20
Cold Powering System for Hi- Luminosity A. Ballarino CERN, Geneva Technical Meeting on Vacuum for HL-LHC 5 th March 2014

Cold Powering System for Hi-Luminosity A. Ballarino CERN, Geneva

Embed Size (px)

DESCRIPTION

Cold Powering System for Hi-Luminosity A. Ballarino CERN, Geneva Technical Meeting on Vacuum for HL-LHC 5 th March 2014. Outline. System overview Where in LHC and Why Status of development Project timeline Milestones and integration in the LHC machine Conclusions. - PowerPoint PPT Presentation

Citation preview

Page 1: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

Cold Powering System for Hi-Luminosity

A. Ballarino

CERN, Geneva

Technical Meeting on Vacuum for HL-LHC5th March 2014

Page 2: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

A. Ballarino, 05/03/2014

Outline

System overview Where in LHC and Why

Status of development

Project timeline Milestones and integration in the LHC machine

Conclusions

Page 3: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

Where in the LHC ?

P1

P6 P4

P2

P8

P3

P5

P7

P1

P6 P4

P2

P8

P3

P5

P7

A. Ballarino, 05/03/2014

Betatron Cleaning Collimators

CMS

ATLAS

Not only powering of the Hi-Lumi Triplets

Page 4: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

Distribution Feedboxes removed from LHC Tunnel

A. Ballarino, 05/03/2014

Page 5: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

Interventions at P7, P1 and P5 P7: Removal of DFBA (2) and DFBM (2)

P1 and P5: removal of DFBX (2 per point) Baseline for Hi-Lumi Triplets

P1 and P5: removal of DFBA (2 per point) and DFBL (2 per point)

A. Ballarino, 05/03/2014

Page 7: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

2150-200 kA

Superconducting Link at LHC P5

A. Ballarino, 05/03/2014

Page 8: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

Superconducting Link at LHC P1

80 m

LHC TunnelIntegration drawings by J.P. Corso and S. Weisz

A. Ballarino, 05/03/2014

Page 9: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

Shaft PM15

LHC P1: Surface Buildings

Integration drawings by J.P. Corso and S. Weisz

A. Ballarino, 05/03/2014

Page 10: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

Superconducting Links Characteristics (1/2) LHC P72 Links, Each 500 m long50 Cables per link rated at 600 AItot= 30 kARemoval of LHC cryostats from tunnelUnderground installation

LHC P1 and P52+2 Links, Each 300 m long42 Cables per link rated at up to 20 kAItot= 150 kAUpgrade of Hi-Luminosity TripletsSurface Installation

P5

P1

P72

2

2

A. Ballarino, 05/03/2014

Page 11: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

Superconducting Links Characteristics (2/2) LHC P1 and P52+2 Links, Each 300 m long63 Cables per link rated at up to 6 kAItot= 200 kARemoval of LHC cryostats from tunnel Feeding of Arc and MSs magnetsSurface Installation

In total: 10 SC Links Multi-circuit assemblies

feeding different magnet circuits

2

2

2 + 2

+ 2

P7

P5

P1

Total length of superconductor required > 1000 km (7 tons)

A. Ballarino, 05/03/2014

Page 12: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

20 kA Six cables, = 19.5 mm

Concentric 3 kASeven cables, = 8.4 mm

0.4 kAFour cables

0.12 kAEighteen cables

ext 65 mm

High-Current Rating, LHC P1 and P5

18 MgB2 wires = 6.5 mm

CuMgB2 , = 0.85 mm

A. Ballarino, 05/03/2014

Hi-Lumi Triplets

Page 13: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

Mass 11 kg/m(880 kg for H=80 m)

Cable for Hi-Luminosity MagnetsLHC P1 and P5

Itot= 150 kA

H=80 mL 24 cm

RB1.5 m

Semi-flexible cryostat external diameter = 220 mmA. Ballarino, 05/03/2014

Page 14: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

Superconducting Link Cooling

Maximum operating temperature of the cables = 25 KHe gas cooling

Operation in self-field (B <1 T)

Tunnel

Surface

1.9 K

5 K

T 25 K

Cryostat with current leads

or TZ 76 (P7)

Interface in the tunnel

A. Ballarino, 05/03/2014

1-2-3: Vacuum Insulation

1

2

3

Page 15: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

In the tunnel

Nb-Ti to HTS connectionsCryogenic supply

A. Ballarino, 05/03/2014

E. Todesco

Page 16: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

At the surface or in TZ 76

New concept: no DFB cryostat

Conceptual design at the University of Southampton, Task 3 of WP 6

A. Ballarino, 05/03/2014

Page 17: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

H 4 mL = 20 m

Page 18: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

2013 202320182017201620152014

SC Links at LHC P7

SC Links atLHC P1 and P5

Test ofhorizontal lines

Test ofvertical lines

Series P7 Series P1 and P5

Timeline Today:Development and test of 20 kA @ 24 K MgB2 SC-Link 20 m long

A. Ballarino, 05/03/2014

Page 19: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

S. Chemli, 26/11/2013

Page 20: Cold Powering System for Hi-Luminosity  A.  Ballarino CERN, Geneva

Thanks for your attention