Upload
almaporyak
View
233
Download
2
Embed Size (px)
Citation preview
8/12/2019 Commissioning Plan Step 2 - RevA
1/64
PRINCE MOHAMMAD BIN ABDULAZIZ INTERNATIONAL AIRPORT IN MEDINA (SAUDI ARABIA)
CONSULTANCY SERVICES FOR
TEST &COMMISSIONING PLAN
STEP 2:DRAFT COMMISSIONING PLAN
8/12/2019 Commissioning Plan Step 2 - RevA
2/64
8/12/2019 Commissioning Plan Step 2 - RevA
3/64
MAJV
Consultancy Services for Test & Commissioning Plan
1 FOREWORD1. Reference is made to the Services Agreement for Consultancy Services for Test and
Commissioning Plan and to its Attachment 1.
2. As per Attachment 1 chapters 4.3 & 5, the Step 2 (Draft Commissioning Plan) is defined as:A draft version of the Test & Commissioning Plan, that will be further amended after writing of the
Specifications per System and to take into account comments from the Subcontractors.
The Test & Commissioning Plan will:
a. Advise about the organization of the Test & Commissioning team at the EPC level;
b. Identify the exhaustive list of subsystems and systems to be tested and commissioned, with the
Subcontractors that will provide them;
c. Define the successive and progressive Test & Commissioning steps (as addressed in paragraph 4.1),
from Factory Acceptance Test and Test Lab test till final integration, including O&M documentation;
d. Provide Guidelines for the writing of the Commissioning Specification per System;
e Provide Guidelines for the test principles (full testing random method average )
8/12/2019 Commissioning Plan Step 2 - RevA
4/64
MAJV
Consultancy Services for Test & Commissioning Plan
2 COMMISSIONING ORGANIZATION2.1 COMMISSIONING SCOPE
Commissioning is a systematic process of ensuring that all building systems perform
interactively according to the design intent and the owners operational needs.
The Commissioning process is intended to achieve the following specific objectives:
Ensure that applicable equipment and systems are installed according to themanufacturers recommendation and to the industry acceptable standards and that they
receive adequate operational check-out by the installing contractors.
Verify and document proper performance of equipment and systems and the inter-relationship between systems.
Ensure readiness and integration of all systems allowing starting ORAT phase
2.2 COMMISSIONING PROCESS2.2.1 PHASES
In order to cope with the above scope, a commissioning process in 5 phases will be followed.
8/12/2019 Commissioning Plan Step 2 - RevA
5/64
MAJV
Consultancy Services for Test & Commissioning Plan
Phase 3:
This phase is covering all tests from phase 2 to phase 4 which means communication tests,remote functional tests, performance tests and interface tests (phase 3.11). Interface tests
are numbered 3.11 but all interfaces must be tested as soon as possible through mock ups or
site platforms in order to validate at the soonest the proper implementation on site (risk is
lower if the interface has already been tested in phase 0)
This phase requires Network
Phase 4:
This phase is covering the integrated tests and is based on a couple of scenario in order to
ensure the full integration of all systems before starting the Operational Trials (ORAT).
This phase requires all systems to be commissioned up to phase 3
All the above phases and related reports will be a prerequisite with the As built drawings, the
O&M manuals and the Training for the handover of the project and the start of the defect
liability period.
2.2.2 COLOR CODINGR f i t b l hi h i th h litti d t ll th t fl h t
8/12/2019 Commissioning Plan Step 2 - RevA
6/64
MAJV
Consultancy Services for Test & Commissioning Plan
30th
May 2013Revision A Page 6 of 13
Package
Mechanical
Package
Electrical/ULV
Package
IT
Package
Conveying
Package
Screening
Package AGL
Phase 1Mechanical installation
Phase 1Electrical installation
Phase 1IT installation
Phase 2Power up/Setting up
Phase 2Deployment/Local functional tests
Phase 3Remote functional tests/Performance tests
Phase 3.11Interface tests
Phase 4Integrated tests
Handover to ORAT
Phase 0FAT/Platform tests
Building areas handed over
Power available
LAN operational
All systems commissioned in stand alone mode
8/12/2019 Commissioning Plan Step 2 - RevA
7/64
MAJV
Consultancy Services for Test & Commissioning Plan
30th
May 2013Revision A Page 7 of 13
2.3 COMMISSIONING TEAM
Below is described a possible organization for the commissioning team. The number of Commissioning Package manager can be reduced pending on
the manager skills (for example, the Commissioning Conveying manager could also manage the Screening commissioning package).
8/12/2019 Commissioning Plan Step 2 - RevA
8/64
MAJV
Consultancy Services for Test & Commissioning Plan
a. Commissioning ManagerManaging the overall commissioning of the project
Interfacing with all package managers and the design department
Reporting to the Project Manager
b. Commissioning Team ManagerManaging all package commissioning manager
Organizing all phase 3.11 interface test (in coordination with the Integration manager)
Reporting to the Commissioning Manager
c.
Integration ManagerWriting the Integrated test procedures used during phase 0.1 and phase 4
Organizing all the phase 0.1 and phase 4 tests
Reporting to the Commissioning Manager
d. LEED CxSupervising the Electrical/Mechanical subcontractor in all aspects related to LEED
Witnessing tests related to the LEED certification
Producing the Summary Commissioning Report as per LEED requirements.
Reporting to the Commissioning Manager
e. Package Commissioning ManagerManaging the sub contractor in all aspects related to commissioning
Reviewing all test procedures/sheets provided by the subcontractor
Witnessing all functional tests
R i h C i i i
8/12/2019 Commissioning Plan Step 2 - RevA
9/64
MAJV
Consultancy Services for Test & Commissioning Plan
3 COMMISSIONING PLAN FOR ALL SYSTEMSFor all following systems, two documents have been developed:
- One flow chart showing graphically the sequence of the commissioning phases and thelinks with internal and external tasks.
- One Excel sheet detailing each commissioning phase in term of content, pre-requisites,attendees,
List of the systems in line with Step 1 analysis:
- Package Electricalo VDGS/GOSo FASo PASo SMISo SACS
8/12/2019 Commissioning Plan Step 2 - RevA
10/64
8/12/2019 Commissioning Plan Step 2 - RevA
11/64
MAJV
Consultancy Services for Test & Commissioning Plan
30th
May 2013Revision A Page 11 of 13
System name
External
prerequisite
External
interface
Commissioning
phase where
subcontractor
is alone
Commissioning
phase where
several
subcontractors
are required
8/12/2019 Commissioning Plan Step 2 - RevA
12/64
MAJV
Consultancy Services for Test & Commissioning Plan
30th
May 2013Revision A Page 12 of 13
Package Phase Descript io n Cont ent Spli t t ing Procedure At t end ees Prerequisit es Remarks
PBB Phase 1.1 PBB
Mechanical
Installation o f all PBB mechanical
items
- qualit y check
- l evel/alignment
- torque
per st and by T hys sen - Thyssen
- M AJV Package
team
-stand area handed over by Building
- anchor bol ts installed (contro lled by Thyssen)
- all drawings/documents approved
- material available
Fixed link bridge to b e ready to finalize
connection with PBB
Phase 1.2 PBB
Electrical
Installation of all PBB electrical
components (panels, trunking,
cables, senso rs )
- qualit y check
- termination
- labelling
per st and by T hys sen - Thyssen
- M AJV Package
team
- Phase 1.1PBB Mechanical done
- all drawings/documents approved
- material available
Phase 2.1PBB Power up for all PBB electrical
cabinets
- continuity/insulation test
- power up
- phase rotation
per st and by T hys sen - Thyssen
- M AJV Package
team
- Phase 1.2 PBB Electrical do ne
- power available fro m Building (including feeding
cables)- no major M echanical/Electrical snags
- all drawings/documents approved
Possible to start with g enerator power
To install VDGS operator panel during
this p hase.
Phase 2.2 PBB Commiss ioning of the PBB - funct ional tes ts
- safety tests
- anticollision tests
per st and by T hys sen - Thyssen
- MA JV Package team
- M A JV
Commissioning
- Phase 2.1PBB done
- all drawings/documents approved
Phase 1.1GPU
Mechanical
Installation o f all GPU mechanical
items
- qualit y check
- l evel/alignment
- torque
per s tand by Thyssen - Thyssen/AXA
- M AJV Package
team
- Phase 1.1PBB Mechanical done (including f ixing f rames)
- all drawings/documents approved
- material available
To do one asap and to perform the
rest all to gether when all PBB' s are
ready.
GPU includes PBB connected units and
standalone units.
Phase 1.2 GPU
Electrical
Installation of all GPU electrical
components
- qualit y check
- termination
- labelling
per s tand by Thyssen - Thyssen/AXA
- M AJV Package
team
- Phase 1.1GPU M echanical done
- all drawings/documents approved
- material available
Phase 2 GPU Commissioning of the GPU - continuity/insulation test
- power up
- phase rotation
- configuration
- f unctional tests
per s tand by Thyssen - Thyssen/AXA
- MA JV Package team
- M A JV
Commissioning
team
- Phase 1.2 GPU Electrical done
- power available fro m Building (including feeding
cables)
- no major M echanical/Electrical snags
- all drawings/documents approved
Phase 1.1
PCA/Hose
Mechanical
Installation of all PCA/Hose
mechanical items
- qualit y check
- l evel/alignment
- torque
per s tand by Thyssen - Thyssen/AXA
- M AJV Package
team
- Phase 1.1PBB Mechanical done (including f ixing f rames)
- all drawings/documents approved
- material available
To do one asap and to perform the
rest all to gether when all PBB' s are
ready
Phase 1.2
PCA/Hose
Electrical
Installation of all PCA/Hose
electrical components
- qualit y check
- termination
- labelling
per s tand by Thyssen - Thyssen/AXA
- M AJV Package
team
- Phase 1.1PCA/ Hose Mechanical done
- all drawings/documents approved
- material available
Phase 2
PCA/Hose
Commissioning of the PCA/Hose - continuity/insulation test
- power up
- phase rotation
- configuration
- f unctional tests
per s tand by Thyssen - Thyssen/AXA
- MA JV Package team
- M A JV
Commissioning
team
- Phase 1.2 PCA/ Hose Electrical do ne
- power available fro m Building (including feeding
cables)
- no major M echanical/Electrical snags
- all drawings/documents approved
Phase 3 .11 PB B Int erf aces t est s - int erlo ck t est s wi th
PCA/GPU/VDGS
- interface tests with
MCS/SCADA/TOIP/FAS
per s tand by Thyssen - Thyssen/AXA
- Safegate
- MA JV Package team
- M A JV
Commissioning
team
- Phase 2.2 PBB and Phase 2 GPU/PCA/Hose done
- network connection available
- VDGS/M CS/SCADA/T OIP/FAS avai lable
- no major Phase 2 snags
- all drawings/documents approved
FAS interface is just a signal (dry
contact)
GPU/PCA interface with PBB with dry
contacts then PBB to SCADA by
software.
Phase 3.12 PBB Performance test and degraded
mode
- power b reak down t ests
(UPS/Batt ery, Generator ,
Tow bar)
- water test
per s tand by Thyssen - Thyssen/AXA
- MA JV Package team
- M A JV
Commissioning
team
- Phase 2.2 PBB done
- all drawings/documents approved
Phase 4.01 Integrated test Aircraft Arrival and
Departure scenario
one s tand by M A JV - A ll i nvo lved sub
contractors
- MA JV Package team
- M A JV
Commissioning
team
- Investor and Investor IE
- Phase 3.11and 3.12 PBB d one
-GOS/RM S/Bi l l ing avai lable
- availability of an aircraft
- all drawings/documents approved
If aircraft with engines ON, possible to
validate the complete process
including RMS/GOS/VDGS/Billing
with flight schedule and block
ON/OFF.
If aircraft with engines OFF, to
concentrate on PBB/GPU/PCA.
System name
List of all
phases. One box
= one Excel line
Detail the
content of
each phase
Indicate the way the phase will be split
from a functional/geographical point of
view. This is the basis of the step 3.
Who is supposed to
write the test
procedures/sheetsWho is supposed to
attend the tests
List of external and
internal prerequisites
Remarks / Comments /
Reminders / Experiences
8/12/2019 Commissioning Plan Step 2 - RevA
13/64
MAJV
Consultancy Services for Test & Commissioning Plan
4 ANNEX 1
8/12/2019 Commissioning Plan Step 2 - RevA
14/64
8/12/2019 Commissioning Plan Step 2 - RevA
15/64
8/12/2019 Commissioning Plan Step 2 - RevA
16/64
8/12/2019 Commissioning Plan Step 2 - RevA
17/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical PAS Phase 0.0 PAS Study - Schematic Diagram
- SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
- SAT Document
Electrical PAS Phase 0.2 PAS Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - BNJV
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
- Splitting Strategy Test
- Definition of PAS Commisioning Team (Main
Commisionning, Contractor and Sub Contractor
Representative)
DEPLOYMENTS
Electrical PAS Phase 2.00 PAS Installation of all IT hardware and network Report To IT's Table Complete by TAV-IT - BNJV/TAV-IT
- MAJV Package team
Electrical PAS Phase 2.11 PAS Power Up - Electrical realisation Complete by BNJV - BNJV
- MAJV Package team
Accessibility of area - Control Center
Electrical PAS Phase 2.12 PAS Deployment of PAS - Loudspeaker
- Amplifier
- Micro
- etc...
Complete by BNJV - BNJV
- MAJV Package team
Accessibilit y of area - Conformed at Split ting St rategy Test
- Following by Test Schedule Document
GLOBAL TEST
Electrical PAS Phase 3.10 PAS Communication Test - power up
- IT hardware configuration
by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
-Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- Network available for the line array
- all drawings/documents approved
- material available
- Communication Validated
E lec tri ca l PAS Ph as e 3. 11 PAS PAS In terfa ces Refer to Diagram by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Automatic Action
- response to alarm
- loss of communication
- Exchange Table
- Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
Electrical PAS Phase 3.12 PAS PAS Functionnalities - Redundancies
- Automatic Annoucement
- Emergency\Priority
- Backup
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Monitoring
- Degraded Mode Philosophy
- etc..
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 40% Others
_Increased % if Crashed Test
Electrical PAS Phase 3.13 PAS PAS Zoning Test - Emergency Announced
- Operationnal Announced
per PAS Zone by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
Phase 3.10 Done -STI Measurement
- Confomity of End Device
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
OPERATIONNAL TESTAll Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
All Phase 4.02 Safety Integrated Test - Safety processus Verification per FAS Zone by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Safety Scenarios
8/12/2019 Commissioning Plan Step 2 - RevA
18/64
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
CommissioningDocument
BuildingMEP
Phase 2.11Electrical Deployment
Phase 2.00
IT LAN Deployment
Phase 3.10
CommunicationTest SMIS
Package Electrical
SMIS
SMIS FAT could be the same than both FATCCTV, SACS.
Global
Deployment or Study Step
Step depending of another SubPackage orPackage
Integrated Commissioning Step
Link with a Mirror Step ofAnother Package
Phase 3.11SACS Interface
Phase 3.11CCTV Interface
Phase 3.11SMIS
Interfaces
Phase 3.11SCADA Interface
Phase 3.12SMIS
Functionalities
Phase 4.01
INTEGRATED TEST
Operational AirportCommissioning under Scenario
Phase 0.1Test PlatformSMIS FAT
HMI
Functionnalities
.
SMIS depends of SACS and CCTV realization
Phase 0.1
SACS FAT
Phase 01
CCTV FAT
Commissioning Step (Stand Alone)
Phase 2.12SMIS Deployment
Phase 0.2
Site Organization
8/12/2019 Commissioning Plan Step 2 - RevA
19/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical SMIS Phase 0.0 SMIS Study - Schedule of SMISs
- FAT and SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
Electrical SMIS Phase 0.1 SMIS Test Platform - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- Redundancy
- SMIS Management
by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FAT Document Validated This FAT could be use to be CCTV and SACS one also.
Electrical SMIS Phase 0.2 SMIS Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - BNJV
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
DEPLOYMENTS
Electrical SMIS Phase 2.00 SMIS Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
Electrical SMIS Phase 2.11 SMIS Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
- handover of the area by Building and MEP
- power available
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical SMIS Phase 2.12 SMIS Deployment of SMIS device - Connection
- labelling
- Servers and Workstation
per Area n by BNJV - BNJV
- MAJV Package team
- material available
- all drawings/documents approved
GLOBAL TEST
Electrical SMIS Phase 3.10 SMIS Communication Test - power up
- IT hardware configuration
per Area by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Phase 3.10
- all drawings/documents approved
- Communication Validated between SMIS equipment
and between interfaced VLAN (CCTV, SACS)
E le ct ri ca l S MI S P hase 3. 11 SM IS S MI S I nt er face s Refer to Diagram per Type by BNJV - BNJV- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 Done- all interfaced systems available
- Automatic and Manual Action- Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
Electrical SMIS Phase 3.12 SMIS SMIS Functionnalities - Validation In-Site of FAT
- Backup
- Redundancy
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 Done - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 30% Others
_Increased % if Crashed Test
OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
8/12/2019 Commissioning Plan Step 2 - RevA
20/64
8/12/2019 Commissioning Plan Step 2 - RevA
21/64
Package Electrical
8/12/2019 Commissioning Plan Step 2 - RevA
22/64
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0Commissioning
Document
Phase 0.1Test Platform
SMIS FAT
BuildingMEP
Phase 2.11
Electrical Deployment
Phase 2.13Camera Deployment
Phase 2.20Unit TestCamera
Phase 2.00IT LAN Deployment
Phase 3.10Communication
Test
Per area
Per area
Phase 3.13Global Camera Test
Phase 3.11CCTV
Interfaces
Phase 3.12CCTV
Functionalities
Network
Elec
ManagementSystem
IT + ELEC
cam
TEST CAMERA PHASE 3.13
SCS
Package Electrical
CCTV
Stand Alone Test Equipment
FAT Validation
Per area
Global
Camera Management
HMIFunctionnalities
.
TEST CAMERA PHASE
2.20
Stand
AloneMoving Unit
Test
ELEC For
Mobile Camera
Phase 2.12
SCS Deployment Per area
Commissioning Step
Deployment or Study Step
Step depending of another SubPackage orPackage
Integrated Commissioning Step
Phase 4.01
INTEGRATED TESTOperational AirportCommissioning under Scenario
MCS
Phase 3.11SMIS
Interface CCTV
Link with a Mirror Step of
Another Package
Phase 0.2Site Organization
8/12/2019 Commissioning Plan Step 2 - RevA
23/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical CCTV Phase 0.0 CCTV Study - Schedule of CCTVs
- Definition of CCTVs Type
- FAT and SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory
Electrical CCTV Phase 0.1 SMIS Test Platform - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- Redundancy
- Recording Philosophy
- CCTV Management
by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FA T Document Val idat ed Funct ionnal Design is fina li zed wit h a ccepta nce of FAT
realization
- Defined Clearly VMS Interfaces between Hardware
and Software
Electrical CCTV Phase 0.2 CCTV Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - BNJV
- MAJV Package team- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
DEPLOYMENTS
Electrical C CTV Phas e 2.00 CCTV Installatio n o f all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/ TAV-IT
- MAJV Package team
Electrical CCTV Phase 2.11 CCTV Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
- handover of the area by Building and MEP
- power available
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical CCTV P hase 2.12 CCTV Deployment of SCS - Outlet Validation per Area n by BNJV - BNJV
- MAJV Package team
- handover of the area by Building and MEP
- floor IDF with switches available
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical CCTV Phase 2.13 CCTV Deployment of CCTV device - quality check
- level/alignment
- Connection
- labelling
per Area n by BNJV - BNJV
- MAJV Package team
- handover of the area by Building and MEP
- to follow the progress of phases 2.11 and
2.12
- material available
- all drawings/documents approved
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
- Installation with In-site Parameters indeed
UNIT TEST
Electrical CCTV Phase 2.20 CCTV Deployment of Unit Test CCTV - Unit Physical Test
- Utilization of a End Device Test
Tools.
per Area n-1 by BNJV - BNJV
- MAJV Package team
- MAJV Commissioning team
- Phase 2.xx Done
- all drawings/documents approved
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
6 The tool can record a picture of onsite camera and
prepared a final document report par area to validate
Quality and point of view.
GLOBAL TEST
Electrical CCTV Phase 3.10 CCTV Communication Test - power up
- IT hardware configuration
per Area by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Phase 3.10
- all drawings/documents approved
- Communication Validated
E lect rica l CCTV P ha se 3 .1 1 CCTV CCTV I nt erfa ces Refer to Diagram per Type by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 Done
- all interfaced systems available
- Automatic and Manual Action
- Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
Electrical CCTV Phase 3.12 CCTV CCTV Functionnalities - Validation In-Site of FAT
- Recording
- Backup
- Redundancy
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 Done - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- WallScreen behaviour, User Management
- Recording
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 20% Others
_Increased % if Crashed Test
Electrical CCTV P hase 3.13 CCTV Global Camera Test - Validation Camera on VMS(Archiver, Viewer, Intrusion
detection, etc..)
per Area by BNJV - BNJV- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Ph as e 3 .1 0 a nd 2. 20 Do ne - Be ha vi ou r o f e ac h C am er a o n V MS So ft wa re- Name, Correct View, Function, Default
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 20%
_Increased % if Crashed Test
OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
8/12/2019 Commissioning Plan Step 2 - RevA
24/64
8/12/2019 Commissioning Plan Step 2 - RevA
25/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical
SCADA
Phase 0.0 SCADA Study - Schedule of SCADAs
- FAT and SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
Electrical
SCADA
Phase 0.1 SCADA Test Platform - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- Redundancy
- SCADA Management
by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FAT Document Validated Like all HMI's, a FAT is recommended to ensure
consistency between End-User needs and the tools.
Electrical
SCADA
Phase 0.2 SCADA Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - BNJV
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
DEPLOYMENTS
Electrical
SCADA
Phase 2.00 SCADA Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
Electrical
SCADA
Phase 2.11 SCADA Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
- handover of the area by Building and MEP
- power available
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical
SCADA
Phase 2.12 SCADA Deployment of SCADA device - Connection
- labelling
per Area n by BNJV - BNJV
- MAJV Package team
- material available
- all drawings/documents approved
Servers and Workstations
GLOBAL TEST
Electrical
SCADA
Phase 3.10 SCADA Communication Test - power up
- IT hardware configuration
per Area by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Phase 2.xx
- all drawings/documents approved
- Communication Validated between SCADA
equipment and between interfaced VLAN (CCTV,
SACS)
Electrical
SCADA
P hase 3. 11 SC AD A S CA DA I nt er face s Refer to Diagram per Type by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 Done
- all interfaced systems available
- Automatic and Manual Action
- Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
Electrical
SCADA
Phase 3.12 SCADA SCADA Functionnalities - Validation In-Site of FAT
- Backup
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 Done - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 30% Others
_Increased % if Crashed Test
OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Package Electrical
8/12/2019 Commissioning Plan Step 2 - RevA
26/64
Consultancy Services for Test & Commissioning Plan
Phase 0.0Commissioning
Document
Building
MEP
Phase 2.11Electrical Deployment
Phase 2.12
IPTV Deployment
Phase 2.00IT LAN Deployment
Phase 3.10Communication
Test IPTV
Package Electrical
IPTV
Global
Global
Commisionning Step
Deployment or Study Step
Step depending of another SubPackage orPackage
Key Elements
End Device Out of Scope
Integrated Commisionning Step
Link with a Mirror Step ofAnother Package
8/12/2019 Commissioning Plan Step 2 - RevA
27/64
Package Electrical
8/12/2019 Commissioning Plan Step 2 - RevA
28/64
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0Commissioning
Document
BuildingMEP
Phase 2.11
Electrical Deployment
Phase 2.12MCS Deployment
Phase 2.00IT LAN Deployment
Phase 3.10Communication
Test MCS
Phase 3.11Interface Test
g
MCS
Loadcharge
Wide System Interfaced
Global
Global
Deployment or Study Step
Step depending of another SubPackage orPackage
Integrated Commisionning StepCommisionning Step (Stand Alone)
Link with a Mirror Step ofAnother Package
8/12/2019 Commissioning Plan Step 2 - RevA
29/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical
MCS
Phase 0.0 MCS Study - Schedule of Clock
- Definition of Clock Type
- ICD global described each
Interface
- FAT and SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory
DEPLOYMENTS
Electrical
MCS
Phase 2.00 MCS Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
Electrical
MCS
Phase 2.11 MCS Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical
MCS
Phase 2.12 MCS Deployment of MCS device - quality check
- level/alignment
- termination
- labelling
Global by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
- Installation of CLOCK with In-site Parameters indeed
GLOBAL TEST
Electrical
MCS
Phase 3. 10 MC S Communica tion Test - power up
- IT hardware configuration
Global by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
-Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
- Communication Validated
Electrical
MCS
Phase 3.11 MCS Interface Test - Verify Reception by at least one
other vlan that NTP signal is
received
Global by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
Phase 3.10 Done MCS Final Validation
Package Electrical
VDGS/GOS
8/12/2019 Commissioning Plan Step 2 - RevA
30/64
Phase 1
VDGS
Phase 2
VDGS
Supports(post,
gantry)
AODB/FIDS
SCADA
MCS (NTS)
VDGS/GOS
Consultancy Services for Test & Commissioning Plan
Phase 4.01Phase 1
GOSPhase 2
GOS
Phase 3.11
GOS
Apronpainting
Phase 1.2PBB
Electrical
Power LAN
Data center/Control Room
PBB
Phase 3.11
VDGS
EMS/SCADA?
Phase 3.12GOS
Phase 3.10GOS
8/12/2019 Commissioning Plan Step 2 - RevA
31/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Electrical
VDGS/GOS
Phase 1 VDGS Installation of all mechanical/electrical items - quality check
- level/alignment
- termination
- labelling
pe r s tand b y S afe gate - Saf egat e
- MAJV Package team
- stand area handed over by Building with proper
supports
- Phase 1.2 PBB Electrical done (to fix the
operator panel in PBB cabin)
- all drawings/documents approved
- material available
Phase 2 VDGS Power up and commissioning - continuity/insulation test
- power up
- setting up
- functional test
pe r s tand b y S afe gate - Saf egat e
- MAJV Package team
- MAJV Commissioning team
- Phase 1 VDGS done
- apron painting done
- building power available
- all drawings/documents approved
Possible to perform this phase with temporary apron
marking and temporary power.
Phase 3.11 VDGS Interface test of the system - interlock test with PBB
- interface test with EMS/SCADA
pe r s tand b y S afe gate - Saf egat e
- MAJV Package team- MAJV Commissioning team
- Phase 2 VDGS done
- PBB/EMS/SCADA available- all drawings/documents approved
Interface with EMS/SCADA to be clarified by MAJV
Phase 1 GOS Installation of all IT hardware and network - quality check
- cable test
- termination
- labelling
c om pl ete b y S afe gate - Saf egat e
- MAJV Package team
- data centers/control room (power socket, data
sockets, light, A/C) handed over
- all drawings/documents approved
- material available
Phase 2 GOS Power up and commissioning - power up
- IT hardware configuration
- functional test
c om pl ete b y S afe gate - Saf egat e
- MAJV Package team
- MAJV Commissioning team
- Phase 1 GOS done
-power available
- all drawings/documents approved
Possible to start with temporary power
Phase 3.10 GOS Communication tests - communication tests
- fleet mix configuration
c om pl ete b y S afe gate - Saf egat e
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2 VDGS and GOS done
- LAN available
- all drawings/documents approved
To ensure the proper/definitive fleet mix is used (fleet mix
must be consistent between VDGS, GOS, RMS and Apron
marking)
Phase 3.11 GOS Interface test of the system - interface test with MCS
- interface test with SCADA
- interface test with AODB/FIDS
c om pl ete b y S afe gate - Saf egat e
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 GOS done
- LAN available
- all interfaced systems available
- all drawings/documents approved
Phase 3.12 GOS Remote functional tests and degraded modes - remote functional test (operational
scenario)
- degraded modes
c om pl ete b y S afe gate - Saf egat e
- MAJV Package team
- MAJV Commissioning team- Investor and Investor IE
- Phase 2 VDGS and Phase 3.10 GOS done
- LAN available
- all drawings/documents approved
Phase 4.01 Integrated test Aircraft Arrival and Departure scenario one stand by MAJV - All involved sub contractors
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 and 3.12 PBB done
- PBB/RMS/Billing available
- availability of an aircraft
- all drawings/documents approved
If aircraft with engines ON, possible to validate the
complete process including RMS/GOS/VDGS/Billing with
flight schedule and block ON/OFF.
If aircraft with engines OFF, to concentrate on
PBB/GPU/PCA.
Package Electrical
EMS/LCS
8/12/2019 Commissioning Plan Step 2 - RevA
32/64
Phase 1
Mechanical
Phase 1
Electrical
Phase 2.1
Power up
Phase 2.2
Static tests
BuildingElectrical
rooms
Phase 1EMS
Phase 3.10
EMS/LCS
IT rooms
IB
SCADA
Phase 2EMS
MCS (NTS)
VDGS?
EMS/LCS
Consultancy Services for Test & Commissioning Plan
Phase 3.12
EMS/LCS
Phase 3.13
EMS/LCS
Phase 3.11
EMS/LCS
LANPower Phase 4.01
Phase 1LCS
IT roomsPhase 2
LCS
AODB?
Power
8/12/2019 Commissioning Plan Step 2 - RevA
33/64
Package P hase Description Content Splitting Procedure Attendees Prerequisites Remarks
Electrical
EMS/LCS
Phase 1Mechanical Mechanical installation
- generator,
- UPS,
- Transformer
- central battery system
- all cabinets
- quality check
- fixing
- level/alignment
per major equipment by BNJV - BNJV
- MAJV package team
- all drawings/documents approved
- material available
FAT report/Material submital are mandatory to
ensure consistency with design.
Phase 1E lec tr ic al E lectrical in s tal lat io n
- trunking
- cables
- quality check
- cable fixing
- termination
- cold test/insulation test
per major equipment by BNJV - BNJV
- MAJV package team
# NO M? T he t ar ge t i s t o b e s af e t o e ne rg iz e ( im po rt an t s te p t o
be documented)
Phase 2.1Power up Power up for all equipment - power up
- voltage check
- phase rotation
- lamps
per major equipment by BNJV - BNJV
- MAJV package team
- LEED Cx
- phase 1 electrical done
- power available
- all drawings/documents approved
FAT report/Material submital are mandatory to
ensure consistency with design and to avoid
repeating all "internal" tests already performed in
factory.
Phase 2.2Static tests Static test - Live tests
- Earth resistance
per major equipment by BNJV - BNJV
- MAJV package team
- LEED Cx
p ha se 2. 1 po we r u p d on e A t a ll s ta ge s, LE ED Cx to ch ec k c om pl ia nc e w it h LE ED
requirements
Phase 1EMS Installation of all IT hardware - quality check
- termination
- labelling
per EMS controller by BNJV - BNJV
- MAJV package team
- IT rooms (finishes, A/C, light, desk)
available
- all drawings/documents approved
- material available
Phase 1LCS Installation of all IT hardware - quality check
- termination
- labelling
Complete by BNJV - BNJV
- MAJV package team
- IT rooms (finishes, A/C, light, desk)
available
- all drawings/documents approved
- material available
Phase 2EMS Power up - power up
- GUI check
- functional test
per EMS controller by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- LEED Cx
- phase 1 EMS done
- power available
Phase 2LCS Power up - power up
- GUI check
- functional test
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- LEED Cx
- phase 1 LCS done
- power available
Phase 3.10EMS/LCS Communication test - network address check
- exchange table check
- labelling and address control
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- LEED Cx
- phases 2.x done
- network available
Phase 3.11EMS/LCS Interface tests - interface tests with all impacted systems Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- LEED Cx
- phase 3.10 done
- all interfaced systems available
- ICD's approved
P ha se 3 .1 2E MS /L CS O per at ing t es t - R emo te c ont ro l - F au lt /st at us /me ter ing ch ec k
- control command test
- operational tests (Manual and Auto (time or
photocell))
- control and measuring of energy consumption
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- LEED Cx
- phase 3.10 done
Phase 3.13EMS/LCS Performance test - availability tests- endurance tests
- redundancy and backup power systems check,
- illumination check
Complete by BNJV - BNJV- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- LEED Cx
- phase 3.12 done
Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- LEED Cx
Phase 3 Done - Different Operationnal Scenarios
Main Prerequisites Synthesis
8/12/2019 Commissioning Plan Step 2 - RevA
34/64
BuildingMEP
SCS
IT LAN
ELEC
EndDevice
ControlDevice
EndDevice
ControlDevice
EndDevice
Communication between
End and Control Device
HardwareSoftware
Rack EquipmentFiber Wiring
Power
Cable Power
Power Providing IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTVPAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODBBRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
Prerequisites are necessary
Prerequisites must be countourned byusing adapted tools and methods
Package IT
LANS
8/12/2019 Commissioning Plan Step 2 - RevA
35/64
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
CommissioningDocument
Phase 0.2Site Organization
Phase 3.10
LANsCommunication
Test
LAN S
Integrated Commisionning Step
Deployment or Study Step
Step depending of another SubPackage orPackage
Commisionning Step (Stand Alone)
Building
MEP
Phase 2.11
Electrical Deployment
LANs Communication commissioning
Major Step
Phase 2.12
SCS Deployment
Per area
Phase 2.13
LANs Deployment
Phase 2.14LANs Configuration
Phase 4.01
INTEGRATED TESTOperational Beahvior
Commissioning under Scenario
Phase 3.12
LANsFunctionalities
Site Optimisation depends ofCompleteness Study
Phas e 2.00IT LAN DEPLOYMENT
Per area
Per area
Per area
Per area
Link with a Mirror Step of
Another Package
All Systems
A method should be edited to define how
lan's up of depending
8/12/2019 Commissioning Plan Step 2 - RevA
36/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Phase 0.00 ORGANISATION
IT LAN Phase 0.0 LAN Study - Schedule of LANs
- FAT and SAT Document
- IP Address List (ULV, IT, etc..)
and port configuration
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
- Final SD for each IT and ULV System
IP Address List is a Main Document.
It could improve considerably time on-site for :
_ Manage Interfaces
_ Reduce Time of Step Commisionning
IT LAN Phase 0.2 LAN Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
P ha se 2 . 00 D EP LO YM EN TS
IT LAN Phase 2.11 LAN Electrical Deployment - Electrical realisation per Area n by BNJV - BNJV- MAJV Package team
Accessibi lity of area - Conformed at Splitting Strategy Test- Following by Test Schedule Document
IT LAN Phase 2.12 LAN SCS Deployment - Outlet Validation per Area n by BNJV - BNJV
- MAJV Package team
Accessibil ity of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
IT LAN Phase 2.13 LAN Deployment of LAN device - Room quality check
- level/alignment
- Cable structure Acceptance
- labelling
per Area n-1 by TAV-IT - TAV-IT
- MAJV Package team
- power available
- all drawings/documents approved
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
IT LAN Phase 2.14 LAN LAN Configuration - power up
- IT hardware configuration
- IT Link validation
per Area n-1 by TAV-IT - TAV-IT
- MAJV Package team
-Phase 2.13 Done Integration of each VLAN
Integration of IP Management Requirement
Link\Trunk Configuration
ICT LAN
NIC
SGS, SA, etc
P ha se 3. 00 GLO BAL T ES T
IT LAN Phase 3.10 LAN Communication Test - Validation for each "User" of
Lan's that communication is
available
- Validation of Necessary
Gateways for "users" (MCS, etc)
per Area by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 2.14 Done If IP Adress List and port configuration had been
transmitted in Phase 2.14; this step could be a stand-
alone step realized by each Interfaced Users'.
Otherwise it could be i ntegrated test and time
consuming taskfor each representant.
IT LAN Phase 3.12 LAN LAN Functionnalities - Degraded Mode Philosophy
- Redundancy
- LAN Management
- Load Bandwitchvalidation
- Performance, QoS, etc
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done Validation of SAT
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 40% Others
_Increased % if Crashed Test
Phase 4.00 OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 .12 Done - Different Operationnal Scenarios
Package IT
AODB/RMS/IBSCADA EMS
8/12/2019 Commissioning Plan Step 2 - RevA
37/64
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0Commissioning
Document
Phase 0.1Test Platform
FAT
Phase 0.2
Site Organization
Phase 2.00
IT LAN Deployment
Phase 3.10
AODBCommunication
Test
Phase 3.12AODB
Funtionnalities
AODB/RMS/IB
FAT Validation
Global
ICDFunctionnalities
.
Phase 3.11AODB Interfaces
Integrated Commisionning Step
Deployment or Study Step
Step depending of another SubPackage orPackage
Phase 3.13ITS Functionalities
3.13.a RMS
A lot of InterfacesDetailed Analysys in Phase 0.0 needed
Phase 4.01
INTEGRATED TESTOperational Behavior
Commissioning under Scenario
Commisionning Step (Stand Alone)
Phase 3.11
CUPPS Interface
Phase 3.11
FIDS Interface
GOSIT MANAGEMENT
MCS
BRS
BHS
Link with a Mirror Step of
Another Package
Phase 2.10AODB Servers
8/12/2019 Commissioning Plan Step 2 - RevA
38/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Phase 0.00 ORGANISATION
IT AODB\IB\RMS Phase 0.0 AODB Study - Schedule of AODBs
- FAT and SAT Document
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory\Laboratory
Provide All necessary ICD Documents
IT AODB\IB\RMS Phase 0.1 AODB Test Platform - Degraded Mode Philosophy
- Redundancy
- AODB Management
- HMI Functionalities (RMS)
by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- F AT D oc um en t Va li da te d F un ct io nn al D es ig n is f in al iz ed w it h ac ce pt an ce o f FA T
realization
RMS Functionnalities
IT AODB\IB\RMS Phase 0.2 AODB Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 0.0 Done Definition of Test and Method
Phase 2.00 DEPLOYMENTS
IT AODB\IB\RMS Phase 2.00 AODB LAN deployment Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
IT AO DB\IB\RMS Phas e 2.10 AODB Dep lo yment o f AODB S ervers - Ins ta lla tion and Con figuratio n of AO DB
Servers
per room by TAV-IT - TAV-IT
- MAJV Package team
- power available
- all drawings/documents approved
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
Installation of AODB Server
Phase 3.00 GLOBAL TEST
IT AODB\IB\RMS Phase 3.10 AODB Communication Test - power up AODB Equipment Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Phase 2.10 Done
- AODB Network Configuration Done
Communication Validated
I T A OD B\ IB\ RMS P ha se 3 .1 1 A OD B A OD B I nte rf ac es Refer to Diagram per Type by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done Validation of all ICD
Validation of Exchange table
Validation of Request
Recommendations :
_ 100% Done by Contractor_ Commissioner : 100%
If available, to perform through RMS GUI's
IT AODB\IB\RMS Phase 3.12 AODB AODB Functionnalities - Degraded Mode Philosophy
- Redundancy
- AODB Management
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 3.10 Done Validation of SAT
Validation of Number of Workstationinstalled
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 40% Others
_Increased % if Crashed Test
IT AODB\IB\RMS Phase 3.13x IT Functionnalities Interfaces - HMI Functionnalities
- Redundance
- Degraded Mode philosophy
- Backup
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.11 Done
Phase 3.12 Done
Validation of RMS
Validation of Number of Workstation installed
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 20%
_Increased % if Crashed Test
Phase 4.00 OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT
- MAJV package team- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done Different Operationnal Scenarios
8/12/2019 Commissioning Plan Step 2 - RevA
39/64
8/12/2019 Commissioning Plan Step 2 - RevA
40/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Phase 0.00 ORGANISATION
IT BRS Phase 0.0 BRS Study - Schedule of BRSs
- FAT and SAT Document
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory\Laboratory
- Provide All necessary ICD Documents
IT BRS Phase 0.1 BRS Test Platform - Degraded Mode Philosophy
- Redundancy
- HMI Functionalities
by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- F AT D oc um en t Va li da te d F un ct io nn al D es ig n is f in al iz ed w it h ac ce pt an ce o f FA T
realization
BRS Functionnalities
IT BRS Phase 0.2 BRS Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
Phase 2.00 DEPLOYMENTS
IT BRS Phase 2.00 BRS Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
IT BRS Phase 2.10 BRS Deployment of BRS Servers - Installation and Configuration of BRS
Servers
by TAV-IT - TAV-IT
- MAJV Package team
- power available
- all drawings/documents approved
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
Installation of BRS Server
Phase 3.00 GLOBAL TEST
IT BRS Phase 3.10 BRS Communication Test - power up BRS Equipment Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Phase 2.10 Done
- BRS Network Configuration Done
- Communication Validated
IT BRS Phase 3.11 BRS BRS Interfaces Refer to Diagram per Type by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
IT BRS Phase 3.12 BRS BRS Functionnalities - Degraded Mode Philosophy
- Redundancy
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 3.10 Done - Validation of SAT
- Validation of Number of Workstationinstalled
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 40% Others
_Increased % if Crashed Test
IT BRS Phase 3.13 IT Functionnalities Interfaces - HMI Functionnalities
- Redundance
- Degraded Mode philosophy
- Backup
- Handset deployment
Global by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.11 Done
Phase 3.12 Done
- Validation of Number of Workstation installed
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 20%
_Increased % if Crashed Test
Phase 4.00 OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Package IT
CUPPS / CUSS
8/12/2019 Commissioning Plan Step 2 - RevA
41/64
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
CommissioningDocument
Phase 0.1
Test PlatformFAT
Phase 0.2
Site Organization
Building
MEP
Phase 2.11
Electrical Deployment
Phase 2.14CUPPS\CUSS Deployment
Phase 2.20
Unit TestCUPPS
Phase 2.00
IT LAN Deployment
Phase 3.10
CUPPSCommunicationTest
Per area
Per
StrategicZone
Phase 3.12
CUPPSFuntionnalities
MCS
FAT Validation
Per area
Global
HMIFunctionnalities
.
Phase 3.11
CUPPSInterfaces
Desk Interfaces
Phase 2.12
Desk Deployment Per area
Phase 2.13
SCS Deployment Per area
Deployment or Study Step
Step depending of another SubPackage orPackage
Phase 3.11AODB
Phase 4.01
INTEGRATED TESTOperational Behavior
Commissioning under Scenario
Integrated Commisionning StepCommisionning Step (Stand Alone)
Link with a Mirror Step of
Another Package
DCSInterface
8/12/2019 Commissioning Plan Step 2 - RevA
42/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
P ha se 0 .0 0 O RG AN ISA TI ON
IT CUPPS Phase 0.0 CUPPS Study - Schedule of CUPPSs
- Definition of CUPPSs Type
- FAT and SAT Document
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory
IT CUPPS Phase 0.1 CUPPS Test Platform - HMI Presentation
- CUTE\CUSS\CUPPS
- CUPPS Management
by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FA T Do cu me nt Va li da te d F un ct io nn al D es ig n is f in al iz ed w it h ac ce pt an ce of F AT
realization
IT CUPPS Phase 0.2 CUPPS Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
P ha se 2 .0 0 D EP LOY MEN TS
IT CUPPS Phase 2.00 IT LAN Installation of all IT hardware and network Report To IT's Table per Area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
IT CUPPS Phase 2.11 CUPPS Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
Accessibil ity of area - Con formed at Sp litting St rat egy Test
- Following by Test Schedule Document
IT CUPPS Phase 2.12 CUPPS Desk Deployment per Area n by MAJV - MAJV Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
IT CUPPS Phase 2.13 CUPPS SCS Deployment - Outlet Validation per Area n by BNJV - BNJV
- MAJV Package team
Accessibil ity of area - Con formed at Sp litting St rat egy Test
- Following by Test Schedule Document
IT CUPPS Phase 2.14 CUPPS Deployment of CUPPS device - quality check
- level/alignment
- termination
- labelling
per Area n by TAV-IT - TAV-IT
- MAJV Package team
Accessibil ity of area - Con formed at Sp litting St rat egy Test
- Following by Test Schedule Document
- Installation with In-site Parameters indeed
UNIT TEST
IT CUPPS Phase 2.20 CUPPS Deployment of Test CUPPS Phase 1 - Unit Physical Test per Area n-1 by TAV-IT - TAV-IT- MAJV package team
- MAJV Commissioning team
Phases 2.1x Done - Conformed at Splitting Strategy Test- Following by Test Schedule Document
P ha se 3.00 GLOBAL TEST
IT CUPPS Phase 3.10 CUPPS Communication Test - power up
- IT hardware configuration
per Area by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
-Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
- Communication Validated
IT CUPPS Phase 3.11 CUPPS CUPPS Interfaces Refer to Diagram per Type by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Validation of all ICD
- Validation of Exchange table
- Validation of Request
- Configuration with all required DCS
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
IT CUPPS Phase 3.12 CUPPS CUPPS Functionnalities - Validation In-Site of FAT Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team- Investor and Investor IE
Phase 3.10 Done - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy- Validation Number of CUTE\CUSS\CUPPS
P ha se 4 .0 0 O PE RA TI ON NA L T ES T
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Phase 2.00
Package Electrical & IT
FIDS
8/12/2019 Commissioning Plan Step 2 - RevA
43/64
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
CommissioningDocument
Phase 0.1
Test PlatformFAT
Phase 0.2Site Organization
BuildingMEP
Phase 2.11Electrical Deployment
Phase 2.13FIDS Deployment
Phase 2.20
Unit Test FIDS
Phase 2.00
IT LAN Deployment
Phase 3.10
CommunicationTest FIDS
Per area
Per area Phase 3.12FIDS
Funtionnalities
Link BNJV/IT
FAT Validation
Per area
Global
HMI
Functionnalities
.
Phase 3.11FIDS
Interfaces
Deployment or Study Step
Step depending of another SubPackage orPackage
Phase 2.12
SCS Deployment Per area
Integrated Commisionning StepCommisionning Step (Stand Alone)
ULV
Phase 4.01
INTEGRATED TEST
Operational BehaviorCommissioning under Scenario
Link with a Mirror Step ofAnother Package
Phase 2.14FIDS Servers
Phase 3.11PASMCS
Phase 3.11TOIP
Phase 3.11
AODB
8/12/2019 Commissioning Plan Step 2 - RevA
44/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
P ha se 0 .0 0 O RG AN IS AT IO N
IT FIDS Phase 0.0 FIDS Study - Schedule of FIDSs
- Definition of FIDSs Type
- FAT and SAT Document
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory\Laboratory
IT FIDS Phase 0.1 FIDS Test Platform - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- Redundancy
- FIDS Management
by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FA T Document Val idat ed Funct ionnal Design is fina li zed wit h a ccepta nce of FAT
realization
IT FIDS Phase 0.2 FIDS Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
P ha se 2. 00 D EP LO YM EN TS
IT FI DS P ha se 2. 00 IT LA N F ID S I ns ta ll at io n o f al l IT ha rd wa re a nd ne tw or k
FIDS Server
Report To IT's Table per Area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
IT FIDS Phase 2.11 FIDS Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
A ccessibility of area - Conf ormed at Splitting Strategy Test
- Following by Test Schedule Document
IT FIDS Phase 2.12 FIDS SCS Deployment - Outlet Validation per Area n by BNJV - BNJV
- MAJV Package team
A cces sibility of area - Conf ormed at Splitting Strategy Test
- Following by Test Schedule Document
IT FIDS Phase 2.13 FIDS Deployment of FIDS device - quality check
- level/alignment
- termination
- labelling
per Area n by TAV-IT - BNJV
- MAJV Package team
A cces sibility of area - Conf ormed at Splitting Strategy Test
- Following by Test Schedule Document
- Installation of FIDS with In-site Parameters indeed is
recommended
IT FIDS Phase 2.14 FIDS Deployment of FIDS Servers - Installation and Configuration of
FIDS Servers
by TAV-IT - TAV-IT
- MAJV Package team
- power available
- all drawings/documents approved
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
UNIT TEST
IT FIDS Phase 2.20 FIDS Deployment of Test FIDS Phase 1 - Unit Physical Test per Area n-1 by TAV-IT - TAV-IT- MAJV package team
- MAJV Commissioning team
Phases 2.1x Done - Conformed at Splitting Strategy Test- Following by Test Schedule Document
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 10%
_Increased % if Crashed Test
P ha se 3. 00 G LO BA L T ES T
IT FIDS Phase 3.10 FIDS Communication Test - power up
- IT hardware configuration
- interface test with LAN ICT
per Area by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
-Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
- Communication Validated
IT FIDS Phase 3.11 FIDS FIDS Interfaces Refer to Diagram per Type by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
If available, prefer to perform test with BHS\GOS
IT FIDS Phase 3.12 FIDS FIDS Functionnalities - Validation In-Site of FAT
- Backup
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
MID\WID\RID\SID etc.
- Validation of Number ofWorkstation installedRecommendations :
_ 100% Done by Contractor
_ Commissioner : 20%
_Increased % if Crashed Test
P ha se 4 .0 0 O PE RA TI ON NA L T ES T
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Package IT
TOIP
8/12/2019 Commissioning Plan Step 2 - RevA
45/64
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0Commissioning
Document
Phase 0.2Site Organization
Phase 2.00
Deployment of IT LAN
Phase 3.10
TOIPCommunication
Test
Phase 3.12TOIP Funtionnalities
End device Deployment need Servers
Configuration
Recommend to configure end-device in controlroom to ensure behaviour before connect and
do Unit Test
Phase 3.11
TOIP Interfaces
Integrated Commisionning Step
Deployment or Study Step
Step depending of another SubPackage or
Package
Phase 4.01
INTEGRATED TESTOperational Behavior
Commissioning under Scenario
Commisionning Step (Stand Alone)
Phase 3.11FIDS Interface
MCS
Link with a Mirror Step of
Another Package
Phase 2.10TOIP Servers
Phase 2.20
TOIPUnit Test
Phase 2.11TOIP
Deployment
8/12/2019 Commissioning Plan Step 2 - RevA
46/64
Package IT
WIFI
8/12/2019 Commissioning Plan Step 2 - RevA
47/64
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0Commissioning
Document
Phase 0.2Site Organization
Phase 2.00 WIFI
Deployment of IT LAN
Phase 3.10
WIFICommunication
Test
Commissioning Signal Quality per Zone
Global
Integrated Commisionning Step
Deployment or Study Step
Step depending of another SubPackage or
Package
Commisionning Step (Stand Alone)
Link with a Mirror Step of
Another Package
Phase 2.10WIFI
Controllers
Phase 3.11
WIFIZone Test
Phase 2.11Deployment Of Wifi Device Global
8/12/2019 Commissioning Plan Step 2 - RevA
48/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Ph as e 0 .0 0 O RGA NIS ATI ON
IT WIFI Phase 0.0 WIFI Study - Schedule of WIFIs
- SAT Document
- Phone List and Number
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
IT WIFI Phase 0.2 WIFI Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
Ph as e 2 .0 0 D EPL OYM ENT S
IT WIFI Phase 2.00 WIFI Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
IT WIFI Phase 2.10 WIFI Deployment of WIFI Contr ollers* - Installation and Configur ation of WIFI
Servers
by TAV-IT - TAV-IT
- MAJV Package team
- power available
- all drawings/documents approved
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
Installation of WIFI Server
IT WIFI Phase 2.11 WIFI Deployment of WIFI device - quality check
- Configuration
- labelling
per area by TAV-IT - TAV-IT
- MAJV Package team
Accessibility of area - Need Server to be configured
- Could be parameter in a "Control Room" to be sure
that End-device is on and optimize time deployment
and test
Ph as e 3 .0 0 G LO BA L T ES T
IT WIFI Phase 3.10 WIFI Communication Test - power up WIFI Equipment
- interface test with LAN ICT
Global by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Phase 2.10 Done
- WIFI Network Configuration Done
- Communication Validated
IT WIFI Phase 3.11 WIFI WIFI Zone Test - Qulaity of Signal deployed in the zone
- Bandwith with a lot of connected user
simultanously
- Check Acces Right Users
per area by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
P ha se s 3 .1 0 a nd 2. 11 Do ne - Co nf or me d a t S pl it ti ng St ra te gy Te st
- Following by Test Schedule Document
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 15%
_Increased % if Crashed Test
Package Conveying
PBB
GOS
8/12/2019 Commissioning Plan Step 2 - RevA
49/64
Phase 1.1PBB
Mechanical
Phase 1.2PBB
Electrical
Apron/
Anchor bolts
Power
TOIP
SCADA
Phase 2.1
PBB
MCS (NTS)
FAS
Consultancy Services for Test & Commissioning Plan
Phase 1.1GPU
Mechanical
Phase 1.2GPU
Electrical
Phase 1.1PCA/HoseMechanical
Phase 1.2PCAHoseElectrical
VDGS
Phase 2.2
PBB
Phase 3.12
PBB
Phase 2
GPU
Phase 2
PCA/Hose
LAN
Phase 4.01
GOS
Phase 3.11PBB
8/12/2019 Commissioning Plan Step 2 - RevA
50/64
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
PBB Phase 1.1 PBB Mechanical Installation of all PBB mechanical items - quality check
- level/alignment
- torque
per stand by Thyssen - Thyssen
- MAJV Package team
-stand area handed over by Building
- anchor bolts installed (controlled by Thyssen)
- all drawings/documents approved
- material available
Fixed link bridge to be ready to finalize connection with PBB
P ha se 1 .2 P BB E lect rica l I nsta llat ion of a ll P BB e lect rica l components (pa nels , trunking , ca bles, sensors ) - qua li ty check
- termination
- labelling
per stand by Thyssen - Thyssen
- MAJV Package team
- Phase 1.1 PBB Mechanical done
- all drawings/documents approved
- material available
Phase 2.1 PBB Power up for all PBB electrical cabinets - continuity/insulation test
- power up
- phase rotation
per stand by Thyssen - Thyssen
- MAJV Package team
- Phase 1.2 PBB Electrical done
- power available from Building (including
feeding cables)
- no major Mechanical/Electrical snags
- all drawings/documents approved
Possible to start with generator power
To install VDGS operator panel during this phase.
Phase 2.2 PBB Commissioning of the PBB - functional tests- safety tests
- anticollision tests
per stand by Thyssen - Thyssen- MAJV Package team
- MAJV Commissioning team
- Phase 2.1 PBB done- all drawings/documents approved
Phase 1.1 GPU Mechanical Installation of all GPU mechanical items - quality check
- level/alignment
- torque
pe r s tand b y T hy ss en - Th ys se n/ AXA
- MAJV Package team
- Phase 1.1 PBB Mechanical done (including fixing
frames)
- all drawings/documents approved
- material available
To do one asap and to perform the rest all together when
all PBB's are ready.
GPU includes PBB connected units and standalone units.
Phase 1.2 GPU Electrical Installation of all GPU electrical components - quality check
- termination
- labelling
pe r s tand b y T hy ss en - Th ys se n/ AXA
- MAJV Package team
- Phase 1.1 GPU Mechanical done
- all drawings/documents approved
- material available
Phase 2 GPU Commissioning of the GPU - continuity/insulation test
- power up
- phase rotation
- configuration
- functional tests
pe r s tand b y T hy ss en - Th ys se n/ AXA
- MAJV Package team
- MAJV Commissioning team
- Phase 1.2 GPU Electrical done
- power available from Building (including
feeding cables)
- no major Mechanical/Electrical snags
- all drawings/documents approved
Phase 1.1 PCA/Hose
Mechanical
Installation of all PCA/Hose mechanical items - quality check
- level/alignment
- torque
pe r s tand b y T hy ss en - Th ys se n/ AXA
- MAJV Package team
- Phase 1.1 PBB Mechanical done (including fixing
frames)
- all drawings/documents approved
- material available
To do one asap and to perform the rest all together when
all PBB's are ready
Phase 1.2 PCA/Hose
Electrical
Installation of all PCA/Hose electrical components - quality check
- termination
- labelling
pe r s tand b y T hy ss en - Th ys se n/ AXA
- MAJV Package team
- Phase 1.1 PCA/Hose Mechanical done
- all drawings/documents approved
- material available
Phase 2 PCA/Hose Commissioning of the PCA/Hose - continuity/insulation test- power up
- phase rotation
- configuration
- functional tests
pe r s tand b y T hy ss en - Th ys se n/ AXA- MAJV Package team
- MAJV Commissioning team
- Phase 1.2 PCA/Hose Electrical done- power available from Building (including
feeding cables)
- no major Mechanical/Electrical snags
- all drawings/documents approved
Phase 3.11 PBB Interfaces tests - interlock tests with PCA/GPU/VDGS
- interface tests with MCS/SCADA/TOIP/FAS
pe r s tand b y T hy ss en - Th ys se n/ AXA
- Safegate
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2.2 PBB and Phase 2 GPU/PCA/Hose done
- network connection available
- VDGS/MCS/SCADA/TOIP/FAS available
- no major Phase 2 snags
- all drawings/documents approved
FAS interface is just a signal (dry contact)
GPU/PCA interface with PBB with dry contacts then PBB to
SCADA by software.
Phase 3.12 PBB Performance test and degraded mode - power break down tests (UPS/Battery,
Generator, Tow bar)
- water test
pe r s tand b y T hy ss en - Th ys se n/ AXA
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2.2 PBB done
- all drawings/documents approved
Phase 4.01 Integrated test Aircraft Arrival and Departure scenario one stand by MAJV - All involved sub contractors
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 and 3.12 PBB done
- GOS/RMS/Billing available
- availability of an aircraft
- all drawings/documents approved
If aircraft with engines ON, possible to validate the
complete process including RMS/GOS/VDGS/Billing with
flight schedule and block ON/OFF.
If aircraft with engines OFF, to concentrate on
PBB/GPU/PCA.
Phase 2.2HBS CT
Package Conveying
BHS Phase 2.2OOG inline
8/12/2019 Commissioning Plan Step 2 - RevA
51/64
Phase 1BHS SW &
Grating
Phase 1BHS
Mechanical
Phase 1.1BHS
Electrical
Phase 2.1
BHS PLC
Phase 2.2
BHS PLC
Phase 2.3
BHS PLC
Phase 3.11BHS
Interfaces
Phase 4.01Building
MEP
Normal &UPS power
Phase 1.1BHS IT
Phase 2.1BHS IT (Scada)
Phase 3.10BHS IT (SAC)
BHScontrol
room
Phase 1
BHS CCTV
Phase 2.1
BHS CCTV
AODB (FIDS)
DCS (BSM/BPM)
SCADA BIDS
Phase 1.2BHS
Electrical
Phase 1.2BHS IT
MCS (NTS)
FAS
Consultancy Services for Test & Commissioning Plan
Phase 3.12
BHS
8/12/2019 Commissioning Plan Step 2 - RevA
52/64
FAS
Access Control
Package Conveying
LET
- Speaker
- Card readerPAS
8/12/2019 Commissioning Plan Step 2 - RevA
53/64
Phase 1.1
LiftMechanical
Phase 1.2Lift Electrical
Phase 2.1Lift
Phase 2.2Lift
Phase 3.11
Lift
3rd partycertification
BuildingShaft/Pit
Phase 1
Lift intercom
Phase 2
Lift intercom
Consultancy Services for Test & Commissioning Plan
Phase 1LET Monitoring
Phase 3.10LET Monitoring
Phase 1.1Escalator
Mechanical
Phase 1.2Escalator
Electrical
Phase 2.1Escalator
Phase 2.2Escalator
Phase 3.11Escalator
BuildingShaft
Phase 1.1Travelator
Mechanical
Phase 1.2Travelator
Electrical
Phase 2.1Travelator
Phase 2.2Travelator
Phase 3.11
Travelator
BuildingShaft
FASPower
Power
LAN
- Car floor
SCADA
MCS
Landings(floor/wall)
Phase 3.12Travelator
Phase 3.12
Escalator
Phase 3.11LET Monitoring
Phase 3.12Lift
ITRoom
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Conveying Phase 1.1Lift I ns ta ll at io n of a ll m ec ha ni ca l it em s - q ua li ty c he ck
/
p er li ft b y T hy ss en - Th ys se n -area handedover byBuilding(shaft/pit)
/
Temporary lightingrequired
8/12/2019 Commissioning Plan Step 2 - RevA
54/64
LET Mechanical - level/alignment
- torque
- MAJV Package team - all drawings/documents approved
- materialavailable
P hase 1 .2 L if tElectr ica l I nstal lation of a l lelectr ica l items - quality check
- termination
- labelling
p er li ft b y T hy ss en - Th ys se n
- MAJV Package team
-landings(floor/wall) handedover toinstall
landingindicator andpushbuttons
- Phase 1.1LiftMechanicaldone
- all drawings/documents approved
- materialavailable
Notto installlanding indicators/pushbuttons if walls
are notfinished
Phase 2.1 Lift Power up - continuity/insulation test
- power up
- phase rotation
p er li ft b y T hy ss en - Th ys se n
- MAJV Package team
- normal power availablefrom Building
- Phase 1.2LiftElectrical done
- all drawings/documents approved
To startwith temporary power if necessary
Phase 2.2 Lift Commissioning - configuration
- settingup
- functionaltest
p er li ft b y T hy ss en - Th ys se n
- MAJV Package team
- MAJV Commissioningteam
- Phase 2.1done
-all devicesout of LET scopetobe installed
(nomoreinstallationrequired)
- all drawings/documents approved
To include tests for grouped lifts when necessary
Phase 3.11 Lift Interfaces tests - interface