Upload
tuantomato
View
21
Download
1
Tags:
Embed Size (px)
DESCRIPTION
fda
Citation preview
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 1 of 64
________________________________________________________________________________________________
Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.
PROJECT TECHNICAL SPECIFICATION
CON 006
SITE INSPECTION AND TESTING
0 15/09/2009 ISSUE FOR LSP PROJECT HHM PCS
REV. DATE DESCRIPTION PREPARED CHECKED APPROVED
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 2 of 64
TABLE OF CONTENTS
1. SCOPE .................................................................................................... 4 1.1. PURPOSE .............................................................................................................. 4 1.2. RESPONSIBILITY .................................................................................................. 4 1.3. CONTRACTORs SCOPE OF SERVICE ............................................................... 4 1.4. RELATED ENGINEERING SPECIFICATIONS...................................................... 4
2. GENERAL ............................................................................................... 4 2.1. INSPECTION PERSONNEL................................................................................... 4 2.2. WELDING INSPECTION ........................................................................................ 4 2.3. WELDING PROCEDURE ....................................................................................... 4 2.4. TESTING ON SITE................................................................................................. 4 2.5. TESTS OUTSIDE THE SITE .................................................................................. 4 2.6. SCOPE OF TESTING............................................................................................. 4 2.7. ACCEPTANCE STANDARD................................................................................... 4 2.8. OWNER INSPECTION ........................................................................................... 4 2.9. DOCUMENTATION ................................................................................................ 4
3. PRESSURE VESSELS, HEAT EXCHANGER, AIR COOLERS ............. 4 3.1. GENERAL............................................................................................................... 4 3.2. FIELD WELDS ........................................................................................................ 4 3.3. TESTING OF FIELD WELD.................................................................................... 4 3.4. PRESSURE TESTING............................................................................................ 4 3.5. DOCUMENTATION ................................................................................................ 4 3.6. STORAGE TANKS ................................................................................................. 4
4. MECHANICAL EQUIPMENTS................................................................ 4 4.1. GENERAL............................................................................................................... 4 4.2. PUMPS (CENTRIFUGAL, RECIPROCATING, METERING, POSITIVE DIPLACEMENT
PUMPS, EXCLUDING FIRE WATER PUMPS)..................................................... 4 4.3. FIRE WATER PUMPS, INCLUDING DIESEL ENGINES....................................... 4 4.4. CENTRIFUGAL COMPRESSORS AND DRIVERS, EXCEPT INSTRUMENT AIR
COMPRESSORS................................................................................................... 4 4.5. INSTRUMENT AIR COMPRESSORS, INCLUDING DRYERS.............................. 4 4.6. RECIPROCATING OXYGEN COMPRESSORS.................................................... 4 4.7. GENERAL AND SPECIAL PURPOSE STEAM TURBINES .................................. 4
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 3 of 64
4.8. INDUSTRIAL COMBUSTION GAS TURBINES ..................................................... 4 4.9. CENTRIFUGAL FANS ............................................................................................ 4 4.10. LUBE OIL AND SEAL OIL SYSTEM ...................................................................... 4
5. PIPING .................................................................................................... 4 5.1. GENERAL............................................................................................................... 4 5.2. ORGANIZATION AND RESPONSIBILITY ............................................................. 4 5.3. CHECK OF MATERIALS RECEIVED .................................................................... 4 5.4. PREFABRICATION ................................................................................................ 4 5.5. WELDING ............................................................................................................... 4 5.6. TESTS AND EXAMINATIONS ............................................................................... 4 5.7. SCOPE OF RT TESTING..................................................................................... 4 5.8. EVALUATION CRITERIA ....................................................................................... 4 5.9. REPAIRS ................................................................................................................ 4 5.10. CHECK OF PIPING COMPONENTS ..................................................................... 4 5.11. PRESSURE AND LEAK TESTS............................................................................. 4 5.12. FLUSHING, PICKLING, DRYING........................................................................... 4 5.13. PAINTING AND INSULATION................................................................................ 4 5.14. MECHANICAL COMPLETION ............................................................................... 4
6. INSTRUMENTATION .............................................................................. 4 6.1. GENERAL............................................................................................................... 4 6.2. DEFINITIONS ......................................................................................................... 4 6.3. INSPECTION AND TESTING DOCUMENTS ........................................................ 4 6.4. INSPECTION AND TESTING REQUIREMENTS .................................................. 4 6.5. INSPECTION AND TESTING BEFORE INSTALLATION COMMENCEMENT ..... 4 6.6. INSPECTION AFTER INSTALLATION COMMENCEMENT.................................. 4 6.7. TESTING AFTER INSTALLATION COMMENCEMENT ........................................ 4 6.8. INSPECTION FOR INSTRUMENT SUPPLIED WITHIN PACKAGE UNIT............ 4 6.9. INSPECTION REPORTS........................................................................................ 4 6.10. TEST RESULTS ..................................................................................................... 4 6.11. OVERALL INSTALLATION CERTIFICATE............................................................ 4 6.12. STARTUP PERSONNEL........................................................................................ 4
7. ELECTRICAL AND COMMUNICATION FACILITIES............................. 4 7.1. SCOPE.................................................................................................................... 4 7.2. GENERAL............................................................................................................... 4
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 4 of 64
7.3. REASONS, TYPES AND PREREQUISITES OF SITE INSPECTION AND TESTS............................................................................................................................... 4
7.4. AS AN INTEGRAL PART OF ALL PARTICULAR SITE INSPECTIONS AND TESTS, CONTRACTOR SHALL BE RESPONSIBLE FOR THE FOLLOWING: ................ 4
7.5. SPECIFIC REQUIREMENTS FOR FIELD INSPECTIONS AND TESTS OF ELECTRICAL AND COMMUNICATION EQUIPMENT ......................................... 4
8. MISCELLANEOUS ITEMS...................................................................... 4
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 5 of 64
1. SCOPE This Specification stipulates the basic scope of inspection activities for construction work on the site, irrespective of whether the plant components to be erected arrives on the site as complete, pre- assembled or semi-finished unit.
1.1. PURPOSE
This specification shall enable the Contractor to incorporate the tests and inspections required by the OWN E R or the Project Specifications in his scope of services and guarantee.
1.2. RESPONSIBILITY
1.2.1. Compliance by the Contractor with this specification does not relieve him from his responsibility to determine and include in his services any test activities exceeding the minimum requirements which, in his opinion, are necessary to fulfill guarantee and prove the quality of construction work on the site.
1.2.2. The scope makes no claims to completeness. The Contractor is responsible to cover in his detailed site inspection procedure and/or specifications all necessary test requirements considering all requirements of this Project Specification, covering also those equipment/material items which are not specifically mentioned herein.
1.2.3. The Contractor shall guarantee that all equipment/material is of first class quality and successfully inspected and tested.
1.3. CONTRACTOR'S SCOPE OF SERVICE
The Contractor shall include in his scope of services detailed inspection and test procedures to be approved by the Owner incorporating also requirements mentioned herein before starting the construction work. The inspection and test procedures shall include hold points for Owner inspection.
1.4. RELATED ENGINEERING SPECIFICATIONS
Project Specification SP-010 Equipment Preservation
Project Specification SP-009 Painting
Project Specification SP-006 Thermo Insulation Design
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 6 of 64
ME-002 Storage Tank
CON-010 Fabrication and Field Works of Piping
EE-001 General Electrical Design Specification
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 7 of 64
2. GENERAL
2.1. INSPECTION PERSONNEL
2.1.1. The Contractor shall prepare organization schedules showing the responsibilities of the inspection personnel. An assigned chief inspector is fully responsible for the following tasks independently of the Site Management.
The inspection personnel shall be trained and qualified for the work to be performed by them.
All necessary specifications and applicable Codes shall be made available by Contractor on site.
Tests and inspections shall be carried out in conformation with their Codes and Standards and related specifications.
The test equipments to be used shall meet the local laws and regulations. (Evaluate test results are a prerequisite for the selection of the test equipments)
Scope and sequence of testing shall be adhered to.
2.1.2. The Contractor is responsible for inviting the Third Party inspector to the test and assuring the proper performance of the testing activities.
2.1.3. Owner shall always have the right to approve or reject inspection personnel of Contractor without clarification.
2.2. WELDING INSPECTION
2.2.1. The Contractor shall assign a weld inspection group to report to the chief inspector. The weld inspection group has the right to give instructions regarding:
Storage and selection of the welding filler metals and auxiliaries
Pre- and post- weld heat treatment
Welders performance qualifications
Assignment of welders
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 8 of 64
Welding equipments
Checking the repair procedure and repair work
Welding documentation
2.2.2. All reports carried by chief inspector shall be also available to Owner representation.
2.3. WELDING PROCEDURE
2.3.1. The Contractor shall supply and prepare welding procedures for field welding showing the:
Welding method
Welding filler metals
Qualification of the welders (including welding test specimens)
Weld shape
Welding sequence and position
Pre- and post- weld heat treatment
Weld examination and evaluation criteria
Scope of weld examination
2.3.2. The welding inspector shall check that the welding data sheets are adhered to during welding regarding the welders, welding procedures, filler metals and weld tests, the requirements of the Project Specification for Welding.
2.3.3. For materials which are not covered by ASTM, the Contractor shall furnish material specific processing documentation from the Vendor for Owner approval prior to use.
2.4. TESTING ON SITE
Unless otherwise stipulated in the Project Specifications or Vendor instructions, the following test shall be made:
2.4.1. Destructive tests shall be made in accordance with the requirements specified in ASTM A to G.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 9 of 64
2.4.2. Non-destructive tests shall be made in accordance with the requirements specified in ASME Section V.
2.5. TESTS OUTSIDE THE SITE
If tests which have been specified cannot be performed on the Site, they shall be made in accordance with Paragraph 2.4 by a test institute approved by the chief inspector without additional cost to the Owner.
2.6. SCOPE OF TESTING
2.6.1. The scope of testing is taken from the Project Specifications, Codes and Standards or this Specification.
2.6.2. The scope of testing may be extended if it is required more by quality assurance. The new scope of testing shall then be established jointly by the chief inspector and the weld inspection group.
2.6.3. The Owner shall be informed thereof in writing.
2.7. ACCEPTANCE STANDARD
2.7.1. The acceptance standard is laid down in the Project Specifications, Codes and Standards and shall be strictly adhered to.
2.7.2. In case of doubt, the requirements of the Codes and Standards shall apply Paragraph 2.8
Owner INSPECTION.
2.8. OWNER INSPECTION
2.8.1. The Owner and/or its representative may witness the tests and inspections at their own discretion.
2.8.2. The Contractor shall submit FIELD INSPECTION NOTICE (FIN) to the Owner by daily basis for field inspection. Other than field inspection, FIN shall be submitted to the Owner not later than 5 working days prior to scheduled inspection date.
2.8.3. The Owner has the right to have tests repeated on Contractors cost if FIN is not submitted in time.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 10 of 64
2.9. DOCUMENTATION
2.9.1. All test results shall be entered in forms issued for the particular tests. The forms shall be signed by the authorized person.
2.9.2. The test reports shall clearly refer to the object tested.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 11 of 64
3. PRESSURE VESSELS, HEAT EXCHANGER, AIR COOLERS
3.1. GENERAL
3.1.1. This chapter applies to tests and inspections of field welds on pressure vessels.
3.1.2. Generally, these plant components except storage tanks are delivered completely to the Site. For the usual piping connection work, the requirements given in Paragraph 5 of this Specification shall be observed.
3.2. FIELD WELDS
3.2.1. If field welds are necessary, the Vendors instructions and the Project Specifications shall be complied with.
3.2.2. The weld inspection group shall check the work documentation and supervises welding and any possible heat treatments and testing.
3.2.3. If any subsequent repairs to plant components are required on site, the repair procedure is part of the Vendors scope. The weld inspection group shall check the Vendors repair instructions for suitably supervise the repair work and report the results to Owner.
3.2.4. Auxiliary structures and transport devices which are welded directly to pressure walls of the plant component and must be removed shall not be knocked off. They shall be removed mechanically and the connection points on the pressure wall shall be ground flushed and checked for cracks. Repair welding requires the procedure approved by Owner prior to start of the work.
3.2.5. Welding on plant components subjected to final heat treatment at the Vendors works is not permitted in any case.
3.3. TESTING OF FIELD WELD
3.3.1. SCOPE OF TESTING
Generally, all field welds of pressure parts shall be 100 % tested. Butt welds shall be radiographic tested as per codes and standards. Fillet welds of austenitic and non-magnetic materials shall be liquid penetrant tested.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 12 of 64
Carbon steel fillet welds shall be subjected to a magnetic particle examination.
3.3.2. ACCEPTANCE STANDARD
The ASME Code shall be the basis for evaluating the welds to be examined.
3.4. PRESSURE TESTING
If pressure testing after welding is required, Paragraph 7.4 of the Project Specification shall be applied.
3.5. DOCUMENTATION
All test activities and results shall be documented. The activities prior to mechanical completion shall be included.
3.6. STORAGE TANKS
3.6.1. Delivery, fabrication and testing on the site shall be accordance with the requirements of Project Specification. The Contractors weld inspection group shall assure that the instructions from the tank Vendor are complied with.
3.6.2. The tank Vendor shall advise the Contractors weld inspection group all of tests to be made in the course of fabrication. If the test results do not meet the specified quality standard, the scope of testing shall be taken by the Contractors chief inspector after consultation with the welding supervisors and weld inspection group.
3.6.3. All test results and dimensional checks shall be recorded according to Paragraph 2.9 and 3.5.
3.6.4. Spherical tanks containing liquefied hydrocarbon and / or substances governed by local laws and regulations shall be performed the inspection and test as required by the regulations or the project specification ME-002 Storage Tank whichever is more stringent. The Contractor shall be responsible for all works and cooperating with government's inspector as his satisfaction to achieve government approval and certificate for such storage tanks.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 13 of 64
4. MECHANICAL EQUIPMENTS
4.1. GENERAL
This chapter applies to the field tests and inspections for the mechanical equipments.
4.1.1. Detailed test procedures shall be prepared by the Contractor and submitted to the Owner for review prior to start the construction work.
4.1.2. Prior to the test runs for each machine the Contractor shall submit to the Owner the following certificates:
Alignment protocol
Protocol of stress-free pipe connection
Internal inspection report (cleaning, clearance check etc.)
If applicable, in addition, the Contractor has to deliver certificates for hydrostatic pressure test, radiographic examination of welds, liquid penetrant examination, etc.
4.1.3. A detailed check list has to be prepared by Contractor for the individual steps from the beginning of the erection up to the tests under operating conditions. The check list shall also contain information about the function and tightness of the mechanical seal, vibration of the machine for the specified operating range, etc.
4.1.4. Detailed records of the test runs containing capacity, pressures, temperatures, vibrations, electric current consumption, steam consumption, cooling water consumption, etc. shall be prepared by the Contractor during the individual tests of the equipment and submitted to the Owner for approval.
4.1.5. Prior to test run of the machinery, the interlocking control electrical safety protection system, and observation system shall be checked for function and used during the test runs of the machinery.
If machines are tested with fluid other than the operating product, some functions of the interlocking system which can't be used have to be bridged.
Before carrying out tests on the machines with the original media/gases all functions of the interlocking system shall be checked for function and used.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 14 of 64
4.1.6. If during the specified test duration the test has to be stopped due to machinery failures, the test run has to be repeated after all causes have been corrected.
4.1.7. If there is any deviations in this specification due to operation condition and a circumstance. Contractor shall inform to Owner and shall then discuss with Owner regarding correct action such as test duration, test method, etc. for Owner approval.
4.2. PUMPS (CENTRIFUGAL, RECIPROCATING, METERING, POSITIVE DIPLACEMENT PUMPS, EXCLUDING FIRE WATER PUMPS)
4.2.1. All pumps shall be mechanically tested with water or suitable fluids specified by the Contractor for at least 4 hours of continuous operation. Every hour bearing temperature and vibration shall be recorded.
4.2.2. All pumps shall be subjected to a performance test of at least 14 days of continuous operation under operating conditions. If one operating and one stand-by pump are installed they are required to change over from operating to standby after two weeks.
4.3. FIRE WATER PUMPS, INCLUDING DIESEL ENGINES
4.3.1. A mechanical test run of at least 4 hours shall be performed with the diesel engine according to ISO 3046. For the diesel engine of the fire pump system, a mechanical test run of at least 4 hours shall be performed, according to ISO 3046.
4.3.2. Complete fire water pumps with diesel engine shall be tested under operating conditions for at least 14 days, according to NFPA 20.
4.4. CENTRIFUGAL COMPRESSORS AND DRIVERS, EXCEPT INSTRUMENT AIR COMPRESSORS
4.4.1. The mechanical test run for all centrifugal compressor units shall be carried out with air or any other suitable fluid specified by the Contractor for at least 48 hours of continuous operation.
When abnormal condition is found, during the mechanical test run, detailed check shall be carried out for corrective action.
4.4.2. All centrifugal compressor units shall be tested with the original gas under operating conditions for at least 14 days of continuous operation.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 15 of 64
4.5. INSTRUMENT AIR COMPRESSORS, INCLUDING DRYERS
Each instrument air compressor unit including dryer shall be tested for at least 14 days of continuous operation under operating conditions.
4.6. RECIPROCATING OXYGEN COMPRESSORS
4.6.1. Mechanical test runs and initial oxygen runs shall be performed in according with IGC-Standard 10/81 section 6.2 and instructions from machine Vendor.
4.6.2. The following additions shall apply to IGC-Standard 10/81, section 6.2 Site work:
(Clarification)
A mechanical test run of at least 48 hours continuous operation shall be performed. After the 48-hour test run, the valves, piston and bearings of the machine shall be visually inspected.
(Clarification)
The oxygen test run shall be performed for at least 14 days continuous operation.
4.7. GENERAL AND SPECIAL PURPOSE STEAM TURBINES
4.7.1. All general-purpose steam turbines shall be mechanically tested for at least 4 hours of continuous operation.
Every hour bearing temperature and vibration shall be recorded.
Before mechanical test, the trip speed of the turbine shall be tested at least 3 times.
4.7.2. General purpose steam turbines and special-purpose steam turbines equipped with oil systems which is according to API 614 excluding gear type turbines shall be mechanically tested for at least 6 hours' continuous operation. Every hour bearing temperature and vibration shall be recorded.
When abnormal condition is found, during the mechanical test run, the bearings and blades of all steam turbines shall be visually inspected.
4.7.3. All general and special-purpose steam turbines shall be tested for at least 14 days of continuous operation under operating conditions together with the driven machine.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 16 of 64
4.8. INDUSTRIAL COMBUSTION GAS TURBINES
4.8.1. Each gas turbine shall be mechanically tested with the driven machine for at least 48 hours of continuous operation. Before this test run, the trip speed must be tested.
After the mechanical test run, bearings of the turbine and the gear shall be visually inspected.
4.8.2. Each gas turbine shall be tested for at least 14 days continuous operation under operating conditions together with the driven machine.
4.9. CENTRIFUGAL FANS
4.9.1. All centrifugal fans shall be mechanically tested for at least 4 hours of continuous operation with all its auxiliaries. Every hour bearing temperature and vibration shall be recorded.
4.9.2. When abnormal condition is found, during the mechanical test run, the bearings of centrifugal fan shall be visually inspected.
4.9.3. Each centrifugal fan shall be tested for at least 14 days of continuous operation under operating conditions.
4.10. LUBE OIL AND SEAL OIL SYSTEM
4.10.1. The complete oil unit shall be flushed and cleaned with oil till clear of dirt and debris as specified by the Contractor/Vendor.
4.10.2. After carrying out the functional tests of the oil system, a test run of at least 14 days continuous operation shall be performed for the original system using the specified oil.
The test run to the oil unit shall be carried out in accordance with API 614.
While the oil unit is flushed the bearing and shaft seals of the lubricated machinery shall be by-passed.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 17 of 64
5. PIPING
5.1. GENERAL
This chapter applies to the tests and inspections of piping.
5.2. ORGANIZATION AND RESPONSIBILITY
5.2.1. The Contractor shall prepare pertinent organization schedules to guarantee the quality assurance for prefabrication and final installation of piping. The organization schedules shall also determine the technical responsibilities.
5.2.2. Regarding the quality assurance of piping installation, the warehouse, prefabrication areas and other piping assembly areas shall be organized so that quality assurance is guaranteed. For this, the Contractor shall prepare a detailed procedure.
5.3. CHECK OF MATERIALS RECEIVED
5.3.1. All piping components received shall be checked. The quality and compliance with the Codes and Standards of all structural parts shall be proved by certificates. Structural parts which do not meet these requirements must be rejected. Random check for the material specification shall be done against certificates by Contractors cost.
5.3.2. Re-stamping of pipes and elbows shall be done by the pertinent field inspectors.
5.4. PREFABRICATION
5.4.1. Systematic process of parts withdrawn from the site warehouse for prefabrication or final installation shall be properly handled, protected, stored before their final use.
5.4.2. All piping components shall be preserved. The Contractor shall make appropriate rooms for prefabrication available. Piping components of carbon steel and of austenitic steel shall be kept separately in the prefabrication area. The prefabricated piping sections shall be properly stored such as capping, marking, grouping, etc. before further use.
5.5. WELDING
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 18 of 64
5.5.1. The Contractor shall prepare welding data sheets for the basic material combinations to be welded. These data sheets shall be based on the Codes and Standards given in the Project Specifications for welding.
5.5.2. Before starting the welding work, all data sheets, PQR and welders' certificates shall be submitted to the weld inspection group. If there are any doubts, the weld inspection group shall check the welder's quality standard by welding test specimens. Wherever possible, welding shall be limited to prefabrication work.
5.6. TESTS AND EXAMINATIONS
The weld examinations shall be made after the last heat treatment based on the data sheets and on a test schedule. The examinations shall be performed using test equipment from which optimal test results for the welds to be examined can be expected. Random test to piping welds must include all weld joints.
5.6.1. VISUAL CHECK OF WELDS
The examination shall be 100% for all types of welds. The examination shall be carried out according to ASME Boiler and Pressure Vessel Code (BPVC) Section V, Article 9.
5.6.2. BUTT WELDS
Radiographic examination shall be performed in accordance with:
ASME Section V, Article 2
Paragraph 341.3.2 and Paragraph 344.5 of ASME B31.3
Paragraph 136.4.5 of ASME B31.1.
The scope of the random test has to be extended by Contractor as per ASME B31.3, Paragraph 341.3.4 if the test results show that the welds are not free of unacceptable defects.
5.6.3. EXAMINATION OF FILLET WELDS
The fillet welds shall be subjected to a magnetic particle or liquid penetrant examination. The liquid penetrant method is being used for nonmagnetic materials. The examination is made as per Boiler and Pressure Vessel Code.
Article 7, Section V for Magnetic Particle method
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 19 of 64
Article 6, Section V for Liquid Penetrant method.
Welds subjected to heat treatment, may be radio-graphed prior to the last heat treatment, if after the heat treatment an additional liquid penetrant examination is made.
5.6.4. HARDNESS TEST
If a heat treatment is required by ANSI/ASME B 31.3 Chapter V, 331.1.1 and Table 331.1.1, the hardness of the weld shall be verified. If piping material and weldment to be expanded to sour environment, hardness shall be verified as requirement of NACE standard MR0175-94.
5.7. SCOPE OF RT TESTING
The scope of testing for the materials/combination used shall be determined by the Contractor appropriate to the stress to which the material is exposed. The scope of testing in general shall be conformed to CON-010 Fabrication and Field Works of Piping.
5.8. EVALUATION CRITERIA
5.8.1. For all welds, the error limits as per ANSI/ASME B 31.3, Chapter V, 328; ANSI/ASME Chapter VI, 341,344 shall be adhered to.
5.8.2. The maximum hardness values are to be taken from the ASME 31.3, Table 331.1.1 and NACE standard MR0175-94.
5.9. REPAIRS
The repairs shall be made in accordance with ASME B31.3, Chapter V, 328.6.
5.10. CHECK OF PIPING COMPONENTS
The Contractors piping specialists shall check the installed piping components for compliance with the P & I diagrams, piping drawings, isometric drawings and bills of materials. If any doubts, material mix up test shall be made.
5.11. PRESSURE AND LEAK TESTS
5.11.1. The Contractors piping specialists shall compile pressure test systems before starting the pressure tests. After completion of all welding, heat treatment and testing of the systems to be pressure-tested, the weld inspection group shall give the approval for pressure testing. The pressure testing shall be made according to ASME B31.3, Chapter VI, 345.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 20 of 64
5.11.2. The water to be used for the hydrostatic test shall be specified by the Contractor. If different materials are used in the hydrostatic test system, such as piping of carbon steel/heat exchanger tubes of stainless steel, water with a limited chloride (less than 10 PPM) content shall be used for this system.
5.11.3. The butt welds of pipes which cannot be subjected to a hydrostatic test shall be 100% radio-graphed. Subsequently, a leakage test is made. This examination is also performed, for all separable connections.
5.11.4. For the leakage test with air or nitrogen, appropriate safety measures shall be taken considering the local requirements.
5.12. FLUSHING, PICKLING, DRYING
For piping systems to be pickled and/or flushed and dried, the requirements of Project Specification SP-010 Equipment Preservation shall be complied with.
5.13. PAINTING AND INSULATION
5.13.1. After completion of the test described in Paragraph 5.10 and 5.11, approval for painting and insulation shall be given. The requirements of Project Specifications for painting (SP-009 Painting) and insulation (SP-006 Thermo Insulation Design) shall be complied with.
5.13.2. Insulation has to be inspected, in particular, for conformation with the specified insulation thickness, numbers of spacers, metal thickness of the weather jacket and proper installation of the jackets (appropriate overlap, tightness to water) and the inspection results have to be recorded.
5.13.3. Thermal conductivity coefficients, apparent densities and the required sound insulation figures of the insulating materials have to be verified.
5.13.4. Surface preparation (degree of rust removal), reference surfaces, workability of the insulating materials shall conform with the manufacturer's handling instructions. For instance regarding humidity, application of insulating materials and thickness per insulation layer shall be inspected / supervised and the inspection results shall be recorded.
5.14. MECHANICAL COMPLETION
After completion of all work on the piping systems and compilation of the drawings and test documentation, the Contractor shall notify the Owner of mechanical completion.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 21 of 64
6. INSTRUMENTATION
6.1. GENERAL
6.1.1. This standard should be used for the inspection and testing of all instrumentation and monitoring equipment for all plant components before and after installation on Site.
6.1.2. The contractor's personnel shall be competent, qualified and fully conversant with the types of equipment to be tested and where necessary the contractor shall arrange for his personnel to attend relevant training course.
6.1.3. A critical path analysis network shall be provided by the contractor and agreed by Owner. This shall define the overall sequence of the testing on the project. Any subsequent deviation from this program shall be agreed in writing.
6.1.4. The contractor shall, at all items, observe and comply with Vietnam and international safety regulation.
6.1.5. The contractor shall set up and maintain a quality assurance system to ensure that all work is carried out in full accordance with the requirements of the relevant parts of BS 5750: 1987 / ISO 9000 - quality system.
6.1.6. The contractor shall set up and maintain a quality assurance system to ensure that all work is carried out in accordance with the relevant specification.
6.1.7. The contractor shall obtain approval from owner before power or pneumatic supplies are switched on to any instrument, panel, and control system of plant.
6.2. DEFINITIONS
Terms used in this specification are defined as follows:
6.2.1. Maximum working pressure means the set pressure of safety valves for process piping and equipments.
6.2.2. Design pressure of instruments means the maximum pressure guaranteed by the manufacturer to which the pressurized parts of the instruments may be subjected without affecting the performance of the instruments.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 22 of 64
6.3. INSPECTION AND TESTING DOCUMENTS
Contractor shall provide the documents listed below to perform site inspection and testing activities as minimum.
Instrument list
Technical data sheets
Installation drawings
Hook-up drawings
Loop diagrams
Circuit diagrams
Wiring diagrams
Terminal connection diagrams
Interlock logic and sequence diagrams
Manufacturer's recommended inspection and testing procedures
Installation check sheets
Testing reports
Calibration reports
Etc.
Format of installation check sheets, testing reports, and calibration reports shall be prepared by Contractor and approved by Owner.
6.4. INSPECTION AND TESTING REQUIREMENTS
6.4.1. INSPECTORS FOR INSPECTION AND TESTING
The inspectors must be familiar with the necessary inspection, testing, and adjustment works for the installed instrumentation.
6.4.2. CALIBRATION FACILITIES
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 23 of 64
Contractor shall provide the dedicated calibration workshop in the site or nearby which meets the requirements of the international standard.
Contractor shall not use the calibration workshop for any other activity.
Entry inside the calibration workshop shall be permitted only to calibration technicians and inspectors from Contractors and owner's side.
The calibration room shall be an air conditioner room. The temperature, humidity, and the quality of air inside shall be controlled suitably for the requirement of calibration room according to the international standard. A thermometer shall be installed inside the room and the set temperature shall be noted down in testing and calibration reports.
The test equipment and the instruments to be calibrated shall be handled and maintained in suitable manner in order to maintain their guaranteed accuracy. Contractor shall maintain test certificates for the calibration of all test equipment by a third party and the calibration procedure shall be traceable to international standards.
Contractor shall also have standard procedures for regular calibration of the test equipment.
6.4.3. INSPECTION AND TESTING ACTIVITIES
The inspection and testing activities shall be included, but not limit to, the followings.
Inspection and testing before installation commencement
- Factory Acceptance Test (FAT)
- Visual inspection
- Calibration
- Etc.
Inspection and testing after installation commencement
- Visual inspection
- Leakage test and pressure test in pneumatic lines and impulse lines
- Inspection of the cables, screening, and protective system for proper connection
- Functional test
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 24 of 64
- Loop test
- Interlock logic and sequence test
- Performance test
- Site Acceptance Test (SAT)
- Etc.
6.4.4. OTHER REQUIREMENTS
The inspection and testing plan including date, procedure, etc. shall be specified by the Contractor and agreed with the Owner. Owner shall have the rights to witness all the inspections and tests. All test equipment and consumables shall be provided by the Contractor.
The contractor shall submit list of all test equipment to be used. This shall be revised and agreed with the Owner before testing is commenced. The list shall contain, but not limit to, the following.
Manufacturer
Instrument Type
Type Number
Quality Class
Instrument Test & Calibration certificate from approved authorities
6.5. INSPECTION AND TESTING BEFORE INSTALLATION COMMENCEMENT
6.5.1. The Factory Acceptance Test (FAT) of the following instrument systems shall be performed by Contractor at Manufacturers or Vendors workshop and approved by Owner prior to delivery. The inspection and test procedure shall be sent to Owner for approval at least 1 week prior to the test. The tested systems shall include, but not limit to, the followings.
DCS system
ESD system
F&G system
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 25 of 64
GC system and Analyzer House
Continuous Emission Monitoring System (CEMS)
COD Analyzer System
Other analyzer systems
Custody Transfer meter system
Truck loading meter system
Pelletizing system
Etc.
6.5.2. All instruments shall be visually inspected by the instrument subcontractor prior to issue from Contractors stores and any discrepancies shall be reported in writing to the contractor immediately.
6.5.3. Scale design, instrumentation symbols and texturing shall be checked at this stage.
6.5.4. Prior to installation, all instruments shall be calibrated by the Contractor in the site workshop. Calibration method and procedure shall be sent to Owner for approval at least 1 week prior to the calibration. The calibration process shall be traceable to international standards. The calibrated instruments shall include, but not limit to, the followings.
6.5.5. Contractor shall use the following inspection and test items of each instrument as a guideline. The inspection and test of equipment which are not listed below shall be proposed by Contractor and approved by Owner.
TRANSMITTERS, GAUGE, AND SIGNAL CONVERTERS:
Calibrate at 0, 25, 50, 75, and 100% of measurement range
CONTROL VALVES:
Each control valve shall be checked against the data sheets
Check to the linearity of the valve lift as against control signal: 0, 25, 50, 75, 100 % direct and reverse
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 26 of 64
Behavior on control air failure
SWITCHES: (INCLUDE TEMPERATURE SWITCH, PRESSURE SWITCH, FLOW SWITCH, LEVEL SWITCH, ETC.)
Checking the switch function (NC or NO)
Adjustment of the necessary switch points
Checking the switch hysteresis
SAFETY VALVES
Each safety valve shall be checked against the data sheets.
Bench test for all safety valves by applying pressure to the design level shall be carried out no earlier than 90 days prior to Mechanical Completion.
Lead seal shall be replaced and certified by Vendors representative at site if the adjustment of spring is requested.
6.5.6. A pre printed calibration sticker showing the tag no, manufacturer's serial number, date of calibration, calibration report serial number and initials of the person who has done the calibration shall be put on the instrument immediately after calibration.
6.6. INSPECTION AFTER INSTALLATION COMMENCEMENT
6.6.1. Contractor shall use the following inspection and test items of each instrument as a guideline. The inspection and test of equipment which are not listed below shall be proposed by Contractor and approved by Owner.
PANELS
Panels are held in place and are fixed firmly in accordance with the related drawings.
Panels are correctly mounted vertically.
The surface of panels is cleaned and has not been dented or scratched.
INSTRUMENT CABLE DUCTS
Instrument cable ducts are laid in according to the routes shown in the drawings using the material specified for the construction and sizes.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 27 of 64
Instrument cable ducts are fixed by the procedure shown in the drawings.
The inside of instrument cable ducts has no projection which may damage cables or wires.
The worked parts of the galvanized steel plates fabricated or welded at construction site are repaired according to the specified procedure.
Instrument cable ducts are certainly fitted with all cover plates.
6.6.2. IMPULSE PIPING / TUBING
VISUAL INSPECTION
Impulse piping/tubing is laid in accordance with the route shown in the drawings.
The materials specified for standards, sizes and quality are used.
The relative elevation and direction of pressure taps and instrument are as shown in the drawing.
Seal pots, condensate pots, etc. are assembled in the same or specified elevation.
Impulse piping/tubing is sloped as specified.
The division of high and low pressure connection of differential pressure instruments is correct.
PRESSURE TESTS AND LEAK TESTS
Those tests shall generally be performed without disconnection of impulse piping/tubing and the test pressure shall be limited to the design pressure of the instrument.
Pressure tests and leak tests shall be carried out simultaneously in accordance with the following procedure (except for 900 # rating and over).
Nitrogen or air shall be used for the pressurization of impulse piping/tubing.
The test pressure shall be 1.25 times the maximum working pressure.
No change on the impulse piping/tubing is confirmed after pressurized at least five minutes at the test pressure.
During the test, no leakage from impulse piping/tubing is checked by soapy water.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 28 of 64
Remarks: The pressurization must be done slowly to maintain the safety.
For 900 # rating and over, pressure tests and leak tests shall be carried out individually. Fluid, pressure and duration is as follows
PRESSURE TESTS
Fluid: water
Pressure: 1.5 times the maximum working pressure
Duration: 5 minutes
LEAK TESTS
Fluid: Air
Pressure: 1.1 times the maximum working pressure
Duration: 3 minutes
6.6.3. SUPPLY AIR PIPING /TUBING
VISUAL INSPECTION
Supply air piping/tubing is arranged as shown in the drawings.
The materials specified for standards, sizes and quality are used.
The piping/tubing method around instruments is correct.
The piping/tubing is routed avoiding an adverse effect from a heat source and is not under the hot or cold insulation materials of process piping and equipments.
The piping/tubing is arranged or supported avoiding the vibration and thermal expansion of process piping or of equipments.
LEAK TESTS
Leak tests shall be performed after cleaning check and the procedure shall be as follows:
Instrument air is used for leak tests.
The pressure of instrument air shall be of the working pressure.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 29 of 64
No leakage from supply air piping/tubing is confirmed by soapy water after pressurized at the test pressure. Leakage is checked after 3 minutes passed.
6.6.4. SIGNAL AIR PIPING / TUBING
VISUAL INSPECTION
Signal air piping/tubing is arranged as shown in the drawings.
The materials specified for standards, sizes and quality are used.
The piping/tubing method around instruments is correct.
The piping/tubing is routed avoiding an adverse effect from a heat source and is not under the hot or cold insulation materials of process piping and equipments.
The piping/tubing is arranged or supported avoiding the vibration and thermal expansion of process piping or of equipments.
CONTINUITY TESTS
Instrument air is used for continuity tests.
The pressure of Instrument air shall be 1 kg / cm2 G or the maximum signal pressure of the system concerned.
Confirm the continuity by checking the air blown through piping. Blow shall be carried out sufficiently.
Confirm the identification of multi-cored signal tube is as shown in the drawings.
LEAK TESTS
Leak tests shall be performed after continuity tests with all joints reconnected.
Instrument air is used.
The pressure of instrument air shall be 1 kg / cm2 G or the maximum signal pressure of the system concerned.
No leakage from signal air piping/tubing shall be confirmed by soapy water after pressurized at the test pressure. Leakage is checked after 3 minutes passed.
6.6.5. WIRING
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 30 of 64
VISUAL INSPECTION
Conduit piping is arranged as shown in the drawings.
The materials specified for standards, sizes and quality are used.
The wiring method around instruments is correct.
Wiring is routed avoiding an adverse effect from a heat source and is not under the hot or cold insulation materials of process piping and equipments.
Wiring is arranged or supported avoiding the vibration and thermal expansion of process piping or of equipments.
Wiring is laid avoiding an adverse effect from power cables.
Sealing method is as specified in the drawings
Grounding method is as specified in the drawings.
CONTINUITY TESTS
Use low voltage apparatus such as testers, buzzers or telephones.
Disconnect the compression fittings from terminal blocks to avoid excessive voltage to the instruments and to prevent the by-pass circuits.
Confirm the continuity of wiring.
Confirm the identification of cables and wiring is as shown in the drawings.
Insulation resistance tests
Insulation resistance tests shall be performed after the said continuity tests and the procedure shall be as follows
Use "Megger" (insulation resistance tester) of rated voltage 500V or higher as a tester.
Measure the insulation resistance between wires and between a wire and earth, disconnecting the compression fittings from terminal blocks after continuity tests.
Check the measured values are greater than 100 M compensation lead wire for thermocouples as 5 M. When specified by the manufacturer of apparatuses, the value shall govern.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 31 of 64
Reconnect the compression fittings to terminal blocks after the charged current in the wire of cable through those tests is discharged to ground.
Grounding resistance tests
Grounding resistance meters shall be used for those tests.
The measured value shall be less than those shown in the following table:
Classification of grounding Grounding resistance (OHMS)
Frame earthling 5 or less
System earthling 1 or less
Shield wire earthling 5 or less
Grounding resistance requirements for special circuits such as PLC, DCS & other computers shall be as per manufacturers recommendation.
6.6.6. HEAT TRACING PIPING
VISUAL INSPECTION
Heat tracing piping is arranged as shown in the drawings.
The materials specified for standards, sizes and quality are used.
The method of the piping (rough coiling, tight coiling or a combination) is correct.
No extremely crushed parts by bending works or the like shall be found on the heat tracing piping.
PRESSURE TESTS AND LEAK TESTS
The procedure of those shall conform to the clause 7.5.2.2 in principle.
For steam tracing, steam practically provided with shall be used for pressure tests and leak tests which are carried out simultaneously.
No change on the heat tracing piping shall be confirmed.
6.6.7. INSTRUMENTS
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 32 of 64
VISUAL INSPECTION
Instruments are not placed at the location that might interfere with their function, operation, maintenance, etc.
Instruments are not installed on the surface which may cause vibration on the instruments.
Instruments are installed by the specified way using the materials shown in the related drawings.
Instruments are correctly mounted horizontally, vertically or at the specified angle.
Instruments are cleaned and have not been damaged.
6.7. TESTING AFTER INSTALLATION COMMENCEMENT
6.7.1. SITE ACCEPTANCE TEST (SAT)
The Site Acceptance Test (SAT) of the following instrument systems shall be performed by Contractor at site after installation and approved by Owner. The inspection and test procedure shall be sent to Owner for approval at least 1 week prior to the test. The tested systems shall include, but not limit to, the followings.
DCS system
ESD system
F&G system
GC system and Analyzer House
Continuous Emission Monitoring System (CEMS)
COD Analyzer System
Other analyzer systems
Custody Transfer meter system
Truck loading meter system
Tank Gauge System
Pelletizing system
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 33 of 64
Auto feeder system
Etc.
6.7.2. INSTRUMENT SYSTEMS
All instrumentation loops shall be subjected to an overall functional test which the measuring ranges for 0, 25, 50, 75 and 100 are simulated from the process side with air or N2. All indicated values are read off and reported. Readjustment is necessary if deviations beyond the allowable accuracies occur.
In regard to controllers, the control characteristic (direct/reverse) shall be checked and adjusted if necessary.
Displacement-type level instruments shall be tested with clean water or suitable liquids.
The control signals to the pertinent control valves shall be pre-selected from the appropriate manual loading station with the values 0, 50 and 100 %.
The bolts for stuffing box packing shall be tensioned as per the manufacturer's instructions.
6.7.3. ALARM, SEQUENCE CONTROL AND SAFETY SYSTEMS
Checks shall include correct function and identification of all parts. Functions shall be checked step-by-step using the process function charts and circuit diagrams including the P & I diagram.
For this purpose, the switching ranges shall be simulated with air or N2 on the process side at the limit switches.
The resulting function indication/control function of solenoid valves and pumps shall be checked and entered in reports.
The sequence controls and safety systems shall then be operated by the startup personnel and, if necessary, the pertinent inspection authorities.
6.7.4. ELECTRICAL THERMOMETERS
Thermocouples to test the temperature measuring loops for correct poling of the extension wire, correct calibration of the instrument and pertinent measuring point, a suitable measuring voltage shall be supplied to the head of each thermocouple and compared on the instrumentation receiver.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 34 of 64
Resistance thermometers to check the temperature measuring loops, a precision resistor of suitable range shall be connected to the head of each resistance thermometer and the pertinent temperature compared on the instrumentation receiver. If necessary, the lines shall be balanced as per the manufacturer's instructions.
6.7.5. ANALYZERS AND SPECIAL INSTRUMENTS
All analyzer probes shall be checked against sample probe drawing for correct direction and installation.
The wake frequency calculation report for all probes shall be provided.
All sampling systems shall be checked for correct installation and tightness.
All analyzers shall be calibrated using the procedure recommended by the manufacturer applying the sample gases and liquids supplied.
All Analyzer houses shall be checked to overall safety function test.
Special instruments shall be checked as per the manufacturer's instructions.
6.7.6. POWER SUPPLIES
The central instrument power supply shall be checked against the terminal layout drawings for correct connection, fuses and texturing.
Automatic changeovers in this area shall be tested by simulation.
The outgoing feeders shall be put into operation one after the other.
6.8. INSPECTION FOR INSTRUMENT SUPPLIED WITHIN PACKAGE UNIT
All instruments supplied within package units shall be accurately checked and shall be subjected to the same preliminary inspection as stated above.
6.9. INSPECTION REPORTS
6.9.1. For each instrument, inspection certificate shall be generated by the contractor. The certificate shall contain all inspection done on a particular instrument including pressure test, Flushing, calibration, loop check etc. The certificate shall be jointly approved by contractor's authorized inspector and Owners inspector. This shall be generated in an electronic file format and handed over to the owner in a electronic media in addition to the approved hard copy.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 35 of 64
6.9.2. Inspection reports will be filled up by the inspector and signed by the inspector of both parties.
6.10. TEST RESULTS
6.10.1. SUCCESS OF INSPECTION
The inspection is considered successful when this is expressly stated in the report and the tested object is approved for use jointly by the contractors inspectors and owners inspections. Faults not requiring re-inspection and having no influence on the use of the test object in respect of its function and safety shall be appropriately entered in the report. An inspection passed sticker shall be put on the instrument after every stage of inspection is successful.
6.10.2. UNSUCCESSFUL TEST
The test is considered unsuccessful when the type and number of defects do not permit the targets of the inspection to be reached or do not allow the inspected object to be used.
Further re-inspections necessitated by the requirements not being met or the tested object being defective have to be done by the Contractor without any cost to the Owner.
6.10.3. CHECK TO ELIMINATE REMAINING DEFECTS
Defects remaining from the above inspections shall be eliminated before a stipulated date.
6.10.4. INSPECTIONS WITH THE Owner AND AUTHORITIES
In accordance with the contract and irrespective of the above inspections, other inspections may be required by the authorities and the Owner to take over the plant.
In such cases, the Contractor shall provide the same personnel and technical prerequisites as for the foregoing inspections.
6.11. OVERALL INSTALLATION CERTIFICATE
After completion of the inspecting, the Contractor shall provide an inspection certificate confirming that the instruments have been installed in conformity with the requirements for hazardous areas.
6.12. STARTUP PERSONNEL
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 36 of 64
The Contractor shall make the requisite number of qualified personnel available for the inspection to support the startup personnel.
The number and selection shall be agreed with the Contractors site management and the Owner.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 37 of 64
7. ELECTRICAL AND COMMUNICATION FACILITIES
7.1. SCOPE
7.1.1. This part of the specification defines Contractors responsibilities and procedures for the testing of electrical and communication installations at site, prior to completely energizing an integrated electrical and/or communication system.
7.1.2. The scope makes no claim to completeness. This Contractor is responsible for covering in his detailed field inspection procedure and/or specifications all necessary test requirements to guarantee that all equipment and material is of first-class quality and successfully inspected and tested.
7.1.3. All field inspections and tests shall be carried out according to the contract requirements, the applicable IEC-Standards-which shall have priority-followed by certain national standards as specified in the project specification EE-001 General Electrical Design Specification.
7.1.4. Test instructions by the equipment manufacturer shall have priority. Tests which are necessary to retain the manufacturer's guarantee shall be conducted by an authorized manufacturer's representation.
7.2. GENERAL
7.2.1. The test methods applied and the test instruments used shall follow the most modern test practice. In view of their great variety, no reference is made here to any specific type thereof.
7.2.2. Setting and calibrating of protective relays shall only be performed by Contractors personnel especially qualified for this function.
7.2.3. Contractor shall exercise care in performing the tests specified so as not to jeopardize the safety of personnel.
All exposed live parts subjected to testing shall be guarded by personnel, barricades, or other practical means to ensure against personnel being injured by coming in contact or too close proximity to exposed parts.
All equipment, exposed live parts, etc. shall be completely discharged by grounding or other accepted methods so as to eliminate the possibility of injury to personnel from electrical shock after the tests have been completed.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 38 of 64
Equipment under test shall be isolated from remote control or feedback circuits to prevent accidental energization by others.
7.2.4. Contractor is responsible for preparing records for all tests and inspections, with complete data on all reading taken and incorporating these in a report for each piece of equipment or item tested.
Test reports shall be signed by the witness heretofore mentioned and approved by the designated representative of Owner.
Normally, the results of all inspections and tests or commissioning functions, such as megger testing of motor or motor feeder and control cables, may be grouped on a single record form.
As a minimum, the records shall contain the following information:
Description of the test or commissioning function, data performed and identification of the test equipment used
Applicable ratings, equipment numbers and location of the facilities
Size, length and rating of cables: whether cables are shielded or unshielded; and manufacturer's test values for medium-voltage cables
Ambient temperature and humidity, where applicable to the particular test or commissioning function
Minimum test values acceptable in compliance with project specifications
Test results, including comments where necessary for clarification
Details of any corrective actions taken
Results after corrective actions have been taken
Signature of Contractors representative and/or Owner.
During each of the inspections and tests, Contractor shall maintain a comprehensive set of test reports defining the specific condition in which the apparatus is left, after it has been given approvals for use in its intended service. The completed reports shall become the property of Owner.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 39 of 64
Among the specific testing requirements to determine the operational conditions of the equipment relative to that particular apparatus, all items shall be visually inspected and evaluated in the report as to the general exterior and interior condition.
A checklist-type report for each major electrical equipment item should be headed with, but not limited to the following identification data:
Equipment name
Tag number
Application
Plant location
Voltage rating
Date of test
Ambient conditions
Tester's signature
Contractors witness signature
7.3. REASONS, TYPES AND PREREQUISITES OF SITE INSPECTION AND TESTS
7.3.1. INSPECTIONS AND/OR TESTS MAY BE REQUIRED FOR THE FOLLOWING REASONS:
Interim inspection/test (depending on the object, the installation sequence or the contract) for internal and external functions
Check of mechanical completion (main inspection)
Pre-commissioning tests (energizing of single or integral systems)
Inspection together with Owner and authorities
Inspection to ascertain that remaining defects have been corrected
Checking document revisions.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 40 of 64
7.3.2. THE INSPECTIONS AND/OR TESTS ARE SUBDIVIDED INTO THE FOLLOWING TYPES:
Visual inspections
Mechanical inspections
Electrical function tests
Electrical operating functions
Measurements
7.3.3. Contractor shall take all necessary measures to ensure a smooth and successful inspection/test. The following prerequisites shall be met:
Completeness of the object as notified
Presentation of the relevant engineering documents
Experienced inspection personnel commanding the specific skills required for the project
Proper safety precautions for the test/inspection location
Suitable testing equipment, auxiliaries and utilities
Description of the testing procedure before the tests and undertaken
Preparation for recording
7.4. AS AN INTEGRAL PART OF ALL PARTICULAR SITE INSPECTIONS AND TESTS, CONTRACTOR SHALL BE RESPONSIBLE FOR THE FOLLOWING:
7.4.1. VISUAL INSPECTIONS:
Intactness from receipt of goods until the custody date as per the Contract expires
Completeness as specified in the shipping documents and Specification
Presentation of a coordinated Program of Tests and Inspections
Completeness of the installation, testing and commissioning documents, including all special provisions
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 41 of 64
Conformity of essential data and characteristics with the working documents
Legibility of test plates and nameplates
Correction of all defects from previous inspections on the basis of the relegate inspection reports
Correctness of all subsequently installed or connected items
Checking that all unnoticeable inlets are properly closed
Proper sealing of all cable inlets
Completeness of all supplementary services rendered at site (finishing coat of paint, covers, inscriptions, etc.)
Removal of holding-down devices
Filling of lubricating, insulating and sealing media and checking their levels
Availability of special tools, wrenches, etc.
Compliance with materials and manufacturer's instruction for auxiliary installation materials
Maintaining distances required for safety, operation and maintenance
Proper condition and function of testing equipment
Usability of escape routes
Availability of first-aid facilities
7.4.2. MECHANICAL CHECKS
Checking movements as well as rigid or detachable connections, in conjunction with a previous or simultaneous visual inspection:
Firm installation of the fixing device and the attached parts on the base structure
Sufficient play of flexible connections and moving parts
Checking defined movements including intermediate and extreme positions, including specified interlocks
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 42 of 64
Firm seating of plug-in components including check of unobstructed space to remove these components
Safety of operation and handling
Adjusting zero position, readings for minimum / maximum / normal conditions according to the specification for all instruments
Checking of all mechanical interlocks
Firm, secured seating of covers
Firm re-fixing or re-closing after visual inspection of concealed components
Conditions of conductor connections e.g. damaged conductor or conductor insulation
Effectiveness of stress-relieving measures on cables and wiring
7.4.3. ELECTRICAL TEST FUNCTIONS
Using voltages and currents to test (cold check) individual equipment items or groups of items for their immediate functions; such tests are normally carried out during intermediate inspections. Previous or simultaneous visual inspections are a prerequisite.
Defining an optimum test sequence under technical and economic aspects
Checking safety requirements with respect to location and test instruments
Informing or inviting the relevant installation supervisor of adjoining systems
Checking covers and insulation of live parts, in particular, of outgoing cables
Defining the necessary or permissible operating and test voltages/currents
Checking function bridging for compliance with protective requirements
Measurements and certification of electrical insulating capacity before connecting operating and auxiliary voltage
Performing functions according to descriptions and checking negative functions (interlocks, etc.)
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 43 of 64
Checking indicating instruments for conformity with switching and operating conditions
Recording modified functions or corrections at the installation
Marking tested circuits, indicating test results, in particular, until critical functions are eliminated
Removing temporary test facilities (bridges, etc.) or marking these facilities
Disconnecting current and voltages and safe-guarding the switches against unauthorized re-connection, or marking connected currents/voltages and safeguarding them against unauthorized disconnection
7.4.4. ELECTRICAL OPERATING FUNCTIONS
Tests under Operating Conditions ("Hot Check") in connection with preceding or subsequent systems on the occasion of main inspections and system connections. All electrical test functions must have been successfully completed and recorded.
Analogous observance and application of the procedures for test functions
Preparation of the operating circuits to be tested
Specification of emergency measures to avoid hazards to personnel or property
Coordination with the authorized commissioning supervisor of connected systems
Specification of the loads and time periods for the tests (no load, partial load, rated load, over-load, initial loading, re-loading and intervals)
Loading of operating circuits while observing the operation and the measuring and indicating instruments
Optimization of set points
Connection of individual units to systems
Checking redundant systems
Simulation of malfunctions, considering the functions of monitoring and signal circuits
Testing of special measures
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 44 of 64
Shut-down of the operating circuit and safeguarding against unauthorized pre-commissioning, or clarifying responsibilities if operation is maintained, and safeguarding against unauthorized shut down.
7.4.5. MEASUREMENTS
Marking quality measurements in connection with test operation (guarantee run) and certifying compliance with requirements:
Checking the measuring set-up, the transmission ratio and the accuracy according to the applicable test instructions and procedures
Recording the measuring set-up and the operating conditions including ambient conditions
Recording the actual measured value
Comparison between actual and specified values and evaluation of tolerances
Checking against permissible + tolerances
Reasons for higher but justifiable deviations
Specifying corrective measures in case of unacceptable deviations
Restoring the object to normal condition after the measurements has been completed
7.5. SPECIFIC REQUIREMENTS FOR FIELD INSPECTIONS AND TESTS OF ELECTRICAL AND COMMUNICATION EQUIPMENT
In the absence of specific manufacturer's instructions, the following tests and inspections shall be performed, but not limited to:
7.5.1. POWER TRANSFORMER
All transformers shall be inspected after installation for:
Damage incurred in transportation
Inspect bushings for chips or cracks
Inspect all gaskets, fittings and radiators for leaks*
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 45 of 64
Check liquid level*
Check mountings for cooling fan, resistor and other accessories
Check out and test cooling fan, control wiring in accordance with applicable parts of this specification
Function-test cooling fan and/or circuits
Check on-load tap changer for proper movement
No leakage of oil
Earthing shall be good condition
Check operation of temperature indicator, pressure relay and other devices
Check operation of pressure relief valve as recommended by the manufacturer*
Note: [*] For liquid-immersed transformer only
All transformers shall be subjected to one-minute megger tests. These shall be performed winding to winding, winding to ground, and including any taps for voltage adjustment.
In addition to the megger tests, high-potential tests shall be performed:
The sequence of megger and high-potential tests shall be:
Megger tests shall be made to determine the condition of the insulation.
The high-potential tests shall be applied only if the megger test passes minimum requirements.
The successful high-potential test shall be followed immediately by another megger test in order to detect any damage incurred by high-voltage stresses.
Each secondary winding of a transformer operating at 380 volts shall be given a megger test only. The test shall include any taps for voltage adjustment.
Megger and high-potential tests on each transformer winding shall be applied between all phases tied together and ground. All windings and adjacent cables or breaker contacts not included in the test shall be grounded.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 46 of 64
Grounding resistors, when used, shall be given megger and high-potential tests. With the neutral grounding resistor lead disconnected from the transformer neutral and the ground side of the resistor and cable, the resistor shall be given a megger test. The resistor housing shall be tied to the test ground.
All control, alarm and metering circuits shall be checked.
The results of all tests shall be in accordance with the manufacture's recommendations.
Transformers larger than 2000 kVA or with windings rated 30kV and higher shall be subjected to a polarization Index. This shall be the ratio of ten-minute to one-minute insulation resistance readings. A 500 volt megger shall be used for windings less than 660 volts. A 2500 volts and higher shall be used for windings higher than 660 volts. Conditions of the insulation shall be indicated as follows:
CONDITION POLARIZATION INDEX
Good 2 and greater
Questionable 1 to 2
Very poor 1 and less
Note: Transformers that are "questionable" shall be reviewed by Contractor. Transformers rated "very poor" shall not be energized. The manufacturer shall be contacted for directions to dry out.
Transformer shall be tested winding resistance test and shall record the values of winding resistance. The values shall be compared with the reports of manufacture.
All transformers shall be tested polarized index test as the following test, but not limited to:
A 10/1 minute polarization index shall be taken for each winding of equipment rated more than 660 volts. If this indicates "Questionable", the cause shall be determined and action taken as determined by Contractor of his designee. If a winding is indicated "Poor", the equipment shall be dried out in accordance with instructions from the manufacturer. The ratios and indicated relative conditions of the insulation are given below.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 47 of 64
For equipment rated 660 to 6,600 volts, both the dielectric absorption and polarization index rations shall be taken. A polarization index shall be taken for equipment 660 volts and less with unacceptable insulation resistance.
INSULATION CONDITION 60/30 SECOND RATIO DIELECTRIC ABSORPTION 10/1 MINUTE RATIO
POLARIZATION INDEX
Dangerous - Less than 1
Poor Less than 1.1 Less than 1.5
Questionable 1.1 to 1.25 1.5 to 2
Fair 1.25 to 1.4 2 to 3
Good 1.4 to 1.6 3 to 4
Excellent Above 1.6 Above 4
Equipment rated less than 660 volts with insulation resistance less than 1 megaohms or insulation condition less than "fair" shall be dried out. Instructions for dry-out shall be obtained from the equipment manufacturer.
Equipment rated more than 6,600 volts or more than 5,000 kW or more than 5,000 kVA shall be subjected to a polarization index and a high direct voltage step test. The procedure and criteria shall be in accordance with the recommended values suggested by the manufacturers.
Exciting test by low voltage.
All transformers shall tested oil test as the clause 8.5.5.
Test and calibration temperature controller.
7.5.2. LV AND MV SWITCH GEAR AND CONTROL GEAR:
Each lineup of switch gear, low-voltage and medium high voltage motor control centers shall be inspected for shipping and handling damage, for mechanical completeness and made ready for operation including the following:
Check connections and test ground busses
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 48 of 64
Check mechanical operation of all breakers, contactors and auxiliary devices
Check and alignment of drawout type equipment including floor steel, main and auxiliary contactors, shutter position indicators, operating linkages, cell and removable element alignment as necessary per manufacturer's instructions, adjust manuals and recommendations
Verify by test the ratio and polarity marking of all current and potential transformers, according to item 8.5.7, for protective relaying and metering
Protective relays such as overcurrent, differential, under-voltage relays, etc. and meters shall be set and functionally tested as outlined in the sections on protective relays and functional testing.
Check selection of thermal overload elements against values shown on the drawings and thermal overload shall be tested as the following test, but not limited to:
(1) Mechanical trip test
(2) Insulation resistance shall be one minute megger test from phase to phase and phase to ground. Insulation resistance shall be recorded. The values of insulation resistance shall be a minimum as per TABLE 1.
(3) Individual pole resistance shall be tested and recorded the values in each pole of relay.
(4) Time delay over current trip shall be tested and recorded the values to compare with standard values.
(5) Instantaneous over current trip test.
(6) Rated current hold in test shall be tested at rated current.
Check settings of circuit breakers
Test and set power breaker trips in accordance with the drawings.
All LV and MV switchgears and control gear shall be tested commissioning test according to the following mention:
(1) Function test of each relay which coordinated with circuit breaker.
(2) Primary injection.
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 49 of 64
(3) Secondary injection.
Check phasing of busses
Function-test all control circuits, protective circuits, powered devices and powered equipment-Ring-out all multiconductor cables and busses
Check out all phasing where more than one supply can be connected to the equipment
Check all fuses.
Testing shall be performed as follows:
Before connecting cables or busses to the switch gear terminals, the insulation resistance of all bus and current carrying paths shall be measured. One-minute megger tests from phase to phase and phase to ground shall be made with a minimum of:
Table 1
Equipment ac rating (volts) 660 and less 660 to 35,000
Megger Rating (Volts) 500 2500 Minimum Resistance (Mega-ohms) 10 400
Before energizing, the insulation resistance of each removable element shall be measured. The element shall be removed from the cell for this test.
Measurements shall be a minimum of the values indicate above.
Oil-immersed equipment shall also be sampled and tested for insulating liquid in accordance with clause 8.5.5
Switch gear, not including motor control, rated 6,600 volts and higher shall also be subjected to a power frequency voltage test according to IEC-298 and IEC- 694.
Prior to energizing the switch gear bus, the following items shall be inspected and tested for proper operation
Control, protective and metering circuit
LSP COMPLEX PROJECT
Package A Olefins and Central Utility Plant ITB Volume I Annex C Rev.: 0
Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 50 of 64
All current transformers shall be tested according to clause 8.5.7 and verify that relays and meters (as applicable) operate properly.
All potential transformers shall be tested according to clause 8.5.7 and verify that relay and meters (as applicable) operate properly.
7.5.3. CIRCUIT BREAKER
All circuit breakers shall be tested as the following test, but not limit to:
Insulation resistance shall be one minute megger test from phase to phase and phase to ground. Insulation resistance shall be recorded. The values of insulation resistance shall be a minimum as per table 1.
Each circuit breaker shall be tested insulation power factor test before energizing.
Moisture content test for SF6 circuit breaker.
Contact Resistance in each phase of circuit breaker shall be tested and the resistance shall not more than test reports from manufacturer.
Closing and tripping time test in each phase of circuit.
Withstand Voltage test for VCCB.
7.5.4. MOLDED CASE CIRCUIT BREAKER
All molded case circuit breakers shall be tested as the following test, but not limited to:
Insulation resistance shall be one minute megger test from phase to phase and phase to ground, Insulation resistance values shall be recorded the values of insulation resistance shall be minimum as per table 1.
Contact resistance