Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Grumman/Butkus Associates Energy Efficiency Consultants and Sustainable Design Engineers
Commissioning Lessons Learned: Pressure-Critical Environments in HealthcareBy: John D. Villani, P.E., CCP, CEM, LEED AP Kurt S. Matsen, P.E., QCxP, LEED AP
This Presentation will cover…. Ø Healthcare Critical Environment Commissioning
o What is and Why do Commissioning (Cx)o Applicable Codes and Standards
§ USP 797/800§ IDPH/ASHRAE
o Cx Process § Design Phase
o Real world healthcare Cx examples that impact patient comfort and energy savings
o Cx Costs and Benefits
Commissioning Codes and StandardsØ To conduct commissioning in the healthcare field, the
provider needs to be intimately familiar with the related codes and standardso State Codeso IBCo IECCo ASHRAEo AIAo ASHEo CDCo NFPAo NEC
Operating RoomsØ Design ConsiderationsØ Occupied vs. UnoccupiedØ Healthcare Critical Environment Commissioning
o What is and Why do Commissioning (Cx)o Applicable Codes and Standards
§ USP 797/800§ IDPH/ASHRAE
o Cx Process § Design Phase
o Real world healthcare Cx examples that impact patient comfort and energy savings
o Cx Costs and Benefits
Case Study #1 – Hospital OR IssuesNew Surgical Pavilion Project Details• 56,000 Sq. Ft New Construction Space• 45,000 Sq. Ft. Renovation of Existing Hospital• $35M Construction costs• 3 New Air Handling Units, ORs and Central Sterile• 15 New Operating Rooms (ORs)
Case Study #1 – Hospital OR IssuesAir Handling Unit Details• ORs served by two air handlers• 50,000 cfm each• Backup through cross over dampers• 50,000 cfm design during backup mode• 25,000 – 30,000 cfm during normal operation• Oversized design to handle backup mode• Coils design for smoke purge mode with is 100%
outside air
Case Study #1 – Hospital OR Issues1½ Year old surgical pavilion problems• Shut down due to increased infection rates• All ductwork was cleaned• Temperature and Humidity was found to be poorly
controlled and possible cause of infections• OR Temperature Range 60 – 78F• Relative Humidity Range 40 – 60 % RH• Occupied Mode – 30 Air Changes per Hour• Unoccupied Mode – 15 Air Changes per Hour
Everything looks good right?Supply CFM is in range, typically 18 to 23kDAT is just over the setpoint of 55Supply Static is at setpointBuilding pressure is at setpoint
SUPPLY SIDE OF AIR HANDLING UNIT
RETURN SIDE OF AIR HANDLING UNIT
Cx and RCx for Patient Comfort and Energy Savings 10
Case Study #1 – Hospital OR IssuesHumidification Issues• Humidification control based on measured return air RH vs.
setpoint via reset schedule• Frequent high humidity alarms
42%
44%
46%
48%
50%
52%
54%
56%
58%42% 44% 46% 48% 50% 52% 54% 56% 58%
Mea
sure
d R
etur
n A
ir H
umid
ity (%
)
Return Air Humidity Setpoint (%)
Humidifier Control Sequence Reset Schedule
Case Study #1 – Hospital OR IssuesØ ORs must be positive to all adjacent areas
Hospital Cx Examples – Case Study #1Ø Operating Conditions
o ORs were found going negatively pressurized during transition from occupied to unoccupied
o 30 ACH to 15 ACHo Supply VAV box can decrease from occupied to
unoccupied CFM in approximately 60 seconds o Return damper controlled by room pressure sensor
takes 20 minutes to regain stable pressure control
Case Study #1 – Hospital OR Issues
Room Pressurization is controlled by actual pressure
Case Study #1 – Hospital OR Issues
3400 cfm
1700 cfm
Added a stepped control loop to go from occupied to unoccupied mode in 300 cfm increments every 5 minutes
Cx should help troubleshoot and offer results based suggestions
Hospital Cx Examples – Case Study #1Ø Backup Mode
o Backup unit tripped offline upon initiation of cross over modeo Backup and restored unit BOTH tripped offline upon activation
and restart of failed unit§ Revised dampers and fan speed timing sequence of
operations§ USE Modulating instead of 2 Position valves / dampers.
These allow for control and manipulation of stroke time
Case Study #2 – OR New Construction
17
OR cfm offset = 2,076 - 1,800 = 276 cfm ACTUAL (Design was ≈ 400 cfm) OR’s started with over 700 cfm offset due to no door sweeps or astragals and incomplete construction such as the med gas column
Due to high leakage rate, unoccupied cfm (ACH) needed to be much higher than design
Cx should help troubleshoot and offer results based suggestions
Code is +0.01” Typically maintain +0.02” to +0.04” OR is cfm offset controlled
ADDED
Compounding Pharmacy LabsØ Design Considerations
o USP 797/800o Lab Equipment and Filtrationo Decontamination
Ø Construction ConsiderationsØ Case Studies (Functional Testing)
Compounding Pharmacy Labs
Non-Sterile HD Compounding C-SEC• Physically separated• Exhausted to outside• 12 ACH• Negatively pressurized to adjacent
spaces, .01” to .03”
Sterile HD Compounding C-SEC• ISO 7 Buffer from ISO 7 Ante• Exhausted to outside• 30 ACH (supply air)• Negatively pressurized, .01” to .03”
Compounding Pharmacy LabsØ Lab Equipment and Filtration
o Hire equipment consultant early§ Glove box vs BSC § Benchtop working heights§ Ceiling access for balance dampers
o Fan filter units§ Challenge ports§ Remote panel and/or pressure
gauges§ Accessible speed controllers and
disconnects§ In series with supply air?
– Constant torque
§ Recirculation?– Consider heat generation
Compounding Pharmacy Labs
Ø Decontaminationo Paired fans for
continuous operationo Manual bubble-tight
dampers at CA/CACI and BSC
o Decontamination mode?o Automatic bubble-tight
dampers on HD supply airflow
Compounding Pharmacy Labs
Ø Construction Considerationso Tightness of room o Pupy padso Door sweepso Sealing around all pass-through equipmento Door closure adjustments
USP 797 Pharmacy Lab– Case Study #1Intended as USP 797 Compounding Lab:• G/BA had over 30 Cx design comments• Wrong hood type in non-Chemo Room• Lack of coordination between disciplines• Return air terminal boxes shown backwards• Workroom and Gowning designed more stringent
than required• Pressurization as shown was not correct• Pressure monitors not shown in drawings• Transfer duct shown in Gowning• Fire dampers shown in HD exhaust• No automation sequences or schematics were
provided• Building, and Lab, was served by self-contained
RTU• Return system was plenum except for few areas,
and drawings called for night setbacks!
USP 797 Pharmacy Lab– Case Study #1
USP 797 Pharmacy Lab– Case Study #1
Initially, all doors had sweeps and frame sealsCode, and therefore testing, requires that rooms must remain properly pressurized when any single door is openedProblems:• Pass-through window in Workroom caused
Gowning to drop in pressure• When opening up Chemo Compounding the
Gowning-Ante door would go neutral
USP 797 Pharmacy Lab– Case Study #1
After all that work, pressures are maintained while the space was being cleaned and prepped for occupancy!
USP 797 Pharmacy Lab– Case Study #2
USP 797 Pharmacy Lab– Case Study #2
The entire return air system had to be rebalanced in order to maintain minimum negative static for Pharmacy VAVs
Isolation RoomsØ Design ConsiderationsØ Construction ConsiderationsØ Case Studies (Functional Testing)
Isolation RoomsØ Design Considerations
o IDPH/ASHRAE§ Airborne Infection Isolation (AII) Room – 12 ACH, Negative to adjacent§ AII Ante Room – 10 ACH, No pressure requirement to corridor
o Diffuser layout in Ante Room§ Protective Environment (PE) vs AII
o Room tightness§ Door sweeps?
Isolation RoomsØ Design Considerations
o Isolation exhaust fan control§ Paired fans run together§ Isolation dampers to isolate fans§ Welded duct at discharge of EF when in
facility§ Static pressure reset?§ Direct pressure vs. Airflow offset control
BHPnew = (80%/100%)3 x BHPoldBHPnew = .512 x BHPold
Isolation Room – Case Study #1
Negative Containment Isolation Room with a single supply diffuser in the Anteroom.Client’s standard is to have the Anteroom positive to the corridor.
Isolation Room – Case Study #2
Negative Containment Isolation Room with a single exhaust grille in the AnteroomClient’s standard is to have the Anteroom negative to the corridor.
Isolation Room – Case Study #3
Negative Containment Isolation Rooms with a shared AnteroomClient’s standard is to have the Anteroom negative to the corridor.
Isolation Rooms Case Study #4
35
No data on EF-2 is shown, VFD speed, static pressure or static pressure setpoint
ISO Rm 123.4 is in negative mode and not maintaining negative 0.01" w.c.
ISO Rm 123.3 is in negative mode and not maintaining negative 0.01" w.c.
Both ISO Rm's should be in alarm but neither indicate an alarm condition
Hospital Cx Examples– AFMS18” x 18” access door is ≈4’-5’ away from AFMS, is this accessible??
This AFMS is here
18”x18” AD
Cx Costs and Benefits
ASHE – Health Facility Commissioning Guidelines1.4 Negotiate the HFCxA Fee and Contract0.5% for large projects, 1.25% for small projects
Thank You - Questions
Ø John Villani, P.E., LEED AP, QCxP, CEM, GBE [email protected]
Grumman/Butkus AssociatesEnergy Efficiency Consultants and Sustainable Design Engineers