Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
CLASSNK’S
EXPERIENCE WITH
BWMS
RETROFITTING
ClassNK Principal Research Scientist Shinichi Hanayama
Day 2 - Wednesday, 28 September 2016
Session Ratification in 3… 2… 1… 0.5… 0.25…
BWMTech North America
BackgroundsBWMS retro-fitting is important for the smooth implementation of BWM Convention (BWMC) just after September 2017.
A significant demand for retrofitting from 2017 to 2021 is expected.
For the smooth implementation, not only the production capacity of BWMSs but also design/yard/survey capacity for retro-fitting should be needed.
This is our first challenge !! Efforts by all stakeholders will beneeded.
2
MEPC 69 approved draft amendments to regulation B-3 of the BWMC, and a draft MEPC resolution on Determination of the date.
The draft MEPC resolution recommends that existing ships, constructed before the date of entry into force of the BWM Convention, should install BWMS by the date of the first renewal survey of the ship associated with the IOPP Certificate.
The renewal survey IOPP certificate should be performed every 5 years, therefore all existing ships should be retro-fit with BWMS in 5 years after the date of entry into force of the BWM Convention.
How many existing ships to istall BWMS? 3
How many existing ships should be retrofit with BWMS in 5 years?
ClassNK used IHS Fairplay ship database of January 2016 to determine the number of existing ships, required to install BWMS to comply with the application schedule of regulation B-3, as amended
Ships of < 400 gross tonnage and not engaged in international voyages are excluded. It is estimated that approximately 35,000 ships would be required to install BWMSs.
4
Under the current requirement, it is quite natural that retro fitting works will be performed together with the dry docking duration for RS of IOPP certificate.
It should also be noted that the total duration of docking may be extended according to the work for retrofitting.
Such additional time may reduce the dockyard capacity for retrofitting.
Therefore, it is crucial to develop a practical solution to increase the capacity from both way.
5
a) Confined engine room space (already optimized to house existing machinery, without additional spaces for BWMS and piping)
b) BWMS retrofitting needs extensive network of various piping, because of its complex construction and operation (both on ballasting and de-ballasting).
c) Difficult to obtain accurate 3D models of engine rooms required for detailed planning
Difficulty of BWMS Installation
6
Phase 2 Phase 3Phase 1
Preliminary Study
Outline Design Onboard Examination& 3D Scanning
Phase 5 Phase 6 Phase 7
Detailed Design Preparationfor Retrofit
Retrofitting at shipyard
Phase 4
3D CAD DataMake up
Process of BWMS Retrofitting
7
Phase 1
Preliminary Study
There are over 50 BWMSs, which have been already approved.
UV Chemical Electrolysis Ozone etc….
Check Points Space utility in engine room and/or pump room (depended
on BWMS with Hazardous gas) Electrical power capacity assessment Assessment of ballasting/de-ballasting rating, capacity etc. Cost assessment including OPEX Whether ship will be operated in US waters.
Decision on which BWMS to install
Preliminary Study
8
Phase 2
Outline Design
Rough planning BWMS Retrofitting, such as location, preliminary piping arrangement, etc., according to existing 2D figures
Outline design
9
Onboard Visible Examination
Check Points Deciding installation locations and ancillary work for
machinery installation Pathway planning of additional pipes Electrical modifications including ballast control system Onboard access route for each components
8
Phase 3
OnboardExamination
10
Onboard measuring by 3D Scanning
Phase 3
Scanning Range : 0.6 - 330mScanning Angle : Horizontal ; 360 , Vertical ; 305Scanning Speed : Max 976,000pt / SecAccuracy of measurement : +-2.0mmScanning with camera to add visible coloring to each dots
Onboard3D Scanning
9
11
Onboard measuring by 3D Scanning
a) 3D scanning is carried out according to the design outline developed.
b) Scanning can be carried out in 3 to 6 hours by two engineers
C) Collected data consists of billions of point data not only XYZ positioning but also RGB information.
12
3D CAD Data Development
Phase 4
3D CAD Data Development
Point Cloud Data with its colour
3D CAD Data ,which can be exported to
the existing CAD system13
New Software is needed
Joint R&D supported by ClassNK
Project Period: April 2012 – June 2014
Object: To develop software with highly accurate measurement
capabilities that can allow for quick utilization of
measurement data from 3D laser scanning data of ships
Participants: ClassNK, NYK Line, Mitsui O.S.K. Lines, "K" Line,
Sasebo Heavy Industries, Sanwa Dock,
MTI, The University of Tokyo, ClassNK Consulting Service,
ARMONICOS, S.E.A. Systems
R&D of new technology
for application in 3D laser scanner
14
Characteristics of ClassNK-PEERLESS
a) The Software can run on a basic work station.
b) Rich stencil template for basic components (such as pipes, valves, etc ) has been already prepared,
c) Automatic pipe recognition function
d) Easy to transfer the 3D CAD data to famous 3D CAD Software, used for Maritime. Exporting to AVEVA Marine in 5 minutes and exporting to
CADMATIC through CADMATIC exchange in 1 minute., and
c) Have been updated according to the feedback from Ship yards and designers.
15
Advantage of ClassNK-PEERLESS
◆ More accurate 3D modeling can be easily made.
◆ Processing period for modeling can be shortened to one week (from 1 month).
16
Detailed Design
Phase 5
Detailed Design
Basic design
3D Data created by ClassNK-PEERLESS
BWMS 3D Model
3D Design Model
17
Detailed Design using existing CAD system
Engine room Pump room
(for Bulk carriers, PCC, etc.) (for Oil Tankers, Chemical Tankers)
Installation for sensors and sampling facility will be varied by ship-type 18
Detailed Design
3D model of Machinery stands3D model of distribution pipes
Can create highly detailed designs includingDistribution pipes, Pipe support, Machinerystands, etc.
19
New Machines for Pipe Works
Pipe Coaster Pipe Form
Elbow Cutter Positioner20
Preparation work for retrofits
Phase 6
Preparationfor Retrofitting
21
Very important to prepare machine supports, and etc. in advance 21
Retrofitting at our shipyard
Phase 7
Retrofitting in our shipyard
Highly experienced engineers and onsite staff will be needed, not only for piping but also wiring and monitoring
3D Model should be used on sight.
22
Retrofitting at our shipyard
Phase 7
Retrofitting in our shipyard
For installation, a new access route to engine room should be newly prepared.
In this case, a new working hole to engine room was made.
23
Our experiences of BWMS retrofit (2016/09)
※1 Designing and engineering work only
No. Type of Ship D/W BWTS Maker BTMS Capacity Work Finish
1 General Cargo 10,000 FILTER + CHEMICAL 250 m3/h 2010/10
2 General Cargo 12,000 FILTER + CHEMICAL 250 m3/h 2013/01
3 General Cargo 14,000 FILTER + UV 250 m3/h 2013/11
4 General Cargo 13,000 FILTER + UV 150 m3/h 2014/03
5 General Cargo 12,000 FILTER + US + UV 500 m3/h 2014/07
6 Chemical Tanker 20,000 FILTER + UV 600 m3/h 2014/10
7 CHIP CARRIER 54,000 OZONE INJECTION 1,500 m3/h 2015/03
8 CHIP CARRIER 54,000 OZONE INJECTION 1,500 m3/h 2015/05
9 LPG Carrier 9,200 FILTER + UV 250 m3/h 2015/05
10 RORO 11,000 FILTER + UV 200 m3/h 2015/07
11 PCC 19,000 FILTER + CHEMICAL 500 m3/h 2015/10
12 Bulk Carrier 28,000 FILTER + UV 1,000 m3/h 2015/11
13 LPG Carrier 4,600 FILTER + UV 250 m3/h 2016/02
14 Chemical Tanker 12,000 FILTER + UV 300 m3/h 2016/04
15 Chemical Tanker 3,500 FILTER + UV 300 m3/h 2016/03
16 PCC 19,000 FILTER + CHEMICAL 500 m3/h 2016/04
17 CHIP CARRIER 52,000 OZONE INJECTION 1,500 m3/h 2016/04
18 Bulk Carrier 58,000 FILTER + CHEMICAL 1,900 m3/h 2016/05
19 Bulk Carrier 28,000 FILTER + UV 900 m3/h 2016/06
20 PCC 18,000 FILTER + UV 400 m3/h 2016/06
21 PCC 17,000 FILTER + UV 400 m3/h 2016/09
22 CHIP CARRIER 64,000 OZONE INJECTION 1,500 m3/h 2016/09
23 OIL TANKER 300,000 FILTER + CHEMICAL 7,500 m3/h 2016/09
24 PCC 18,000 FILTER + UV 400 m3/h 2016/09
24
Retrofitting at our shipyard
BWMS EQUIPMENT
NEW BALLAST PIPE
EXIST. EQUIPMENTS
EXIST. PIPE LINES
HULL CONSTRUCTION
FLOOR JOISTS
<Processing>Filtration + UV
<Capacity>500m3/h
25
Retrofitting at our shipyard
<Processing>Filtration+ Chemical Injection
<Capacity>500m3/h
BWMS EQUIPMENT
NEW BALLAST PIPE
EXIST. EQUIPMENTS
EXIST. PIPE LINES
HULL CONSTRUCTION
FLOOR JOISTS26
Retrofitting at our shipyard
<Processing>Filtration+ UV
<Capacity>1,900m3/h
BWMS EQUIPMENT
NEW BALLAST PIPE
EXIST. EQUIPMENTS
EXIST. PIPE LINES
HULL CONSTRUCTION
FLOOR JOISTS27
Retrofitting at our shipyard
<Processing>Filtration+ UV
<Capacity>1,900m3/h
BWMS EQUIPMENT
NEW BALLAST PIPE
EXIST. EQUIPMENTS
EXIST. PIPE LINES
HULL CONSTRUCTION
FLOOR JOISTS28
Phase 2 Phase 3 Phase 4Phase 1
Preliminary Study
Outline Design Onboard Examination& 3D Scanning
3D CAD Data Development
<1Month 1 Month 2days-<1week < 2weeks
Phase 6 Phase 7
Detailed Design by usual CAD
Retrofitting at our shipyard
1Month 1 Month 2 weeks
Phase 5
Preparation for Retrofit
Time schedule prior to the actual work at dry-dock(targets for total duration is less than 6 month,
Phase7 should be finished during the duration for SS. )
29
Position of SANWA DOCK, which is specialized “Ship Repair and Retrofitting” Dock
30
New Dock, Factory, Office for 2016
New Factory
New Office
New DockNO.7 : 220m x 45.0m
31
Length x Breadth : 220.0m x 45.0mDocking capacity : 63,000 G/TScheduled Completion Date : May 2016
Large size Dry Dock for retro-fiting is newly constructed
32
http://www.armonicos.co.jp/products/classnk-peerless-en/
33