64
LSP COMPLEX PROJECT Package A – Olefins and Central Utility Plant ITB Volume I – Annex C Rev.: 0 Long Son Petrochemicals Co., Ltd Document No.: CON - 006 Sheet: 1 of 64 ________________________________________________________________________________________________ Confidential : This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd. PROJECT TECHNICAL SPECIFICATION CON – 006 SITE INSPECTION AND TESTING 0 15/09/2009 ISSUE FOR LSP PROJECT HHM PCS REV. DATE DESCRIPTION PREPARED CHECKED APPROVED

CON-006 Site Inspection and Testing Rev.00

Embed Size (px)

DESCRIPTION

fa

Citation preview

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 1 of 64

________________________________________________________________________________________________

Confidential : This document is confidential and must not be copied or reproduced except with the express

permission of Long Son Petrochemicals Co., Ltd.

PROJECT TECHNICAL SPECIFICATION

CON – 006

SITE INSPECTION AND TESTING

0 15/09/2009 ISSUE FOR LSP PROJECT HHM PCS

REV. DATE DESCRIPTION PREPARED CHECKED APPROVED

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 2 of 64

TABLE OF CONTENTS

1. SCOPE .................................................................................................... 4

1.1. PURPOSE .............................................................................................................. 4

1.2. RESPONSIBILITY .................................................................................................. 4

1.3. CONTRACTOR’s SCOPE OF SERVICE ............................................................... 4

1.4. RELATED ENGINEERING SPECIFICATIONS...................................................... 4

2. GENERAL ............................................ ................................................... 4

2.1. INSPECTION PERSONNEL................................................................................... 4

2.2. WELDING INSPECTION ........................................................................................ 4

2.3. WELDING PROCEDURE ....................................................................................... 4

2.4. TESTING ON SITE................................................................................................. 4

2.5. TESTS OUTSIDE THE SITE .................................................................................. 4

2.6. SCOPE OF TESTING............................................................................................. 4

2.7. ACCEPTANCE STANDARD................................................................................... 4

2.8. OWNER INSPECTION ........................................................................................... 4

2.9. DOCUMENTATION ................................................................................................ 4

3. PRESSURE VESSELS, HEAT EXCHANGER, AIR COOLERS ...... ....... 4

3.1. GENERAL............................................................................................................... 4

3.2. FIELD WELDS ........................................................................................................ 4

3.3. TESTING OF FIELD WELD.................................................................................... 4

3.4. PRESSURE TESTING............................................................................................ 4

3.5. DOCUMENTATION ................................................................................................ 4

3.6. STORAGE TANKS ................................................................................................. 4

4. MECHANICAL EQUIPMENTS.............................. .................................. 4

4.1. GENERAL............................................................................................................... 4

4.2. PUMPS (CENTRIFUGAL, RECIPROCATING, METERING, POSITIVE DIPLACEMENT PUMPS, EXCLUDING FIRE WATER PUMPS)..................................................... 4

4.3. FIRE WATER PUMPS, INCLUDING DIESEL ENGINES....................................... 4

4.4. CENTRIFUGAL COMPRESSORS AND DRIVERS, EXCEPT INSTRUMENT AIR COMPRESSORS................................................................................................... 4

4.5. INSTRUMENT AIR COMPRESSORS, INCLUDING DRYERS.............................. 4

4.6. RECIPROCATING OXYGEN COMPRESSORS.................................................... 4

4.7. GENERAL AND SPECIAL PURPOSE STEAM TURBINES .................................. 4

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 3 of 64

4.8. INDUSTRIAL COMBUSTION GAS TURBINES ..................................................... 4

4.9. CENTRIFUGAL FANS ............................................................................................ 4

4.10. LUBE OIL AND SEAL OIL SYSTEM ...................................................................... 4

5. PIPING .................................................................................................... 4

5.1. GENERAL............................................................................................................... 4

5.2. ORGANIZATION AND RESPONSIBILITY ............................................................. 4

5.3. CHECK OF MATERIALS RECEIVED .................................................................... 4

5.4. PREFABRICATION ................................................................................................ 4

5.5. WELDING ............................................................................................................... 4

5.6. TESTS AND EXAMINATIONS ............................................................................... 4

5.7. SCOPE OF “RT” TESTING..................................................................................... 4

5.8. EVALUATION CRITERIA ....................................................................................... 4

5.9. REPAIRS ................................................................................................................ 4

5.10. CHECK OF PIPING COMPONENTS ..................................................................... 4

5.11. PRESSURE AND LEAK TESTS............................................................................. 4

5.12. FLUSHING, PICKLING, DRYING........................................................................... 4

5.13. PAINTING AND INSULATION................................................................................ 4

5.14. MECHANICAL COMPLETION ............................................................................... 4

6. INSTRUMENTATION .............................................................................. 4

6.1. GENERAL............................................................................................................... 4

6.2. DEFINITIONS ......................................................................................................... 4

6.3. INSPECTION AND TESTING DOCUMENTS ........................................................ 4

6.4. INSPECTION AND TESTING REQUIREMENTS .................................................. 4

6.5. INSPECTION AND TESTING BEFORE INSTALLATION COMMENCEMENT ..... 4

6.6. INSPECTION AFTER INSTALLATION COMMENCEMENT.................................. 4

6.7. TESTING AFTER INSTALLATION COMMENCEMENT ........................................ 4

6.8. INSPECTION FOR INSTRUMENT SUPPLIED WITHIN PACKAGE UNIT............ 4

6.9. INSPECTION REPORTS........................................................................................ 4

6.10. TEST RESULTS ..................................................................................................... 4

6.11. OVERALL INSTALLATION CERTIFICATE............................................................ 4

6.12. STARTUP PERSONNEL........................................................................................ 4

7. ELECTRICAL AND COMMUNICATION FACILITIES............ ................. 4

7.1. SCOPE.................................................................................................................... 4

7.2. GENERAL............................................................................................................... 4

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 4 of 64

7.3. REASONS, TYPES AND PREREQUISITES OF SITE INSPECTION AND TESTS

............................................................................................................................... 4

7.4. AS AN INTEGRAL PART OF ALL PARTICULAR SITE INSPECTIONS AND TESTS, CONTRACTOR SHALL BE RESPONSIBLE FOR THE FOLLOWING: ................ 4

7.5. SPECIFIC REQUIREMENTS FOR FIELD INSPECTIONS AND TESTS OF ELECTRICAL AND COMMUNICATION EQUIPMENT ......................................... 4

8. MISCELLANEOUS ITEMS................................ ...................................... 4

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 5 of 64

1. SCOPE

This Specification stipulates the basic scope of inspection activities for construction work on the

site, irrespective of whether the plant components to be erected arrives on the site as complete,

pre- assembled or semi-finished unit.

1.1. PURPOSE

This specification shall enable the Contractor to incorporate the tests and inspections required

by the OWN E R or the Project Specifications in his scope of services and guarantee.

1.2. RESPONSIBILITY

1.2.1. Compliance by the Contractor with this specification does not relieve him from his responsibility

to determine and include in his services any test activities exceeding the minimum requirements

which, in his opinion, are necessary to fulfill guarantee and prove the quality of construction

work on the site.

1.2.2. The scope makes no claims to completeness. The Contractor is responsible to cover in his

detailed site inspection procedure and/or specifications all necessary test requirements

considering all requirements of this Project Specification, covering also those

equipment/material items which are not specifically mentioned herein.

1.2.3. The Contractor shall guarantee that all equipment/material is of first class quality and

successfully inspected and tested.

1.3. CONTRACTOR'S SCOPE OF SERVICE

The Contractor shall include in his scope of services detailed inspection and test procedures to

be approved by the Owner incorporating also requirements mentioned herein before starting the

construction work. The inspection and test procedures shall include hold points for Owner

inspection.

1.4. RELATED ENGINEERING SPECIFICATIONS

• Project Specification SP-010 Equipment Preservation

• Project Specification SP-009 Painting

• Project Specification SP-006 Thermo Insulation Design

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 6 of 64

• ME-002 Storage Tank

• CON-010 Fabrication and Field Works of Piping

• EE-001 General Electrical Design Specification

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 7 of 64

2. GENERAL

2.1. INSPECTION PERSONNEL

2.1.1. The Contractor shall prepare organization schedules showing the responsibilities of the

inspection personnel. An assigned chief inspector is fully responsible for the following tasks

independently of the Site Management.

• The inspection personnel shall be trained and qualified for the work to be performed by

them.

• All necessary specifications and applicable Codes shall be made available by Contractor

on site.

• Tests and inspections shall be carried out in conformation with their Codes and

Standards and related specifications.

• The test equipments to be used shall meet the local laws and regulations. (Evaluate test

results are a prerequisite for the selection of the test equipments)

• Scope and sequence of testing shall be adhered to.

2.1.2. The Contractor is responsible for inviting the Third Party inspector to the test and assuring the

proper performance of the testing activities.

2.1.3. Owner shall always have the right to approve or reject inspection personnel of Contractor

without clarification.

2.2. WELDING INSPECTION

2.2.1. The Contractor shall assign a weld inspection group to report to the chief inspector. The weld

inspection group has the right to give instructions regarding:

• Storage and selection of the welding filler metals and auxiliaries

• Pre- and post- weld heat treatment

• Welders’ performance qualifications

• Assignment of welders

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 8 of 64

• Welding equipments

• Checking the repair procedure and repair work

• Welding documentation

2.2.2. All reports carried by chief inspector shall be also available to Owner representation.

2.3. WELDING PROCEDURE

2.3.1. The Contractor shall supply and prepare welding procedures for field welding showing the:

• Welding method

• Welding filler metals

• Qualification of the welders (including welding test specimens)

• Weld shape

• Welding sequence and position

• Pre- and post- weld heat treatment

• Weld examination and evaluation criteria

• Scope of weld examination

2.3.2. The welding inspector shall check that the welding data sheets are adhered to during welding

regarding the welders, welding procedures, filler metals and weld tests, the requirements of the

Project Specification for Welding.

2.3.3. For materials which are not covered by ASTM, the Contractor shall furnish material specific

processing documentation from the Vendor for Owner approval prior to use.

2.4. TESTING ON SITE

Unless otherwise stipulated in the Project Specifications or Vendor instructions, the following

test shall be made:

2.4.1. Destructive tests shall be made in accordance with the requirements specified in ASTM A to G.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 9 of 64

2.4.2. Non-destructive tests shall be made in accordance with the requirements specified in ASME

Section V.

2.5. TESTS OUTSIDE THE SITE

If tests which have been specified cannot be performed on the Site, they shall be made in

accordance with Paragraph 2.4 by a test institute approved by the chief inspector without

additional cost to the Owner.

2.6. SCOPE OF TESTING

2.6.1. The scope of testing is taken from the Project Specifications, Codes and Standards or this

Specification.

2.6.2. The scope of testing may be extended if it is required more by quality assurance. The new

scope of testing shall then be established jointly by the chief inspector and the weld inspection

group.

2.6.3. The Owner shall be informed thereof in writing.

2.7. ACCEPTANCE STANDARD

2.7.1. The acceptance standard is laid down in the Project Specifications, Codes and Standards and

shall be strictly adhered to.

2.7.2. In case of doubt, the requirements of the Codes and Standards shall apply Paragraph 2.8

Owner INSPECTION.

2.8. OWNER INSPECTION

2.8.1. The Owner and/or its representative may witness the tests and inspections at their own

discretion.

2.8.2. The Contractor shall submit FIELD INSPECTION NOTICE (FIN) to the Owner by daily basis for

field inspection. Other than field inspection, FIN shall be submitted to the Owner not later than 5

working days prior to scheduled inspection date.

2.8.3. The Owner has the right to have tests repeated on Contractor’s cost if FIN is not submitted in

time.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 10 of 64

2.9. DOCUMENTATION

2.9.1. All test results shall be entered in forms issued for the particular tests. The forms shall be

signed by the authorized person.

2.9.2. The test reports shall clearly refer to the object tested.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 11 of 64

3. PRESSURE VESSELS, HEAT EXCHANGER, AIR COOLERS

3.1. GENERAL

3.1.1. This chapter applies to tests and inspections of field welds on pressure vessels.

3.1.2. Generally, these plant components except storage tanks are delivered completely to the Site.

For the usual piping connection work, the requirements given in Paragraph 5 of this

Specification shall be observed.

3.2. FIELD WELDS

3.2.1. If field welds are necessary, the Vendor’s instructions and the Project Specifications shall be

complied with.

3.2.2. The weld inspection group shall check the work documentation and supervises welding and any

possible heat treatments and testing.

3.2.3. If any subsequent repairs to plant components are required on site, the repair procedure is part

of the Vendor’s scope. The weld inspection group shall check the Vendor’s repair instructions

for suitably supervise the repair work and report the results to Owner.

3.2.4. Auxiliary structures and transport devices which are welded directly to pressure walls of the

plant component and must be removed shall not be knocked off. They shall be removed

mechanically and the connection points on the pressure wall shall be ground flushed and

checked for cracks. Repair welding requires the procedure approved by Owner prior to start of

the work.

3.2.5. Welding on plant components subjected to final heat treatment at the Vendor’s works is not

permitted in any case.

3.3. TESTING OF FIELD WELD

3.3.1. SCOPE OF TESTING

• Generally, all field welds of pressure parts shall be 100 % tested. Butt welds shall be

radiographic tested as per codes and standards. Fillet welds of austenitic and non-

magnetic materials shall be liquid penetrant tested.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 12 of 64

• Carbon steel fillet welds shall be subjected to a magnetic particle examination.

3.3.2. ACCEPTANCE STANDARD

The ASME Code shall be the basis for evaluating the welds to be examined.

3.4. PRESSURE TESTING

If pressure testing after welding is required, Paragraph 7.4 of the Project Specification shall be

applied.

3.5. DOCUMENTATION

All test activities and results shall be documented. The activities prior to mechanical completion

shall be included.

3.6. STORAGE TANKS

3.6.1. Delivery, fabrication and testing on the site shall be accordance with the requirements of Project

Specification. The Contractor’s weld inspection group shall assure that the instructions from the

tank Vendor are complied with.

3.6.2. The tank Vendor shall advise the Contractor’s weld inspection group all of tests to be made in

the course of fabrication. If the test results do not meet the specified quality standard, the scope

of testing shall be taken by the Contractor’s chief inspector after consultation with the welding

supervisors and weld inspection group.

3.6.3. All test results and dimensional checks shall be recorded according to Paragraph 2.9 and 3.5.

3.6.4. Spherical tanks containing liquefied hydrocarbon and / or substances governed by local laws

and regulations shall be performed the inspection and test as required by the regulations or the

project specification ME-002 Storage Tank whichever is more stringent. The Contractor shall be

responsible for all works and cooperating with government's inspector as his satisfaction to

achieve government approval and certificate for such storage tanks.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 13 of 64

4. MECHANICAL EQUIPMENTS

4.1. GENERAL

This chapter applies to the field tests and inspections for the mechanical equipments.

4.1.1. Detailed test procedures shall be prepared by the Contractor and submitted to the Owner for

review prior to start the construction work.

4.1.2. Prior to the test runs for each machine the Contractor shall submit to the Owner the following

certificates:

• Alignment protocol

• Protocol of stress-free pipe connection

• Internal inspection report (cleaning, clearance check etc.)

If applicable, in addition, the Contractor has to deliver certificates for hydrostatic pressure test,

radiographic examination of welds, liquid penetrant examination, etc.

4.1.3. A detailed check list has to be prepared by Contractor for the individual steps from the

beginning of the erection up to the tests under operating conditions. The check list shall also

contain information about the function and tightness of the mechanical seal, vibration of the

machine for the specified operating range, etc.

4.1.4. Detailed records of the test runs containing capacity, pressures, temperatures, vibrations,

electric current consumption, steam consumption, cooling water consumption, etc. shall be

prepared by the Contractor during the individual tests of the equipment and submitted to the

Owner for approval.

4.1.5. Prior to test run of the machinery, the interlocking control electrical safety protection system,

and observation system shall be checked for function and used during the test runs of the

machinery.

• If machines are tested with fluid other than the operating product, some functions of the

interlocking system which can't be used have to be bridged.

• Before carrying out tests on the machines with the original media/gases all functions of

the interlocking system shall be checked for function and used.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 14 of 64

4.1.6. If during the specified test duration the test has to be stopped due to machinery failures, the test

run has to be repeated after all causes have been corrected.

4.1.7. If there is any deviations in this specification due to operation condition and a circumstance.

Contractor shall inform to Owner and shall then discuss with Owner regarding correct action

such as test duration, test method, etc. for Owner approval.

4.2. PUMPS (CENTRIFUGAL, RECIPROCATING, METERING, P OSITIVE DIPLACEMENT PUMPS, EXCLUDING FIRE WATER PUMPS)

4.2.1. All pumps shall be mechanically tested with water or suitable fluids specified by the Contractor

for at least 4 hours of continuous operation. Every hour bearing temperature and vibration shall

be recorded.

4.2.2. All pumps shall be subjected to a performance test of at least 14 days of continuous operation

under operating conditions. If one operating and one stand-by pump are installed they are

required to change over from operating to standby after two weeks.

4.3. FIRE WATER PUMPS, INCLUDING DIESEL ENGINES

4.3.1. A mechanical test run of at least 4 hours shall be performed with the diesel engine according to

ISO 3046. For the diesel engine of the fire pump system, a mechanical test run of at least 4

hours shall be performed, according to ISO 3046.

4.3.2. Complete fire water pumps with diesel engine shall be tested under operating conditions for at

least 14 days, according to NFPA 20.

4.4. CENTRIFUGAL COMPRESSORS AND DRIVERS, EXCEPT IN STRUMENT AIR COMPRESSORS

4.4.1. The mechanical test run for all centrifugal compressor units shall be carried out with air or any

other suitable fluid specified by the Contractor for at least 48 hours of continuous operation.

When abnormal condition is found, during the mechanical test run, detailed check shall be

carried out for corrective action.

4.4.2. All centrifugal compressor units shall be tested with the original gas under operating conditions

for at least 14 days of continuous operation.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 15 of 64

4.5. INSTRUMENT AIR COMPRESSORS, INCLUDING DRYERS

Each instrument air compressor unit including dryer shall be tested for at least 14 days of

continuous operation under operating conditions.

4.6. RECIPROCATING OXYGEN COMPRESSORS

4.6.1. Mechanical test runs and initial oxygen runs shall be performed in according with IGC-Standard

10/81 section 6.2 and instructions from machine Vendor.

4.6.2. The following additions shall apply to IGC-Standard 10/81, section 6.2 Site work:

• (Clarification)

A mechanical test run of at least 48 hours continuous operation shall be performed. After

the 48-hour test run, the valves, piston and bearings of the machine shall be visually

inspected.

• (Clarification)

The oxygen test run shall be performed for at least 14 days continuous operation.

4.7. GENERAL AND SPECIAL PURPOSE STEAM TURBINES

4.7.1. All general-purpose steam turbines shall be mechanically tested for at least 4 hours of

continuous operation.

• Every hour bearing temperature and vibration shall be recorded.

• Before mechanical test, the trip speed of the turbine shall be tested at least 3 times.

4.7.2. General purpose steam turbines and special-purpose steam turbines equipped with oil systems

which is according to API 614 excluding gear type turbines shall be mechanically tested for at

least 6 hours' continuous operation. Every hour bearing temperature and vibration shall be

recorded.

When abnormal condition is found, during the mechanical test run, the bearings and blades of

all steam turbines shall be visually inspected.

4.7.3. All general and special-purpose steam turbines shall be tested for at least 14 days of

continuous operation under operating conditions together with the driven machine.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 16 of 64

4.8. INDUSTRIAL COMBUSTION GAS TURBINES

4.8.1. Each gas turbine shall be mechanically tested with the driven machine for at least 48 hours of

continuous operation. Before this test run, the trip speed must be tested.

After the mechanical test run, bearings of the turbine and the gear shall be visually inspected.

4.8.2. Each gas turbine shall be tested for at least 14 days continuous operation under operating

conditions together with the driven machine.

4.9. CENTRIFUGAL FANS

4.9.1. All centrifugal fans shall be mechanically tested for at least 4 hours of continuous operation with

all its auxiliaries. Every hour bearing temperature and vibration shall be recorded.

4.9.2. When abnormal condition is found, during the mechanical test run, the bearings of centrifugal

fan shall be visually inspected.

4.9.3. Each centrifugal fan shall be tested for at least 14 days of continuous operation under operating

conditions.

4.10. LUBE OIL AND SEAL OIL SYSTEM

4.10.1. The complete oil unit shall be flushed and cleaned with oil till clear of dirt and debris as specified

by the Contractor/Vendor.

4.10.2. After carrying out the functional tests of the oil system, a test run of at least 14 days continuous

operation shall be performed for the original system using the specified oil.

• The test run to the oil unit shall be carried out in accordance with API 614.

• While the oil unit is flushed the bearing and shaft seals of the lubricated machinery shall

be by-passed.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 17 of 64

5. PIPING

5.1. GENERAL

This chapter applies to the tests and inspections of piping.

5.2. ORGANIZATION AND RESPONSIBILITY

5.2.1. The Contractor shall prepare pertinent organization schedules to guarantee the quality

assurance for prefabrication and final installation of piping. The organization schedules shall

also determine the technical responsibilities.

5.2.2. Regarding the quality assurance of piping installation, the warehouse, prefabrication areas and

other piping assembly areas shall be organized so that quality assurance is guaranteed. For

this, the Contractor shall prepare a detailed procedure.

5.3. CHECK OF MATERIALS RECEIVED

5.3.1. All piping components received shall be checked. The quality and compliance with the Codes

and Standards of all structural parts shall be proved by certificates. Structural parts which do not

meet these requirements must be rejected. Random check for the material specification shall be

done against certificates by Contractor’s cost.

5.3.2. Re-stamping of pipes and elbows shall be done by the pertinent field inspectors.

5.4. PREFABRICATION

5.4.1. Systematic process of parts withdrawn from the site warehouse for prefabrication or final

installation shall be properly handled, protected, stored before their final use.

5.4.2. All piping components shall be preserved. The Contractor shall make appropriate rooms for

prefabrication available. Piping components of carbon steel and of austenitic steel shall be kept

separately in the prefabrication area. The prefabricated piping sections shall be properly stored

such as capping, marking, grouping, etc. before further use.

5.5. WELDING

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 18 of 64

5.5.1. The Contractor shall prepare welding data sheets for the basic material combinations to be

welded. These data sheets shall be based on the Codes and Standards given in the Project

Specifications for welding.

5.5.2. Before starting the welding work, all data sheets, PQR and welders' certificates shall be

submitted to the weld inspection group. If there are any doubts, the weld inspection group shall

check the welder's quality standard by welding test specimens. Wherever possible, welding

shall be limited to prefabrication work.

5.6. TESTS AND EXAMINATIONS

The weld examinations shall be made after the last heat treatment based on the data sheets

and on a test schedule. The examinations shall be performed using test equipment from which

optimal test results for the welds to be examined can be expected. Random test to piping welds

must include all weld joints.

5.6.1. VISUAL CHECK OF WELDS

The examination shall be 100% for all types of welds. The examination shall be carried out

according to ASME Boiler and Pressure Vessel Code (BPVC) Section V, Article 9.

5.6.2. BUTT WELDS

• Radiographic examination shall be performed in accordance with:

• ASME Section V, Article 2

• Paragraph 341.3.2 and Paragraph 344.5 of ASME B31.3

• Paragraph 136.4.5 of ASME B31.1.

• The scope of the random test has to be extended by Contractor as per ASME B31.3,

Paragraph 341.3.4 if the test results show that the welds are not free of unacceptable

defects.

5.6.3. EXAMINATION OF FILLET WELDS

• The fillet welds shall be subjected to a magnetic particle or liquid penetrant examination.

The liquid penetrant method is being used for nonmagnetic materials. The examination is

made as per Boiler and Pressure Vessel Code.

• Article 7, Section V for Magnetic Particle method

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 19 of 64

• Article 6, Section V for Liquid Penetrant method.

• Welds subjected to heat treatment, may be radio-graphed prior to the last heat treatment,

if after the heat treatment an additional liquid penetrant examination is made.

5.6.4. HARDNESS TEST

If a heat treatment is required by ANSI/ASME B 31.3 Chapter V, 331.1.1 and Table 331.1.1, the

hardness of the weld shall be verified. If piping material and weldment to be expanded to sour

environment, hardness shall be verified as requirement of NACE standard MR0175-94.

5.7. SCOPE OF “RT” TESTING

The scope of testing for the materials/combination used shall be determined by the Contractor

appropriate to the stress to which the material is exposed. The scope of testing in general shall

be conformed to CON-010 Fabrication and Field Works of Piping.

5.8. EVALUATION CRITERIA

5.8.1. For all welds, the error limits as per ANSI/ASME B 31.3, Chapter V, 328; ANSI/ASME Chapter

VI, 341,344 shall be adhered to.

5.8.2. The maximum hardness values are to be taken from the ASME 31.3, Table 331.1.1 and NACE

standard MR0175-94.

5.9. REPAIRS

The repairs shall be made in accordance with ASME B31.3, Chapter V, 328.6.

5.10. CHECK OF PIPING COMPONENTS

The Contractor’s piping specialists shall check the installed piping components for compliance

with the P & I diagrams, piping drawings, isometric drawings and bills of materials. If any

doubts, material mix up test shall be made.

5.11. PRESSURE AND LEAK TESTS

5.11.1. The Contractor’s piping specialists shall compile pressure test systems before starting the

pressure tests. After completion of all welding, heat treatment and testing of the systems to be

pressure-tested, the weld inspection group shall give the approval for pressure testing. The

pressure testing shall be made according to ASME B31.3, Chapter VI, 345.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 20 of 64

5.11.2. The water to be used for the hydrostatic test shall be specified by the Contractor. If different

materials are used in the hydrostatic test system, such as piping of carbon steel/heat exchanger

tubes of stainless steel, water with a limited chloride (less than 10 PPM) content shall be used

for this system.

5.11.3. The butt welds of pipes which cannot be subjected to a hydrostatic test shall be 100% radio-

graphed. Subsequently, a leakage test is made. This examination is also performed, for all

separable connections.

5.11.4. For the leakage test with air or nitrogen, appropriate safety measures shall be taken considering

the local requirements.

5.12. FLUSHING, PICKLING, DRYING

For piping systems to be pickled and/or flushed and dried, the requirements of Project

Specification SP-010 Equipment Preservation shall be complied with.

5.13. PAINTING AND INSULATION

5.13.1. After completion of the test described in Paragraph 5.10 and 5.11, approval for painting and

insulation shall be given. The requirements of Project Specifications for painting (SP-009

Painting) and insulation (SP-006 Thermo Insulation Design) shall be complied with.

5.13.2. Insulation has to be inspected, in particular, for conformation with the specified insulation

thickness, numbers of spacers, metal thickness of the weather jacket and proper installation of

the jackets (appropriate overlap, tightness to water) and the inspection results have to be

recorded.

5.13.3. Thermal conductivity coefficients, apparent densities and the required sound insulation figures

of the insulating materials have to be verified.

5.13.4. Surface preparation (degree of rust removal), reference surfaces, workability of the insulating

materials shall conform with the manufacturer's handling instructions. For instance regarding

humidity, application of insulating materials and thickness per insulation layer shall be inspected

/ supervised and the inspection results shall be recorded.

5.14. MECHANICAL COMPLETION

After completion of all work on the piping systems and compilation of the drawings and test

documentation, the Contractor shall notify the Owner of mechanical completion.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 21 of 64

6. INSTRUMENTATION

6.1. GENERAL

6.1.1. This standard should be used for the inspection and testing of all instrumentation and

monitoring equipment for all plant components before and after installation on Site.

6.1.2. The contractor's personnel shall be competent, qualified and fully conversant with the types of

equipment to be tested and where necessary the contractor shall arrange for his personnel to

attend relevant training course.

6.1.3. A critical path analysis network shall be provided by the contractor and agreed by Owner. This

shall define the overall sequence of the testing on the project. Any subsequent deviation from

this program shall be agreed in writing.

6.1.4. The contractor shall, at all items, observe and comply with Vietnam and international safety

regulation.

6.1.5. The contractor shall set up and maintain a quality assurance system to ensure that all work is

carried out in full accordance with the requirements of the relevant parts of BS 5750: 1987 / ISO

9000 - quality system.

6.1.6. The contractor shall set up and maintain a quality assurance system to ensure that all work is

carried out in accordance with the relevant specification.

6.1.7. The contractor shall obtain approval from owner before power or pneumatic supplies are

switched on to any instrument, panel, and control system of plant.

6.2. DEFINITIONS

Terms used in this specification are defined as follows:

6.2.1. Maximum working pressure means the set pressure of safety valves for process piping and

equipments.

6.2.2. Design pressure of instruments means the maximum pressure guaranteed by the

manufacturer to which the pressurized parts of the instruments may be subjected without

affecting the performance of the instruments.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 22 of 64

6.3. INSPECTION AND TESTING DOCUMENTS

Contractor shall provide the documents listed below to perform site inspection and testing

activities as minimum.

• Instrument list

• Technical data sheets

• Installation drawings

• Hook-up drawings

• Loop diagrams

• Circuit diagrams

• Wiring diagrams

• Terminal connection diagrams

• Interlock logic and sequence diagrams

• Manufacturer's recommended inspection and testing procedures

• Installation check sheets

• Testing reports

• Calibration reports

• Etc.

Format of installation check sheets, testing reports, and calibration reports shall be prepared by

Contractor and approved by Owner.

6.4. INSPECTION AND TESTING REQUIREMENTS

6.4.1. INSPECTORS FOR INSPECTION AND TESTING

The inspectors must be familiar with the necessary inspection, testing, and adjustment works for

the installed instrumentation.

6.4.2. CALIBRATION FACILITIES

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 23 of 64

Contractor shall provide the dedicated calibration workshop in the site or nearby which meets

the requirements of the international standard.

Contractor shall not use the calibration workshop for any other activity.

Entry inside the calibration workshop shall be permitted only to calibration technicians and

inspectors from Contractor’s and owner's side.

The calibration room shall be an air conditioner room. The temperature, humidity, and the

quality of air inside shall be controlled suitably for the requirement of calibration room according

to the international standard. A thermometer shall be installed inside the room and the set

temperature shall be noted down in testing and calibration reports.

The test equipment and the instruments to be calibrated shall be handled and maintained in

suitable manner in order to maintain their guaranteed accuracy. Contractor shall maintain test

certificates for the calibration of all test equipment by a third party and the calibration procedure

shall be traceable to international standards.

Contractor shall also have standard procedures for regular calibration of the test equipment.

6.4.3. INSPECTION AND TESTING ACTIVITIES

The inspection and testing activities shall be included, but not limit to, the followings.

• Inspection and testing before installation commencement

- Factory Acceptance Test (FAT)

- Visual inspection

- Calibration

- Etc.

• Inspection and testing after installation commencement

- Visual inspection

- Leakage test and pressure test in pneumatic lines and impulse lines

- Inspection of the cables, screening, and protective system for proper connection

- Functional test

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 24 of 64

- Loop test

- Interlock logic and sequence test

- Performance test

- Site Acceptance Test (SAT)

- Etc.

6.4.4. OTHER REQUIREMENTS

The inspection and testing plan including date, procedure, etc. shall be specified by the

Contractor and agreed with the Owner. Owner shall have the rights to witness all the

inspections and tests. All test equipment and consumables shall be provided by the Contractor.

The contractor shall submit list of all test equipment to be used. This shall be revised and

agreed with the Owner before testing is commenced. The list shall contain, but not limit to, the

following.

• Manufacturer

• Instrument Type

• Type Number

• Quality Class

• Instrument Test & Calibration certificate from approved authorities

6.5. INSPECTION AND TESTING BEFORE INSTALLATION COM MENCEMENT

6.5.1. The Factory Acceptance Test (FAT) of the following instrument systems shall be performed by

Contractor at Manufacturer’s or Vendor’s workshop and approved by Owner prior to delivery.

The inspection and test procedure shall be sent to Owner for approval at least 1 week prior to

the test. The tested systems shall include, but not limit to, the followings.

• DCS system

• ESD system

• F&G system

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 25 of 64

• GC system and Analyzer House

• Continuous Emission Monitoring System (CEMS)

• COD Analyzer System

• Other analyzer systems

• Custody Transfer meter system

• Truck loading meter system

• Pelletizing system

• Etc.

6.5.2. All instruments shall be visually inspected by the instrument subcontractor prior to issue from

Contractor’s stores and any discrepancies shall be reported in writing to the contractor

immediately.

6.5.3. Scale design, instrumentation symbols and texturing shall be checked at this stage.

6.5.4. Prior to installation, all instruments shall be calibrated by the Contractor in the site workshop.

Calibration method and procedure shall be sent to Owner for approval at least 1 week prior to

the calibration. The calibration process shall be traceable to international standards. The

calibrated instruments shall include, but not limit to, the followings.

6.5.5. Contractor shall use the following inspection and test items of each instrument as a guideline.

The inspection and test of equipment which are not listed below shall be proposed by

Contractor and approved by Owner.

• TRANSMITTERS, GAUGE, AND SIGNAL CONVERTERS:

Calibrate at 0, 25, 50, 75, and 100% of measurement range

• CONTROL VALVES:

Each control valve shall be checked against the data sheets

Check to the linearity of the valve lift as against control signal: 0, 25, 50, 75, 100 % direct

and reverse

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 26 of 64

Behavior on control air failure

• SWITCHES: (INCLUDE TEMPERATURE SWITCH, PRESSURE SWITCH, FLOW

SWITCH, LEVEL SWITCH, ETC.)

Checking the switch function (NC or NO)

Adjustment of the necessary switch points

Checking the switch hysteresis

• SAFETY VALVES

Each safety valve shall be checked against the data sheets.

Bench test for all safety valves by applying pressure to the design level shall be carried

out no earlier than 90 days prior to Mechanical Completion.

Lead seal shall be replaced and certified by Vendor’s representative at site if the

adjustment of spring is requested.

6.5.6. A pre printed calibration sticker showing the tag no, manufacturer's serial number, date of

calibration, calibration report serial number and initials of the person who has done the

calibration shall be put on the instrument immediately after calibration.

6.6. INSPECTION AFTER INSTALLATION COMMENCEMENT

6.6.1. Contractor shall use the following inspection and test items of each instrument as a guideline.

The inspection and test of equipment which are not listed below shall be proposed by

Contractor and approved by Owner.

• PANELS

Panels are held in place and are fixed firmly in accordance with the related drawings.

Panels are correctly mounted vertically.

The surface of panels is cleaned and has not been dented or scratched.

• INSTRUMENT CABLE DUCTS

Instrument cable ducts are laid in according to the routes shown in the drawings using the

material specified for the construction and sizes.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 27 of 64

Instrument cable ducts are fixed by the procedure shown in the drawings.

The inside of instrument cable ducts has no projection which may damage cables or

wires.

The worked parts of the galvanized steel plates fabricated or welded at construction site

are repaired according to the specified procedure.

Instrument cable ducts are certainly fitted with all cover plates.

6.6.2. IMPULSE PIPING / TUBING

• VISUAL INSPECTION

Impulse piping/tubing is laid in accordance with the route shown in the drawings.

The materials specified for standards, sizes and quality are used.

The relative elevation and direction of pressure taps and instrument are as shown in the

drawing.

Seal pots, condensate pots, etc. are assembled in the same or specified elevation.

Impulse piping/tubing is sloped as specified.

The division of high and low pressure connection of differential pressure instruments is

correct.

• PRESSURE TESTS AND LEAK TESTS

Those tests shall generally be performed without disconnection of impulse piping/tubing

and the test pressure shall be limited to the design pressure of the instrument.

Pressure tests and leak tests shall be carried out simultaneously in accordance with the

following procedure (except for 900 # rating and over).

Nitrogen or air shall be used for the pressurization of impulse piping/tubing.

The test pressure shall be 1.25 times the maximum working pressure.

No change on the impulse piping/tubing is confirmed after pressurized at least five

minutes at the test pressure.

During the test, no leakage from impulse piping/tubing is checked by soapy water.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 28 of 64

Remarks: The pressurization must be done slowly to maintain the safety.

For 900 # rating and over, pressure tests and leak tests shall be carried out individually.

Fluid, pressure and duration is as follows

• PRESSURE TESTS

Fluid: water

Pressure: 1.5 times the maximum working pressure

Duration: 5 minutes

• LEAK TESTS

Fluid: Air

Pressure: 1.1 times the maximum working pressure

Duration: 3 minutes

6.6.3. SUPPLY AIR PIPING /TUBING

• VISUAL INSPECTION

Supply air piping/tubing is arranged as shown in the drawings.

The materials specified for standards, sizes and quality are used.

The piping/tubing method around instruments is correct.

The piping/tubing is routed avoiding an adverse effect from a heat source and is not

under the hot or cold insulation materials of process piping and equipments.

The piping/tubing is arranged or supported avoiding the vibration and thermal expansion

of process piping or of equipments.

• LEAK TESTS

Leak tests shall be performed after cleaning check and the procedure shall be as follows:

Instrument air is used for leak tests.

The pressure of instrument air shall be of the working pressure.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 29 of 64

No leakage from supply air piping/tubing is confirmed by soapy water after pressurized at

the test pressure. Leakage is checked after 3 minutes passed.

6.6.4. SIGNAL AIR PIPING / TUBING

• VISUAL INSPECTION

Signal air piping/tubing is arranged as shown in the drawings.

The materials specified for standards, sizes and quality are used.

The piping/tubing method around instruments is correct.

The piping/tubing is routed avoiding an adverse effect from a heat source and is not

under the hot or cold insulation materials of process piping and equipments.

The piping/tubing is arranged or supported avoiding the vibration and thermal expansion

of process piping or of equipments.

• CONTINUITY TESTS

Instrument air is used for continuity tests.

The pressure of Instrument air shall be 1 kg / cm2 G or the maximum signal pressure of

the system concerned.

Confirm the continuity by checking the air blown through piping. Blow shall be carried out

sufficiently.

Confirm the identification of multi-cored signal tube is as shown in the drawings.

• LEAK TESTS

Leak tests shall be performed after continuity tests with all joints reconnected.

Instrument air is used.

The pressure of instrument air shall be 1 kg / cm2 G or the maximum signal pressure of

the system concerned.

No leakage from signal air piping/tubing shall be confirmed by soapy water after

pressurized at the test pressure. Leakage is checked after 3 minutes passed.

6.6.5. WIRING

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 30 of 64

• VISUAL INSPECTION

Conduit piping is arranged as shown in the drawings.

The materials specified for standards, sizes and quality are used.

The wiring method around instruments is correct.

Wiring is routed avoiding an adverse effect from a heat source and is not under the hot or

cold insulation materials of process piping and equipments.

Wiring is arranged or supported avoiding the vibration and thermal expansion of process

piping or of equipments.

Wiring is laid avoiding an adverse effect from power cables.

Sealing method is as specified in the drawings

Grounding method is as specified in the drawings.

• CONTINUITY TESTS

Use low voltage apparatus such as testers, buzzers or telephones.

Disconnect the compression fittings from terminal blocks to avoid excessive voltage to

the instruments and to prevent the by-pass circuits.

Confirm the continuity of wiring.

Confirm the identification of cables and wiring is as shown in the drawings.

Insulation resistance tests

Insulation resistance tests shall be performed after the said continuity tests and the

procedure shall be as follows

Use "Megger" (insulation resistance tester) of rated voltage 500V or higher as a tester.

Measure the insulation resistance between wires and between a wire and earth,

disconnecting the compression fittings from terminal blocks after continuity tests.

Check the measured values are greater than 100 M compensation lead wire for

thermocouples as 5 M. When specified by the manufacturer of apparatuses, the value

shall govern.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 31 of 64

Reconnect the compression fittings to terminal blocks after the charged current in the

wire of cable through those tests is discharged to ground.

Grounding resistance tests

Grounding resistance meters shall be used for those tests.

The measured value shall be less than those shown in the following table:

Classification of grounding Grounding resistance (OHMS)

Frame earthling 5 or less

System earthling 1 or less

Shield wire earthling 5 or less

Grounding resistance requirements for special circuits such as PLC, DCS & other

computers shall be as per manufacturer’s recommendation.

6.6.6. HEAT TRACING PIPING

• VISUAL INSPECTION

Heat tracing piping is arranged as shown in the drawings.

The materials specified for standards, sizes and quality are used.

The method of the piping (rough coiling, tight coiling or a combination) is correct.

No extremely crushed parts by bending works or the like shall be found on the heat

tracing piping.

• PRESSURE TESTS AND LEAK TESTS

The procedure of those shall conform to the clause 7.5.2.2 in principle.

For steam tracing, steam practically provided with shall be used for pressure tests and

leak tests which are carried out simultaneously.

No change on the heat tracing piping shall be confirmed.

6.6.7. INSTRUMENTS

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 32 of 64

VISUAL INSPECTION

Instruments are not placed at the location that might interfere with their function, operation,

maintenance, etc.

Instruments are not installed on the surface which may cause vibration on the instruments.

Instruments are installed by the specified way using the materials shown in the related

drawings.

Instruments are correctly mounted horizontally, vertically or at the specified angle.

Instruments are cleaned and have not been damaged.

6.7. TESTING AFTER INSTALLATION COMMENCEMENT

6.7.1. SITE ACCEPTANCE TEST (SAT)

The Site Acceptance Test (SAT) of the following instrument systems shall be performed by

Contractor at site after installation and approved by Owner. The inspection and test procedure

shall be sent to Owner for approval at least 1 week prior to the test. The tested systems shall

include, but not limit to, the followings.

• DCS system

• ESD system

• F&G system

• GC system and Analyzer House

• Continuous Emission Monitoring System (CEMS)

• COD Analyzer System

• Other analyzer systems

• Custody Transfer meter system

• Truck loading meter system

• Tank Gauge System

• Pelletizing system

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 33 of 64

• Auto feeder system

• Etc.

6.7.2. INSTRUMENT SYSTEMS

All instrumentation loops shall be subjected to an overall functional test which the measuring

ranges for 0, 25, 50, 75 and 100 are simulated from the process side with air or N2. All indicated

values are read off and reported. Readjustment is necessary if deviations beyond the allowable

accuracies occur.

In regard to controllers, the control characteristic (direct/reverse) shall be checked and adjusted

if necessary.

Displacement-type level instruments shall be tested with clean water or suitable liquids.

The control signals to the pertinent control valves shall be pre-selected from the appropriate

manual loading station with the values 0, 50 and 100 %.

The bolts for stuffing box packing shall be tensioned as per the manufacturer's instructions.

6.7.3. ALARM, SEQUENCE CONTROL AND SAFETY SYSTEMS

Checks shall include correct function and identification of all parts. Functions shall be checked

step-by-step using the process function charts and circuit diagrams including the P & I diagram.

For this purpose, the switching ranges shall be simulated with air or N2 on the process side at

the limit switches.

The resulting function indication/control function of solenoid valves and pumps shall be checked

and entered in reports.

The sequence controls and safety systems shall then be operated by the startup personnel and,

if necessary, the pertinent inspection authorities.

6.7.4. ELECTRICAL THERMOMETERS

Thermocouples to test the temperature measuring loops for correct poling of the extension wire,

correct calibration of the instrument and pertinent measuring point, a suitable measuring voltage

shall be supplied to the head of each thermocouple and compared on the instrumentation

receiver.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 34 of 64

Resistance thermometers to check the temperature measuring loops, a precision resistor of

suitable range shall be connected to the head of each resistance thermometer and the pertinent

temperature compared on the instrumentation receiver. If necessary, the lines shall be balanced

as per the manufacturer's instructions.

6.7.5. ANALYZERS AND SPECIAL INSTRUMENTS

All analyzer probes shall be checked against sample probe drawing for correct direction and

installation.

The wake frequency calculation report for all probes shall be provided.

All sampling systems shall be checked for correct installation and tightness.

All analyzers shall be calibrated using the procedure recommended by the manufacturer

applying the sample gases and liquids supplied.

All Analyzer houses shall be checked to overall safety function test.

Special instruments shall be checked as per the manufacturer's instructions.

6.7.6. POWER SUPPLIES

The central instrument power supply shall be checked against the terminal layout drawings for

correct connection, fuses and texturing.

Automatic changeovers in this area shall be tested by simulation.

The outgoing feeders shall be put into operation one after the other.

6.8. INSPECTION FOR INSTRUMENT SUPPLIED WITHIN PACK AGE UNIT

All instruments supplied within package units shall be accurately checked and shall be

subjected to the same preliminary inspection as stated above.

6.9. INSPECTION REPORTS

6.9.1. For each instrument, inspection certificate shall be generated by the contractor. The certificate

shall contain all inspection done on a particular instrument including pressure test, Flushing,

calibration, loop check etc. The certificate shall be jointly approved by contractor's authorized

inspector and Owners inspector. This shall be generated in an electronic file format and handed

over to the owner in a electronic media in addition to the approved hard copy.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 35 of 64

6.9.2. Inspection reports will be filled up by the inspector and signed by the inspector of both parties.

6.10. TEST RESULTS

6.10.1. SUCCESS OF INSPECTION

The inspection is considered successful when this is expressly stated in the report and the

tested object is approved for use jointly by the contractor’s inspectors and owner’s inspections.

Faults not requiring re-inspection and having no influence on the use of the test object in

respect of its function and safety shall be appropriately entered in the report. An inspection

passed sticker shall be put on the instrument after every stage of inspection is successful.

6.10.2. UNSUCCESSFUL TEST

The test is considered unsuccessful when the type and number of defects do not permit the

targets of the inspection to be reached or do not allow the inspected object to be used.

Further re-inspections necessitated by the requirements not being met or the tested object

being defective have to be done by the Contractor without any cost to the Owner.

6.10.3. CHECK TO ELIMINATE REMAINING DEFECTS

Defects remaining from the above inspections shall be eliminated before a stipulated date.

6.10.4. INSPECTIONS WITH THE Owner AND AUTHORITIES

In accordance with the contract and irrespective of the above inspections, other inspections

may be required by the authorities and the Owner to take over the plant.

In such cases, the Contractor shall provide the same personnel and technical prerequisites as

for the foregoing inspections.

6.11. OVERALL INSTALLATION CERTIFICATE

After completion of the inspecting, the Contractor shall provide an inspection certificate

confirming that the instruments have been installed in conformity with the requirements for

hazardous areas.

6.12. STARTUP PERSONNEL

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 36 of 64

The Contractor shall make the requisite number of qualified personnel available for the

inspection to support the startup personnel.

The number and selection shall be agreed with the Contractor’s site management and the

Owner.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 37 of 64

7. ELECTRICAL AND COMMUNICATION FACILITIES

7.1. SCOPE

7.1.1. This part of the specification defines Contractor’s responsibilities and procedures for the testing

of electrical and communication installations at site, prior to completely energizing an integrated

electrical and/or communication system.

7.1.2. The scope makes no claim to completeness. This Contractor is responsible for covering in his

detailed field inspection procedure and/or specifications all necessary test requirements to

guarantee that all equipment and material is of first-class quality and successfully inspected and

tested.

7.1.3. All field inspections and tests shall be carried out according to the contract requirements, the

applicable IEC-Standards-which shall have priority-followed by certain national standards as

specified in the project specification EE-001 General Electrical Design Specification.

7.1.4. Test instructions by the equipment manufacturer shall have priority. Tests which are necessary

to retain the manufacturer's guarantee shall be conducted by an authorized manufacturer's

representation.

7.2. GENERAL

7.2.1. The test methods applied and the test instruments used shall follow the most modern test

practice. In view of their great variety, no reference is made here to any specific type thereof.

7.2.2. Setting and calibrating of protective relays shall only be performed by Contractor’s personnel

especially qualified for this function.

7.2.3. Contractor shall exercise care in performing the tests specified so as not to jeopardize the

safety of personnel.

• All exposed live parts subjected to testing shall be guarded by personnel, barricades, or

other practical means to ensure against personnel being injured by coming in contact or

too close proximity to exposed parts.

• All equipment, exposed live parts, etc. shall be completely discharged by grounding or

other accepted methods so as to eliminate the possibility of injury to personnel from

electrical shock after the tests have been completed.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 38 of 64

• Equipment under test shall be isolated from remote control or feedback circuits to prevent

accidental energization by others.

7.2.4. Contractor is responsible for preparing records for all tests and inspections, with complete data

on all reading taken and incorporating these in a report for each piece of equipment or item

tested.

• Test reports shall be signed by the witness heretofore mentioned and approved by the

designated representative of Owner.

• Normally, the results of all inspections and tests or commissioning functions, such as

megger testing of motor or motor feeder and control cables, may be grouped on a single

record form.

• As a minimum, the records shall contain the following information:

• Description of the test or commissioning function, data performed and identification of

the test equipment used

• Applicable ratings, equipment numbers and location of the facilities

• Size, length and rating of cables: whether cables are shielded or unshielded; and

manufacturer's test values for medium-voltage cables

• Ambient temperature and humidity, where applicable to the particular test or

commissioning function

• Minimum test values acceptable in compliance with project specifications

• Test results, including comments where necessary for clarification

• Details of any corrective actions taken

• Results after corrective actions have been taken

• Signature of Contractor’s representative and/or Owner.

• During each of the inspections and tests, Contractor shall maintain a comprehensive set

of test reports defining the specific condition in which the apparatus is left, after it has

been given approvals for use in its intended service. The completed reports shall become

the property of Owner.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 39 of 64

• Among the specific testing requirements to determine the operational conditions of the

equipment relative to that particular apparatus, all items shall be visually inspected and

evaluated in the report as to the general exterior and interior condition.

• A checklist-type report for each major electrical equipment item should be headed with,

but not limited to the following identification data:

• Equipment name

• Tag number

• Application

• Plant location

• Voltage rating

• Date of test

• Ambient conditions

• Tester's signature

• Contractor’s witness signature

7.3. REASONS, TYPES AND PREREQUISITES OF SITE INSPECTION AND TESTS

7.3.1. INSPECTIONS AND/OR TESTS MAY BE REQUIRED FOR THE FOLLOWING REASONS:

• Interim inspection/test (depending on the object, the installation sequence or the contract)

for internal and external functions

• Check of mechanical completion (main inspection)

• Pre-commissioning tests (energizing of single or integral systems)

• Inspection together with Owner and authorities

• Inspection to ascertain that remaining defects have been corrected

• Checking document revisions.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 40 of 64

7.3.2. THE INSPECTIONS AND/OR TESTS ARE SUBDIVIDED INTO THE FOLLOWING TYPES:

• Visual inspections

• Mechanical inspections

• Electrical function tests

• Electrical operating functions

• Measurements

7.3.3. Contractor shall take all necessary measures to ensure a smooth and successful

inspection/test. The following prerequisites shall be met:

• Completeness of the object as notified

• Presentation of the relevant engineering documents

• Experienced inspection personnel commanding the specific skills required for the project

• Proper safety precautions for the test/inspection location

• Suitable testing equipment, auxiliaries and utilities

• Description of the testing procedure before the tests and undertaken

• Preparation for recording

7.4. AS AN INTEGRAL PART OF ALL PARTICULAR SITE INS PECTIONS AND TESTS, CONTRACTOR SHALL BE RESPONSIBLE FOR THE FOLL OWING:

7.4.1. VISUAL INSPECTIONS:

• Intactness from receipt of goods until the custody date as per the Contract expires

• Completeness as specified in the shipping documents and Specification

• Presentation of a coordinated Program of Tests and Inspections

• Completeness of the installation, testing and commissioning documents, including all

special provisions

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 41 of 64

• Conformity of essential data and characteristics with the working documents

• Legibility of test plates and nameplates

• Correction of all defects from previous inspections on the basis of the relegate inspection

reports

• Correctness of all subsequently installed or connected items

• Checking that all unnoticeable inlets are properly closed

• Proper sealing of all cable inlets

• Completeness of all supplementary services rendered at site (finishing coat of paint,

covers, inscriptions, etc.)

• Removal of holding-down devices

• Filling of lubricating, insulating and sealing media and checking their levels

• Availability of special tools, wrenches, etc.

• Compliance with materials and manufacturer's instruction for auxiliary installation

materials

• Maintaining distances required for safety, operation and maintenance

• Proper condition and function of testing equipment

• Usability of escape routes

• Availability of first-aid facilities

7.4.2. MECHANICAL CHECKS

Checking movements as well as rigid or detachable connections, in conjunction with a previous

or simultaneous visual inspection:

• Firm installation of the fixing device and the attached parts on the base structure

• Sufficient play of flexible connections and moving parts

• Checking defined movements including intermediate and extreme positions, including

specified interlocks

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 42 of 64

• Firm seating of plug-in components including check of unobstructed space to remove

these components

• Safety of operation and handling

• Adjusting zero position, readings for minimum / maximum / normal conditions according

to the specification for all instruments

• Checking of all mechanical interlocks

• Firm, secured seating of covers

• Firm re-fixing or re-closing after visual inspection of concealed components

• Conditions of conductor connections e.g. damaged conductor or conductor insulation

• Effectiveness of stress-relieving measures on cables and wiring

7.4.3. ELECTRICAL TEST FUNCTIONS

Using voltages and currents to test (cold check) individual equipment items or groups of items

for their immediate functions; such tests are normally carried out during intermediate

inspections. Previous or simultaneous visual inspections are a prerequisite.

• Defining an optimum test sequence under technical and economic aspects

• Checking safety requirements with respect to location and test instruments

• Informing or inviting the relevant installation supervisor of adjoining systems

• Checking covers and insulation of live parts, in particular, of outgoing cables

• Defining the necessary or permissible operating and test voltages/currents

• Checking function bridging for compliance with protective requirements

• Measurements and certification of electrical insulating capacity before connecting

operating and auxiliary voltage

• Performing functions according to descriptions and checking negative functions

(interlocks, etc.)

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 43 of 64

• Checking indicating instruments for conformity with switching and operating conditions

• Recording modified functions or corrections at the installation

• Marking tested circuits, indicating test results, in particular, until critical functions are

eliminated

• Removing temporary test facilities (bridges, etc.) or marking these facilities

• Disconnecting current and voltages and safe-guarding the switches against unauthorized

re-connection, or marking connected currents/voltages and safeguarding them against

unauthorized disconnection

7.4.4. ELECTRICAL OPERATING FUNCTIONS

Tests under Operating Conditions ("Hot Check") in connection with preceding or subsequent

systems on the occasion of main inspections and system connections. All electrical test

functions must have been successfully completed and recorded.

• Analogous observance and application of the procedures for test functions

• Preparation of the operating circuits to be tested

• Specification of emergency measures to avoid hazards to personnel or property

• Coordination with the authorized commissioning supervisor of connected systems

• Specification of the loads and time periods for the tests (no load, partial load, rated load,

over-load, initial loading, re-loading and intervals)

• Loading of operating circuits while observing the operation and the measuring and

indicating instruments

• Optimization of set points

• Connection of individual units to systems

• Checking redundant systems

• Simulation of malfunctions, considering the functions of monitoring and signal circuits

• Testing of special measures

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 44 of 64

• Shut-down of the operating circuit and safeguarding against unauthorized pre-

commissioning, or clarifying responsibilities if operation is maintained, and safeguarding

against unauthorized shut down.

7.4.5. MEASUREMENTS

Marking quality measurements in connection with test operation (guarantee run) and certifying

compliance with requirements:

• Checking the measuring set-up, the transmission ratio and the accuracy according to the

applicable test instructions and procedures

• Recording the measuring set-up and the operating conditions including ambient

conditions

• Recording the actual measured value

• Comparison between actual and specified values and evaluation of tolerances

• Checking against permissible + tolerances

• Reasons for higher but justifiable deviations

• Specifying corrective measures in case of unacceptable deviations

• Restoring the object to normal condition after the measurements has been completed

7.5. SPECIFIC REQUIREMENTS FOR FIELD INSPECTIONS AND TESTS OF ELECTRICAL AND COMMUNICATION EQUIPMENT

In the absence of specific manufacturer's instructions, the following tests and inspections shall

be performed, but not limited to:

7.5.1. POWER TRANSFORMER

• All transformers shall be inspected after installation for:

• Damage incurred in transportation

• Inspect bushings for chips or cracks

• Inspect all gaskets, fittings and radiators for leaks*

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 45 of 64

• Check liquid level*

• Check mountings for cooling fan, resistor and other accessories

• Check out and test cooling fan, control wiring in accordance with applicable parts of

this specification

• Function-test cooling fan and/or circuits

• Check on-load tap changer for proper movement

• No leakage of oil

• Earthing shall be good condition

• Check operation of temperature indicator, pressure relay and other devices

• Check operation of pressure relief valve as recommended by the manufacturer*

Note: [*] For liquid-immersed transformer only

• All transformers shall be subjected to one-minute megger tests. These shall be performed

winding to winding, winding to ground, and including any taps for voltage adjustment.

• In addition to the megger tests, high-potential tests shall be performed:

The sequence of megger and high-potential tests shall be:

• Megger tests shall be made to determine the condition of the insulation.

• The high-potential tests shall be applied only if the megger test passes minimum

requirements.

• The successful high-potential test shall be followed immediately by another megger

test in order to detect any damage incurred by high-voltage stresses.

• Each secondary winding of a transformer operating at 380 volts shall be given a

megger test only. The test shall include any taps for voltage adjustment.

• Megger and high-potential tests on each transformer winding shall be applied between

all phases tied together and ground. All windings and adjacent cables or breaker

contacts not included in the test shall be grounded.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 46 of 64

• Grounding resistors, when used, shall be given megger and high-potential tests. With

the neutral grounding resistor lead disconnected from the transformer neutral and the

ground side of the resistor and cable, the resistor shall be given a megger test. The

resistor housing shall be tied to the test ground.

• All control, alarm and metering circuits shall be checked.

• The results of all tests shall be in accordance with the manufacture's

recommendations.

• Transformers larger than 2000 kVA or with windings rated 30kV and higher shall be

subjected to a polarization Index. This shall be the ratio of ten-minute to one-minute

insulation resistance readings. A 500 volt megger shall be used for windings less than

660 volts. A 2500 volts and higher shall be used for windings higher than 660 volts.

Conditions of the insulation shall be indicated as follows:

CONDITION POLARIZATION INDEX

Good 2 and greater

Questionable 1 to 2

Very poor 1 and less

Note:

Transformers that are "questionable" shall be reviewed by Contractor. Transformers rated "very poor" shall not be energized. The manufacturer shall be contacted for directions to dry out.

• Transformer shall be tested winding resistance test and shall record the values of winding

resistance. The values shall be compared with the reports of manufacture.

• All transformers shall be tested polarized index test as the following test, but not limited

to:

• A 10/1 minute polarization index shall be taken for each winding of equipment rated

more than 660 volts. If this indicates "Questionable", the cause shall be determined

and action taken as determined by Contractor of his designee. If a winding is

indicated "Poor", the equipment shall be dried out in accordance with instructions from

the manufacturer. The ratios and indicated relative conditions of the insulation are

given below.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 47 of 64

• For equipment rated 660 to 6,600 volts, both the dielectric absorption and polarization

index rations shall be taken. A polarization index shall be taken for equipment 660

volts and less with unacceptable insulation resistance.

INSULATION CONDITION 60/30 SECOND RATIO DIELECTRIC ABSORPTION

10/1 MINUTE RATIO POLARIZATION INDEX

Dangerous - Less than 1

Poor Less than 1.1 Less than 1.5

Questionable 1.1 to 1.25 1.5 to 2

Fair 1.25 to 1.4 2 to 3

Good 1.4 to 1.6 3 to 4

Excellent Above 1.6 Above 4

• Equipment rated less than 660 volts with insulation resistance less than 1 megaohms

or insulation condition less than "fair" shall be dried out. Instructions for dry-out shall

be obtained from the equipment manufacturer.

• Equipment rated more than 6,600 volts or more than 5,000 kW or more than 5,000

kVA shall be subjected to a polarization index and a high direct voltage step test. The

procedure and criteria shall be in accordance with the recommended values

suggested by the manufacturers.

• Exciting test by low voltage.

• All transformers shall tested oil test as the clause 8.5.5.

• Test and calibration temperature controller.

7.5.2. LV AND MV SWITCH GEAR AND CONTROL GEAR:

• Each lineup of switch gear, low-voltage and medium high voltage motor control centers

shall be inspected for shipping and handling damage, for mechanical completeness and

made ready for operation including the following:

• Check connections and test ground busses

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 48 of 64

• Check mechanical operation of all breakers, contactors and auxiliary devices

• Check and alignment of drawout type equipment including floor steel, main and

auxiliary contactors, shutter position indicators, operating linkages, cell and removable

element alignment as necessary per manufacturer's instructions, adjust manuals and

recommendations

• Verify by test the ratio and polarity marking of all current and potential transformers,

according to item 8.5.7, for protective relaying and metering

• Protective relays such as overcurrent, differential, under-voltage relays, etc. and

meters shall be set and functionally tested as outlined in the sections on protective

relays and functional testing.

• Check selection of thermal overload elements against values shown on the drawings

and thermal overload shall be tested as the following test, but not limited to:

(1) Mechanical trip test

(2) Insulation resistance shall be one minute megger test from phase to phase and

phase to ground. Insulation resistance shall be recorded. The values of insulation

resistance shall be a minimum as per TABLE 1.

(3) Individual pole resistance shall be tested and recorded the values in each pole of

relay.

(4) Time delay over current trip shall be tested and recorded the values to compare with

standard values.

(5) Instantaneous over current trip test.

(6) Rated current hold in test shall be tested at rated current.

• Check settings of circuit breakers

• Test and set power breaker trips in accordance with the drawings.

• All LV and MV switchgears and control gear shall be tested commissioning test

according to the following mention:

(1) Function test of each relay which coordinated with circuit breaker.

(2) Primary injection.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 49 of 64

(3) Secondary injection.

• Check phasing of busses

• Function-test all control circuits, protective circuits, powered devices and powered

equipment-Ring-out all multiconductor cables and busses

• Check out all phasing where more than one supply can be connected to the

equipment

• Check all fuses.

• Testing shall be performed as follows:

• Before connecting cables or busses to the switch gear terminals, the insulation

resistance of all bus and current carrying paths shall be measured. One-minute

megger tests from phase to phase and phase to ground shall be made with a

minimum of:

Table 1

Equipment ac rating (volts) 660 and less 660 to 35,000

Megger Rating (Volts) 500 2500

Minimum Resistance (Mega-ohms)

10 400

• Before energizing, the insulation resistance of each removable element shall be

measured. The element shall be removed from the cell for this test.

Measurements shall be a minimum of the values indicate above.

• Oil-immersed equipment shall also be sampled and tested for insulating liquid in

accordance with clause 8.5.5

• Switch gear, not including motor control, rated 6,600 volts and higher shall also be

subjected to a power frequency voltage test according to IEC-298 and IEC- 694.

• Prior to energizing the switch gear bus, the following items shall be inspected and

tested for proper operation

• Control, protective and metering circuit

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 50 of 64

• All current transformers shall be tested according to clause 8.5.7 and verify that relays

and meters (as applicable) operate properly.

• All potential transformers shall be tested according to clause 8.5.7 and verify that relay

and meters (as applicable) operate properly.

7.5.3. CIRCUIT BREAKER

All circuit breakers shall be tested as the following test, but not limit to:

• Insulation resistance shall be one minute megger test from phase to phase and phase to

ground. Insulation resistance shall be recorded. The values of insulation resistance shall

be a minimum as per table 1.

• Each circuit breaker shall be tested insulation power factor test before energizing.

• Moisture content test for SF6 circuit breaker.

• Contact Resistance in each phase of circuit breaker shall be tested and the resistance

shall not more than test reports from manufacturer.

• Closing and tripping time test in each phase of circuit.

• Withstand Voltage test for VCCB.

7.5.4. MOLDED CASE CIRCUIT BREAKER

All molded case circuit breakers shall be tested as the following test, but not limited to:

• Insulation resistance shall be one minute megger test from phase to phase and phase to

ground, Insulation resistance values shall be recorded the values of insulation resistance

shall be minimum as per table 1.

• Contact resistance in each phase of circuit breaker shall be tested and the resistance

shall not more than test reports from manufactory.

• Withstand Voltage test.

• All circuit breaker shall be tested open circuit at 125%, 200% and 500% rated current

test.

7.5.5. DIELECTRIC TESTS

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 51 of 64

• All equipment, such as transformers, circuit breakers and switches, containing insulation

oil shall have the oil dielectrically tested. Refer to IEC-Standards (e.g. IEC-156, -296, -

422, and 474) for more specific information on insulating oil to equipment.

• Generally, the following dielectric breakdown voltage shall apply to the testing of

insulating oil:

• Oil for transformers 26 kV minimum with normally expected values of 30kV or more.

• Oil for circuit breakers and switches 24 kV minimum with normally expected values of

26kV or more.

• The following procedures and equipment shall be used in testing dielectric breakdown

voltage:

• One (1) breakdown voltage test shall be conducted on each of two (2) separate test

samples. If either of the breakdown voltages is less than the minimum acceptable, a

breakdown test shall be made on each of three (3) additional samples. The either two

or five tests, as applicable, breakdown voltage shall be as follow.

• Test voltage shall be applied and increased at the rate of 3 kV/s

• The temperature of the test sample shall not be less than 20oC or greater than 30oC

• Test electrodes shall be 1 inch diameter discs spaced at 0.1 inch.

• Insulation power factor test shall be tested and recorded the values of power factor.

• All transformers shall be tested water content & color of oil test.

• Insulating oil which breaks down under test shall be filtered by approved means or

replaced where necessary.

7.5.6. RELAY AND PROTECTIVE DEVICES

All relay and protective devices shall be tested and adjusted according to relay setting and

coordination curve as the following mention:

• Relay and Protective devices test.

Individual test and record the following information:

• Pick up time

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 52 of 64

• Time curve and characteristic of each relay

• Functions of each relay such as metering, fault location, event recorder and relay fail

etc.

• Indicator.

• All relays and protective devices shall be adjusted according to relay settings and

coordination curves as described below:

• Each adjustable relay shall be set, calibrated and tested using a cycle counter, load

box, ammeter, voltmeter, or using a relay test set having good wave form

• All relays will be set in accordance with the relay tabulations furnished

• Relays with time characteristics shall be tested at three points on the item

coordination curves

• Procedure for protective relay settings and adjustments shall be made in accordance

with manufacturer's applicable instruction books.

7.5.7. CURRENT TRANSFORMER AND POTENTIAL TRANSFORME R

All current transformers and potential transformers shall be tested as the following test, but not

limit to:

• Insulation resistance of current transformer and potential transformer shall be one-minute

megger test. Insulation resistance of current and potential transformer shall be measured.

Measurements shall be a minimum of the values as per table 1.

• Rated of primary winding shall be checked matching of primary current or primary voltage

before energizing.

• Insulation power factor of each current and potential transformer shall be tested and

recorded.

• Ratio test.

• Polarity test.

• Exciting current for current transformer test.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 53 of 64

7.5.8. CONTROL SYSTEMS OF ELECTRICAL AND COMMUNICAT ION FACILITIES

• Electrical and communication controls, circuits and systems shall be tested by trial

operation of control equipment after all wiring is competed to see that each interlock and

control function operates in accordance with the contract drawings, specifications and the

description of equipment operation. Where field conditions prevent actual equipment from

functioning during testing, Contractor shall simulate the intended operating condition in

the associated control circuits.

• Contractor shall locate the cause of any malfunction and make the necessary wiring

and/or equipment changes or corrections to obtain the particular intended operation as

defined. Such changes shall be included in the test report.

• Control panels shall be operated through all design functions. This shall include remote

operation of all equipment and actuation of the alarms and indicating devices according

to design requirements.

Complete operational testes shall be made to all relays and control devices to show that

the equipment performs all design functions and meets design and procurement

specifications.

• Annunciator testing shall include the checking of each point by closing the trouble contact

and observing the panel operation. Correct functioning of all lamps, alarm cutoffs, reset

relay, etc. shall be checked.

• Ammeters shall be tested by checking the connections from current transformer for AC

(Shunts for DC) to ammeters. Ammeter scales shall be checked against current

transformer ratio for AC (shunt millivolt rating for DC) and pointers shall be set at zero

with no load.

• Communication systems only:

After installation, Contractor shall arrange for proof-operation and testing to the

satisfaction of the local Communication Authorities, where required, and of Owner.

7.5.9. ROTATING EQUIPMENT

• Preferably, an authorized manufacturer's representative should field-inspect and

commission generators and large motors.

• All rotating equipment rated 5,000 volts and less, shall be inspected after installation and

shall be checked for competence with the following:

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 54 of 64

• Check bearings for free operation

• Check lubrication system

• Check that frame is grounded

• Check equipment for proper rotation

• Run motors uncoupled or per section 8.5.9.4

• Observe running equipment for proper ventilation, vibration and bearing performance

• Check coupling for proper installation

• Check accuracy of alignment with driven equipment

• Check brushes, commutation speed or voltage range, polarity and general operation

of DC equipment

• Check that all auxiliary devices and protective control systems are operative

• Check load on motor under normal operating conditions

• All rotating equipments shall be tested stator and rotor winding impedance test and

recorded the values of impedance.

• All rotating equipments shall be tested stator winding capacitance test.

• All rotating equipments shall be tested stator and rotor resistance test and recorded the

values of resistance.

• All rotating equipment rated 6,600 volts and less shall be subjected to a 30-second

megger test.

• A test shall be performed when the equipment arrives at the job site.

• A test shall be performed before connecting the conductors and immediately before

energizing.

• The megger test shall be performed on each phase winding to ground. Other winding,

as may be, shall be tied together and connected to the frame which shall be

grounded. Windings tied together internally must be tested as one component.

• The test voltage shall be:

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 55 of 64

Equipment AC rating (volts) DC Test Voltage

250 Volts 250 Volts

660 Volts 550 Volts

6,600 Volts and more 2,500 Volts

• All rotating equipment is expected to have a winding insulation resistance in the order

of hundreds of mega-ohms. Windings with only a few mega-ohms may have a

problem of moisture, contamination of insulation. Windings with Low insulation

resistance shall be brought to the attention of Owner or his representative.

Equipment AC rating (volts) Insulation Resistance Minimum

Up to 660 Volts 10 Mega-ohms

6,600 Volts and more 20 Mega-ohms

• A 10-1 minute polarization index shall be taken for each winding of equipment rated

more than 660 volts. If this indicates "Questionable", the cause shall be determined

and action taken as determined by Contractor of his designee. If a winding is

indicated "Poor", the equipment shall be dried out in accordance with instructions from

the manufacturer. The ratios and indicated relative conditions of the insulation are

given below.

For equipment rated 660 t 6,600 volts, both the dielectric absorption and polarization

index rations shall be taken. A polarization index shall be taken for equipment 660

volts and less with unacceptable insulation resistance.

INSULATION CONDITION 60/30 SECOND RATIO DIELECTRIC ABSORPTION

10/1 MINUTE RATIO POLARIZATION INDEX

Dangerous - Less than 1

Poor Less than 1.1 Less than 1.5

Questionable 1.1 to 1.25 1.5 to 2

Fair 1.25 to 1.4 2 to 3

Good 1.4 to 1.6 3 to 4

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 56 of 64

Excellent Above 1.6 Above 4

• Equipment rated less than 660 volts with insulation resistance less than 1 mega-ohms

or insulation condition less than "fair" shall be dried out. Instructions for dry-out shall

be obtained from the equipment manufacturer.

• Equipment rated more than 6,600 volts or more than 5,000 kW or more than 5,000

kVA shall be subjected to a polarization index and a high direct voltage step test. The

procedure and criteria shall be in accordance with the recommended values

suggested by the manufacturers.

• In general, disconnect all capacitors and possible voltage sources from the

equipment. Maintenance tests can be run with the equipment feeder connected;

however, if unsatisfactory results are found, the feeder should be disconnected.

• All motors shall be run unloaded with the coupling disconnected for a period of at least 6

hours. During the running period, the motors shall be checked periodically for excessive

noise, current, speed, vibration or overheating of the bearing housing and motor frame.

• All rotating equipments shall be tested tan δ and power factor of stator winding test.

• Anti-condensation heater (if applicable) shall be tested.

• A check shall be made that space heaters are properly interlocked with the motor control

unit.

• Motors cannot be finally accepted until the equipment is energized during operational

tests.

• All motors shall be tested load run test and record the values of temperature, noise,

speed and vibration.

7.5.10. CABLES AND WIRES

• All cable connections must pass visual inspection for workmanship and conformance with

standard practices.

• All wires and cables shall be tested for continuity.

• All wires and cables shall be tested with a megger.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 57 of 64

• Lighting circuits and all general L.V. power services shall be tested during construction for

continuity, identification, and shall pass an operational test to see that the circuits perform

all functions for which they are designed.

Cables shall be visually inspected on the reels when received at the job site. Where

damage to metal-clad, metal-sheathed or shielded cables is suspected or indicated,

preliminary insulation tests shall be performed in accordance with the requirements of this

specification to determine that the cables are not less than those recommended by the

manufacturer. For nonmetallic sheathed and unshielded cables, special testing

arrangements may be necessary to proof-test cable insulation.

• Control wire and cables shall be checked by megger test, connections in accordance with

termination diagrams or tables, continuity of loops in accordance with elementary

diagrams and/or instrument loop drawings. All cables shall be identified in accordance

with appropriate tags on each end of the cable tested. The electrician shall attach a

temporary tag indicating the electrician's name and the date of testing the cable.

All solid-state devices shall be disconnected before megger tests are made.

• Test procedures - 380 volt service and less:

• Each 380 volt service cable from substations shall be meggered with the cable

connected to the open breaker in the racked position at the substation.

• Cables to individual motors shall be disconnected from motors for initial tests, and

followed by cables connected to motors.

• Cables to control centers shall be connected to the control center main breaker with

breaker in the open position during the test.

• Each phase shall be tested between conductor and ground and between phases,

except where the test includes windings, in which case the test may be applied

between all phases and ground.

• Minimum megger readings shall be:

10 mega-ohms for 380 volt services

5 mega-ohms for lower voltage services

� The megger test must be held until reading reaches a constant value. For 380 volt

cables, the megger test shall be held until three equal reading, each 1 minute apart,

are obtained.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 58 of 64

� A 1,000 volt motor-driven megger shall be used on all 380 volt cables and a 500 volt

motor driven megger shall be used on lower voltage cables.

• Test procedures for 6.6 kV cables and above:

� Each 6.6 kV cable from substations shall be tested with the cable connected to the

open breaker in the racked position at the substation.

� Cables to individual motors shall be disconnected from the motors for initial test, and

followed by tests on cables connected to motors.

� Cables to transformers shall be disconnected from transformer terminals but cable

termination shall be complete and intact. Testing shall not include any bus beyond the

pot-head or stress-cone terminations.

� All cable shall be tested between one (1) conductor and ground with the other two (2)

conductors and the metal sheath grounded to the same ground. Each conductor to be

tested in that manner.

� The dielectric absorption megger test shall be applied for duration long enough to fully

charge the cable. Megger readings shall be taken every 15 seconds during the first 3

minutes and at 1 minute intervals thereafter. The test shall continue until three equal

readings 1 minute apart are obtained. The cables should have approximately the

same megaohms reading. In the event that a cable shows an appreciably lower

resistance value than the others, it shall be brought to the attention of the Construction

Superintendent prior to application of the high-potential test.

� After an acceptable megger test, Contractor shall give the cables a high-potential test.

For metallic-armored, metallic-sheathed and metallic-shielded cables, the DC test

potential shall be 80 percent of the factory test voltage for 5 minutes. The test voltage

shall be applied gradually during the first minute, initial application being no greater

than rated. For unshielded nonmetallic jacketed cables, the test voltage shall not be

more than the rated voltage. All test values and results shall be in accordance with

IEC-Standards and the manufacturer's recommendations.

� The successful high-potential test shall be immediately followed by another megger

test as previously described.

� After completion of these tests, all conductors shall be discharged to ground.

� All cable which are pulled in duct bank or cable trench shall be tested tension during

pulling the cable and compare with the manufacture’s recommendation.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 59 of 64

7.5.11. BATTERY AND BATTERY CHARGER

• The following precautions should be taken before taking the battery in service:

� Check the battery cells for proper level of electrolyte, for specific gravity of electrolyte

by using a hydrometer, and for cracked jars.

� Check the cell connections and wiring for continuity and polarity.

� Check all protective devices for proper rating.

� Check the battery output voltage.

� All batteries shall be given a booster charge in accordance with the manufacturer's

instructions.

� Battery shall be discharged and recorded voltage, temperature, current and specific

gravity.

• Before energizing the battery charger, the battery should be connected across the output

terminal in such a manner that the positive battery terminal is connected to the positive

terminal of the charger. If the polarity of the battery terminals has been lost in a cable run,

a polarity check can be made pounding the AC supply switch to the charger and

connecting the battery leads to the output terminal of the charger. If it reads on scale, the

battery is connected correctly to the output terminal. It shall be verified that the battery

charger is delivering its maximum rated output.

• Chargers shall be tested in "Float" and “Equalizing” operation. Recorded Voltage in VDC

and Vrms at no-load and full load condition.

7.5.12. UNINTERRUPTIBLE POWER SYSTEMS (UPS)

• Preferably, an authorized manufacturer's representative should field-inspect and

commission uninterruptible power systems.

• In addition to routine inspection, the following minimum field checks and tests shall be

made:

� Adjustment of the battery charger for normal float and equalizing charge rates

including, as applicable, a check of the battery electrolyte or cell voltage.

� UPS shall be tested in “Float” and “Equalizing” operation. Record voltage and

waveform at no-load and full-load condition.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 60 of 64

� Short-circuit test to check the performance of the current-limit mode and, where

applicable, the operation of the transfer switch without loss of load.

� Transient-response tests, as applicable to the particular installation, including

measuring and recording the results.

� Simulation of all alarm conditions.

• For short-circuit and transient-response tests, equivalent test loads may be used when

the actual loads cannot be connected for test.

• Transient-response tests shall be made under the following conditions:

� Simulation of inverter failure and operation of the transfer switch without loss of load.

� Retransfer of full load to the inverter without loss of load.

� Simulation of a battery failure where facilities are provided to enable successful

inverter operation under this condition.

� Energization of the single largest inductive load or combination of loads which may be

energized simultaneously without loss of other operating loads.

7.5.13. EMERGENCY POWER

Emergency generation facilities shall be checked for automatic starting, generation and power

transfer during a simulated loss of voltage.

7.5.14. PACKAGED FACILITIES

• Where required or recommended by the manufacturer, special tests shall be performed to

confirm that equipment operation is in accordance with the intended service.

• Alarms for all electrical equipment shall be tested for proper operation by causing alarm

to sound under simulated abnormal conditions.

7.5.15. MISCELLANEOUS

• All other breakers, switches and conductor shall be given complete operational tests to

determine that all design functions are satisfactorily performed.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 61 of 64

• All switches (e.g. control, instrument, disconnect and safety), shall be inspected and

tested as to cleanliness and operation. Contacts, if so required, shall be cleaned before

operation.

• Switches shall be checked for correct sequence of operation. Fuses shall be inspected

for correct rating.

• Pressures, level, limit switches, etc. shall be inspected and tested in accordance with the

manufacture's recommendations. Adjustment shall be made so that switches will perform

the functions intended.

• Coordinate all testing of instruments for those devices.

• All bolts, which are held on bus bar, shall be measured torque. The values of torque shall

be compared with manufacture’s recommendations.

• All units, which are installed on the floor, shall be fixed with bolts in the floor.

7.5.16. EARTHING AND LIGHTNING SYSTEM

• Ground tests shall be accomplished with a proven instrument and shall include the

measurement of ground resistance at the following equipment items and structures:

� Medium high and low voltage switch gear

� All generators and motors

� Power transformer frames and neutral grounds

� Control Panels and consoles

� Panel boards

� Substation structures

� Lightning system components

� Equipotential bonding components

� Other miscellaneous grounds selected at random in a manner to be representative of

the entire installation.

• All connections shall be inspected before resistance measurement.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 62 of 64

• Ground resistivity test.

• Substation and plant ground system as a whole shall be tested using a four (4) terminal

Megger- Ground Tester on three occasions (with dry, normal, and wet ground conditions)

if possible.

• Each ground area shall measure less than 2.0 OHMS, ground resistance. Larger

substations and generating station areas shall measure resistance not to exceed 1 ohm.

Should higher resistance be obtained, existing ground rods shall be driven to a greater

depth by means of extensions or additional ground rods.

The final ground resistance measurement shall be taken with all grounds interconnected,

at which time the overall ground resistance shall be less than 2.0 ohms.

7.5.17. CAPACITOR BANK

All capacitors bank shall be tested and inspected as the following test and inspection, but not

limited to:

• All capacitors shall be inspected after installation and shall be checked for competence

with the following:

� Damage incurred in transportation.

� Check mounting for capacitors.

� Check that frame is grounded.

� No leakage of oil.

• Insulation resistance shall be one minute megger test and shall be recorded the values of

insulation resistance. The values of insulation shall be minimum as per table 1.

• In addition to the megger test, high potential test shall be performed. The sequence of

megger and high potential test shall be:

� Megger tests shall be made to determine the condition of insulation.

� The high potential test shall be applied only if the megger test passes minimum

requirements.

� The successful high potential test shall be followed immediately by another megger

test in order to detect any damage incurred by high voltage stresses.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 63 of 64

� All control, alarm and metering circuits shall be checked.

� The results of all tests shall be in accordance with the manufacture’s commendations.

� Resistor Discharge test.

7.5.18. METER AND TRANSDUCER

All meters and transducers shall be inspected before energizing and shall be calibrated after

energizing.

7.5.19. LIGHTING SYSTEM

• All lightings shall be inspected after installation and shall be checked for competence with

the following, but not limited to:

� All lighting shall be checked installation and compare with drawing.

� Damage incurred in transportation.

• In each area shall be tested illumination level. The values of illumination level shall refer

to specification.

• All lightings shall be energized for forty-eight (48) hours.

LSP COMPLEX PROJECT

Package A – Olefins and Central Utility Plant ITB Volume I – Annex C

Rev.: 0 Long Son Petrochemicals Co., Ltd

Document No.: CON - 006 Sheet: 64 of 64

8. MISCELLANEOUS ITEMS

All equipment, materials, infrastructure and other supplies not specifically mentioned in this

specification but forming part of Contractor’s Scope of Work/supply shall be tested and

inspected as follow

• Equipment, materials and supplies which can be allocated to any of the preceding shall

be tested and inspected as described therein.

• For equipment, materials and supplies, which cannot be allocated, the type and scope of

inspection and testing shall be specified by Contractor.

All above-mentioned equipment, materials and supplies shall be included in Contractor’s

Inspection Specification, without any cost to Owner.