Civil Par1

Embed Size (px)

DESCRIPTION

Civil Par1

Citation preview

  • 304537469.xls / Sheet1 1 of 26

    BATTERBOARD

    1. To estimate the lumber to be used as batterboard for lay-out, compute the lineal meter of the structure all around giving an allowance or margin of 1.00. Count also the number of stakes tobe used. Multiply the number of stakes by 1.2 (length of stake) and add the sum to the first linealmeter change to lineal foot. Then compute the board depending to the size of the lumber to be used as batterboard (2" x 2" or 2" x 3")

    2.to get number of kilos. If by keg, divide the total board foot by factor 2500 equals keg of nails.

    3. To estimate guide wire #12 to be used in layouting, divide the total boardfoot by 4000 to obtain roll of wire.

    Note: The Drawing below is an illustration of layout showing the location of batterboard and stake.

    Guide Wire Batterboard

    Stake

    EXCAVATION

    1. To estimate the volume of excavation, compute the area to be excavated then multiply by thedepth.For cut and fill excavation, use the prismoidal formula

    2

    To estimate the nails to be used, divide the total boardfoot by 1000 then multiply by factor 15

    A1 + A2 x depth or length = CU. MT.

  • 304537469.xls / Sheet1 2 of 26

    BACKFILL

    To estimate bacfilling or gravel bed multiply the width, the length and the depth or thickness (w x l x d)

    If the backfilling will be compacted add 10% for compaction and 3% for waste.

    CONCRETE

    To estimate the volume or cubic meter of concrete, use same formula as of backfilling.

    To obtain bag of cement, cu.m. of sand and cu.m. of gravel, determined the class of mixture or psirequired. Then cu.m. of concrete multiply by the given factor of mixture.

    FACTOR OF CONCRETE MIXTURE

    4,500 - 5,000 psi (Class AAA) 1 : 1 : 2

    Cement 13.50 bagsSand 0.51 cu.m.Gravel 1.02 cu.m.

    4,000 psi (Class AA) 1 : 1 : 3

    Cement 10.00 bagsSand 0.41 cu.m.Gravel 0.92 cu.m.

    3,500 - 3,000 psi (Class A) 1 : 2 : 4

    Cement 9.50 bagsSand 0.42 cu.m.Gravel 0.84 cu.m.

    2,500 - 2,000 psi (Class B) 1 : 2 : 5

    Cement 8.50 bagsSand 0.52 cu.m.Gravel 0.87 cu.m.

    1,600 psi (Class C) 1 : 3 : 6

    Cement 7.50 bagsSand 0.64 cu.m.Gravel 0.91 cu.m.

  • 304537469.xls / Sheet1 3 of 26

    FACTOR OF MORTAR / Cu.M Mixture 1 : 2

    Cement 17.87 bagsSand 1.00 cu.m.

    Mixture 1 : 3 Cement 13.00 bagsSand 1.06 cu.m.

    Mixture 1 : 4 Cement 9.00 bagsSand 0.91 cu.m.

    CURB AND GUTTER1. To estimate curbe and gutter: l.m. x 74=total cu.m.2. To obtain form lumber to be used l.m. x 8.5 BF = total BFT3. To obtain cement, sand and gravel determine the class or mixture, then multiply by the

    corresponding factor.

    ASPHALT1. To obtain asphalt: one (1) metric ton of asphalt the coverage is 8.78 s.m.2. Total area x 8.78=metric ton of asphalt.3. To obtain prime coating (liquid) total area (s.m.) divide by 400 equals number of drums (area

    divided by 400 = drum) or one (1) gal. Of liquid prime coat the coverage is 64 SF or 6.00 s.m.

    CONE PAVEMENT1. To obtain bag of cement for 6" to 8" thk. Pavement: total cu.m. x 8.5 = bags or total sm x 1.9 =

    bags or sand: total cu.m. x 66.4 = 4 gals.

    BASE COARSE1. To obtain base coarse for 6.00 wide x 0.20 road compacted every k.m. use factor 1200 cu.m.

    (hauled) in place (quarry). For every k.m. use 1,260 cu.m. for loose hauled use 1,400 cu.m.2. 3.00 wide x .20road compacted (hauled) use 600 cu.m. for quarry: use 630 cu.m. for loose

    hauled use 700 cu.m.

    SUBGRADE OR ROAD BED1. To obtain subgrade or road bed of 9.00 x .15 road using common borrow: compacted (hauled)

    use 1,350 cu.m. for every km. For quarry: use 1,500 cu.m; for loose (hauled) use 2,010 cu.m.for every km.

    GROUTED RIPRAP1. To estimate riprap grouting vol. Of riprap x .15 or .30 = vol. of concrete. To obtain cement:

    vol. x factor or area x .425 = cement and area x .03 = sand

  • 304537469.xls / Sheet1 4 of 26

    CEMENT AND SAND FACTORFOR CONCRETE PIPE JOINT COLLAR

    Pipe Diameter Cement Sand

    4" NRCP 0.02 bags 0.13 cu.m. 6" 0.03 bags 0.19 cu.m. 8" 0.05 bags 0.26 cu.m.

    12" RCP 0.10 bags 0.39 cu.m. 15" RCP 0.15 bags 0.49 cu.m. 18" RCP 0.20 bags 0.59 cu.m. 24" RCP 0.35 bags 0.79 cu.m. 30" RCP 0.50 bags 0.99 cu.m. 36" RCP 0.70 bags 1.19 cu.m. 42" RCP 0.75 bags 1.38 cu.m. 48" RCP 1.20 bags 1.58 cu.m.

    FACTOR FOR CHB CONCRETE FOOTING PER LINEAR METER

    CHB FTG. THK FTG. BASE CEMENT SAND GRAVEL VOL/MT.

    4" 0.10 0.30 0.27 0.01 0.02 0.03to 0.15 0.30 0.45 0.02 0.04 0.056" 0.20 0.60 1.08 0.06 0.10 0.12

    0.15 0.45 0.63 0.03 0.06 0.070.20 0.45 0.81 0.04 0.08 0.09

    1. To estimate CHB wall, compute the total area then less all openings such as doors and windows.2. To obtain pieces of CHB: Area of coverage x 12.15 or 12.53. To obtain cement:

    For 4" CHB : Area x 0.27 = bagsFor 6" CHB : Area x 0.71 = bagsFor 8" CHB : Area x 1.16 = bags

    4. To obtain sand:

    For 4" CHB : Area x 0.022 = bagsFor 6" CHB : Area x 0.058 = bagsFor 8" CHB : Area x 0.094 = bags

  • 304537469.xls / Sheet1 5 of 26

    5. To obtain rebars:

    6" CHB: Using #3 rebars @ every 3 layers bothwaysArea x 1.64 = kg. of rebarsUsing #4 rebars @ 32" vert. & 24" horizontal Area x 2.90 = kg. of rebars

    4" CHB: Using #3 rebars @ every 3 layers bothwaysArea x 1.64 = kg. of rebarsUsing #3 rebars @ 32" vert. & 4" horizontal @ 24"Area x 1.85 = kg. of rebars

    8" CHB: Using #3 rebars @ every 3 layers bothwaysArea x 3.32 = kg. of rebarsUsing #3 rebars @ 32" vert. & 4" horizontal @ 24"Area x 2.00 = kg. of rebars

    6. TO obtain #16 tie wire:

    For 4" CHB Area x .0005 = roll of w1 roll = 900 kg. 6" CHB Area x .0008 = roll of wire 8" CHB Area x .0009 = roll of wire

    or total kg. Of rebars divide by factor 3000 equals roll of wire.

    PLASTERING1. To estimate mortar for plastering of wall, compute the volume to be plasterded then multiply by

    the number of face.

    For 1" thk. : Area x .025 = volume 1/2" thk. : Area x .0217 = volume 3/4" thk. : Area x .0315 = volume

    2. To obtain cement : volume x 13 = bags3. To obtain sand : volume x 1.06 = cu.m.4. To obtain cement by area : Area x .33 = bags5. TO obtain sand by area : Area x .03 = cu.m.

  • 304537469.xls / Sheet1 6 of 26

    KG. OF SLAB REBARS PER SQUARE METER

    1. For #3 rebars - .616 kg/m ; 3/8" KG. NO. OF BARS

    0.15 bothways 7.39 12 pcs. 0.20 bothways 6.16 10 pcs. 0.30 bothways 3.70 6 pcs. 0.40 bothways 2.46 4 pcs. 0.45 bothways 2.46 4 pcs. 0.60 bothways 1.23 2 pcs.

    2. For #4 Rebars - .888 kg/m ; 4/8" = 12mm

    0.15 bothways 10.66 12 pcs. 0.20 bothways 8.88 10 pcs. 0.25 bothways 7.1 8 pcs. 0.30 bothways 5.33 4 pcs. 0.40 bothways 3.55 4 pcs. 0.45 bothways 3.55 4 pcs. 0.60 bothways 1.78 2 pcs.

    3. For #5 Rebars - 1.579 ; 5/8" = 16mm

    0.15 bothways 18.95 12 pcs. 0.20 bothways 15.75 10 pcs. 0.25 bothways 12.63 8 pcs. 0.30 bothways 9.47 4 pcs. 0.45 bothways 6.32 4 pcs. 0.60 bothways 3.16 2 pcs.

  • 304537469.xls / Sheet1 7 of 26

    4. For #6 Rebars - 2.466 ; 20mm

    0.15 bothways 29.59 12 pcs. 0.20 bothways 24.66 10 pcs. 0.25 bothways 19.75 8 pcs. 0.30 bothways 14.80 6 pcs.

    Rebars KG of Concrete Wall per Sq. Meters

    TYPE OF LAYING REBARS KILOGRAM NO. OF BAR.10 - 2 WAYS # 3 12.32 20 pcs.

    # 4 17.76# 5 31.58# 6 49.32# 7 51.54# 8 77.08

    .15 - 2 ways # 3 7.39 12 pcs. # 4 10.66

    .25 - 3 ways # 3 7.39 12 pcs. # 4 10.66# 5 18.95# 6 29.59# 7 30.92# 8 46.25

    .30 - 3 ways # 3 5.54 9 pcs. # 4 7.99# 5 14.21# 6 22.19# 7 23.19# 8 34.67

    .10 - 4 ways # 3 24.64 40 pcs. # 4 35.52# 5 63.16# 6 98.64# 7 103.08# 8 154.16

    .15 - 4 ways # 3 14.78 24 pcs # 4 21.31# 5 37.9# 6 59.18# 7 61.85# 8 92.5

    .20 - 4 ways # 3 12.32 20 pcs. # 4 17.76# 5 32.58# 6 49.32# 7 51.54

  • 304537469.xls / Sheet1 8 of 26

    # 8 77.08

  • 304537469.xls / Sheet1 9 of 26

    .25 - 4 ways # 3 9.86 16 pcs. # 4 14.21# 5 25.26# 6 39.46# 7 41.23# 8 61.66

    .30 - ways # 3 7.39 12 pcs, # 4 10.66# 5 18.95# 6 29.59# 7 30.92# 8 46.25

    VOLUME OF SLAB PER SQ. METER

    2" thk. 0.05 cu.m. 3" thk. 0.07 cu.m. 4" thk. 0.10 cu.m. 5" thk. 0.125 cu.m. 6" thk. 0.15 cu.m. 7" thk. 0.175 cu.m. 8" thk. 0.20 cu.m. 9" thk. 0.225 cu.m.

    10" thk. 0.25 cu.m. 11" thk. 0.275 cu.m. 12" thk. 0.30 cu.m.

    VOLUME OF WALL PER SQ. METER

    4" thk. 0.10 cu.m. 6" thk. 0.15 cu.m. 8" thk. 0.20 cu.m.

    10" thk. 0.25 cu.m. 12" thk. 0.30 cu.m. 14" thk. 0.35 cu.m. 16" thk. 0.40 cu.m. 18" thk. 0.45 cu.m. 20" thk. 0.50 cu.m. 22" thk. 0.55 cu.m. 24" thk. 0.60 cu.m.

    ADOBE STONE

    1. To estimate adobe of 6" x 6" x 18" Wall : Area x 15 = pieces Cross footing : Area x 6 = piecesFor Stairs : Cu.m. x 90 = pieces

    2. To obtain cement and sand for mortar in laying adobe:For cement : Area x 2.19 = bagsSand : Area x .097 = Cu.m.

  • 304537469.xls / Sheet1 10 of 26

    VINYL TILES1. To obtain pieces of vinyl tiles 12" x 12"

    Area x 12 = no of piecesTo obtain in holdtite adhesive:Area x .0016 = gallons

    PEBBLES AND SYNTHETIC1. To estimate pebbles or synthetic materials:

    SF : Area x .33 = bagsPebbles or SyntheticArea x 1.5 = no. of can SM x 100 = no. of bricks

    2. To obtain cement bed:Area x .60 = bags Area x .16 = cement

    Area x .01 = cu.m. sand

    3. Filler Cement bed : Area x .042 = bags

    CEMENT TILES PER SQ. METER

    SIZE PIECES CEMENT BED FILLER6" X 6" 45 pcs 0.06 0.0428" X 8" 25 pcs 0.06 0.042

    10" X106" 16 pcs 0.06 0.04212" X 12" 12 pcs 0.06 0.04214" X 14" 9 pcs 0.06 0.04216" X 16" 7 pcs 0.06 0.04218" X 18" 5 pcs 0.06 0.04220" X 20" 4 pcs 0.06 0.04224" X 24" 3 pcs 0.06 0.042

    VITRIFIED TILES PER SQ. METER

    4 1/4" X 4 1/4" 86 pcs. 0.06 0.042

    MOSAIC TILES PER SQ.M.

    12" X 12" 12 pcs. 0.06 0.042

    GROUTING COMPOUND

    1. Horntop Coating 1 liter per sq. m.2. Horntop Flr. Topping 1.2 liter per sq.m.

    Application: Part A & B should be mixed by machine at a rate of 250 to 300 rpm (4 min.). Duringmixing period add 5 parts by volume of sand. Coating thickness should be 1/16" (2mm) fortopping thickness should 1/4" (5mm)

    3. Daraweld C for bonding mixture : 1 part daraweld 5 parts cement, 2.5 parts sand and 1 partwater. 'For topping : 1 part daraweld, 5 parts cement, 15 parts sand and 1 part water. For non-skid 'surface: 1 part of daraweld, 3 part cement, 5 part sand and 1.5 water. For waterproofing 'mixture : 1 part daraweld, 1 part cement, 6 part sand and 1 part water.

  • 304537469.xls / Sheet1 11 of 26

    4. Hornseal:Floor hardener : 1 liter for every 10 sm.Curing compound : 1 liter for every 5 sm.Sealing : 1 liter for every 6 sm.If rough seal : 1 liter for every 9 sm.

    5. Hydratite Compound : 1 lb. For every 1 bag cement6. Sahara Compound : 1bag for every 1 bag cement

    SCAFFOLDING1. To estimate scaffolding, compute the area elevation of the structure.2. To obtain the boardfoot of lumber : using 2 x 8

    Area x 6.56 = total board foot using 2 x 4Area x 8.75 = total board foot

    3. TO obtain nails : divide the total board foot using 2500 will give you keg of nails.

    FORMWORKS1. To estimate formworks, compute the area that need formwoks.2. To obtain boardfoot of lumber:

    For column : Area x 33 = bd.ft.For Pedestal : Area x 19 = bd.ft.For Beam : Area x 34 = bd.ft.For Concl. Wall : Area x 19 = bd.ft.For Slab : Area x 25 = bd.ftFor Curbe and Gutter : Area x 8.5 = bd.ft.For Cone slab : Area x 36 = bd.ft.For Sill & Lintel : Area x 18 = bd.ft.

    3.4. After arriving on the total bd.ft. and plywood, divide it by the no. of use, the answer is the required

    bd.ft. of lumber and pieces of plywood.5.6.7.

    formoil.

    FLOOR JOIST

    1. To estimate floor joist at .30 o.c. : compute the area then multiply by the factor for each size.

    For 2 x 3 : Area x 9.84 = BDFT2 x 4 : Area x 13.12 = BDFT2 x 5 : Area x 16.40 = BDFT2 x 6 : Area x 19.68 = BDFT2 x 8 : Area x 26.24 = BDFT

    2.3. Another procedure in computing the floor joist is to count the pieces of joist indicated in the

    framing plan, then count the board foot.

    To obtain 1/2 x 4 x 8 plywood divide the area by 2.88

    To obtain keg of nails : divide the required bd.ft. by 2500.To obtain #16 tie wire : divide the bd.ft. by 4000.To obtain formoil : Change sq. meter to sq. foot then divide by 200, will give no. of gallon of

    To obtain nails in keg: Boardfoot divide by 2500 (1keg = 45 kilos)

  • 304537469.xls / Sheet1 12 of 26

    T & G FLOORING

    1. Compute the lineal meter of spread then multiply by the factor to get the number of pieces to be used.

    For 1 x 3 T & G : l.m. x 16.66 = pieces1 x 4 T & G : l.m. x 11.77 = pieces1 x 6 T & G : l.m. x 7.87 = pieces

    2. Compute the boardfoot.3.

    WOODEN STUDS

    1. To estimate wooden studs at 0.60 o.c. compute the area of the siding of partition, then multiplyby the factor of the lumber to be used.

    For 2 x 3 : Area x 9.84 = BDFT2 x 2 : Area x 6.54 = BDFT2 x 4 : Area x 13.08 = BDFT2 x 5 : Area x 16.38 = BDFT

    2.

    S-CUT SIDINGS

    1. To estimate sidings, compute the lineal meter of spread then multiply by the factor:For 1 x 3 : l.m. x 20 = pieces

    1 x 4 : l.m. x 13.16 = pieces1 x 6 : l.m. x 7.87 = pieces1 x 8 : l.m. x 5.95 = pieces

    2.

    DOUBLE WALLING & PARTITION

    1. To estimate plyewood walling, compute by area of both side of the wall, then divide the total area

    2.for kilos of 1" finishing nails.

    3. For studs, use wooden stud.

    CEILING JOIST

    1. To estimate ceiling joist, compute the area then multiply by the factor:

    For 0.40 o.c. bothways2 x 2 lumber : Area x 6.55 = BDFT2 x 3 lumber : Area x 9.6 = BDFT2 x 4 lumber : Area x 13.2 = BDFT

    For 0.45 o.c. bothways2 x 2 lumber : Area x 4.37 = BDFT2 x 3 lumber : Area x 6.56 = BDFT2 x 4 lumber : Area x 8.75 = BDFT

    To obtain nails : total bdft divide by 2500 equals keg.

    To obtain nails : divide the boardfoot by 2500 equals keg.

    To change the keg to kilo, multiply the keg by 45.

    by 2.88 to obtain pieces of plywood.To obtain nails: pieces of plywood x 1.33 then divide the answer by 1000 and multiply by 9.10

  • 304537469.xls / Sheet1 13 of 26

  • 304537469.xls / Sheet1 14 of 26

    For 0.60 o.c. bothways2 x 2 lumber : Area x 4.37 = BDFT2 x 3 lumber : Area x 6.56 = BDFT2 x 4 lumber : Area x 8.75 = BDFT

    For 0.30 o.c. bothways2 x 2 lumber : Area x 8.75 = BDFT2 x 3 lumber : Area x 13.12 = BDFT2 x 4 lumber : Area x 17.49 = BDFT

    For 0.30 x 0.40 framing2 x 2 lumber : Area x 7.65 = BDFT2 x 3 lumber : Area x 11.48 = BDFT2 x 4 lumber : Area x 15.30 = BDFT

    For 0.40 x .45 framing2 x 2 lumber : Area x 6.56 = BDFT2 x 3 lumber : Area x 9.84 = BDFT2 x 4 lumber : Area x 13.12 = BDFT

    For 0.40 x .60 framing2 x 3 lumber : Area x 8.20 = BDFT2 x 4 lumber : Area x 13.66 = BDFT

    ALUMINUM TEE RUNNER1.

    multiply no. of spread on the length and width.Example: the ceiling is 3.00 x 6.00

    300 divide by 0.60 = 5 x 6.00 = 30.00

    Total length 45.00 45 divide by 6.0 (commercial length of the runner) = 7.5 say 8 pieces at 20' or 6.00 length

    2.

    BASEBOARD1. To estimate boardfeet :

    For 1 x : l.m. x 1.09 = boardfeetFor 1 x : l.m. x 1.37 = boardfeetFor 1 x : l.m. x 1.64 = boardfeet

    2. For nails : same procedure in obtaining nails.

    FACIA BOARD1. To compute the total lineal meter of the roof end where facia board is required, multiply the linel

    meter by the factor to obtain board feet.For 1 x : l.m. x 2.73 = boardfeetFor 1 x : l.m. x 3.28 = boardfeetFor 1 x : l.m. x 2.18 = boardfeet

    2.

    To obtain pieces of aluminum, the runner, divide the length and width by 0.60 or 1.20. Then

    6.00 divide by 1.20 = 5 x 3.00 = 15.00

    For #12 guidewire and the wire hanger : total area multiply by 6.54 divide by 4,000 equals roll

    To obtain nail : same procedure-bdft divide by 2,500 or bdft divide by 1000 multiply by 5.5=kls

  • 304537469.xls / Sheet1 15 of 26

    WOODEN TRUSS & RAFTERS1. Compute area of the roof.2. Obtain total boarfeet : count number of truss member (same to rafter) then compute the

    boardfeet according to size and length of the lumber in the drawing.3. After computing the boardfeet for one truss of rafter, multiply this number of unit specified in the

    roof framing.4. For nail : boardfeet divide by 2,500 equals keg. If by the kilo, divide the boardfeet by 1000 then

    multiply by 6.8

    PURLINS1. To estimate total boardfeet of purlins : make an actual counting of purlins as shown in the roof

    framing plan and truss details, then compute the boardfeet according to the specified size and length of the lumber.

    2. Or compute the area then multiply including the greats

    For 0,80 - 0.90 using:2 x 3 : Area x 3.88 = boardfeet2 x 4 : Area x 5.17 = boardfeet2 x 5 : Area x 6.47 = boardfeet

    For 1.20 o.c. using:2 x 4 : Area x 2.59 = boardfeet2 x 5 : Area x 3.23 = boardfeet2 x 6 : Area x 3.88 = boardfeet

    ROOFING1.

    2. To divide the slotted area by factor from the table of the G.I sheet coverage and the answeris the pieces of sheet to be used.

    3. Another procedure : length of spread divide by .67 if the length is in meter and 27". If the length is in feet, then multiply by the number of lapping or row.

    4. To obtain metal rivet:

    For strap:

    see the table of strap.5. To obtain gutter, ridge row, valley row and flushing:

    6.7.8.

    To estimate G.I sheet roofing by area, compute the area in the flat then add the pitch factor(the sum of 1 & 2 percentage) the total area is the slotted area of the roof.

    pieces of G.I sheet x 0.073 = kilo of rivetpieces of G.I sheet x 0.146 = kilo of washer

    pieces of G.I sheet x 12 or 9 = pieces of strap to convert this to pieces of plain G.I sheet

    Length of spread or lineal meter divide by 2.25 = ridge roll, valley roll or flashing.For copper rivet: no. of joint multiply by 8 then divide by 50 = no. of box of copper rivet.For nikolite : length of foot divide by 24 = kiloFor muriatic acid : piece of nikolite x 10cc = total cc of muriatic

  • 304537469.xls / Sheet1 16 of 26

    PITCH FACTOR OF TRUSS & RAFTERNo. 1 Symmetrical No. 2 Unsymmetrical

    Pitch Inch % Decimal% Pitch Inch % Decimal%0.32 5.5 0.055 0.32 2 0.020.36 6 0.06 0.36 3 0.030.40 8 0.08 0.40 4 0.040.45 10 0.10 0.45 5 0.050.50 12 0.12 0.50 6 0.060.55 14 0.14 0.55 7 0.070.60 16 0.16 0.60 8 0.080.70 22 0.22 0.70 11 0.110.80 28 0.28 0.80 14 0.140.90 35 0.35 0.90 18 0.181.00 42 0.42 1.00 21 0.211.20 46 0.46 1.20 23 0.231.50 54 0.54 1.50 27 0.27

    TABLE OF COVERAGE - 10" ENDLAP 32" 7' 27" X 6 - 2" 1.23/sm

    8' 7 - 2" 1.44/sm9' 8 - 2" 1.64/sm10' 9 - 2" 1.84/sm12' 11- 2" 2.24/sm14' 13 - 2" 2.64/sm

    TABLE OF COVERAGE - 12" ENDLAP 32" 6' 27" X 5' 1.01/sm

    7' 6' 1.21/sm8' 7' 1.40/sm9' 8' 1.60/sm10' 9' 1.79/sm12' 10' 2.21/sm14' 13' 2.61/sm

    TABLE OF FASTENERG.I Nails - 2 102 pcs / kiloLeadwasher 36 pcs / kiloG.I Rivet - 1/4 x 3/8 180 pcs / kiloG.I Rivet - 1/4 x 1/2 157 pcs / kiloMetal Washer 152 pcs / kilo

    TABLE OF RIVET PER SHEET6' - 0" 6 pcs / sht.7' - 0" 9 pcs / sht.8' - 9" 9 pcs / sht.10 - 12" 12 pcs / sht.

    TABLE OF STRAP PER PLAIN G.I. SHEETPURLIN SIZE STRAP SIZE PIECES PER SHEET

    2 X 2 1" x 9" 3802 X 4 1" x 10" 3402 X 6 1" x 12" 285

  • 304537469.xls / Sheet1 17 of 26

  • 304537469.xls / Sheet1 18 of 26

    TABLE OF TEGULA(Basic Technical Date)

    Size of Tile 16 1/2" x 13" (420 x 331mm)OverallHeadlap (minimum) 4 1/2" (115mm)Botton Gauge 12" max (305mm x max)

    Minimum Pitch - 25

    STANDARD REINFORCEMENT OF WALLSThickness Type Vertical Bars Horizontal Bars Kg/Cu.m Kg/Sm.

    0.10 1 1 - #3 at 0.30 1 - #3 at 0.30 37.20 3.770.15 2 2 - #3 at 0.30 2 - #3 at 0.30 49.60 7.440.15 1 1 - #4 at 0.30 1 - #4 at 0.30 44.20 6.630.20 2 2 - #3 at 0.30 2 - #3 at 0.30 41.00 8.220.25 3 2 - #4 at 0.30 2 - #4 at 0.30 44.48 11.120.30 3 2 - #4 at 0.30 2 - #4 at 0.30 44.20 13.250.35 3 2 - #4 at 0.30 2 - #4 at 0.30 37.90 13.250.40 3 2 - #4 at 0.30 2 - #4 at 0.30 42.25 16.980.45 3 2 - #4 at 0.30 2 - #4 at 0.30 37.50 16.980.50 3 2 - #5 at 0.30 2 - #5 at 0.30 37.50 18.780.55 3 2 - #5 at 0.30 2 - #5 at 0.30 41.40 20.7

    NAILS CONVERSION TABLEJoist and sill 1000 BDFT 11.4 kilos 4" C.W.Studs 1000 BDFT 6.8 kilos 3" C.W. Sheatings/siding 1000 BDFT 9.1 kilos 2 1/2 C.W. Rafters 1000 BDFT 6.8 kilos 3" C.W. Cornice 1000 L.F. 11.4 kilos 2 1/2 Finishing Shingling 1000 PCS. 1.8 kilos 1 1/2 C.W. Bevel siding 1000 BDFT 8.2 kilos 2" C.W. Ceiling Joist 1000 BDFT 9.1 kilos 2" C.W. Flooring 1000 BDFT 13.6 kilos 2 1/2 C.W. Baseboard 1000 BDFT 5.5 kilos 2 1/2 Finishing Window trim - one side per side 0.5 kilos 2 1/2 Finishing Door trim - one side per side 0.3 kilos 2 1/2 Finishing Lath 1000 BDFT 3.6 kilos 1 1/4 C.W. Lattice 1000 S.F. 9.1 kilos 1 1/4 C.W. Ballusters 1000 L.F. 8.2 kilos Assorted Formworks 1000 BDFT 15.0 kilos 2" x 4" C.W.

    SPREADING RATE OF PAINTSCoating Surface Gallon CoverageOil Paint smooth wood 1st coat - 600 S 55.74 sm

    2nd coat - 325 S 30.19 sm3rd coat - 225 S 21.19 sm

    rough wood 1st coat - 350 S 32.38 sm2nd coat - 200 S 15.50 sm3rd coat - 135 S 12.54 sm

    metal 1st coat - 700 S 62.02 sm

  • 304537469.xls / Sheet1 19 of 26

    2nd coat - 340 S 31.59 sm3rd coat - 230 S 21.37 sm

  • 304537469.xls / Sheet1 20 of 26

    plaster 1st coat - 450 S 41.81 sm2nd coat - 250 S 23.23 sm3rd coat - 175 S 16.25 sm

    handbricks 1st coat - 400 S 37.16 sm2nd coat - 225 S 20.90 sm3rd coat - 160 S 14.86 sm

    softbricks 1st coat - 350 S 32.38 sm2nd coat - 200 S 18.50 sm3rd coat - 150 S 13.94 sm

    smooth cement 1st coat - 350 S 32.30 sm2nd coat - 200 S 18.50 sm3rd coat - 150 S 13.94 sm

    rough cement 1st coat - 200 S 18.59 sm2nd coat - 140 S 9.29 sm3rd coat - 50 SF 4.65 sm

    Oil flat paint smooth wall 1st coat - 500 S 46.25 sm2nd coat - 275 S 25.55 sm3rd coat - 200 S 18.50 sm

    plaster 1st coat - 400 S 37.00 sm2nd coat - 225 S 20.80 sm3rd coat - 150 S 14.86 sm

    stucco 1st coat - 150 S 13.94 sm2nd coat - 75 SF 6.97 sm

    Enamel paint smooth width under coat 1st coat - 500 S 46.25 sm2nd coat - 250 S 25.55 sm

    Exterior spur smooth wood 1st coat - 500 S 46.25 smvarnish 2nd coat - 275 S 25.55 sm

    3rd coat - 200 S 18.50 sm

    Interior spur smooth wood 1st coat - 450 S 41.81 smvarnish 2nd coat - 250 S 23.23 sm

    3rd coat - 175 S 16.25 sm

    Shellac smooth wood 1st coat - 600 S 65.74 sm2nd coat - 300 S 27.87 sm

    rough wood 1st coat - 125 S 11.61 sm2nd coat - 75 SF 16.97 sm

    Shingle satin fin smooth wood 1st coat - 250 S 23.23 sm

    Asphalt rough rough 1st coat - 150 S 13.94 smpaint 2nd coat - 100 S 9.29 sm

  • 304537469.xls / Sheet1 21 of 26

    WATER PAINT1. Goldwater paint - 5 lbs. Powder

    smooth 1st coat - 300 S 27.87 sm

    2. Calsomine - 5 lbs. Powder

    plaster 1st coat - 400 S 37.00 smwood 1st coat - 250 S 23.23 sm

    3. whitewash - 4 to 5 lbs.powder

    brick 1st coat - 200 S 18.50 sm

    4. hydrated limeplaster 1st coat - 300 S 27.87 sm

    MOTORPOOL CONSUMPTION OF EQUIPMENTSItem Fuel Liter / HourAuger, earth Gasoline 10.00 Air compressor 15 cfm Gasoline 2.30 Air compressor 210 cfm Gasoline 20.00 Air compressor 312 cfm Diesel 1.50 Crushing plant Gasoline 7.50 3 units 50 tons per hr. Diesel 20.00 Ditching machine (ladder type) Gasoline 20.00 Distributor, bituminus 800 gals., c Gasoline 15.50 Water distributor 100 gal. Gasoline 15.50 Perccussion drill Gasoline 10.00 Genset - 5 kw Gasoline 13.00 Genset - 15 kw Gasoline 11.00 Electric welder Gasoline 5.00 Road grader Diesel 15.00 Asphalt heater Gasoline 2.20 Asphalt heater Diesel 10.00 Asphalt kettle 165 gal. Gasoline 7.50 Bucket loads Gasoline 20.00 Lubbricator Gasoline 3.80 Conccrete mixer Gasoline 7.60 Centrifugal pump 240 gpu Gasoline 3.00 Road roller 3w lot Gasoline 15.00 Road tandem roller Gasoline 13.00 Roller pneumatic towed 50-ton Gasoline 13.00 Roller pneumatic towed Gasoline 13.00 Sheepfoot roller towed Gasoline 13.00 Tractor dozer - D7, 8 & 6 Diesel 2.50 Dumptruck 5 - ton Gasoline 0.95 6 x 6 Truck 5 - ton Gasoline 0.80

    RATE PER ITEM OF WORKSCeiling - 2 carpenters

    Frame installation 1.33 hr/sm

  • 304537469.xls / Sheet1 22 of 26

    Plywood installation 1.00 hr/sm

  • 304537469.xls / Sheet1 23 of 26

    Flushdoor - 3' x 7' - 6" = 21sf.Frame 32.50 bdft.Board 2.00 bdft.Glue 0.10 gal.Fabrication - 1 man-work 1 man-work 12 hr/pc

    Door jamb - 2 x 6 lumberFabrication 1 carpenter 4.50 bdfft./hrInstallation 2 carpenters 6.00 bdfft./hr

    Metal door - 3' x 7'1. Steel door w/ #16 cladding & LGS C frames # 12 of 50 LF

    Fabrication 2 steelmen / welder 24 hr/pcEquipment 1 welding machine 8 hr/pc

    Manual clearing & grubbingClearing undergrowth & trees - 12" 20.00 sm/hrClearing undergrowth & shrubs 40.00 sm/hr

    Excavation manualCommon earth 1 man-work - 1.00cum./8 0.125 cu.m./hrLoam of sand 1 man-work 0.76 cu.m./hrClay or heavy soil 1 man-work 0.61 cu.m./hrRock 1 man-work 0.38 cu.m./hr

    Mechanical excavationCommon earth 0.15 cu.m./hrRock w/ jackhammer 0.06 cu.m./hr

    Backfilling 1 man-workCommon manual 1.22 cu.m./hrGravel fill manual 0.20 cu.m./hr

    Mechanical compaction 7.00 cu.m./hrPlate ccompaction 18.00 cu.m./hrSpreading, tamping 7 grading 1 man-work 2.09 sm/hrEsccombro bacckfilling 1 man-work 4.78 cu.m./hrPlacing binder-gravel 1 man-work 9.46 cu.m./hr

    Trenching and backfilling of underground piping using excavation materials manual

    From 0 to 2m. Depth 0.80 LM/Hr. 2 to 3 m. depth 0.60 LM/Hr. 3 to 4 m. depth 0.40 LM/Hr. 4 to 5 m. depth 0.30 LM/Hr.

    Placing concreteSlab on fill 0.20 cu.m./hrSlipform 0.04 cu.m./hrFLr. Finish unhardened 1.00 sm/hrConcrete finish hardened 0.70 sm/hr

    Water stop installation 1 man-work 1.50 lm./hr

  • 304537469.xls / Sheet1 24 of 26

    Caulking slab joint 1 man-work 5.00 sm/hr

  • 304537469.xls / Sheet1 25 of 26

    Asphalting 1 man-work 1.25 sm/hr

    Grouting & plastering 1 man-work 0.60 sm/hr

    Pebble finish 1 man-work 0.70 sm/hr

    Marble slab installation 1 man-work 0.50 sm/hr

    1/4 x 2 x 8 red bricks 1 man-work 0.20 sm/hr

    Glaze tiles 1 manson & helper 0.19 sm/hr

    Unglazed tiles 1 manson & helper 0.23 sm/hrFormworks installation

    Wall on ground 2 carpenters 1.00 sm/hrWall above 10' 2 carpenters 0.85 sm/hrBeams 2 carpenters 0.65 sm/hrColumns 2 carpenters 0.85 sm/hrSuspended slab: 0 - 18" 2 carpenters 1.20 sm/hr

    18" - 36" 0.80 sm/hr 36" up 2 carpenters 0.60 sm/hr

    Formworks fabrication 2 carpenters 1.86 sm/hr

    Stripping of formworksWall on ground 2 carpenters 8.00 sm/hrWall above 10' 2 carpenters 1.55 sm/hrBeams 2 carpenters 1.95 sm/hrColumns 2 carpenters 2.35 sm/hrSuspended slab: 0 - 18" 2 carpenters 3.60 sm/hr

    18" - 36" 2.40 sm/hr 36" up 2 carpenters 1.85 sm/hr

    Reinforcing bars Fabrication 1 steelman 10.00 kg/hrInstallation 2 steelmen 10.00 kg/hr

    Metal WorksStructural Steel 1 welder 20.00 kg/hrFabrication of anchor bolts 1 welder 10.00 kg/hrInstallation of anchor bolts1 Man 3.00 kg/hrFabrication of embeded it 1 welder 7.00 kg/hr

    Laying RCP with 8 men (1 item)24" 2.10 m.hr36" 1.25 lm/hr48" 0.75 lm/hr 6" to 18" 6.00 lm/hr

    Carpentry Works:Plywood partitionT & G flooring & siding Ceiling frameworkSiding framingFloor framing

  • 304537469.xls / Sheet1 26 of 26

    Wooden post erectionTruss erectionGir

    Sheet1