1 | Page May 1, 2020 Clarification # 1 T14.2020 Roachs Pond Pump Station Upgrades To All Bidders of T14.2020: Please note: the following clarification is in response to questions received for T14.2020 and should be taken into consideration when preparing bid submission. Question 1: I am just wondering in the event of travel restrictions due to covid 19, would a contractor still be required to fulfill their contract as per the spec time phases or would a delayed schedule be acceptable given the circumstances? If the project do get delayed I assume the existing pumps would just stay in the system working until such time the contractor can complete the work. Answer 1: The CCDC general terms and conditions section 6.5 addresses delays. Additional time will be provided to accommodate delays beyond the contractor’s control, but the contractor is not entitled to any additional payment for costs incurred due to the delays. These items are for clarification purposes only and does not change the scope of work of the tender. If you have any questions, please contact our office by email at [email protected]. ALL OTHER SPECIFICATIONS, TERMS AND CONDITIONS REMAIN UNCHANGED. A signed copy of the Clarification is NOT required with your bid submission. End of Clarification #1

Clarification # 1 · 2020. 5. 1. · Clarification # 1 T14.2020 Roach’s Pond Pump Station Upgrades To All Bidders of T14.2020: Please note: the following clarification is in response

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Clarification # 1 · 2020. 5. 1. · Clarification # 1 T14.2020 Roach’s Pond Pump Station Upgrades To All Bidders of T14.2020: Please note: the following clarification is in response

1 | P a g e

May 1, 2020

Clarification # 1

T14.2020 Roach’s Pond Pump Station Upgrades

To All Bidders of T14.2020: Please note: the following clarification is in response to questions received for T14.2020 and should be taken into consideration when preparing bid submission.

Question 1: I am just wondering in the event of travel restrictions due to covid 19, would a contractor still be required to fulfill their contract as per the spec time phases or would a delayed schedule be acceptable given the circumstances? If the project do get delayed I assume the existing pumps would just stay in the system working until such time the contractor can complete the work. Answer 1: The CCDC general terms and conditions section 6.5 addresses delays. Additional time will be provided to accommodate delays beyond the contractor’s control, but the contractor is not entitled to any additional payment for costs incurred due to the delays. These items are for clarification purposes only and does not change the scope of work of the tender. If you have any questions, please contact our office by email at [email protected].

ALL OTHER SPECIFICATIONS, TERMS AND CONDITIONS REMAIN UNCHANGED.

A signed copy of the Clarification is NOT required with your bid submission.

End of Clarification #1

Page 2: Clarification # 1 · 2020. 5. 1. · Clarification # 1 T14.2020 Roach’s Pond Pump Station Upgrades To All Bidders of T14.2020: Please note: the following clarification is in response

1 | P a g e

May 1, 2020

Addendum # 3

T14.2020 Roach’s Pond Pump Station Upgrades

- Pump Installation

To All Bidders of T14.2020: Please note: the following addendum applies to T14.2020 and shall be taken into consideration when preparing bid submission. Question 1: Re: Sketch 3 and Scope of Work C.2 item 3. Section 1 on sketch 3 details 4 – 20M dowels embedded 800 mm. Scope of Work C.2 item 3 notes a minimum embedment of 75mm. Please confirm if the 800 mm of embedment is correct. Answer 1: “Sketch SK03, Section 1 indicates that 4 – 20M dowels are to be embedded 800 mm. This is incorrect. Proponents are to assume dowels will be embedded 75 mm.” A signed copy of each Addendum must also be included with the bid submission. Failure to include this Addendum may be cause for rejection. If you have any questions, please contact our office by email at [email protected].

ALL OTHER SPECIFICATIONS, TERMS AND CONDITIONS REMAIN UNCHANGED.

Acknowledgement by Bidder: Company Name: _________________________ Print Name: _____________________________ Signed: ________________________________ Date: __________________________________

End of Addendum #3

Page 3: Clarification # 1 · 2020. 5. 1. · Clarification # 1 T14.2020 Roach’s Pond Pump Station Upgrades To All Bidders of T14.2020: Please note: the following clarification is in response

1 | P a g e

April 27, 2020

Addendum # 2

T14.2020 Roach’s Pond Pump Station Upgrades

- Pump Installation

To All Bidders of T14.2020: Please note: the following addendum applies to T14.2020 and shall be taken into consideration when preparing bid submission. The closing date has been extended to Tuesday May 5, 2020 at 2:00 p.m. Atlantic Time. Question 1: Re: Scope of Work C. Site Work – Overview item 2.c (phase one complete 6 weeks after pump delivery) & Common Installation Elements C.2 item 3, (28 day concrete cure). Due to the 28 day concrete cure completion 6 weeks after pump delivery would be tight, is it possible to get the pump frames (with certified pump / suction elbow drawings) delivered before the pumps? Answer 1: It will not be necessary to wait 28 days for full cure of concrete. Proponents are to allow 7 days for concrete curing prior to commencement of pump installation. A signed copy of each Addendum must also be included with the bid submission. Failure to include this Addendum may be cause for rejection. If you have any questions, please contact our office by email at [email protected].

ALL OTHER SPECIFICATIONS, TERMS AND CONDITIONS REMAIN UNCHANGED.

Acknowledgement by Bidder: Company Name: _________________________ Print Name: _____________________________ Signed: ________________________________ Date: __________________________________

End of Addendum #2

Page 4: Clarification # 1 · 2020. 5. 1. · Clarification # 1 T14.2020 Roach’s Pond Pump Station Upgrades To All Bidders of T14.2020: Please note: the following clarification is in response

April 22, 2020

Addendum # 1

T14.2020 Roach’s Pond Pump Station Upgrades

– Pump Installation

To All Bidders of T14.2020:

Please note: the following addendum applies to T14.2020 and shall be taken into consideration when preparing bid submission. SECTION C – Site Work - Overview New Subsection 7: Add subsection 7 as below:

7. Net weight of Owner Supplied Pump is 1,725 kg. This weight includes pump, motor, and cables.

New Subsection 8: Add subsection 8 as below:

8. Delivery trailers cannot enter the building. Contractor shall be responsible for receiving and offloading all deliveries to site, including pump deliveries. Contractor may use existing 3,000 kg SWL mono rail electrical hoist/gantry system in building for material handling.

SECTION C.1 – Removals

Subsection 3: delete existing clause and replace with:

3. Pumps, piping, valves, and fittings shall be disposed of appropriately by the Contractor.

New Subsection 4: Add the following new subsection 4.

4. All removed materials including pipe, pumps, motors, fittings, housekeeping pads, etc. shall be disposed of appropriately. Contractor to pay all costs and fees associated with the removal from site and disposal.

1 | P a g e

Page 5: Clarification # 1 · 2020. 5. 1. · Clarification # 1 T14.2020 Roach’s Pond Pump Station Upgrades To All Bidders of T14.2020: Please note: the following clarification is in response

SECTION C.2 Common Installation Elements

General change

Reference to DN pipe work and fittings to be deleted throughout specification document.

Subsection 12: delete existing clause and replace with:

12. An acceptable alternative to Stainless Steel Pipe Work, as per subsection 16, is Ductile Iron. Ductile Iron to AWWA C151, Class 54, cement mortar lined to AWWA C104, maximum working pressure 2,400 kPa. Pipe joints for ductile iron shall be flanged to AWWA C115 with 125 lb flange dimensions to ANSI/ASME B16.1

Subsection 14: (pressure gauges not required) delete existing clause and replace with:

14. Install pressure gauge pipe work on each suction elbow and discharge pipe – total of ten (10) pressure gauge pipe work sets required; five (5) on the suction and five (5) on the discharge. Suction elbow comes with connection port of 1½” NPT. Pump Discharge comes with a connection port of 1½” NPT. Gauge pipe work shall be equipped with isolation valve to allow gauge to be removed. Pipe work shall be provided with method of draining. Pipe work and isolation valve(s) shall be 1” stainless steel 316L. Pipe work to be fitted with ½” NTP female connection for Owner supplied pressure gauge.

Subsection 15: delete Subsection 16.f: delete existing clause and replace with:

f. 316L Stainless steel, grooved end couplings are an acceptable alternative and to be:

.1 Rigid style 14” to 24” Victaulic #W89 AGS Coupling; or

.2 Rigid style 2” to 12”, Victaulic #489 Coupling. Subsection 19: delete clause

2 | P a g e

Page 6: Clarification # 1 · 2020. 5. 1. · Clarification # 1 T14.2020 Roach’s Pond Pump Station Upgrades To All Bidders of T14.2020: Please note: the following clarification is in response

The following Images of the interior of the station are provided for information. Image 1: Existing Pump Cable Junction Boxes

3 | P a g e

Page 7: Clarification # 1 · 2020. 5. 1. · Clarification # 1 T14.2020 Roach’s Pond Pump Station Upgrades To All Bidders of T14.2020: Please note: the following clarification is in response

Image 2: Existing Panel Room

Image 3: Existing Pump Arrangement #1

4 | P a g e

Page 8: Clarification # 1 · 2020. 5. 1. · Clarification # 1 T14.2020 Roach’s Pond Pump Station Upgrades To All Bidders of T14.2020: Please note: the following clarification is in response

Image 4: Existing Pump Arrangement #2

5 | P a g e

Page 9: Clarification # 1 · 2020. 5. 1. · Clarification # 1 T14.2020 Roach’s Pond Pump Station Upgrades To All Bidders of T14.2020: Please note: the following clarification is in response

A signed copy of each Addendum must also be included with the bid submission. Failure to include this Addendum may be cause for rejection. If you have any questions, please contact our office by email at [email protected].

ALL OTHER SPECIFICATIONS, TERMS AND CONDITIONS REMAIN UNCHANGED.

Acknowledgement by Bidder: Company Name:

Print Name:

Signed:

Date:

End of Addendum # 1