CLWC Water System Improvement Project
Overview
Project Elements
Phase 1• Portable Generator• Install Flowmeters• New SCADA for Existing
System• New Well #7
Phase 2• New Well 7 house/pump
station • New Tank 1 (450,000 gal)• New Tank 1 BPS• New Tank 3 (450,000 gal)• New Big Bend BPS• Additional Hydrants• Complete SCADA
Phase 1 Status
Element
• Portable Generator• Install Flowmeters• New SCADA for Existing
System• New Well #7
Status
• Complete – in place• Underway – 31 May• Complete – operational • Cased to 695’, water
level at 590’ – pump test pending
Phase 2 Status
• Final Design near completion– Well 7 House/Pump Station design dependent
upon pump test results • Anticipate going to bid end of May– Award by end of Jun– Construction underway by end of Jul
• Project completion (including O&M manual) by Apr 2016