Why was the Claim Tracking System Built?
• Mandated by the 2002 Legislature• Automated Monthly Summary Reports• Track and Ensure Construction and Contractor
Timeliness on Claims• Enhanced Statistical Reporting for Construction
Engineering Services Bureau Management Staff and Legislature
• Standardized MS Word Templates
Standardized MS Word Templates
• Construction Engineering Services Bureau– Response to Notice of Claim– Response to Certified Claim– Extension Request for Response to Certified Claim– Request to Schedule a Mediation Date– Decision from Mediation– Board of Contract Appeals Decision– Lessons Learned
• Contractor– Notice of Claim– Request for Mediation– Request for Appeal
Accessing the Claim Tracking System
• MDT Intranet - http://mdtinfo.mdt.state.mt.us/
• Access the Oracle Menu– Log on to Oracle
• Select TRNS*PORT
• Select Claim Tracking System
• Select Claim Data Entry and Query Form
Claim Data Entry Screen Features
• List of Values (LOV)– Project Number– Cntl No– EPM Name– Subcontractor– Claim Type– Subject of Claim Type– Bid Item
• Drop Down List– Claim Status– Proj Type– Board Apl Dec– Mediation Decision
• Date Calendar– EPM Dates
• Notice• Response• Received Cert Claim
– DCE Dates• Decision• Submit Claim Package
– CES Dates• Received Request for Appeal• Received Claim Package
– Construction Engineer Dates• Mediation Rqst• Mediation Meet
• User Documentation– Available online
• Lessons Learned– Link to Lessons Learned
documents via the comments
Establishing a Claim for a ProjectTo record a claim for a project the user must first determine if the
project already exists in the Claim Tracking System
• Existing Project – Query on the Project– Record a new claim on
the existing Project
• New Project– Record the Project– Record a new claim
Query on Project Project Exists Record ClaimYes
No
Record Project
Query on Project
• Click on Query Button
• Query Fields– Project Number– Control Number– Project Description
• Enter selection criteria
• Click on Execute Button
Required Fields for Establishing a Claim for a Project
• Project Information• Claim Information
– Claim Number – automatically generated
– EPM Name– Claim Type– Claim Status– Project Type
• Dates– Dates will be required
as claim progresses through business process
– Date counter begins when date is entered
Optional but Recommended Fields for Claims
• Subcontractor • Subject of Claim Type• Bid Item• Add Time• Claim Amount• Settled Time• Settled Amount• Comments
Email NotificationLinks in email allow for easy access to application and standardized
word templates
Date Logic and Status
• Notice of Claim Date– 01/12/2007
• Response to Notice of Claim– Due 14 days from Notice of Claim Date– Warning message will be sent on the 12th
day– Overdue message will be sent 14th day