑠) ∗ 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦

10.1.3 Required Hourly Production Rate

The product of targeted mining rates and the fraction of the working day available is the required daily

productivity. The product of the previously calculated mining rates and daily productive hours results in

a required production rate of 494 t/hr of ore and 3160 t/hr of waste.

𝐻𝑜𝑢𝑟𝑙𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 = 𝐷𝑎𝑖𝑙𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 ∗𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑒 𝐻𝑜𝑢𝑟𝑠

𝑆𝑐ℎ𝑒𝑑𝑢𝑙𝑒𝑑 𝐻𝑜𝑢𝑟𝑠

Page 42: Conceptual Mine Design, Grum YT

42

10.1.4 Potential Truck and Shovel Models

Out of the different types of loading vehicles, the front shovel was recommended for its greater

versatility than excavators and rope shovels [11]. Variety in the haulage fleet would be limited to only

one model of shovel and one model of truck, to avoid issues with maintenance and inventory of spare

parts.

Using the Toromont Pass Match chart shown in Figure 10-1, for a mine between 8000 to 10000 tpd

milled, the CAT 785 truck is recommended, in conjunction with shovel models from 6030FS to 6050FS.

To account for variations in mine geometry and strip ratios, trucks from 777G, 785D, and 789D and each

model of shovel would be considered for analysis.

Figure 10-1 Toromont pass match chart for determining truck model based on milling rate and recommended shovel models based on truck model [12]

10.1.5 Properties of Trucking Routes

The properties of the trucking routes (the distance, rolling resistance, slopes of roads) site was

determined from measurements of the of the site layout map shown in Appendix Section 16.13. Sloped

distances were determined from the horizontal distances on the map and slope grades using

trigonometry.

𝑆𝑙𝑜𝑝𝑒 𝐷𝑖𝑠𝑡𝑎𝑛𝑐𝑒 =𝑀𝑎𝑝 𝐷𝑖𝑠𝑡𝑎𝑛𝑐𝑒

cos(𝐺𝑟𝑎𝑑𝑒)

Page 43: Conceptual Mine Design, Grum YT

43

The grades of the dump and pit ramps were determined in the Final Pit Design Section. Rolling

resistance (RR) values were adopted from the Toromont’s sample values [12]. Compiled properties of

road segments are in shown in Table 10-4.

Table 10-4 Distances, grades and rolling resistances involved in the haulage routes for ore and waste.

Segment Length Grade RR

Units m % %

Load area 100 0 4

Ramp 3298 10 3

Crusher Road 1713 0 3

Crusher Ramp 100 10 3

Crusher Pad 50 0 3

Dump Road 702 0 3

Dump Ramp 3224 10 3

Dump Run 423 0 3

10.1.6 Time Spent on Travelling to and from Dump and Mill

From the geometry of the site layout (the distance, rolling resistance, slopes of roads), assumed speed

limits, and the truck models chosen for analysis, appropriate truck speeds for each road segment could

be determined using the appropriate rimpull and retarding curves (Appendix Section 16.3). Rimpull

curves were used for uphill travel, retardation curves were used for downhill travel.

After taking appropriate speed estimates from the charts, a speed limit of 35 km/h was applied to

sections in the pit or on a slope and a 50 km/h limit was applied mine wide [12]. Knowing the speed and

distance of each segment, the time required to traverse each segment could also be calculated. The

calculated speeds and time to traverse each segment are shown in Appendix Section 16.4.

10.1.7 Loading Time

Loading time depends on the number of passes required by a certain shovel to fill a truck. The number

of passes required would depend on the ratio of bucket capacity to truck capacity.

The capacity of a truck depends on its model. Considering trucks 777, 785, and 789, bucket capacities

range from 100 to 200 tons.

The capacity of the bucket and the number of passes required can be calculated from its volume using

typical fill factors and loose densities of ore and waste [12]. The total time spent loading would be the

sum of every pass and spotting times. Typical pass and spot times were recommended by Toromont

Industries Ltd., 2016. Calculated values are shown in Appendix Section 16.13.

𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑃𝑎𝑠𝑠𝑒𝑠 =𝑇𝑟𝑢𝑐𝑘 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦

𝑆ℎ𝑜𝑣𝑒𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 ∗ 𝐿𝑜𝑜𝑠𝑒 𝐷𝑒𝑛𝑠𝑖𝑡𝑦 ∗ 𝐹𝑖𝑙𝑙 𝐹𝑎𝑐𝑡𝑜𝑟

Page 44: Conceptual Mine Design, Grum YT

44

𝐿𝑜𝑎𝑑 𝑇𝑖𝑚𝑒 = 𝐹𝑖𝑟𝑠𝑡 𝑃𝑎𝑠𝑠 + 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑃𝑎𝑠𝑠𝑒𝑠 ∗ 𝑃𝑎𝑠𝑠 𝑇𝑖𝑚𝑒 + 𝑆𝑝𝑜𝑡 𝑇𝑖𝑚𝑒

10.1.8 Truck Cycle Time

Having previously determined the time spent in travel, the total cycle time required for a truck to have

hauled and dumped its load and returned for another load is the sum of loading time, travel time to the

dump/crusher, dumping time, and return time to the bottom of the pit.

𝑇𝑟𝑢𝑐𝑘 𝐶𝑦𝑐𝑙𝑒 𝑇𝑖𝑚𝑒 = 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 + 𝑇𝑟𝑎𝑣𝑒𝑙 𝑡𝑜 𝐷𝑢𝑚𝑝 𝑆𝑖𝑡𝑒 + 𝐷𝑢𝑚𝑝𝑖𝑛𝑔 + 𝑇𝑟𝑎𝑣𝑒𝑙 𝑡𝑜 𝑃𝑖𝑡

10.1.8.1 Number of Required Trucks

The number of required trucks is the ratio of the hourly production rate to the productivity of a single

truck. The productivity of a single truck is a ratio of its actual capacity, which is the product of the

number of shovel passes used for loading and the capacity of the shovel bucket, to its total cycle time.

The results are shown in Appendix Section 16.17.

𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑇𝑟𝑢𝑐𝑘𝑠 =𝐻𝑜𝑢𝑟𝑙𝑦 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛

𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑃𝑎𝑠𝑠𝑒𝑠 ∗ 𝑆ℎ𝑜𝑣𝑒𝑙 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦

10.1.9 Number of Required Shovels

Number of required shovels can be calculated from rounding up the ratio of the cycle time for a truck to

the sum of loading times for each truck in the fleet. The results are shown in Appendix Section 16.17.

𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑆ℎ𝑜𝑣𝑒𝑙𝑠 = 𝑅𝑂𝑈𝑁𝐷𝑈𝑃 (𝑇𝑟𝑢𝑐𝑘 𝐶𝑦𝑐𝑙𝑒 𝑇𝑖𝑚𝑒

𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑇𝑟𝑢𝑐𝑘𝑠 ∗ 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 𝑇𝑖𝑚𝑒)

10.1.9.1 Comparison Metrics

The combinations between trucks and shovels can be compared by their capital cost and shovel

efficiencies. Typical capital costs were taken from the Relative Pricing chart [13]. Shovel efficiencies

were calculated as the ratio of time the shovel spends loading to the productive hours available for the

shovel to work. Graphs depicting capital cost and efficiencies of each truck and shovel pairing are shown

in Figure 10-2 and Figure 10-3.

𝑆ℎ𝑜𝑣𝑒𝑙 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 =𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑇𝑟𝑢𝑐𝑘𝑠 ∗ 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 𝑇𝑖𝑚𝑒

𝑇𝑟𝑢𝑐𝑘 𝐶𝑦𝑐𝑙𝑒 𝑇𝑖𝑚𝑒 ∗ 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑆ℎ𝑜𝑣𝑒𝑙𝑠

Page 45: Conceptual Mine Design, Grum YT

45

Figure 10-2 Capital cost associated with each shovel truck pairing

Figure 10-3 Efficiency of each shovel truck pairing

Based on these performance metrics, the pairing of the CAT 785G truck and the 6040 shovel were

selected due to the high efficiency and low cost of this pairing, with the required number of each

detailed in Table 10-5. Of concern is the reliance on only one shovel, but capital would be allocated to

ensure proper maintenance and replacement parts if needed.

$60,000,000

$65,000,000

$70,000,000

$75,000,000

$80,000,000

$85,000,000

$90,000,000

777G 785D 789D

Truck Model

Capital Cost of Shovel-Truck Pairings

6015 6018 6030 6040 6050 6060

30%

40%

50%

60%

70%

80%

90%

100%

777G 785D 789D

Truck Model

Efficiencies of Shovel-Truck Pairings

6015 6018 6030 6040 6050 6060

Page 46: Conceptual Mine Design, Grum YT

46

Table 10-5 Number of trucks and shovel s expected throughout the mine life

-2 -1 1 to 17 18

Trucks 7 13 21 8

Shovels 1 1 1 1

10.1.10 Additional Equipment and Support Fleet

Based on recommendations from Moebus and reference to other technical reports, additional

equipment requirements are detailed in Table 10-6. CAT models are used as reference for cost at this

time and unspecified models would be determined in later studies.

Table 10-6 Number of additional and support equipment expected

2 Front End Loaders CAT 994F 18 m3

4 Track Dozer CAT D9T 13.5 m3

2 Wheel Dozer CAT 854K 7.9 m3

3 Motor Grader CAT 24M 24’ blade

1 Water Truck --- 10000 gal

1 Articulated Truck CAT 735B 19.7 m3

1 Vibratory Compactor CAT CS-64 112 kW

1 Tool Carrier CAT IT 38H 2.5 m3

6 Diesel Drill --- 4.5’’ to 8.5’’

1 Secondary Drill --- 4.5’’ to 5.5’’

10.2 Benchmarking

10.2.1 ARCTIC (NovaCopper Inc.)

NovaCopper Inc. is a company operating in Alaska, USA, with several polymetallic properties. Of note is

their planned ARCTIC mine in Alaska [14], which like Grum is a polymetallic open pit mine with a similar

milling rate of 10000 tpd, about 12% larger than 8900 tpd for the Grum project. A comparison of the

chosen fleet provides reasonable benchmarking. A comparison of equipment is listed in Table 10-7

below.

Table 10-7 A comparison of preliminary equipment fleets of Grum and NovaCopper’s ARCTIC

ARCTIC Grum

Capacity Number Capacity Number

Shovels 11.0 m3 4 22.0 m3 1

Haul Trucks 100 t 24 150 t 21

Page 47: Conceptual Mine Design, Grum YT

47

NovaCopper’s ARCTIC uses 4 times to number of shovels, with a total shovel capacity twice that of

Grum, but only 12% higher milling rate. Also, the trucks of ARCTIC have only two thirds the capacity of

the trucks selected for Grum. This suggests that ARCTIC has shorter haulage routes, allowing trucks to

return quicker and more often to utilize more shovels. This suggests that Grum may have longer haul

lengths and could not achieve the greater efficiency and redundancy from using smaller equipment.

These advantages more be possible for the Grum pit if the site layout and ramp exit are better

optimized in the future; currently, the ramp exits in a direction opposite to that of the mill, requiring an

extra 3 km of travel.

10.3 Meadowbank (Agnico-Eagle Mines Ltd.)

Meadowbank [15] is a gold mine located in Nunavut, Canada, which has a milling rate of 10100 tpd,

which is 13% larger than the 8900 tpd of Grum. A comparison of equipment is shown in Table 10-8.

Table 10-8 A comparison of loading and haulage fleets between Grum and Agnico Eagle’s Meadowbank

Meadowbank Grum

Capacity Number Capacity Number

Shovels 15.0 m3 3 22.0 m3 1

Haul Trucks 150 t 11 150 t 21

100 t 8

Similar conclusions from ARCTIC can be drawn for the differences between Grum and Meadowbank;

Meadowbank likely has shorter haulage routes, which would be an objective for later Grum designs.

11 Environmental and Social Impact Assessment

11.1 Required Legal Documents

Along with this very brief and preliminary summary, many documents are required to determine and

describe the environmental and social impacts of the project. A full federal Environmental Impact

Assessment (EIA) or Environmental and Social Impact Assessment (ESIA) is required by law by the

Canadian Environmental Assessment Agency as well as the Yukon Environmental and Socio-economic

Assessment required by the Yukon Environmental and Socio-economic Assessment Board. These

documents must be filed and approved before construction commences. Table 11-1 describes the legal

steps that must be followed to obtain approval to mine in the area [16]. It outlines the authorization,

which act it is from and who requires it for each activity. Section 11.4 also outlines a preliminary

potential Impact Benefit Agreement (IBA) with the local Aboriginal Communities.

Page 48: Conceptual Mine Design, Grum YT

48

Table 11-1 Permits for various Mine Activities

11.2 Valued Ecosystem Components

Valued Ecosystem Components (VECs) are defined as broad components of the biophysical and human

environments, which, if altered by the project, would be of concern to regulators, participating

Aboriginal Groups, resource managers, scientists, and the public. The purpose of identifying the VECs is

not to be all inclusive, recognizing the practical impossibility of analyzing everything, but to look at

potential project effects on representative components.

11.2.1 Atmospheric Systems

11.2.1.1 Air Quality

Air quality can be subdivided into three key indicators: ambient air quality concentrations, particulate

matter deposition, and greenhouse gases in the atmosphere. Ambient air quality deals with the

potential effects of air emissions on the environment. Mining activities generate air emissions due to

fuel consumption, erosion, and material transfer caused by ore processing and traffic on unpaved roads.

Table 16-23, in Appendix Section 16.18, outlines the ambient air quality and particulate matter

standards for Yukon Territory [17]. The standards must be met to ensure the safety and sustainability of

the area and its components. Major air pollutants such as sulphur dioxide, nitrogen dioxide, carbon

monoxide and particulate matter in the study area must be monitored.

Page 49: Conceptual Mine Design, Grum YT

49

11.2.1.2 Noise

Noise levels are important to individuals and wildlife for several reasons such as sleep disturbance and

annoyance. Both the Fannin’s Sheep and Boreal Woodland Caribou are sensitive to noise, so special

consideration is required for the eastern side of the site. More noise is expected during the construction

phase; the site will be run on diesel power generators and more vehicle traffic is expected. Mitigation

strategies are outlined in Section 11.3. Baseline studies on the A-weighted noise levels (dBA) are

required. Yukon does not currently have any published noise guidelines or regulation [18].

11.2.2 Water Systems

The mine site is located within the Yukon River drainage basin, Figure 11-1. The site is upstream of

Vangorda Creek, which empties into the Pelly River approximately twelve kilometers from the mine site.

Within four kilometers of the Pelly River, the Vangorda Creek provides some seasonal recreational

fishing. However, there are better choices in the area, including the Pelly [19]. A water treatment plant

will be located on site to treat the effluent water from pumping and processing. By managing the quality

of released water, the nearby water systems and aquatic habitat will be preserved. An adaptive

treatment plant that allows for fluctuating discharge rates will ensure the effluent quality does not

exceed limits outlined in Table 16-24 in Appendix Section 16.18 [17].

Figure 11-1 Yukon Drainage Basins [20]

11.2.2.1 Pelly River

Pelly River contains various types of fish including:

Rainbow trout

Kokanee salmon

Arctic char

Jackfish or pike

Lake trout

Page 50: Conceptual Mine Design, Grum YT

50

Arctic Grayling [19]

The most likely catch is the Salmon and Arctic Grayling. Most of the above fish are found in much

greater abundance in the surrounding lakes leading to the Pelly River. The indicator species in the area is

the Rainbow Trout. The Pelly River fish are not considered at risk, endangered or of special concern. The

river is also used as canoe and kayak routes for tourists [21].

11.2.2.2 Vangorda Creek

The sections of Vangorda Creek affected by the project are not fish bearing. Several kilometers

downstream, there is a natural waterfall that prevents fish passage to this section of the creek. Two

testing points on Vangorda Creek are planned to monitor for possible effluent caused toxins [22].

11.2.3 Terrestrial Environment

In 1969, a forest fire cleared most of the old growth boreal forest in the faro area and Cyprus Anvil’s

Faro Mine cleared the adjacent property by 1998. A baseline study is necessary to determine if any rare

plant species exist on or close to the mine site. Various lichen species should be mapped to determine

wintering grounds of the woodland caribou.

11.2.3.1 Vegetation Communities

In 1969, a forest fire cleared most of the old growth boreal forest in the faro area and Cyprus Anvil’s

Faro Mine cleared the adjacent property by 1998. A baseline study is necessary to determine if any rare

plant species exist on or close to the mine site. Various lichen species should be mapped to determine

wintering grounds of the woodland caribou.

11.2.3.2 Wildlife

The mine is not located within a game management subzone. Hunting by non-aboriginals in this

area is limited to special guide license [21].

Three large prey species live within the Grum project area; moose, woodland caribou and

Fannin’s sheep. The largest population of wildlife in the area consists of moose. There are 1 to 10 moose

per square kilometer on the immediate Grum site and adjacent property. Moose are not considered of

special concern and can adapt easily to noises and habitat loss. Moose are most susceptible to vehicle

collisions and increased non-aboriginal hunting [23]. Boreal populations of woodland caribou in the

Yukon are not considered of special concern. Measures will be taken to avoid the habitat of the

woodland caribou because they are a sensitive species. Revegetation during remediation will focus on

jack pine forests which are lichen bearing. Lichen is the caribou’s primary food source in the winter.

Every fall sheep gather in the mountains and cliff sides around Faro to spend the winter. The cliff sides

provide grasses that remain from the summer and a secure home for the sheep [24]. Fannin’s sheep are

an important tourist attraction for the Faro Community. The sheep, like caribou are sensitive to habitat

changes.

Page 51: Conceptual Mine Design, Grum YT

51

Wolves, coyotes, wolverines, lynx and bears prey on the moose, caribou and sheep in the Faro

Area. Coyotes and bears could be an issue on the future mine site if drawn by food waste scents. The

predators tend to follow the big game and prey mostly on the smaller sheep and young moose and

caribou. More information is required regarding predator habitat in the Faro region.

11.2.4 Natural Heritage System

Heritage resource sites commonly found in the Yukon include cabins, tent frames, brush camps, caches,

traps and snares, fire-cracked rock, fish camps, watercraft, stone adze-cut stumps, game drives and

surrounds, trails, and graves. The Faro Interpretive Centre is open May to September and accounts for

0.4% of Faro’s economy. The center highlights the natural heritage in the Faro region and organizes

various activities [25]. The Dena Cho Trail retraces the 80-km route between Ross River and Faro

originally used by gold prospectors [26].

11.2.5 Socio-Economic Factors

A full Social Assessment is required, and will outline local economy, traditional pursuits, aboriginal

community, health, heritage resources and physical infrastructure, regional economy and mining

industry. The two groups to focus on are the Ross River Dena Council of the Kaska traditional territory,

and the community of Faro.

11.2.5.1 Faro

Faro is a town with a population of 367, located 12 km downstream of the potential Grum Pit.

Although Faro was created as a community to house workers and provide services to the Cyprus Anvil

Mine, mining is no longer the base of the community's economy. In 1996, when the Anvil Range mine

was still producing, well over 50 percent of the community's workforce was employed in mining. Other

industries provided services to the mine, such as transportation of minerals or delivery of goods. The

people of Faro are now focused on practical economic development opportunities to guide the

community. Important issues include residential development, community facilities, recreation, the

environment, infrastructure and social well-being. Because Faro established a wide variety of

community and recreational facilities when the Faro Mine was in operation, there is a high level of

services and well-developed community and recreational infrastructure. A good housing stock, along

with extensive community services, can help support economic growth. The people of Faro are wary of

new mining projects within close proximity to the mine due to the abandoned Faro Mine and the

environmental issues it has caused. It is important to assess potential effects on employment and

income as it is a prominent factor in determining community benefits arising from the project. Changes

in employment and income can affect the wellbeing of individuals, families, and communities in the

area. Public consultations will occur during each stage of the design and the Environmental Assessment.

Benny Resource Group will also invest a percentage of monthly profits in the community to support post

mining prosperity.

Page 52: Conceptual Mine Design, Grum YT

52

11.2.5.2 Ross River Dena Council

The land in which the Grum project is located is within the Kaska Nation and is governed by the

Ross River Dena Council. From an Aboriginal perspective, maintaining cultural identity requires the use

of land for harvesting traditional resources, opportunities to transfer traditional knowledge and skills,

and speaking the local language. The Kaska people are settled in Ross River, upstream of the Grum site.

Since the closure and lack of remediation of the Faro Mine, traditional hunting and trapping has ceased

in the project area [27]. The Ross River Dena will be appropriately compensated for lost land and

employed in the Grum Mine. It is important not to infringe on aboriginal rights. A preliminary Impact

Benefit Agreement is presented in Section 11.4.

11.3 Assessment of Impacts

It is important to identify the potential impacts the project may have on the stakeholders and VECs.

Understanding the consequences helps to manage and mitigate the causes. Table 16-28 through Table

16-34 in Appendix Section 16.18 establish the preliminary impacts, associated risks and preliminary

mitigation measures. The significance of environmental impacts were determined for effects after

application of appropriate mitigation measures, and was evaluated on the basis of the criteria described

in Table 16-25 through Table 16-27, Appendix Section 16.18 [28].

Table 11-2 below, provides a summary of the key impacts, the cause of the impact, and the mitigation

strategies in place to reduce the risk negative impacts.

Table 11-2 Summary of Key Impacts, Causes, and Mitigation Strategies

Valuable Ecosystem Component System

Cause Effect Mitigation

Socioeconomic

Lack of transparency, dishonesty, cumulative and/or combined causes stated below.

Inability to obtain permits, degradation of public reputation, strikes, blockades and damage to property.

Say what you mean and do what you say. Implement mitigation measures stated below. Consult with the community and remain transparent, honest and approachable.

Mine site accidents, vehicle accidents, natural disasters

Injury to employees Dry mine site, proper preventative and reactive training.

Visual impact of mine structures, degradation of water quality,

Decreased tourism and recreation leading to reduced economic prosperity

Compensation and contribution to community amenities. Vegetated barrier, natural slopes at closure.

See all below See all below See all below

Water Stream diversion/area loss Contaminated surface water-

sediment build up Divert minimum, consider different site layout. Monitor water quality.

Page 53: Conceptual Mine Design, Grum YT

53

Acid mine drainage Contaminated groundwater/surface water

Divert water to catchment pond and treat, line TSF and WRD. Monitor water quality upstream and downstream. Place pipelines from Mill to TSF and TSF to water treatment plant so they do not cross water systems. Remain within one watershed (Vangorda Creek/Pelly River).

Pumping Reduced local and regional groundwater affecting aquatic species.

Release treated water as required. Recycle tailings water for processing.

Cultural Heritage Restriction of project area and clearing area for the site

Interference to traditional pursuits, damage to local heritage

Report found artefacts, consult with community to determine options, if any.

Terrestrial

Clearing area for site Habitat loss Provide 150 m buffer around streams. Condense site as much as possible. Reclaim area as a productive ecosystem. Monitor wildlife

Acid mine drainage Contaminated habitat See above Water Systems mitigation measures. Monitor wildlife

Atmospheric

Vehicles, blasting, mill, generators

Noise: Negative effects on animals and people.

Increased greenhouse gas emissions

Vegetation barrier, use electrical power after construction, blast during afternoon shift change

Vehicles, blasting Increased dust in the air: reduced air quality

Water sprayers to reduce airborne particulate matter

Monitor air quality.

The focus of the summary is on the impact on the socio-economical system. The Faro community and

the Kaska people will be affected in changes to the environment. It is important to Benny Resource

Group to prevent another Faro Mine disaster and foster mutual respect with the communities. Many of

the mitigation strategies involve site characteristics, such as footprint considerations and inclusion of a

water treatment facility. The site layout, as discussed in Section 8, was designed to reflect such

considerations. Consultation to present and discuss designs is also a pertinent way to diffuse potential

social issues, and obtain valuable input from the community. It is also important to provide

compensation when negative effects are foreseen that cannot be avoided. Monitoring is planned to take

place throughout all phases of mine life including post-closure. Proactively monitoring and having

procedures in place, to adapt and prevent significant negative events is incorporated into the design of

the project.

11.4 Impact Benefit Agreement

The Kaska and the natural resource development sector is committed to the reclamation of impacted

sites. Consideration must be given to compensation for impacts incurred. An important issue is how to

determine fair compensation and how to implement a compensation policy. The Kaska expect

compensation plans to be applied to themselves, wildlife and habitat, Kaska Land Stewards, and

Page 54: Conceptual Mine Design, Grum YT

54

Trappers. In addition, there is expected resource development and federal regulatory compensation

plans [29].

In order to properly compensate the Kaska Nation for the future mine impacts, payment, in addition to

jobs and training, should be provided. The agreement includes a payment plan, training and

employment opportunities, and environmental commitments for the Kaska First Nations. Until the mine

goes into production, the Kaska would receive fixed bonus payments at different points during the

permitting process. Once the mine is in operation, the First Nations would continue to receive fixed

annual payments until Benny Resource Group has paid off the cost of building the mine. After that, the

Kaska would receive a percentage of the mine’s monthly profits [30]. Those payments would be divided

among the Nations according to the Kaska Collaboration Agreement, which sets out guidelines for

sharing the benefits of resource development among the communities [31]. Money will also be invested

in first nation’s communities and shares will be offered to the community to directly involve the band so

positive outcomes for the company mean positive outcomes or the band.

Benny Resource Group will provide Ross River Dena a voice in the remediation planning, and

consultation will occur at each stage of design. Careers in waste, food service, custodial services, and

mine labour will be made available for the Native people first with few restrictions and thorough

training. There will also be career development workshops and information sessions with regional high

schools. Contracts will be made with aboriginal construction companies to make certain that local

communities gain experience and thrive. The target for Aboriginal workforce is 20%. Post-secondary

equivalent training for more technical positions in the mine will also be available to members of the Faro

and Kaska communities. During the early phases, Traditional Ecological Knowledge consultants can aid in

baseline studies, wildlife patterns, obtaining information on traditional cultural heritage and take part in

monitoring programs [32]. Remediation strategies will be greatly affected by the First Nation

community.

12 Mine Closure

12.1 Introduction

This section will address potential environmental issues, regulations, required permits, social

involvement, and information in regards to environmental sustainability during operation, and closure.

This section will also cover the following, as in compliance with the Yukon Mine Reclamation and

Closure Policy:

Some baseline studies for important environmental components with their environmental monitoring programs that plan to be implemented

Reclamation objectives

Stabilization of structures and workings

Areas of re-vegetation where practicable

Cost estimate for the reclamation process

Page 55: Conceptual Mine Design, Grum YT

55

12.2 Regulatory Requirements

BRG will be responsible for the reclamation process in accordance with the established legislative

framework set by the Yukon government. The reclamation process will be integrated during the

planning, development and operating phases of the mine. Before advancing with the development, the

Yukon government will need to approve the reclamation and closure plan. A Certificate of Closure, as

stated in section 137 of the Quartz Mining Act, will be issued by the Yukon government, given it is in

compliance with the prescribed conditions set by the government [33]. It is mandated that BRG seek

consultation of government, First Nation, and local community member during the reclamation and

closure planning, which is also part of the provision of the Certificate of Closure.

12.2.1 Permits

In order to operate the Grum Pit successfully, obtaining permits and licenses will be necessary. The

process of receiving permits can be between 100-130 days after submission. This time frame can

include: appropriately addressing concerns of all parties affected by the operation such as the

government agencies; the First Nations; and local stakeholders. Table 12-1 displays the permits required

for all closure activities.

Table 12-1 Permits Required for Mine Closure

12.3 Environmental Studies

For successful mine closure, the Yukon Environmental and Socio-economic Assessment (YESA) will be

required, which outlines and identifies the potential environmental and socio-economic effects. YESA

will be necessary to obtain the permits needed to launch development. The process will entail a

systematic approach to identifying potential issues by conducting series of baseline studies of the

environment, with the main focus on the Valued Ecosystem Components (VECs).

Page 56: Conceptual Mine Design, Grum YT

56

12.3.1 Environmental Baseline Studies

Collecting the environmental baseline data is a key element of the YESA for the Grum Pit. The data will

include: climate; air quality; hydrology; sediment and water quality; and flora and fauna. The data will

be collected for the whole year, which will aid in observing the seasonal variation of these different

environmental disciplines. YESA will be submitted to the Yukon Environmental and Socio-economic

Assessment Board (YESAB), and will be important in evaluating the potential impacts from the project so

alternative actions and mitigation measures be constructed. A rough baseline study will also be

conducted for site layout, but it will be based be on information already available, and not carried out by

BRG. Table 12-2 summarizes the environmental baseline data BRG need to collect and study.

Table 12-2 Environmental Baseline Studies

Category Program Elements

Climate Meteorology stations, providing up-to-date information

Air Quality/Noise Total Particulate (Dust fall) samples

Hydrology Water quality measurements and evaluation

Fisheries and flora Monitoring population of distinct fish species and flora communities

Fauna Monitoring wildlife communities and population

Hydrogeological studies

Determining the distribution of groundwater and its quality, depth and other properties. Study of watersheds.

Geophysical studies Monitoring seismic activities

Socioeconomic studies

Background studies on First Nations, communities and other stakeholders

Archeological studies Determining scientific interest archeological sites and First Nation heritage sites.

Sediments and Water quality

Observing existing chemicals and pH level

12.4 Objectives and Environmental Issues

The closure plans and design process will incorporate opinions of many stakeholders including the

indigenous communities. The main targets of the closure phase are:

1. To safeguard the health and welfare of all humans, plants and animals 2. To safeguard and return the environment to as close as possible to its pre-disturbed state 3. To restore and re-contour the mine site for both aesthetic and land use purposes, especially the

tourist sites 4. To assist in socio-economic benefits and opportunities 5. To implementing cost-effective measures to mitigate long-term risks

In order to achieve these targets, potential environmental will be assessed and analyzed. The main

concern is the acid rock drainage. Therefore, appropriate measures will have to be taken to address, and

prevent this concern from occurring.

Page 57: Conceptual Mine Design, Grum YT

57

12.4.1 Acid Mine Generation

Acid Mine Drainage (AMD) forms when the sulphide minerals, (e.g. in lead and zinc ores), oxidize. These

oxidized sulphide minerals are later discharged into the environment. The leaching of these materials

can occur in various ways like along the pit slopes, on the base of the waste rock pile and tailings, and

often occurs during rainfall, where water becomes the medium of transport. Both WRD and the tailings

outputted from the mill and stored in the tailings impoundment will have PAG waste. The occurrence of

AMD will have adverse effect on the immediate environment particularly the aquatic ecosystems, those

near the Vangorda Creek and the watersheds. Acid contact with water bodies will reduce the pH level

and increase the toxicity, posing a threat to the biotic life. The oxidized sulphide minerals may seep into

the ground, contaminating groundwater and negatively affect those that rely on it as a source of

drinking water. AMD will require a long-term remediation plan and it will have adverse effects that last

many years if not dealt appropriately and will be discussed in the following section.

12.5 Environmental Management

Environmental Management Systems (EMS) will be developed for both corporate and specific to the

operation throughout the entire mine life and will be consistent with both ISO 14001 EMS standards and

the standardized framework established by the Yukon government. Upon the commencement of the

operation, a more elaborate and complete environmental management plan will be made to better

reflect the practicality of the operation. The subsection below provides ways in which the waste will be

managed. This is the initial, ostensible closure plan and therefore is subjected to change once mine

begins to operate and if unforeseen circumstances abound. The mine site is expected to have one Waste

Rock Dump (WRD) and one Tailings Storage Facility, seen in Section 8.

12.5.1 Waste Rock Dump

The main aim will be to return the dump site to close as possible to the original state, identical to

surrounding lands, while ensuring that both physical (slope) and chemical (prevention of metal

transport) stability remains robust for long-term basis. The following plans will be implemented for

waste rock dump during closure:

Re-contouring of WRD terraced slopes to appear less steep and to naturally blend in with surrounding landform

Implementing a drainage system to better cope with heavy rainfalls and prevent soil erosion. If stream diversion results due to expansion of WRD, that would be considered when implementing the drainage system

Re-sloping of terraced slopes to establish long-term stability with cover on top

Restoring watersheds affected by both WRD and TSF

A multi-layer, engineered cover system will be placed on the acid-generating tailings impoundment. The

first layer placed directly on top of the tailings will comprise of sand. The sand layer will then be overlain

by coarser material. On top of the coarser material will lay a layer comprised of stockpiled fine-soil

mixed with gravel. The interface between the fine and course layer will be the capillary barrier for

Page 58: Conceptual Mine Design, Grum YT

58

controlling percolating water and water migration. The main aim for the fine-soil layer will be to retain

the infiltrated water until the water is recycled back to the atmosphere through evaporation. Another

way to recycle water back to the atmosphere is through transpiration; therefore the top layer will be

fertilized and seeded to re-vegetate. Vegetation on the cover will consists of a diverse mixture of native

plants, which will not only maximize the removal of retained water through evapotranspiration process,

but will also remain stable and resilient to unforeseen alteration in the environment and climatic

fluctuations. These plant species have the inherent ability to quickly adapt to environmental changes.

The gravel mixed with fine-soil, will help in preventing wind erosion by reducing tractive shear stresses.

Figure 12-1 shows the schematic of a cross-section of the cover to be used on the WRD.

Figure 12-1 Schematic cross-section of the cover over WRD

12.5.2 Tailings Dam

A two meter water cover will be used to prevent acid generation in the tailings dam. This cost-effective

method will mitigate AMD on long-term basis because oxygen has a very low diffusion and solubility rate

in water [34]. The main aim will be to prevent cover from drying up or spilling out. Therefore, a

catchment area will be made to ensure that there is adequate inflow to sustain water balance. There will

be a sufficient freeboard with emergency spillway to prevent overtopping during extreme flood events.

Lime will be added to increase the pH level of the waste before the cover is placed to further prevent

the potential of AMD from occurring. In order to maintain the integrity of the cover, the stability of the

dams on long-term basis will be important. This is further discussed under monitoring.

12.5.3 Pit Lake

Since the PAG rock associated with mineralization will be mined out and placed in the tailings pond, and

because no excess material will be left for backfilling; the open pit will be flooded to form an end-pit

lake. The water cover will slow acid generation, until BRG finds other means to permanently prevent it.

The bottom of the pit will contain a layer of highly permeable gravel and crushed limestone to neutralize

acid and prevent leaching. BRG will promote an ice-cover over the lake. The ice-cover will prevent

diffusion of oxygen with column of water below it and therefore prevent ARD [35]. The pit lake will be

integrated into the landscape aesthetically. The pit lake will neither be used for recreational purposes

Page 59: Conceptual Mine Design, Grum YT

59

nor will it have any aquatic life until it is deemed safe. Placards and fences will be placed around areas of

the pit lake to prevent human and animal intrusions.

12.6 Site Monitoring

Monitoring various environmental components will be largely contingent to specific requirements

outlined in the permits issued by the government agencies, as was discussed in Section 11, as well as

assessing it relative to the baseline data collected. The following section will briefly cover some of the

main environmental components be monitored. The full monitoring program will be outlined in the

YESA.

12.6.1 Water

Monitoring both surface water and groundwater along different locations to determine if any impacts

have occurred due to the operation. Wells will be drilled for monitoring groundwater. Water quality

parameter, such as pH level, and as well as hydrometric parameters of surface water will be monitored

to observe for any concerning and significant changes.

12.6.2 Air

Air quality will constantly be monitored during the operation. It will also be monitored during

reclamation phase to assess metal-bearing particles that may be airborne. A monitoring plan will be

placed in compliance with Yukon air quality guidelines and standards. This will entail monitoring the

total suspended particulates, metal concentrations, and emissions related to the mining operation.

12.6.3 Acid Mine Drainage

Long-term monitoring of the WRD will include monitoring the covers used and to ensure performance is

acceptable in mitigating infiltration and diffusion of water and oxygen. The monitoring program will

include the following:

Ensuring the covers are preventing the mobilization and release of contaminates

Monitoring water infiltration

Checking signs for potential desiccation and frost cracking (results in high permeability) within compacted soil layers

Monitoring for frost heaving that may result into layers mixture

The following would need to be monitored for the tailings dam:

Ensure that the water cover is no less than two meters

Prevent ice lenses from forming on the surface of tailings. This will require the monitoring of water temperature on top of the tailings to ensure it’s well above freezing point

Monitor abrupt climate change such as heavy rainfall or intense drop in temperature

Monitoring potential piping in dam structures and take appropriate measures to prevent it

The following would need to be monitored for the pit lake:

Page 60: Conceptual Mine Design, Grum YT

60

Promoting ice-cover and ensuring that it remains

Physical-chemical and biological monitoring

Monitoring of long-term water balance and water quality

Monitoring for potential leaching

12.7 Community Relations

Along with taking the initiative to conduct baseline studies and undertaking YESA, BRG will display

authentic corporate responsibility by consulting with the local community stakeholders and the First

Nations during mine closure. BRG plans to develop and maintain a strong rapport with First Nations and

other stakeholders by proactively consulting with them throughout the entire mine life and reclamation

process. Under the Yukon First Nation Final Agreement, BRG are obligated to consult and create

transparent relationships with the First Nations, and will respectfully uphold such requirements.

Another part of BRG corporate responsibility includes helping the local community members on socio-

economic grounds, by helping in the following ways:

Create employment opportunities for local community members

Find local community contractors for needed materials during mine closure

Financially assist the education system

Fund various community organizations and hospitals

12.8 Closure Costs

The costs of decommission and reclamation is estimated based on the costs incurred by two zinc-lead

mining companies, Teck and Yukon Zinc Corp., both which are operating in Yukon [36] [37]. The costs for

both companies varied partly due to the terms set by independent contractors. It is important to note

that these costs are estimated and are prone to changes during the operation. The costs summarized

below entail costs related to project closure, the decommissioning of facilities and structures,

reclamation undertakings, and post monitoring. The approximated costs are based on the following

assumptions and premises:

Exclusion of salvage value

Non-discounted estimate

Costs relating to reclamation and decommissioning are based on terms set by third party contractor

Unit rates were obtained from Government of Yukon Third Party Equipment Rental Rates. Shown in Appendix Section 16.19.

Contingencies costs, ranging from 10% to 20%, will be added in addition due to degree of potential risk and level of uncertainty

Costs based on assuming closure phase for over 10 years after end-of-mine-life

Costs for water treatment is based on 3 year period

Note that the costs are subjected to change to better reflect the Grum Pit conditions. The total closure

cost accounting for contingency (average of 15%) and monitoring, along with necessary things like liners

and covers can be anywhere between $7 M to $15 M as summarized in Table 12-3.

Page 61: Conceptual Mine Design, Grum YT

61

Table 12-3 Estimated Closure Costs

13 Detailed Economic Analysis

The economic analysis is preliminary in nature and depends on a block model of unknown origin. It is

not known if inferred resources are included in the block model definition. 2012 InfoMine cost models

[38] were used for estimating operating costs, the capital cost of the processing equipment, and freight.

Performance metrics are shown in Table 13-1 and a summary of financial results are shown in Table

13-2. A 15% discount rate was used, based on standard industry practice of 14% discount in the scoping

stage as well as a 1% risk adjustment for arctic mining [39].

Table 13-1 – Performance metrics

At a 15 % discount rate and 30% tax rate

NPV $156,072,026

IRR 21%

Payback Period 4.8 years

Life of Mine 22 years

Highest Sensitivities of NPV

Zinc price

Mining operating cost

+$4.74M/% increase of price

-$3.45M/% increase of costs

Table 13-2 - Summary of financial results

Revenues $ 6,163,300,000

Lead

Zinc

Gold

Silver

$ 1,863,200,000

$ 2,769,200,000

$ 909,600,000

$ 621,300,000

Page 62: Conceptual Mine Design, Grum YT

62

Operating Costs $ 2,901,900,000

Mining $ 1,171,500,000

Milling $ 714,200,000

Freight $ 364,700,000

Capital Cost $ 534,200,000

Pre-strip $ 115,500,000

Mining Equipment $ 86,900,000

Processing Equipment $ 108,400,000

Sustaining Capital $ 145,300,000

Closure $ 15,000,000

Taxes $ 911,700,000

Net Cash Flow $ 1,815,500,000

NPV $ 156,100,000

The cash flow model and the production schedule it models, are shown in Figure 13-1. The variation in

revenues are largely due to variation in grades and the recoveries of different host rocks over the mine

life. The largest costs in this design are operating costs and taxes.

Page 63: Conceptual Mine Design, Grum YT

63

Figure 13-1 - The production schedule and resulting cash flow model for the current pit design and operation

The sensitivity analysis for this design is shown in Figure 13-2. The current design has its greatest

sensitivities in zinc price and mining operating costs. Every percent increase in zinc price could raise NPV

by $4.74 M, is due to zinc contributing to 45% of total revenues. Every percent increase in mining

operating costs could reduce NPV by $3.45 M; reductions in this area would greatly increase profitability

of the mine and would be explored in future studies.

0

5000000

10000000

15000000

20000000

25000000

-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Balanced Production Schedule with Stockpiles

Stockpile Processed Ore Mined and Processed Ore Stockpiled Waste

-$400

-$200

$-

$200

$400

$600

-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Free

Cas

h F

low

s ($

M)

Years into Production

Cash Flow Model

Revenue Operating Costs Initial Capital Taxes

Pre Strip Sustaining Capital Closure Bond

Page 64: Conceptual Mine Design, Grum YT

64

Figure 13-2 - Sensitivities of prices and operating costs.

Estimation methodology of revenues, operating and capital costs, and taxes are detailed in the following

subsections.

13.1 Revenues: $6,163,000,000

Revenue was determined from the payable metal contained in the ore and the price it could be sold for

over a long period of time. Payable metal depends on the grade, the recovery and smelter terms on the

sale of the concentrate.

13.1.1 Price

The price used in this model were the consensus price forecasts by Scotiabank, Bank of America, and

National Bank Financial. The consensus prices are shown in Table 13-3 below. Long term price

predictions made by each bank for each metal are shown in

Table 13-4.

Table 13-3 - The forecast prices used for the model

zinc $ 1.03 /lb gold $ 1303 /toz

lead $ 0.97 /lb silver $ 18.93 /toz

$(400)M

$(200)M

$M

$200M

$400M

$600M

$800M

-150% -100% -50% 0% 50% 100% 150%Ch

ange

in N

PV

($

M)

Axis Title

NPV Sensitivity to Prices and Opex

Pb Price ($/lb) Zn Price ($/lb) Au Price ($/toz)

Ag Price ($/toz) Mining Cost ($/ton mined) Processing Cost ($/ton ore)

Page 65: Conceptual Mine Design, Grum YT

65

Table 13-4 - The long term price forecasts and the average, consensus price from three banks

Zn ($/lb) Pb ($/lb) Au ($/toz) Ag ($/toz)

Scotiabank $ 1.00 $ 0.95 $ 1,200 $ 17.50

Bank of America $ 1.06 $ 0.98 $ 1,358 $ 19.80

National Bank $ - $ - $ 1,350 $ 19.50

Average $ 1.03 $ 0.97 $ 1,303 $ 18.93

13.1.2 Variable Grades and Contained Metal over LOM

Contained metal was determined on an annual basis, based on the annual production tonnages and

their associated grades, in both the mill throughout and stockpile. The variability in the grades results in

variability of the contained metal for processing. The changing average annual grades are shown in

Figure 13-3 and Figure 13-4. A graph of the annual contained metal processed is shown in Appendix

16.20.

Figure 13-3 - The average annual Pb and Zn grades over the LOM

0

1

2

3

4

5

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Gra

de

(%)

Years into Production

Pb and Zn Grades over LOM

PB ZN

0

0.2

0.4

0.6

0.8

0

10

20

30

40

50

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Au

Gra

de

(g/t

)

Ag

Gra

de

(%)

Years into Production

Ag and Au Grades over LOM

AG AU

Page 66: Conceptual Mine Design, Grum YT

66

Figure 13-4 - The average annual Au and Ag grades over the LOM

13.1.3 Variable Rock Type, Recoveries, and Recoverable Metal over LOM

A key factor considered in the metal production model was the variation of the recoveries over the mine

life, which affects the recoverable metal sent to the mill or kept in stockpile. Recovery varies with

different rock types and the rock type mined changes over the course of production. It is assumed that

the recoveries of each ore type, provided from the Whittle model, are accurate enough for this

economic model. These recoveries are shown in Table 13-5. The annual recoveries are shown in Figure

13-5 and Figure 13-6.

Table 13-5 - The recoveries of each metal for each rock type

QRTZ MQRT PYMS BMAS PHYL BAMS GREE

Pb 87% 85% 86% 86% 89% 91% 88%

Zn 87% 85% 86% 86% 89% 91% 88%

Au 58% 61% 65% 65% 61% 63% 63%

Ag 52% 50% 55% 52% 50% 51% 55%

Figure 13-5 - The variation in lead and zinc recoveries over the scheduled mine life

85%

86%

87%

88%

89%

90%

91%

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Rec

ove

ry (

%)

Year of Production

PB ZN

50%

52%

54%

56%

58%

60%

62%

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Rec

ove

ry (

%)

Year of Production

AG AU

Page 67: Conceptual Mine Design, Grum YT

67

Figure 13-6 - The variation in gold and silver recoveries over the scheduled mine life

A limitation of this approach is the incomplete metallurgical data. It is unknown which processing

method produced these recoveries or what effects from mixing ore types have on recovery. Until more

data it is acquired, this model will assume that these recoveries can be achieved regardless of processing

method and that mixing ores are inconsequential. These assumptions may be incorrect and it is

recommended that more extensive metallurgical testing be performed. Detailed tables of recoverable

metal tonnages are shown in Appendix Section 16.21.

13.1.4 Smelter Terms

Appropriate smelter terms are difficult to benchmark due to the polymetallic nature and poorly

understood metallurgy of the ore. Smelter terms would depend on the grade of each metal in each

concentrate, presence of deleterious elements, and the impact of the ore chemistry on smelter

recovery.

It was assumed that 60% of the lead and zinc concentrates to metal by weight [40], but it is unknown

what proportion and grade of gold and silver would be reporting to each of these concentrates.

Deductions for gold and silver were not considered for this reason.

Without knowledge on the expected metallurgical behaviour of the ore, smelter terms used in this

model are the medians of typical smelter term values [40]. The smelter contract terms used in this

model are listed in Table 13-6.

Table 13-6 - Smelter terms used, adapted from Prices and Revenues [40]

Pb Zn Au Ag

Payables 95% 95% 95% 95%

Deductions 2% 8% --- ---

TC/RC $180/dmt $170/dmt $5.00/oz $0.30/oz

13.2 Operating Costs: $2,902,000,000

13.2.1 Mining Operating Cost: $1,171,500,000 from $3.01/tonne mined

The mining cost was determined using the 2012 InfoMine cost model [38], which models costs per ton

milled based on a milling rate and strip ratio. Having a milling rate of about 8800 tpd and a strip ratio of

around 6, the expected mining unit costs were interpolated from model estimates, as shown in Figure

13-7. This gave the estimate of $20.95/tonne milled. Translating this value into 2016 USD and to a “per

tonne mined” basis results in a value of $2.00/tonne mined. Considering a +50% factor for arctic mines,

the cost $3.01/tonne mined was used.

Page 68: Conceptual Mine Design, Grum YT

68

Figure 13-7 - The interpolated unit cost of Grum, at 8800 tpd and a strip ratio of 6.

13.2.2 Processing Cost: $741,200,000 from $14.05/tonne milled

Processing unit costs were determined from InfoMine cost models [38], which determines a cost per

tonne milled, based on a milling rate and number of concentrates produced. Grum has is designed for a

milling rate of 8800 tpd and two concentrates, as shown in Figure 13-8.

Figure 13-8 - Interpolated processing unit cost for two concentrates at a milling rate of 8800 tpd

13.2.3 Freight Cost: $326,700,000 from $74.50/dmt

Freight costs were determined from expected costs incurred transporting concentrate to a chosen

smelter. Chosen smelters, for simplicity, were able to smelt both lead and zinc concentrates. All unit

costs are in relation to dry metric tonnes (dmt), assuming an increase of 8% in mass from water.

Two smelters were considered, one for a land freight case, with the Teck Trail Smelter, located in B.C.,

Canada, and a shipping case, for the Korea Zinc smelter, in Onsan, South Korea. The current design finds

shipping freight preferable and its associated costs were used in this model.

$0.00

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

100 1000 10000 100000Un

it C

ost

($

/to

nn

e m

illed

)

Milling Rate

Mining Unit Cost to Milling Rate and Number of Concentrates

1

2

4

8

Grum

$-

$50.00

$100.00

$150.00

$200.00

$250.00

10 100 1000 10000 100000

Pro

cess

ing

Co

st (

$/t

on

ne

mill

ed)

Milling Rate (tpd)

Processing Cost to Milling Rate and Number of Concentrates

1 2 3 Grum

Page 69: Conceptual Mine Design, Grum YT

69

13.2.3.1 Land Freight to Teck Smelter

The Trail smelter is physically the closest lead-zinc smelter to Faro, allowing freight over land. However,

the shortest routes cover at least 5700 km roundtrip and requires passage through highways in the

Rocky Mountains, as shown in fig. The cost associated with such a delivery has poor economics, with an

estimate by Minecost models to cost at least $240.47/dmt by trucking. Train routes were not found at

this point in the study; further research may bring expected costs down.

Figure 13-9 - The route and distance from Faro to Trail [41]

13.2.3.2 Shipping Freight to Korea Zinc Smelter

The Korea Zinc smelter was chosen for being the world’s largest smelter [42], regularly smelting large

quantities of lead and zinc concentrates. The smelter is located near the port of the city Onsan, which

facilitates shipping, as shown in Figure 13-10.

Transport to this smelter requires transport from the mill to a port, where handling and shipping costs

would be incurred. The closest port to Faro is Skagway, which is located 331 miles from Faro, as shown

in Figure 13-11, and has a history of providing transport for metal mines in the Yukon [43]. At this

distance, the trucking cost is estimated to be about $44.69/dmt.

Page 70: Conceptual Mine Design, Grum YT

70

Figure 13-10 - The Korea Zinc Onsan smelter, located close to a port [44]

Figure 13-11 - An aerial photograph of the port town Skagway is shown on the left and the shortest route from Faro to Skagway is shown on the right [45]

The median InfoMine cost estimate for shipping cost from western Canada to East Asia is $23.81/dmt. It

was assumed Skagway, a southern Alaskan port, would have similar costs. The handling charge of

Anchorage has a median value of $3.00/dmt; it was assumed that this value was applicable for Skagway

and would be incurred again in the port of Onsan.

Page 71: Conceptual Mine Design, Grum YT

71

This totals to about $74.50/dmt, which is less than a third of the costs expected for transportation to

Trail in B.C. These costs were used for the cash flow model.

Additional costs associated with freight are insurance and losses transport. Insurance was assumed to

be 0.5% of the ore’s payable value and losses were assumed to be 0.1% per handling [40]. With three

handlings at the mill, at Skagway, and at Onsan, 0.3% would be lost.

13.3 Capital Cost: $534,200,000

13.3.1 Processing Equipment Capital Cost: $108,400,000

The capital cost of the processing equipment were determined by linear interpolation between

InfoMine cost models for a 8800 tpd milling rate and 2 concentrates, as shown in Figure 13-12.

Figure 13-12 - Interpolated processing capital cost for two concentrates at a milling rate of 8800 tpd

13.3.2 Mining Equipment Capital Cost: $86,900,000

The capital costs of the mining equipment refers to typical costs of Caterpillar vehicles [46] and the costs

of drills from similar mines in the area [14]. The list of equipment models selected and their unit costs

are listed in table below. These costs are incurred over the two years ramping up to full production as

the fleet expands to its max size. Shown in Table 13-7 are the total costs attributed to each type of

equipment.

Table 13-7 – The total capital costs associated with the total mining equipment fleet

Number of Units Capital Cost

Haul Trucks CAT 785D 150 ton 21 $ 63,680,000 Shovels CAT 6040 22 m3 1 $ 8,641,500 Front End Loaders CAT 994F 7.7 m3 1 $ 1,166,000 Track Dozer CAT D9T 13.5 m3 2 $ 2,684,000

$-

$100,000,000

$200,000,000

$300,000,000

$400,000,000

$500,000,000

$600,000,000

$700,000,000

$800,000,000

0 10000 20000 30000 40000 50000 60000 70000 80000 90000

Cap

ital

Co

st (

$)

Milling Rate (tpd)

Capital Cost of Processing Equipment to Milling Rate and Nubmer of Concentrates

1 2 3 Grum

Page 72: Conceptual Mine Design, Grum YT

72

Wheel Dozer CAT 834K 7.9 m3 1 $ 1,388,000 Motor Grader CAT 16M 16’ blade 2 $ 2,080,000 Articulated Truck CAT 735B 24 m3 1 $ 782,000 Vibratory Compactor CAT CS-64 112 kW 1 $ 230,000 Tool Carrier CAT IT 38H 2.5 m3 1 $ 379,000 Diesel Drill --- 4.5’’ to 8.5’’ 4 $ 5,060,000 Secondary Drill --- 4.5’’ to 5.5’’ 1 $ 806,000

Total: $ 86,896,000

13.3.3 Capital Pre-strip Cost: $115,500,000

Capital pre-stripping was determined from the mining unit cost applied to the initial waste-only

production. Larry Smith has observed that pre-stripping tends to far exceed budgets; his suggestion for

doubling pre-strip unit costs were used. For a planned 19.186 Mt of pre-strip, at a unit cost of

$6.02/tonne moved, $115,499,000 was allocated for pre-stripping.

13.3.4 Closure Cost: $15,000,000

The closure cost was determined in Section 12. Due to its low weighting compared with other capital

costs, it was treated as a capital cost incurred at the beginning of mine life. This produced a more

conservative estimation in case of an overly low valuation of closure.

13.3.5 Sustaining Capital: $145,300,000

Sustaining capital was allotted based on the rule of thumb proposed by Larry Smith, at $0.30/tonne

mined per year for mining equipment and 1% of initial capital of processing equipment. The annual

allotted sustaining capital is shown in Appendix Section 16.22.

13.4 Taxes: $911,700,000 at a 30% tax rate

The effective tax rate of 30% was the sum of the 15% tax rate in the Yukon territories and 15% corporate

tax rate to the Federal government [47]. Depreciation rate used was the standard CCA rate for large,

industrial equipment at 30% [48]. The annual tax and depreciation calculations are shown in Appendix

Section 16.23.

14 Conclusions & Recommendations

By looking at the various aspects of potential operations at the Grum site, it appears that despite the

relatively remote location and environmental concerns with the sites waste products, this project should

be advanced to the next stage. Its high internal rate of return and reasonable NPV of $156.1 Million

suggests further studies are warranted.

In order to conduct a successful next round of study current findings suggests that a detailed look into

the metallurgical behaviour and processing scheme is necessary. Additionally further site investigation

for potential building material, such as the overburdens, would be useful to confirm availability. Lastly

Page 73: Conceptual Mine Design, Grum YT

73

baseline studies should be considered to ensure appropriate time is given to allow necessary permits

time to be processed. If these steps are taken the next stage of study should be successful.

15 References

[1] K. Esmaeili, Pit Slope Design (Comp.), Toronto,ON: University of Toronto: Min 466: Mineral

Project Design 1, 2015.

[2] W. Hastrulid, Open Pit Mine Planning and Design, USA, 2013.

[3] W. W. Kaufman and J. C. Ault, "Design of Surface Mine Haulage Raods - Manual," [Online].

Available: http://www.cdc.gov/niosh/mining/userfiles/works/pdfs/ic8758.pdf.

[4] L. Smith, "Processing Methods and Illustrations," 2007.

[5] "Faro A Yukon Territory Canada Yearly/Monthly/Daily Climate Data," 2016. [Online]. Available:

http://www.eldoradocountyweather.com/canada/climate2/Faro%20A.html. [Accessed 10

March 2016].

[6] M. O'Kane and C. Wels, "Mine Waste Cover System Design-Linking Predicted Performance to

Groundwater and Surface Water Impacts," 6th Icard, pp. 341-349, 2003.

[7] T. R. West, Geology applied to engineering, Prentice Hall, 1995, p. 560.

[8] G. H. McNally, Soil & Rock Construction Materials, E & FN Spon, 1998, p. 187.

[9] G. McPhail, "Getting the Water Balance Right," Tailings & Paste Management and

Decommisioning, pp. 1-11.

[10] G. den Hartog and H. I. Ferguson, Plate 17. Mean Annual Lake Evaporation, 1978: Hydrological

Atlus of Canada 17, Department of Energy, Mines and Resources, Surveys and Mapping Branch.

[11] A. Moebus, Interviewee, Recommendations for Equipment Selection of Arctic Open Pit Mines.

[Interview]. 2016.

[12] Toromont Industries Ltd., "Sizing and Selection of a Hauling Fleet," 2016.

Page 74: Conceptual Mine Design, Grum YT

74

[13] Toromont Industries Ltd., "Relative Pricing," 2016.

[14] G. Wilikins and e. al., "Preliminary Economic Assessment Report on the Arctic Project, Ambler

Mining District, Northwest Alaska," NovaCopper Inc., 2013.

[15] M. Ruel, A. Proulx, P. J. Muteb and L. Connell, "Technical Report on the Mineral Resources and

Mineral Reservesat Meadowbank Gold Mine, Nunavut, Canada as at December 31, 2011,"

Agnico-Eagle Mines Ltd., 2011.

[16] Yukon Government, "Energy, Mines and Resources: Mine Licensing," 17 11 2015. [Online].

[Accessed 3 2016].

[17] Casino Mining Corporation, "Project Proposal for Executive Committee Review," 2014.

[18] Yukon Government, "Unofficial Consolidation of the Statutes of Yukon," Legislative Counsel

Office, Whitehorse, 2002.

[19] Yukon Wild, Yukon Freshwater Fisheries, Government of Yukon, 2010.

[20] D. Mossop, The 1995 Peregrine Falcon survey in the Yukon, Whitehorse: Environment Canada,

2004.

[21] Environment Yukon, "Yukon Species At Risk," 2015. [Online]. [Accessed 10 3 2016].

[22] C. Oke, "Yukon News: Faro struggling to deal with meltwater," 25 May 2011. [Online]. [Accessed

16 March 2016].

[23] M. Clarke, R. Drummond, R. Ward and S. Westover, Moose Survey, Faro, Early Winter 2011,

Whitehorse: Environment Yukon, 2012.

[24] Town of Faro, "Traveling to Faro: Learn about our Fannin's Sheep," [Online]. [Accessed 22 March

2016].

[25] Environment Yukon, "Wildlife Viewing in Faro," Faro, 2011.

[26] D. Bishop and W. Bishop, "Dena Cho Trail," 29 June 2006. [Online]. [Accessed 12 March 2016].

Page 75: Conceptual Mine Design, Grum YT

75

[27] R. Stasyszyn, "Yukon News: Faro mine's remediation mess," 3 July 2012. [Online]. [Accessed

February 2016].

[28] URS and BOPL, "Risk Assessment," Princess Louise and North Point, 2000.

[29] Canadian Environmental Assessment Agency, "Cumulative Effects Assessment Practioners'

Guide," Government of Canada, 2014.

[30] N. Thomson, "Ross River Kaska weigh benefits of massive lead-zinc mine," 23 November 2015.

[Online]. [Accessed 3 February 2016].

[31] Kaska Dena Council, "Resource Development," [Online]. [Accessed 2016].

[32] Dena Kayeh Institute, "Kaska Dena Management Practices: Kaska Dena Land Used Framework,"

Dena Kayeh Institute, Lower Post, 2010.

[33] Yukon Government, "Yukon Mine Site Reclamation and CLosure Policy," 2006. [Online].

Available: http://www.emr.gov.yk.ca/mining/pdf/mine_reclamation_policy_web_nov06.pdf .

[34] IMWA, "Acid Mine Drainage Prevention and Closure Policy," 2012. [Online]. Available:

http://www.imwa.info/docs/imwa_1999/IMWA1999_Kuyucak_599.pdf.

[35] C. H. Gammons, "Creating Lakes from Open Pit Mines:process and emphasis considerations, with

emphasis on northern environment," 2009. [Online]. Available: http://www.dfo-

mpo.gc.ca/Library/337077.pdf.

[36] Yukon Zinc, Wolverine Mine Reclamation and Closure Plan, Canada, 2015.

[37] Teck, Sa Dena Hes Mine Detailaed Decommission and Reclamation Plan, Canada, 2015.

[38] InfoMine USA Inc., Mining Cost Service, 2012.

[39] L. D. Smith, Discount Rates, RADR, Country Risk, 2016.

[40] L. D. Smith, Prices and Revenues, 2015.

[41] Google Inc., "Faro, YT to Trail, BC," 2016. [Online]. Available:

Page 76: Conceptual Mine Design, Grum YT

76

https://www.google.ca/maps/dir/Faro,+YT/Trail,+BC/@54.5201333,-

132.8043953,4.75z/data=!4m14!4m13!1m5!1m1!1s0x5150b66882cd1707:0x18bf64e7f49b3df!2

m2!1d-

133.3531599!2d62.2285419!1m5!1m1!1s0x5362d9f2d078efbb:0xdabf948e746e9f84!2m2!1d-

117.7117301!2d49.0965676.

[42] S. J. Choi, "Korea Zinc to become the world's largest lead smelter," The Korea Times, 25 January

2016.

[43] Municipality of Skagway Borough, "Port of Skagway," 2007. [Online]. Available:

http://www.skagway.org/index.asp?SEC=21FD65B5-E64D-488B-9F51-

51B650B9D6DE&Type=B_BASIC.

[44] Google Inc., "Onsan Smelter, Korea," 2016. [Online]. Available:

https://www.google.ca/maps/place/Onsan-eup,+Ulju-

gun,+Ulsan,+South+Korea/@35.432512,129.1953824,11z/data=!3m1!4b1!4m2!3m1!1s0x3567d

4ca287710a3:0xa024a034c8ed2acf.

[45] Google Inc., "Faro, YT to Skagway, AK, USA," 2016. [Online]. Available:

https://www.google.ca/maps/dir/Faro,+YT/Skagway,+AK,+USA/@60.8284354,-

137.0660333,7z/data=!3m1!4b1!4m13!4m12!1m5!1m1!1s0x5150b66882cd1707:0x18bf64e7f49

b3df!2m2!1d-

133.3531599!2d62.2285419!1m5!1m1!1s0x56aaa92500de9141:0x5e251777323a536a!2m2!1d-

135.3138889!.

[46] Caterpillar Inc., Relative Pricing, 2015.

[47] PWC, Canadian mining taxation, 2013.

[48] Canada Revenue Agency, "Classes of Depreciation," 5 January 2016. [Online]. Available:

http://www.cra-arc.gc.ca/tx/bsnss/tpcs/slprtnr/rprtng/cptl/dprcbl-eng.html.

[49] CAT, "785C Mining Truck," 2016. [Online]. Available: http://www.witraktor.lt/pdf/E1-5320-

785C.pdf. [Accessed March 2016].

Page 77: Conceptual Mine Design, Grum YT

77

16 Appendices

16.1 Ramp Design Considerations

Figure 16-1 Haulage Truck Specifications- Cat 785C [49]

Page 78: Conceptual Mine Design, Grum YT

78

Figure 16-2 Ramp Design for the first push back at Whittle Pit 6

Figure 16-3 Ramp Design for the second push back at Whittle Pit 9

Page 79: Conceptual Mine Design, Grum YT

79

Figure 16-4 Ramp Design for the third push back at Whittle Pit 18

16.2 Re-sloped Pit Calculations

Formula employed sectors 8, 9, 10 and 1:

Tan = {(n x h) / [((n-1) x w) + ((n x h)/ tan) + Ramp width]}

= Overall pit slope angle with ramp

n= Number of benches

h = Bench height

w = Bench width

= Bench face angle

Sample Calculation of sector 8

= tan-1 {(25 x 12) / [((25 -1) x 6.9) + ((25 x 12) / tan (80)) + 30]} = 49

Note: The same process for calculating was carried out for sectors 1, 9 and 10, but with different bench

dimensions.

Page 80: Conceptual Mine Design, Grum YT

80

16.3 Equipment Unit Costs

Table 16-1 Summary of Associated Unit Costs for Selected Machinery

Page 81: Conceptual Mine Design, Grum YT

81

16.4 Provided Metallurgical Recovery Data

Table 16-2 Preliminary Recovery Data Provided for the Grum Deposit

Page 82: Conceptual Mine Design, Grum YT

82

16.5 Initial Tailings Volumes

Table 16-3 Table Showing the process in Calculating Annual Tailings Volumes

End of Production Year Incremental Ore Processed (Tonnes) Process Dry Waste (Ton) Volume Water Added (m3)

1 1.60E+05 1.54E+05 6.14E+04

2 8.80E+05 8.44E+05 3.38E+05

3 2.40E+06 2.30E+06 9.21E+05

4 3.12E+06 2.99E+06 1.20E+06

5 2.80E+06 2.69E+06 1.07E+06

6 2.48E+06 2.38E+06 9.52E+05

7 3.20E+06 3.07E+06 1.23E+06

8 3.20E+06 3.07E+06 1.23E+06

9 3.20E+06 3.07E+06 1.23E+06

10 3.20E+06 3.07E+06 1.23E+06

11 3.20E+06 3.07E+06 1.23E+06

12 3.20E+06 3.07E+06 1.23E+06

13 3.20E+06 3.07E+06 1.23E+06

14 3.20E+06 3.07E+06 1.23E+06

15 3.20E+06 3.07E+06 1.23E+06

16 3.20E+06 3.07E+06 1.23E+06

17 3.20E+06 3.07E+06 1.23E+06

18 3.20E+06 3.07E+06 1.23E+06

19 3.20E+06 3.07E+06 1.23E+06

20 1.84E+06 1.77E+06 7.06E+05

End of Production Year Dry Volume Added (m3) Tailings Volume Added (m3) Cumm. Tailings Volume (m3)

1 5.81E+04 1.20E+05 1.20E+05

2 3.20E+05 6.58E+05 7.77E+05

3 8.72E+05 1.79E+06 2.57E+06

4 1.13E+06 2.33E+06 4.90E+06

5 1.02E+06 2.09E+06 6.99E+06

6 9.01E+05 1.85E+06 8.85E+06

7 1.16E+06 2.39E+06 1.12E+07

8 1.16E+06 2.39E+06 1.36E+07

9 1.16E+06 2.39E+06 1.60E+07

10 1.16E+06 2.39E+06 1.84E+07

11 1.16E+06 2.39E+06 2.08E+07

12 1.16E+06 2.39E+06 2.32E+07

13 1.16E+06 2.39E+06 2.56E+07

14 1.16E+06 2.39E+06 2.80E+07

15 1.16E+06 2.39E+06 3.04E+07

16 1.16E+06 2.39E+06 3.28E+07

17 1.16E+06 2.39E+06 3.51E+07

18 1.16E+06 2.39E+06 3.75E+07

19 1.16E+06 2.39E+06 3.99E+07

20 6.69E+05 1.37E+06 4.13E+07

Page 83: Conceptual Mine Design, Grum YT

83

16.6 TSF Volume Calculations: Volume of a Truncated Pyramid

𝑉 = ℎ

6(𝑎𝑏 + (𝑎 + 𝑐)(𝑏 + 𝑑) + 𝑐𝑑) [6]

Figure 16-5 Diagram showing the Meanings of each constant in the Truncated Pyramid Volume Calculation

Page 84: Conceptual Mine Design, Grum YT

84

16.7 Summary of the Annual Rate of Rise of Tailings Deposition

Table 16-4 Table Showing Summary of Tailings Rate of Rise for the final TSF design. Notice the given Storage Length and Width used in the design.

Dam Height 60 m

Storage Width 800 m

Storage Length 1500 m

Year of Production Pond Width (m) Pond Length (m) Beach Length of Tails (m)

1 501 1201 0.5

2 506 1206 3.5

3 521 1221 11.2

4 539 1239 20.8

5 554 1254 29.1

6 567 1267 36.2

7 583 1283 44.9

8 599 1299 53.4

9 614 1314 61.5

10 629 1329 69.3

11 643 1343 76.9

12 656 1356 84.3

13 670 1370 91.4

14 683 1383 98.3

15 695 1395 105.0

16 707 1407 111.6

17 719 1419 118.0

18 731 1431 124.2

19 742 1442 130.3

20 748 1448 133.7

Year of Production Pond Area(m2) Itterative Tailing Height (m) Incremental Rate of Rise (m/year)

1 6.02E+05 0.20 0.2

2 6.11E+05 1.28 1.1

3 6.36E+05 4.16 2.9

4 6.67E+05 7.74 3.6

5 6.95E+05 10.81 3.1

6 7.19E+05 13.43 2.6

7 7.49E+05 16.69 3.3

8 7.78E+05 19.82 3.1

9 8.07E+05 22.84 3.0

10 8.35E+05 25.75 2.9

11 8.63E+05 28.57 2.8

12 8.90E+05 31.29 2.7

13 9.17E+05 33.94 2.6

14 9.44E+05 36.51 2.6

15 9.70E+05 39.01 2.5

16 9.95E+05 41.44 2.4

17 1.02E+06 43.81 2.4

18 1.05E+06 46.13 2.3

19 1.07E+06 48.39 2.3

20 1.08E+06 49.67 1.3

Page 85: Conceptual Mine Design, Grum YT

85

16.8 Soil Classification of the Overburden Material

Table 16-5 Summary of the Soil Classification of the Grum Overburden Material, including Key Findings

Plasticity index 10%

Liquid limit 25%

15% CL or OL > Plots between "U" line and "A" line

Sand 35%

Silt 40%

Clay 25%

Gravel 0%

Calcite 3%

Dolomite 3%

Closing Remarks

>Likely to be SC-Clayey Sand

Important Note: No info provided on Oven dried LL, as a result could be classified as Sandy Organic Clay

which is a serious cause for concern for the development of long term or permanent infrastructure.

Further lab tests are required to confirm this.

>12% fines w/ CL symbol

Weak material % is low

Notice that trench data (shown on the right) reflects closer to 15%

Low amounts of Carbonate minerals are present; as a result there is low concern for their possible

decreasing of the soil strength. However there does appear to be localized anomalies containing

higher contents of dolomite which should be looked out for.

Supplimentary information on till:

Atterberg limits

Grain size distribution

Carbonate content

Comments

Plastic Limit Plasticity Chart:

ie. Quartz and feldspar, between clay and Sand

ie. Fines < Sieve #200

Assumed inorder to add to 100%

Page 86: Conceptual Mine Design, Grum YT

86

16.9 TSF Option Comparison

Table 16-6 Economic Indicators TSF Option Comparison

Page 87: Conceptual Mine Design, Grum YT

87

Table 16-7Environmental Indicators TSF Option Comparison

Table 16-8 Social Indicators TSF Option Comparison

Page 88: Conceptual Mine Design, Grum YT

88

16.10 WRD Option Comparison

Table 16-9 Economic Indicators WRD Option Comparison

Page 89: Conceptual Mine Design, Grum YT

89

Table 16-10 Environmental Indicators WRD Option Comparison

Table 16-11 Social Indicators WRD Option Comparison

Page 90: Conceptual Mine Design, Grum YT

90

16.11 Detailed Water Balance

Table 16-12 Summary of the reported Detailed Water Balance

End of Production Year Volume Water Added with Tailings (m3) Trapped Water in Tailings Bleed Water

1 6.14E+04 2.30E+04 3.84E+04

2 3.38E+05 1.27E+05 2.11E+05

3 9.21E+05 3.45E+05 5.76E+05

4 1.20E+06 4.49E+05 7.48E+05

5 1.07E+06 4.03E+05 6.72E+05

6 9.52E+05 3.57E+05 5.95E+05

7 1.23E+06 4.61E+05 7.68E+05

8 1.23E+06 4.61E+05 7.68E+05

9 1.23E+06 4.61E+05 7.68E+05

10 1.23E+06 4.61E+05 7.68E+05

11 1.23E+06 4.61E+05 7.68E+05

12 1.23E+06 4.61E+05 7.68E+05

13 1.23E+06 4.61E+05 7.68E+05

14 1.23E+06 4.61E+05 7.68E+05

15 1.23E+06 4.61E+05 7.68E+05

16 1.23E+06 4.61E+05 7.68E+05

17 1.23E+06 4.61E+05 7.68E+05

18 1.23E+06 4.61E+05 7.68E+05

19 1.23E+06 4.61E+05 7.68E+05

20 7.06E+05 2.65E+05 4.41E+05

Total Over LOM 2.12E+07 7.96E+06 1.33E+07

% Contribution 24% 9% 15%

End of Production Year Catchment Area (m2) Vol. of Yearly Avg Rainfall (m3) Vol. of Soil Seepage (m3) Vol. of Evaporation(m3)

1 3.01E+06 9.51E+05 5.22E+05 1.81E+05

2 3.05E+06 9.65E+05 5.30E+05 1.83E+05

3 3.18E+06 1.00E+06 5.51E+05 1.91E+05

4 3.34E+06 1.05E+06 5.79E+05 2.00E+05

5 3.47E+06 1.10E+06 6.03E+05 2.08E+05

6 3.59E+06 1.14E+06 6.23E+05 2.16E+05

7 3.74E+06 1.18E+06 6.49E+05 2.25E+05

8 3.89E+06 1.23E+06 6.75E+05 2.33E+05

9 4.04E+06 1.28E+06 7.00E+05 2.42E+05

10 4.18E+06 1.32E+06 7.25E+05 2.51E+05

11 4.32E+06 1.36E+06 7.49E+05 2.59E+05

12 4.45E+06 1.41E+06 7.72E+05 2.67E+05

13 4.59E+06 1.45E+06 7.95E+05 2.75E+05

14 4.72E+06 1.49E+06 8.18E+05 2.83E+05

15 4.85E+06 1.53E+06 8.41E+05 2.91E+05

16 4.98E+06 1.57E+06 8.63E+05 2.99E+05

17 5.10E+06 1.61E+06 8.85E+05 3.06E+05

18 5.23E+06 1.65E+06 9.07E+05 3.14E+05

19 5.35E+06 1.69E+06 9.28E+05 3.21E+05

20 5.42E+06 1.71E+06 9.40E+05 3.25E+05

Total Over LOM 2.67E+07 1.47E+07 5.07E+06

% Contribution 3.00E-01 1.65E-01 5.71E-02

Page 91: Conceptual Mine Design, Grum YT

91

End of Production Year Yearly TSF Water Balance (m3) Cummulative Water Balance (m3)

1 2.87E+05 2.87E+05

2 4.63E+05 7.50E+05

3 8.38E+05 1.59E+06

4 1.02E+06 2.61E+06

5 9.58E+05 3.57E+06

6 8.91E+05 4.46E+06

7 1.08E+06 5.54E+06

8 1.09E+06 6.63E+06

9 1.10E+06 7.73E+06

10 1.11E+06 8.84E+06

11 1.12E+06 9.96E+06

12 1.14E+06 1.11E+07

13 1.15E+06 1.22E+07

14 1.16E+06 1.34E+07

15 1.17E+06 1.46E+07

16 1.18E+06 1.57E+07

17 1.19E+06 1.69E+07

18 1.20E+06 1.81E+07

19 1.21E+06 1.93E+07

20 8.89E+05 2.02E+07

Total Over LOM 2.02E+07

Page 92: Conceptual Mine Design, Grum YT

92

16.12 Suggested Water Pumping Schedule to Maintain the Water Cover

Table 16-13 Summary of the Recommended Pumping Schedule and resulting Water Balance (note the negative values require pumping of water out of the dam)

Page 93: Conceptual Mine Design, Grum YT

93

16.13 Measurement of Truck Routes

Figure 16-6 – An overview of the mine site layout for context, with dimensions of paths superimposed. For a clearer depiction of measurements, refer to subsequent figures.

Page 94: Conceptual Mine Design, Grum YT

94

Figure 16-7 - View of horizontal projection distances of equipment travel paths; due to the high degree of segmentation in the pit, dimensions are overlapping and difficult to read. A magnified view could be found in Figure 16-6.

Page 95: Conceptual Mine Design, Grum YT

95

Figure 16-8 - A magnified view of the horizontal projection lengths of the pit ramp.

Page 96: Conceptual Mine Design, Grum YT

96

16.14 Rimpull and Retardation Curves

Figure 16-9 - Rimpull curve of the CAT 777G, with appropriate speeds determined for loaded travel on effective grades of 3%, 4%, and 13%.

Page 97: Conceptual Mine Design, Grum YT

97

Figure 16-10 - Retardation curve of an empty CAT 777G on effective grades of 0% and 7%.

Page 98: Conceptual Mine Design, Grum YT

98

Figure 16-11 - Rimpull curve of the CAT 785D, with appropriate speeds determined for loaded travel on effective grades of 3%, 4%, and 13%.

Page 99: Conceptual Mine Design, Grum YT

99

Figure 16-12 - Retardation curve of an empty CAT 785D on effective grades of 0% and 7%.

Page 100: Conceptual Mine Design, Grum YT

100

Figure 16-13 - Rimpull curve of the CAT 789D, with appropriate speeds determined for loaded travel on effective grades of 3%, 4%, and 13%.

Page 101: Conceptual Mine Design, Grum YT

101

Figure 16-14 - Retardation curve of an empty CAT 789D on effective grades of 0% and 7%.

Page 102: Conceptual Mine Design, Grum YT

102

16.15 Travel Times

Table 16-14 - Travel times for various road segments on the route of a CAT 777G

Segment Length Grade RR Total RR

Loaded Speed

Time in seg

Total RR

Empty Speed

Time in seg

Units m % % % km/h min % km/h min

Load area 100 0 4 4 32 0.19 0 35 0.17

Ramp 3298 10 3 13 10 19.79 7 35 5.65

Crusher Road 1713 0 3 3 43 2.39 0 50 2.06

Crusher Ramp 100 10 3 13 10 0.6 7 35 0.17

Crusher Pad 50 0 3 3 15 0.2 0 35 0.09

Dump Road 702 0 3 3 43 0.98 0 50 0.84

Dump Ramp 3224 10 3 13 10 19.34 7 35 5.53

Dump Run 423 0 3 3 30 0.85 0 35 0.73

Dumping Time 1 1

Table 16-15 -Travel times for various road segments on the route of a CAT 785D

Segment Length Grade RR Total RR

Loaded Speed

Time in seg

Total RR

Empty Speed

Time in seg

Units m % % % km/h min % km/h min

Load area 100 0 4 4 33 0.18 0 35 0.17

Ramp 3298 10 3 13 10 19.79 7 35 5.65

Crusher Road 1713 0 3 3 45 2.28 0 50 2.06

Crusher Ramp 100 10 3 13 10 0.6 7 35 0.17

Crusher Pad 50 0 3 3 15 0.2 0 35 0.09

Dump Road 702 0 3 3 45 0.94 0 50 0.84

Dump Ramp 3224 10 3 13 10 19.34 7 35 5.53

Dump Run 423 0 3 3 30 0.85 0 35 0.73

Dumping Time 1 1

Table 16-16 - Travel times for various road segments on the route of a CAT 789D

Segment Length Grade RR Total RR

Loaded Speed

Time in seg

Total RR

Empty Speed

Time in seg

Units m % % % km/h min % km/h min

Load area 100 0 4 4 35 0.17 0 35 0.17

Ramp 3298 10 3 13 10 19.79 7 35 5.65

Crusher Road 1713 0 3 3 50 2.06 0 50 2.06

Page 103: Conceptual Mine Design, Grum YT

103

Crusher Ramp 100 10 3 13 10 0.6 7 35 0.17

Crusher Pad 50 0 3 3 20 0.15 0 35 0.09

Dump Road 702 0 3 3 50 0.84 0 50 0.84

Dump Ramp 3224 10 3 13 10 19.34 7 35 5.53

Dump Run 423 0 3 3 30 0.85 0 35 0.73

Dumping Time 1 1

16.16 Loading Times

Table 16-17 -The time involved in a load, haul, dump, return cycle of a CAT 777D

6015 6018 6030

Load Time Units ORE WASTE ORE WASTE ORE WASTE

Bucket size m3 7 7 10 10 16.5 16.5

Bucket fill factor % 95.00% 95.00% 95.00% 95.00% 95.00% 95.00%

Loose density t/m3 2.00 1.80 2.00 1.80 2.00 1.80

Bucket payload - Actual t 13.30 11.97 19.00 17.10 31.35 28.22

Haul Truck payload - Target t 100.0 100.0 100.0 100.0 100.0 100.0

Passes to Fill Truck # 8 8 5 6 3 4

Haul Truck Payload - Actual t 106.4 95.8 95.0 102.6 94.1 112.9

Haul Truck Payload Utilized % 106% 96% 95% 103% 94% 113%

First Bucket min 0.10 0.10 0.10 0.10 0.10 0.10

Time per pass (cycle time) min 0.5 0.5 0.5 0.5 0.5 0.5

Spot time min 0.75 0.75 0.75 0.75 0.75 0.75

Loading Time - Total min 3.60 3.60 2.10 2.60 1.10 1.60

6040 6050 6060

Load Time Units ORE WASTE ORE WASTE ORE WASTE

Bucket size m3 22 22 26 26 34 34

Bucket fill factor % 95.00% 95.00% 95.00% 95.00% 95.00% 95.00%

Loose density t/m3 2.00 1.80 2.00 1.80 2.00 1.80

Bucket payload - Actual t 41.80 37.62 49.40 44.46 64.60 58.14

Haul Truck payload - Target t 100.0 100.0 100.0 100.0 100.0 100.0

Passes to Fill Truck # 2 3 2 2 2 2

Haul Truck Payload - Actual t 83.6 112.9 98.8 88.9 129.2 116.3

Haul Truck Payload Utilized % 84% 113% 99% 89% 129% 116%

Page 104: Conceptual Mine Design, Grum YT

104

First Bucket min 0.10 0.10 0.10 0.10 0.10 0.10

Time per pass (cycle time) min 0.5 0.5 0.5 0.5 0.5 0.5

Spot time min 0.75 0.75 0.75 0.75 0.75 0.75

Loading Time - Total min 0.60 1.10 0.60 0.60 0.60 0.60

Table 16-18 - The time involved in a load, haul, dump, return cycle of a CAT 785D

6015 6018 6030

Load Time Units ORE WASTE ORE WASTE ORE WASTE

Bucket size m3 7 7 10 10 16.5 16.5

Bucket fill factor % 95.00% 95.00% 95.00% 95.00% 95.00% 95.00%

Loose density t/m3 2.00 1.80 2.00 1.80 2.00 1.80

Bucket payload - Actual t 13.30 11.97 19.00 17.10 31.35 28.22

Haul Truck payload - Target t 150.0 150.0 150.0 150.0 150.0 150.0

Passes to Fill Truck # 11 13 8 9 5 5

Haul Truck Payload - Actual t 146.3 155.6 152.0 153.9 156.8 141.1

Haul Truck Payload Utilized % 98% 104% 101% 103% 105% 94%

First Bucket min 0.10 0.10 0.10 0.10 0.10 0.10

Time per pass (cycle time) min 0.5 0.5 0.5 0.5 0.5 0.5

Spot time min 0.75 0.75 0.75 0.75 0.75 0.75

Loading Time - Total min 5.10 6.10 3.60 4.10 2.10 2.10

6040 6050 6060

Load Time Units ORE WASTE ORE WASTE ORE WASTE

Bucket size m3 22 22 26 26 34 34

Bucket fill factor % 95.00% 95.00% 95.00% 95.00% 95.00% 95.00%

Loose density t/m3 2.00 1.80 2.00 1.80 2.00 1.80

Bucket payload - Actual t 41.80 37.62 49.40 44.46 64.60 58.14

Haul Truck payload - Target t 150.0 150.0 150.0 150.0 150.0 150.0

Passes to Fill Truck # 4 4 3 3 2 3

Haul Truck Payload - Actual t 167.2 150.5 148.2 133.4 129.2 174.4

Haul Truck Payload Utilized % 111% 100% 99% 89% 86% 116%

First Bucket min 0.10 0.10 0.10 0.10 0.10 0.10

Time per pass (cycle time) min 0.5 0.5 0.5 0.5 0.5 0.5

Spot time min 0.75 0.75 0.75 0.75 0.75 0.75

Loading Time - Total min 1.60 1.60 1.10 1.10 0.60 1.10

Page 105: Conceptual Mine Design, Grum YT

105

Table 16-19 -The time involved in a load, haul, dump, return cycle of a CAT 789D

6015 6018 6030

Load Time Units ORE WASTE ORE WASTE ORE WASTE

Bucket size m3 7 7 10 10 16.5 16.5

Bucket fill factor % 95.00% 95.00% 95.00% 95.00% 95.00% 95.00%

Loose density t/m3 2.00 1.80 2.00 1.80 2.00 1.80

Bucket payload - Actual t 13.30 11.97 19.00 17.10 31.35 28.22

Bucket payload - maximum (rated) t

Haul Truck payload - Target t 200.0 200.0 200.0 200.0 200.0 200.0

Passes to Fill Truck # 15 17 11 12 6 7

Haul Truck Payload - Actual t 199.5 203.5 209.0 205.2 188.1 197.5

Haul Truck Payload Utilized % 100% 102% 105% 103% 94% 99%

First Bucket min 0.10 0.10 0.10 0.10 0.10 0.10

Time per pass (cycle time) min 0.5 0.5 0.5 0.5 0.5 0.5

Spot time min 0.75 0.75 0.75 0.75 0.75 0.75

Loading Time - Total min 7.10 8.10 5.10 5.60 2.60 3.10

6040 6050 6060

Load Time Units ORE WASTE ORE WASTE ORE WASTE

Bucket size m3 22 22 26 26 34 34

Bucket fill factor % 95.00% 95.00% 95.00% 95.00% 95.00% 95.00%

Loose density t/m3 2.00 1.80 2.00 1.80 2.00 1.80

Bucket payload - Actual t 41.80 37.62 49.40 44.46 64.60 58.14

Bucket payload - maximum (rated) t

Haul Truck payload - Target t 200.0 200.0 200.0 200.0 200.0 200.0

Passes to Fill Truck # 5 5 4 4 3 3

Haul Truck Payload - Actual t 209.0 188.1 197.6 177.8 193.8 174.4

Haul Truck Payload Utilized % 105% 94% 99% 89% 97% 87%

First Bucket min 0.10 0.10 0.10 0.10 0.10 0.10

Time per pass (cycle time) min 0.5 0.5 0.5 0.5 0.5 0.5

Spot time min 0.75 0.75 0.75 0.75 0.75 0.75

Loading Time - Total min 2.10 2.10 1.60 1.60 1.10 1.10

16.17 Number of Trucks Required per Shovel

Table 16-20 - The number of CAT 777G trucks required for each type of shovel

Page 106: Conceptual Mine Design, Grum YT

106

6018 6018 6030

Truck Count Calculation Units Ore Waste Ore Waste Ore Waste

Total Cycle min 35.91 61.30 34.41 60.30 33.41 59.30

Productivity/hr Trucks t/hr 178 94 166 102 169 114

Required Productivity/hr t/hr 494 3618 494 3618 494 3618

Required trucks units 2.92 38.59 2.92 35.44 2.92 31.68

Total Required Trucks Units 42 39 35

6040 6050 6050

Truck Count Calculation Units Ore Waste Ore Waste Ore Waste

Total Cycle min 32.91 58.80 32.91 58.30 32.91 58.30

Productivity/hr Trucks t/hr 152 115 180 91 236 120

Required Productivity/hr t/hr 494 3618 494 3618 494 3618

Required trucks units 2.92 31.41 2.92 39.55 2.92 30.23

Total Required Trucks Units 35 43 34

Table 16-21 - The number of CAT 785D trucks required for each type of shovel

6018 6018 6030

Truck Count Calculation Units Ore Waste Ore Waste Ore Waste

Total Cycle min 37.29 63.68 35.79 61.68 34.29 59.68

Productivity/hr Trucks t/hr 235 147 255 150 274 142

Required Productivity/hr t/hr 494 3618 494 3618 494 3618

Required trucks units 1.8 24.68 1.8 24.17 1.8 25.51

Total Required Trucks Units 27 26 28

6040 6050 6050

Truck Count Calculation Units Ore Waste Ore Waste Ore Waste

Total Cycle min 33.79 59.18 33.29 58.68 32.79 58.68

Productivity/hr Trucks t/hr 297 153 267 136 236 178

Required Productivity/hr t/hr 494 3618 494 3618 494 3618

Page 107: Conceptual Mine Design, Grum YT

107

Required trucks units 1.8 23.71 1.8 26.53 1.8 20.29

Total Required Trucks Units 26 29 23

Table 16-22 - The number of CAT 789D trucks required for each type of shovel

6018 6018 6030

Truck Count Calculation Units Ore Waste Ore Waste Ore Waste

Total Cycle min 37.29 63.68 35.79 61.68 34.29 59.68

Productivity/hr Trucks t/hr 235 147 255 150 274 142

Required Productivity/hr t/hr 494 3160 494 3160 494 3160

Required trucks units 1.8 21.56 1.8 21.11 1.8 22.28

Total Required Trucks Units 24 23 25

6040 6050 6050

Truck Count Calculation Units Ore Waste Ore Waste Ore Waste

Total Cycle min 33.79 59.18 33.29 58.68 32.79 58.68

Productivity/hr Trucks t/hr 297 153 267 136 236 178

Required Productivity/hr t/hr 494 3160 494 3160 494 3160

Required trucks units 1.8 20.71 1.8 23.17 1.8 17.72

Total Required Trucks Units 23 25 20

Page 108: Conceptual Mine Design, Grum YT

108

16.18 Environmental and Social Impact Assessment

Table 16-23 Yukon Air Quality and Particulate Matter Standards

Parameter Yukon Guideline

Sulphur Dioxide (SO2) μg/m3

1-hour average 450

24-hour average 160

Annual arithmetic mean 25

Nitrogen Dioxide (NO2) μg/m3

1-hour average 400

24-hour average 200 (106 ppb)

Annual arithmetic mean 100 (53 ppb) 60 (32 ppb)

Carbon Monoxide (CO) μg/m3

1-hour average 14,300 (13 ppm)

8-hour average 5,500 (5 ppm)

Total Suspended Particulate Matter (TSP) μg/m3

24-hour average 120

Annual arithmetic mean 60

Particulate Matter (PM2.5) μg/m3

24-hour average 30

Page 109: Conceptual Mine Design, Grum YT

109

Excerpt from interview of Ian Dunlop, CAO Faro by Pearl Barrett:

“… The Pelly River is noted for its fishing opportunities including Arctic Grayling and Salmon. Vangorda

Creek is a small tributary that may have some seasonal fishing but there are better choices in the area.

Swimming in the Pelly is not recommended due to the swift currents, but you could wade into the

shallower areas near shore if you like. Typical water mammals in the area include beaver and muskrat.

The Town also has a stocked lake with a day-use recreation park called Fisheye Lake, with Kokanee and

Rainbow Trout. You can swim in the lake in summer…, but keep in mind the water is quite cold as it is

throughout the Yukon…”

Page 110: Conceptual Mine Design, Grum YT

110

Table 16-24: Yukon water quality standards to monitor and follow, the bolded items are pertinent to the Grum Site.

Parameter

Units

WUL QZ96-006 Effluent Quality Standards

Frequency Daily Limit

pH pH units Weekly 6.5-9.0

Suspended Solids mg/L Weekly 15

Aluminum mg/L Weekly 0.5

iron mg/L Weekly 1

Copper mg/L Weekly 0.01

Lead mg/L Weekly 0.002

Manganese mg/L Weekly 0.2

Nickel mg/L Weekly 0.065

Zinc mg/L Weekly 0.03

Total Ammonia mg/L Weekly 1

Oil and Grease visibility Weekly No visible oil or grease

Rainbow Trout Acute Lethality Test

<50% mortality in 100% effluent

Monthly

Pass

Page 111: Conceptual Mine Design, Grum YT

111

Table 16-25: Risk assessment criteria for event severity

Level Descriptor Detail Descriptions

Safety Cultural Socio-Economic Economic Environmental

1 Insignificant Minor injury, requiring first aid only.

No to minimal impact on Indigenous or historical heritage sites or values.

No or few reported complaints about the project. No socio-economic impacts.

<1% of revenue

No impact, minor breach in procedure, minor nonconformance

2 Minor Medical attention required.

Minor impact on Indigenous or historical heritage sites or values (e.g. restricted access to recreation areas).

Some inconvenience to stakeholders, minimal adverse impact on socio-economic environment, and some intervention required.

1%-2% of revenue

Minimal impact outside the local area.

3 Moderate Disability/ Lost Time Incident

Moderate impact on Indigenous or historical heritage sites, managed under normal procedures. Some negative media coverage could be expected.

Moderate disruption or inconvenience to stakeholders. Require careful management to restore trust.

2%-5% of revenue

Minimal impact outside the local area.

4 Major Permanent Disability / Fatality

Major disturbances to 1 or 2 significant Indigenous or historical heritage sites or values. Major breach of statutory obligation, access to resource denied in the medium to long-term.

Significant adverse impacts to sectors of the community and stakeholders. Long-term social disruption, diminished quality of life of large or specific sectors of the community (e.g. fishing sector)

5%-10% of revenue

Major environmental harm or breach of license conditions or obligations, discharges off site.

5 Catastrophic Multiple Fatalities

Major disturbances to a number (3 or more) of significant Indigenous or historical heritage sites or values. Major breach of statutory obligation, access to resource permanently denied.

Irreversible damage to the socio-economic environment. Potential for strike or riot and major damage to property or haul routes.

>10% of revenue

Long term, significant ecological changes, with legal implications and potential to affect community health.

Page 112: Conceptual Mine Design, Grum YT

112

Table 16-26: Risk assessment criteria for event probability

Level Measure Description Guide

A Almost certain Issue will or almost certainly will occur, is currently a problem or is expected to occur in most circumstances (e.g. acid generation from waste).

Weekly

B Likely to occur Issue has been a common problem in the past and there is a high probability it will occur in most circumstances.

Once per month

C Moderate Issue may have arisen in the past and there is a high probability that it should occur at some time.

Once per year

D Unlikely Issue may have occurred in the past, and there is a moderate probability that it could occur at some time.

Once per 10 years

E Rare Issue has not occurred in the past, and there is a low probability that it may occur in exceptional circumstances.

Once per 100 years

Table 16-27: Risk Matrix

Severity

Probability 1

Insignificant

2

Minor

3

Moderate

4

Major

5

Catastrophic A. Almost Certain M S H H H

B. Likely to occur M M S H H

C. Moderate L M S S H

D. Unlikely L L M S S

E. Rare L L M M S

H- High

Detailed research and management planning required at senior levels. Immediate action required

S- Significant

Senior management attention needed

M- Moderate

Management responsibility and integration into management plans required

Page 113: Conceptual Mine Design, Grum YT

113

L- Low

Manage by routine procedures

Table 16-28: Impact assessment: Pit development and mining

Key Issues Key Potential Impacts, VEC impacted Consequence Ranking

Likelihood Ranking

Risk Ranking Mitigation Strategy

Pit Development and Mining

Clearing Area for Pit development, and site necessities (TSF, WRD, etc)

Terrestrial System 2 A S - Create habitat buffer

areas around streams

- Loss of vegetation and habitat - Increased weed species

Cultural Heritage 3 C S - Report any found

artefacts or sites - Consult with community

- Interference/ damage/ destruction to local heritage

Water Systems

3

A

H

- Divert the minimum amount of stream

- Place all other site infrastructure away from streams

- Monitor water quality

- Stream diversion causing erosion and increased suspended solids

Atmospheric System 2 B M - Design a vegetated

buffer zone - Use water spraying to

reduce airborne dust - Noise caused by vehicle traffic - Dust generated by exposed

areas and machinery

Socioeconomic 1 A M

- Provide compensation for lost land

- Employ local community members

- Give preference to Faro members and Kaska members for jobs and bids within means

- Loss of recreational land - Increase in nuisance noise,

vibrations - Creation of jobs

Acid generation Water Systems 3 B S - Pump contaminated

water to treatment

Page 114: Conceptual Mine Design, Grum YT

114

from pit walls - Increased acidity of groundwater, surface water and soil

plant, clean and use for processing

Dewatering Water Systems 2 D L - Release appropriate

amount of water where needed

- Treat water before release - Decrease in regional

groundwater - Decrease in regional water

quality

Terrestrial System 2 D L - Release appropriate

amount of water where needed

- Treat water before release - Decreased groundwater leads

to vegetation impacts

Blasting Atmospheric System

2

A

S

- Blast at certain times of the day

- Use mobile water sprayers to reduce dust

- Design a vegetated buffer zone

- Dust: Increased particulate matter in the air

- Noise and vibration

Terrestrial System

1

B

M

- Monitor wildlife - Provide a barrier

- Damage by fly rock - Cumulative effect on wildlife

Greenhouse gas emissions

Atmospheric System 1 A M - Reduce number of diesel

powered equipment - Use electric power at

the site - Send only full load trucks

to smelter

- Contribution to human caused climate change

- Contribution to Canada’s overall greenhouse gas emissions

- Degradation of the environment

Explosives incident Socioeconomic

5 E S - Ensure person managing

explosives is qualified and well trained

- Place explosives magazine far from infrastructure

- Blast only during shift change

- Injury to employees - Damage to mine infrastructure

Page 115: Conceptual Mine Design, Grum YT

115

Heavy equipment accident

- Injury to truck driver/ other employees 4 D S

- A dry site will reduce the number of accidents, no drinking, no drugs

Pit ramp/wall failure

Socioeconomic

4

D

S

- Properly train employees

- Monitor the pit walls - Install displacement

monitors near ramp to monitor integrity of rock

- Injury to employees - Damage to mine infrastructure - Disruption of production

Flooding of open pit Water Systems 3 E M - Install pumping sites

directed to water treatment plant

- Effluent likely pumped untreated

Socioeconomic 3 D M - Train employees for

events

- Injury to employees - Disruption of production

Page 116: Conceptual Mine Design, Grum YT

116

Table 16-29: Impact assessment: Waste rock dump

Key Issues Key Potential Impacts, VEC impacted Consequence Ranking

Likelihood Ranking

Risk Ranking Mitigation Strategy

Waste Rock Dump

Placement and visual impact of waste rock dumps on surrounding landscape

Socioeconomic

3

A

H

- Vegetation barrier - Natural slopes at closure - Dump can be reduced in

height if increase in footprint, consult with community

- Decreased tourism and recreation

- Aesthetics

Generation of acid rock drainage

Water/Terrestrial Systems 4 A H - Impermeable barrier

below waste rock - Catchment ditch around

structure to capture runoff

- Well distributed particle size to reduce oxygen contact

- Increased acidity of soil, groundwater, and surface water

- Erosion causing sediment build up

Table 16-30: Impact assessment: Tailings storage facility

Key Issues Key Potential Impacts, VEC impacted Consequence Ranking

Likelihood Ranking

Risk Ranking Mitigation Strategy

Tailings Storage Facility

Generation of acid rock drainage

Water/Terrestrial Systems 2 A S - Impermeable barrier

below dam - Conservative dam design - Catchment ditch around

structure to capture runoff

- Increased acidity of soil, groundwater, and surface water

Complete Dam Failure

Water/ Terrestrial Systems 5 E S - Monitor water levels - Repair the dam as soon

as maintenance is required

- Recycle tailings water to reduce volumes

- Monitor pore pressures and wall displacements

- Increased acidity of soil, groundwater, and surface water

- Sediment build up - Effluent limits exceeded killing

fish populations

Page 117: Conceptual Mine Design, Grum YT

117

Placement and visual impact of tailings facility on surrounding landscape

Socioeconomic 2 D L - Consult community to discuss alternatives

- Decreased tourism and recreation

- Aesthetics

Table 16-31: Impact assessment: Waste Management

Key Issues Key Potential Impacts, VEC impacted Consequence Ranking

Likelihood Ranking

Risk Ranking Mitigation Strategy

Waste Management

Odour Terrestrial/

Socioeconomic

1

C

L

- On site waste incinerator

- Enclosed compost facility for revegetation nursery

- Attraction of scavengers such as bears

- Safety issues

Disposal Terrestrial/ Water Systems 1 C L - On site waste

incinerator - Enclosed compost

facility for revegetation nursery

- Septic management

- Contamination of soil, groundwater and surface water

- Vegetation Loss

Atmospheric System

1

C

L

- Incinerate waste and filter byproduct

- Landfill greenhouse gas emissions

Page 118: Conceptual Mine Design, Grum YT

118

Table 16-32: Impact assessment: General operational

Key Issues Key Potential Impacts, VEC impacted Consequence Ranking

Likelihood Ranking

Risk Ranking Mitigation Strategy

General Operational

Increased large vehicle use on roads

Atmospheric System 3 A H - Send trucks in convoys

at low speeds to reduce frequency of noise

- Increased noise and air emissions

Terrestrial Systems

4

B

H

- Send trucks in convoys at low speeds to reduce chance of wildlife collisions

- Create wildlife crossing points

- Wildlife roadkill

Light vehicle accident

Socioeconomic 4 B H - Post and monitor speed

limits

- Injury to employees or

members of the public

Table 16-33: Impact assessment: Closure and remediation

Key Issues Key Potential Impacts, VEC impacted Consequence Ranking

Likelihood Ranking

Risk Ranking Mitigation Strategy

Closure and Remediation

Impact on environment over time after pit closes

Socioeconomic 3 E M - Return the site to

sustainable pre-mining landscape

- Monitor and provide proper signage - Third party use

- Ex. swimming - Visual disturbance

Water System 3 D M - Monitor water quality

and levels

- Change in groundwater quality

and levels

Page 119: Conceptual Mine Design, Grum YT

119

Poor seeding success

Terrestrial System 3 D M - Test multiple native flora

species - Try again using tested

vegetation - Use fertilizers or

resurface with new topsoil

- Loss of vegetation - Slow growth rates - Loss of stabilization of soil

Impact on soils and degree of erosion

Water System

3

B

S

- Progressive remediation to reduce vulnerable areas

- Sediment buildup in surface water and other drainage systems; water finding alternative route causing erosion and flooding of areas

Atmospheric System 3 C S - Progressive remediation to reduce vulnerable areas

- Monitor air quality - Cover if necessary

- Wind erosion before revegetation causing suspended particulate matter

Page 120: Conceptual Mine Design, Grum YT

120

Table 16-34: Impact assessment: Natural disasters

Key Issues Key Potential Impacts, VEC impacted Consequence Ranking

Likelihood Ranking

Risk Ranking Mitigation Strategy

Natural Disasters

Severe Electrical Storm

Socioeconomic 5 D S - Have backup generators

ready in case of power outage

- Make sure all employees wear proper clothing

- Disaster training for employees

- Employee struck by lightning - Lightning initiating fire or

explosion - Disruption to power/ security

systems

Cyclone or seismic event

Water Systems 4 E M - Design tailings facility

conservatively to keep the tailings behind the dam in such circumstances - Collapse of mine infrastructure

- Release of untreated effluent, tailings, acid generating waste

Socioeconomic 5 C H - Have a medical trained

staff member on site at all times

- Record events - Communication disruptions - Employee injury and inability to

evacuate

Major Forest Fire Socioeconomic

4

C

S

- Have a medical trained staff member on site at all times

- make sure the employee fighting the fire has been properly trained

Injury to employees fighting the bushfire

Atmospheric Systems 3 C S - House flammable goods

such as fuel in flame retardant containers

- Unregulated burning of fuel, waste, materials, etc.

- Decrease in air quality

Page 121: Conceptual Mine Design, Grum YT

121

16.19 Closure Costs Table 16-35 Unit Costs of Items Needed for Closure

Contractor Unit Rates; Misc Costs Units Cost ($)

Excavation of Soil in Stockpile m3 5

Supply & place geotextile m2 12

Load, haul and place topsoil m3 5

Load, haul and place tailings cover m3 7

Load, haul and place rock cover, m3 8 organics, granular till and clay

Drill, Blast and Haul Rip Rap m3 22

Place Rip Rap m3 14 Camp costs day/person 75 Surface water quality analyses sample set 420 Ground water quality analyses sample set 290

Water treatment costs m3 0.4 Revegetation seed mix kg 13 Fertilizer kg 1 Seed and fertilizer application ha 1,500

Concrete m3 85 Erosion Barrier /linear km 3,000

Page 122: Conceptual Mine Design, Grum YT

122

16.20 Contained Process Metals

Figure 16-15 - Annual contained lead and zinc processed

Figure 16-16 - Annual contained silver and gold processed

0

50000000

100000000

150000000

200000000

250000000

300000000

350000000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Po

un

ds

of

Co

nta

ined

Met

al

Year into Production

Annual Contained Lead and Zinc Processed

Lead Zinc

0

20000

40000

60000

80000

100000

120000

140000

160000

0

1000000

2000000

3000000

4000000

5000000

6000000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Co

nta

ined

Go

ld (

toz)

Co

nta

ined

Silv

er (

toz)

Year into Production

Annual Contained Gold and Silver Processed

Silver Gold .

Page 123: Conceptual Mine Design, Grum YT

123

16.21 Mill Recoveries Used for Economics

Table 16-36 - The effective recoveries and recoverable metal of ore sent to the mill for each year of mine production

Recoveries of Ore Mined sent to the Mill (from the Mine)

Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

PB% 87 87 88 88 89 88 90 88 88 90 89 88 88 87 87 86 88 87

ZN% 87 87 88 88 88 88 89 88 88 90 88 88 88 87 87 85 88 88

AU% 58 58 59 60 60 60 60 61 58 60 60 59 60 59 59 55 59 59

AG% 52 52 52 52 52 52 52 52 51 52 51 52 51 51 51 51 51 51

Recoverable Metal from Ore sent to the Mill (from the Mine)

Year 1 2 3 4 5 6

PB (lbs) 4654451 35304064 108217502 150897225 133187762 115014877

ZN (lbs) 9379724 64222084 182306434 262753294 227153465 185289697

AU (toz) 1246 7679 24314 37228 35895 29772

AG (toz) 87213 540496 1542040 2143442 1915519 1681286

Year 7 8 9 10 11 12

PB (lbs) 146065776 127414654 136986276 138194609 103201042 85790397

ZN (lbs) 235351647 208004230 225962990 216882760 161840422 133118121

AU (toz) 45627 40677 39401 45552 39390 31025

AG (toz) 2152248 1886674 1948951 1984997 1513032 1268474

Year 13 14 15 16 17 18

PB (lbs) 104803958 71945331 79700163 104729101 122557357 130649169

ZN (lbs) 162766841 108687421 113090669 152516536 185219914 178477739

AU (toz) 34350 24343 27354 32936 40720 42666

AG (toz) 1581843 1047825 1190311 1562914 1796422 1753048

Page 124: Conceptual Mine Design, Grum YT

124

Table 16-37 - The effective recoveries and recoverable metal of ore sent from the stockpile

Recoveries of Ore sent to Mill from Stockpile

Year 11 12 13 14 15 16 17 18 19 20

PB % 88 88 88 88 88 0 0 0 88 88

ZN % 88 88 88 88 88 0 0 0 88 88

AU % 60 60 60 60 60 0 0 0 60 60

AG % 51 51 51 51 51 0 0 0 51 51

Recoverable Metal from Ore sent to Mill (from Stockpile)

Year 11 12 13 14 15 16 17 18 19 20

PB (lbs) 249158 298989 199326 548147 348821 0 0 0 1993260 1146125

ZN (lbs) 397561 477073 318049 874634 556585 0 0 0 3180487 1828780

AU (toz) 249158 298989 199326 548147 348821 0 0 0 1993260 1146125

AG (toz) 397561 477073 318049 874634 556585 0 0 0 3180487 1828780

16.22 Sustaining Capital

Table 16-38 - The calculated sustaining capital to be allotted annually over the LOM

-2 -1 1 2 3

Equipment $ 1,918,584 $ 3,837,168 $ 5,814,977 $ 6,917,247 $ 6,640,367

Processing - $ 1,083,638 $ 1,083,638 $ 1,083,638 $ 1,083,638

Total $ 1,918,584 $ 4,920,806 $ 6,898,614 $ 8,000,884 $ 7,724,005

4 5 6 7 8

Equipment $ 6,685,401 $ 6,762,947 $ 6,714,842 $ 6,689,750 $ 6,744,664

Processing $ 1,083,638 $ 1,083,638 $ 1,083,638 $ 1,083,638 $ 1,083,638

Total $ 7,769,039 $ 7,846,585 $ 7,798,480 $ 7,773,387 $ 7,828,301

9 10 11 12 13

Equipment $ 6,729,956 $ 6,716,486 $ 6,707,313 $ 6,704,690 $ 6,704,531

Processing $ 1,083,638 $ 1,083,638 $ 1,083,638 $ 1,083,638 $ 1,083,638

Total $ 7,813,594 $ 7,800,123 $ 7,792,950 $ 8,000,884 $ 7,724,005

14 15 16 17 18

Equipment $ 6,697,299 $ 3,837,168 $ 5,814,977 $ 6,917,247 $ 6,640,367

Processing - $ 1,083,638 $ 1,083,638 $ 1,083,638 $ 1,083,638

Total $ 1,918,584 $ 4,920,806 $ 6,898,614 $ 8,000,884 $ 7,724,005

19 20

Equipment $ 1,918,584 $ 3,837,168

Processing - $ 1,083,638

Total $ 1,918,584 $ 4,920,806

Page 125: Conceptual Mine Design, Grum YT

125

16.23 Depreciation and Tax Calculations

Table 16-39 - Depreciation (at 20%) and tax (at 30%) calculations