City of Revelstoke
Development Services Committee Regular Meeting
AGENDA
August 21, 2014 - Commencing at 3:00 PM
Council Chambers
Page
1. CALL TO ORDER
2. ADOPTION OF AGENDA
3. ADOPTION OF MINUTES 2 - 3 a. Draft July 31, 2014 Meeting Minutes
4. BUSINESS ARISING FROM THE MINUTES
5. CORRESPONDENCE
6. OLD BUSINESS
7. NEW BUSINESS 4 - 64 a. 2015-2019 Engineering and Utilities Capital Projects
8. FOR INFORMATION
9. ADJOURNMENT
Page 1 of 64
CITY OF REVELSTOKE
MINUTES OF THE DEVELOPMENT SERVICES COMMITTEE MEETING HELD IN
COUNCIL CHAMBERS THURSDAY, JULY 31, 2014 COMMENCING AT 3:00 P.M.
PRESENT: Council: L. Nixon, C. Johnston, S. Bender Staff: M. Thomas, Director of Engineering & Development Services M. Smyrl, GIS/Asset Management Technician D. Komonoski, Operations Manager P. Page Brittin, Environmental Sustainability Coordinator G. Ferguson, Development Services Clerk D. Strachan, Manager Development Services 1. CALL TO ORDER Councillor L. Nixon, Chair called the meeting to order at 3:05 pm 2. ADOPTION OF AGENDA The agenda was adopted as presented with the addition of item 6(a) Composting of ash from RCEC 3. ADOPTION OF MINUTES a. June 30 Meeting Minutes
June 30, 2014 meeting minutes were formally approved as presented. 4. BUSINESS ARISING FROM THE MINUTES When asked if the Ford dealership sign concrete base is expected to be removed, staff confirmed that it will be. 5. CORRESPONDENCE - NIL
AGENDA ITEM #3.a.
Draft July 31, 2014 Meeting Minutes Page 2 of 64
Development Services Committee Regular Minutes Thursday, July 31, 2014,
6. OLD BUSINESS When asked about the process of composting the ash from RCEC, D. Komonoski replied that he is waiting for a report, but the components of the ash at this time do not look like they are favorable for composting at our Jordan pit facility. 7. NEW BUSINESS a. Engineering Operating Budget Suggested Changes 2015 - Verbal
M. Thomas gave the Committee a verbal report on possible suggested changes which may be upcoming to the Engineering Department Operating Budget. b. 2014 Workplan Update - Verbal
M. Thomas gave a brief update on where the Department stands on the 2014 Workplan. c. Draft Stormwater Management RFP
P. Page Brittin presented to the Committee a draft of the Stormwater Management RFP which will go out later this year. 8. FOR INFORMATION-NIL 9. ADJOURNMENT The meeting was adjourned at 4:15 pm. __________________________ Councillor L. Nixon, Chair
AGENDA ITEM #3.a.
Draft July 31, 2014 Meeting Minutes Page 3 of 64
Area Start Year Priority Project Cost 2015 Cost 2016 Cost 2017 Cost 2018 Cost 2019 Status Estimate Ready Data Sheet ReadyADM 2015 4 Court House DDC Controls $5,000.00 4 Final FinalADM 2015 3 Court House FA Panel $15,000.00 4 Final FinalADM 2015 4 Moberly Monument $10,000.00 4 Final FinalADM 2015 2 City Hall Renovations - Interior Downstairs in development 2 Draft DraftADM 2015 2 City Hall Renovations - Elevator in development 2 Draft DraftADM 2015 3 City Hall Renovations - Exterior /Siding in development 2 Draft DraftADM 2015 2 City Hall Renovations - Council Chambers in development 2 Draft DraftADM 2016 3 Facilities Lifecycle Review and Planning $80,000.00 2 Draft DraftADM Total $30,000.00 $80,000.00 $0.00 $0.00 $0.00DEV 2015 3 Subdivision Bylaw Update $60,000.00 4 Final FinalDEV 2015 2 OCP Review $30,000.00 4 Final FinalDEV 2016 City Centre Plan $20,000.00 2 Draft DraftDEV 2016 Victoria Road Corridor Plan $20,000.00 2 Draft DraftDEV Total $90,000.00 $40,000.00 $0.00 $0.00 $0.00ENG 2015 5 Shoring $16,500.00 4 Final FinalENG 2015 5 Streetlight Removal $5,000.00 4 Final FinalENG 2015 1 Streetlight Upgrades $35,000.00 $35,000.00 $35,000.00 4 Final FinalENG 2015 3 Tire Cleanup $12,000.00 $12,000.00 $12,000.00 $12,000.00 4 Final DraftENG 2015 5 Tool Budget $10,000.00 4 Final FinalENG 2015 3 Washbay $40,000.00 4 Final FinalENG 2015 1 Garbage Truck Replacement $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 4 Final FinalENG 2015 3 PW HVAC $25,000.00 4 Final FinalENG 2015 3 PW Yard Electrical Upgrades $7,000.00 4 Final FinalENG 2015 1 4th Street E Streetlights $70,000.00 4 Final FinalENG 2015 3 Courthouse LED Lighting $23,000.00 4 Final FinalENG 2015 1 Mackenzie Streetlights $130,000.00 4 Final FinalENG 2015 2 Victoria Road Resurfacing – Wright to Kootenay $353,000.00 4 Final FinalENG 2015 1 Airport Way Resurfacing – Nichol to Schiel $219,000.00 4 Final FinalENG 2019 2 Eastern Access Resurfacing - CPR Overpass to TCH $528,000.00 4 Final FinalENG 2017 1 Lower Town Utility and Street Upgrades $744,000.00 $1,135,000.00 Final DraftENG 2016 1 Nichol Road - Hay to Camozzi $370,000.00 4 Final FinalENG 2015 1 Design Intersection TCH-Victoria-Mutas $50,000.00 $500,000.00 3 Draft FinalENG 2015 2 7th to Rec Centre Pathway Improvements $100,000.00 3 Draft FinalENG 2015 2 Design Intersection 4th-Victoria-Townley $40,000.00 $40,000.00 $400,000.00 3 Draft FinalENG 2015 1 Illecillewaet River Dyke Repair $80,000.00 3 Draft FinalENG 2015 3 Roof Loads Assesment $30,000.00 3 Final DraftENG 2015 1 Aerial Photo and Lidar $20,000.00 3 Draft FinalENG 2015 1 Pavement Condition Assessment $80,000.00 3 Draft FinalENG 2018 3 1st and Campbell Curb 2 Draft DraftENG 2015 2 Victoria Avenue redesign $50,000.00 $200,000.00 2 Draft DraftENG 2015 3 Demonstration Local Street Project $35,000.00 $100,000.00 2 Draft DraftENG 2019 2 Other Paving Priorities $100,000.00 $650,000.00 2 Draft DraftENG Total $1,480,500.00 $1,307,000.00 $1,241,000.00 $1,297,000.00 $1,228,000.00
AG
END
A ITEM
#7.a.
2015-2019 Engineering and U
tilities Capital P
rojectsPage 4 of 64
Area Start Year Priority Project Cost 2015 Cost 2016 Cost 2017 Cost 2018 Cost 2019 Status Estimate Ready Data Sheet ReadySEW 2018 5 WWTP 2nd Screen $340,000.00 4 Final FinalSEW 2015 3 Downie Forcemain $50,000.00 $50,000.00 $50,000.00 $850,000.00 4 Final FinalSEW 2015 1 UPS Upgrades $10,000.00 4 Final FinalSEW 2016 1 Burke Lift Station Upgrade $60,000.00 $350,000.00 4 Final FinalSEW 2015 5 HVAC Upgrades $17,500.00 4 Final FinalSEW 2015 Lagoon Building Upgrade $25,000.00 3 Final DraftSEW 2015 Lagoon Roof $15,000.00 3 Final DraftSEW 2015 5 STP Discharge Relocation $50,000.00 $50,000.00 $1,850,000.00 $2,550,000.00 3 Final DraftSEW 2016 2 Wales Street LS $300,000.00 3 Final DraftSEW Total $167,500.00 $460,000.00 $1,900,000.00 $3,740,000.00 $350,000.00WAT 2015 1 Hydrant Replacement Program $60,000.00 $60,000.00 $60,000.00 $60,000.00 $60,000.00 4 Final FinalWAT 2016 4 Heat Tape Kiosk Access $20,000.00 4 Final FinalWAT 2015 1 Illecillewaet River Crossing $600,000.00 4 Final FinalWAT 2015 5 Greeley WTP Hypo Transfer Pump $5,000.00 4 Final FinalWAT 2015 5 Greeley WTP Turbidity Meters $33,000.00 4 Final FinalWAT 2015 4 Greeley Flow Monitoring $10,000.00 4 Final FinalWAT 2015 1 Historian $12,000.00 4 Final FinalWAT 2015 1 Water Emergency Response Plan $15,000.00 4 Final FinalWAT 2015 3 Greeley Chlorine shut offs $35,000.00 4 Final FinalWAT 2019 2 Greeley Creek Filter Replacement $615,000.00 4 Final FinalWAT 2016 2 Greeley WTP Dosing $15,000.00 4 Final FinalWAT 2016 5 West Laforme Fireflow $330,000.00 4 Final FinalWAT 2017 5 WTP Biomass $172,000.00 4 Final FinalWAT 2015 1 Water Metering and Loss $136,300.00 3 Final DraftWAT 2016 3 Shiell Road Fire Flow $35,000.00 3 Final DraftWAT 2016 2 Hillcrest Fire Flow $70,000.00 3 Final DraftWAT 2017 3 Arrow Drive Fire Flow $75,000.00 3 Final DraftWAT 2016 5 Farrel Road Fireflow $90,000.00 3 Final DraftWAT 2017 3 Columbia Park Drive North Fireflow $114,000.00 3 Final DraftWAT 2018 4 Well #2 Industrial Park $290,000.00 3 Final DraftWAT 2017 5 Williamson Lake Road Watermain $390,000.00 3 Final DraftWAT 2018 5 Looping Phase 1 $420,000.00 3 Final DraftWAT 2019 5 Looping Phase 2 $850,000.00 3 Final DraftWAT 2015 4 Valve Replacement Program $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 2 Draft DraftWAT 2015 2 Water Supply and Model Review $50,000.00 2 Draft DraftWAT 2018 2 Arrow Heights PRV Station $35,000.00 2 Draft DraftWAT Total $986,300.00 $650,000.00 $669,000.00 $1,007,000.00 $1,555,000.00Grand Total $2,754,300.00 $2,537,000.00 $3,810,000.00 $6,044,000.00 $3,133,000.00
AG
END
A ITEM
#7.a.
2015-2019 Engineering and U
tilities Capital P
rojectsPage 5 of 64
Comments
Need scope and costs -may require borrowingNeed scope and costs -may require borrowingNeed scope and costs -may require borrowingNeed scope and costs -may require borrowingNeeds sheet
Needs sheet
lease payments
Needs sheet
Costs may change as project proceedsNeed cost estimateJust Needs PhotoNeed cost of repair workNeeds sheetNeed cost estimateNeed cost estimateNeeds sheetNeeds sheetNeeds sheetNeeds sheet
AG
END
A ITEM
#7.a.
2015-2019 Engineering and U
tilities Capital P
rojectsPage 6 of 64
Comments
may require borrowing
Needs sheetNeeds sheetNeeds sheet - may require borrowingNeeds sheet
may require borrowing
Needs sheetNeeds sheetNeeds sheetNeeds sheetNeeds sheetNeeds sheetNeeds sheetNeeds sheetNeeds sheetNeeds sheetNeeds sheetNeeds sheetNeeds sheet
AG
END
A ITEM
#7.a.
2015-2019 Engineering and U
tilities Capital P
rojectsPage 7 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title 4th ST E Street Lighting
Project ID ENG
Project Priority 1
Date June 17 2014 v1.0
Project Description
Project Purpose To install proper conduit and grounding for the street lighting on 4th ST E
Results New bases, 9M poles, fixtures, conduit and wiring for streetlights along 4th ST E
Scope of Project Replace 8 street lights, complete with new conduit, wiring, bases, poles and fixtures
Justification Safety issue. Poles are not grounded in accordance with the Canadian Electrical Code. Wires are run directly in the ground which is against Canadian Electrical Code. Safety concerns around metal poles not being grounded properly.
Cost
Estimated Cost $70,000
Method of Financing General Revenue
Estimate Quality Material quoted from wholesaler, may change. Labour costs estimated.
Schedule
Project Milestone Date
Construction Complete September 2015
Personnel
Person Project Role and Responsibilities
Electrical Foreman Project Manager
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 8 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Photos
Conduit stubbed out of streetlight base. No conduit extended, wires directly buried. No ground wire, only 2 wires, Hot and Neutral.
No grounding at street light.
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 9 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Existing lighting
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 10 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering PHOTO
Project Title 7th Street Pathway Improvements
Project ID ENG -
Project Priority 2
Date 9 August 2014 v0.1
Project Description
Project Purpose
The pathway between the Rec Centre parking lot and 7th Street is heavily used by cyclists and pedestrians; however the pathway has not been designed as a multi -use pathway. Issues include steep unprotected grades, narrow paved width, small radius corners and short sight distances. This project would convert this path to a functional multi -use pathway, al lowing safe access for al l users.
Results Construction of safe multi-use trai l .
Scope of Project The pathway wil l be regraded and widened. The preliminary design work is complete.
Justification
ICSP 2.1 Healthy Living, 3.2 Community Transportation
City Active Transportation Plan (2010) -42% of respondents stated that a lack of sidewalk/trai ls/bike lanes was a barrier to active transportation. (A propose multi use trai l is identified on Map 3 in this area).
Cost
Estimated Cost Total Project Cost
Method of Financing General Revenues
Estimate Quality Engineer’s Estimate.
Schedule
Project Milestone Date
Personnel
Comment [MT1]: Add a photo of existing pathway
Comment [MT2]: Waiting on cost from MMM DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 11 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Aerial Photography and LIDAR
Project ID ENG
Project Priority 1
Date June 10, 2014 v1.0
Project Description
Project Purpose Update the City’s aerial photography, including terrain mapping using LIDAR technology.
Results Updated mapping data
Scope of Project Procure specialist consultant services to deliver aerial photography and LIDAR terrain mapping for the City and surrounding areas. City staff have partnered with RMR, BC Hydro, and several ministries to minimize costs.
Justification
The City’s current aerial photography is from 2011. Regular aerial photography updates provide benchmarking of development and infrastructure data. The inclusion of LIDAR terrain is necessary for stormwater management and slope stability planning and reduces the need for survey work at the preliminary design stage. Buildings can also be automatically extracted from the LIDAR data for analysis purposes.
Cost
Estimated Cost $20,000
Method of Financing Engineering Capital
Estimate Quality Based on budget level quote from supplier
Schedule
Project Milestone Date
RFP
Flight
Data Delivery
January 2015
April/May 2015
July/August 2015
Personnel
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 12 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Person Project Role and Responsibilities
Mike Thomas P.Eng. ENV SP
Melinda Smyrl - GIS and Asset Mgmt Tech
Consultant
Project Director
Project Manager
Flight and Data Preparation
Example LIDAR terrain mapping.
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 13 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Airport Way Resurfacing – Nichol to Schiel
Project ID ENG -
Project Priority 1
Date 05/08/2014.
Project Description
Project Purpose To rehabilitate a 431m section of failing road. Surface is cracked and rutted severely. Improves the quality of the city’s road system and reduces maintenance costs.
To improve vehicle, bike and pedestrian safety and mobility.
Results Improved ride comfort, decreased annual maintenance, increased vehicle/bike/pedestrian safety, more efficient snow removal.
Scope of Project
Pulverize existing asphalt and re-grade in place. Pave with 75mm thick asphalt, 3.4m wide driving lanes and 1.6m wide bike lanes. Re-grade shoulders and ditches. Disconnect water service at 2102 Airport Way from existing 100mm AC main and connect to 200mm PVC main.
Justification Asset Management Policy – Statement 1- “The City of Revelstoke will maintain and manage infrastructure assets at defined levels to support public safety, community well-being and community goals.”
Cost
Estimated Cost $ 219 000
Method of Financing Capital
Estimate Quality Pre-design
Schedule
Project Milestone Date
Survey/ Design 2014
Construction
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 14 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Personnel
Person Project Role and Responsibilities
Derek Low Survey/Design
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 15 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Admin - Buildings
Project Title Courthouse Decorative Lighting Upgrade
Project ID ADM
Project Priority 3
Date July 21 2014. V1.0
Project Description
Project Purpose
The existing exterior light fixtures at the courthouse have degraded to the point that they are becoming un-serviceable. Parts have rusted and the clarity of the light has degraded as the acrylic lenses are weathered and cracking. Replacement parts such as the lens and reflector are no longer available and the lamp technology, mercury vapour, is outdated. The LED consume 30% less power than the old mercury vapour.
Results A new LED fixture replaces the old mercury vapour, maintaining the heritage look but creating a bright and safe area.
Scope of Project
14 decorative fixtures to replace. Possible to replace 10 one year and 4 the next, in order to break up the cost of the project. As it is a heritage building it makes the most sense to complete one side of the building at a time, minimum, in order to maintain a completed look. The LED fixtures, although very similar, do look a little different than the old mercury vapour (see photos).
Justification
Upgrading fixtures that are discontinued and degrading. If parts corrode and break during routine maintenance of the light fixture we have no way to replace them. LED fixtures will be maintenance-free for up to 15 years, saving costs associated with maintenance over that time.
Cost
Estimated Cost Over 1 year: 14 fixtures; $23,000
Over 2 years: 1st year: 10 fixtures; $16,500, 2nd year: 4 fixtures; $6,500
Method of Financing General revenues
Estimate Quality Written Quote on Material
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 16 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Schedule
Project Milestone Date
Installation Complete September 2015
Personnel
Person Project Role and Responsibilities
Jason Zimmer Project Manager
Pictures
New fixture style
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 17 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Intersection 4th, Townley and Victoria
Project ID ENG -
Project Priority 1
Date 9th August, 2014 v0.1
Project Description
Project Purpose The intersection of 4th, Townley and Victoria has been identified as a high priority location for traffic upgrades in the City.
Results Preliminary design and early consultation complete in 2015, ready for detailed design in 2016
Scope of Project In 2015, preliminary design work will be procured and completed.
Justification Identified in Draft Master Transportation Plan
ICSP 3.2 - Transportation
Cost
Estimated Cost $40,000 in 2015 (Estimated $40,000 in 2016 and $400,000 in 2017 for construction)
Method of Financing General revenues
Estimate Quality Pre Tender
Schedule
Project Milestone Date
Personnel
Person Project Role and Responsibilities
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 18 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Design TCH/Mutas/Victoria
Project ID ENG
Project Priority 1
Date 9 August 2014
Project Description
Project Purpose
The intersection of Victoria Avenue and the Trans Canada Highway, and the adjacent intersection accessing Mutas Loop, (McDonalds, Tim Hortons, A&W, Shell etc) has been identified as the highest priority transportation project within the City.
In 2014, the City started the design process, this project is the continuation of the design, with tender-ready design drawings and contract documents completed ready for construction in early 2016. (A separate 2016 project will be proposed and revised with tender specific pricing based on the project scope at that stage).
Results Tender-ready design drawings and contract documents completed
Scope of Project
Community and stakeholder consultation
Detailed design work
Development of construction contract package.
Justification ICSP 3.2 – Transportation
Draft Master Transportation Plan
Cost
Estimated Cost $50,000 in 2015. (Estimated $500,000 in 2016 for construction).
Method of Financing General Revenues
Estimate Quality Pre-design,
Schedule
Project Milestone Date
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 19 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Personnel
Person Project Role and Responsibilities
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 20 of 64
City of Revelstoke - Capital Project Data Sheet 2016
Project Data
Project Area Engineering
Project Title Eastern Access Resurfacing - CPR Overpass to TCH
Project ID ENG -
Project Priority 1
Date 06/08/2014.
Project Description
Project Purpose To rehabilitate 861m of heavily used arterial road. This is a high traffic arterial road, asphalt surface is approaching the end of its useful service life. Improves the quality of the city’s road system and reduces maintenance costs on failing roads.
Results Improved ride comfort, decreased annual maintenance, increased vehicle/bike/pedestrian safety, more efficient snow removal.
Scope of Project Mill 25mm of existing asphalt and re-pave with 50mm thick asphalt, 3.7m wide driving lanes and 1.6m wide bike lanes. Install 600m of monolithic asphalt curbs.
Justification Asset Management Policy – Statement 1 – “The City of Revelstoke will maintain and manage infrastructure assets at defined levels to support public safety, community well-being and community goals”.
Cost
Estimated Cost $528,000
Method of Financing Capital
Estimate Quality Pre-design
Schedule
Project Milestone Date
Survey/ Design 2014/2015
Construction
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 21 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Garbage Truck Replacement
Project ID ENG -
Project Priority 1
Date 10 August 2014
Project Description
Project Purpose Due to Worksafe BC operational requirements and the remaining useful life of the City’s garbage trucks, staff have conducted an assessment of garbage collection options. The City will procure a new garbage truck
Results New garbage truck, meeting operational needs and Worksafe requirements.
Scope of Project Delivery of a new garbage truck following tender process
Justification ICSP 4.1 – Solid Waste
Cost
Estimated Cost $250,000 for a new truck. Leased cost could be $50,000 per year.
Method of Financing General revenues- Leased Asset
Estimate Quality pre-tender
Schedule
Project Milestone Date
Personnel
Person Project Role and Responsibilities
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 22 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Illecillewaet River Dyke Repair
Project ID ENG -
Project Priority 1
Date 10 August 2014
Project Description
Project Purpose
During summer 2014, a section of the Illecillewaet River Dyke upstream of powerhouse road failed, compromising the bank stability adjacent to a water system pressure reducing station (PRV). This project is designed to restabilize the dyke, preventing erosiona dn protecting the PRV and industrial park from flooding.
Results Bank stabilization constructed in accordance with environmental regulations.
Scope of Project Bank stabilization design and construction. Management of environmental and fisheries issues.
Justification ICSP – 4. Resilient Infrastructure
Cost
Estimated Cost Total Project Cost
Method of Financing General Revenues
Estimate Quality pre-design
Schedule
Project Milestone Date
Personnel
Person Project Role and Responsibilities
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 23 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Road Street Lighting
Project Title MacKenzie Conduit/Grounding upgrade
Project ID
Project Priority 1
Date July 21 2014 v1.0
Project Description
Project Purpose
To install conduit where it is missing underground and to install proper grounding in that conduit to each 9M pole on MacKenzie Ave. The bases should be upgraded while we are digging up the area as well as they do not have proper provisions for new conduit entry and new poles put up on McKenzie to bring everything up to codes and standards. The existing concrete bases do not have proper conduit in the concrete to conform to current code so we cannot simply run new conduit tot eh old bases.
Results Proper grounding and conduit run underground to the streetlights on MacKenzie complete with new concrete bases, 9M poles and new fixtures, bringing the installation up to current safety standards and local codes.
Scope of Project Replace 18 streetlight bases and poles. Install new conduit between poles and pull in proper wire to bring the installation to code. Project to be done one side of the roadway at a time to minimize downtime of lighting at night.
Justification
The streetlights on MacKenzie Ave are not properly installed safely or up to today’s code. They are not grounded, leaving a potential for injury if a fault occurs and the wires that are underground are simply directly buried, not in conduit. This is a major violation of safety standards and poses a risk to public safety as the poles may become energized with no path to ground to trip the circuit breaker. Worse case scenario is that someone leans against the pole in a fault situation and is exposed to upwards of 40A at 120V.
Cost
Estimated Cost $130,000
Method of Financing General Revenues
Estimate Quality Written quote on material (subject to change), labour estimated for public works employees and equipment.
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 24 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Schedule
Project Milestone Date
Installation Complete September 2015
Personnel
Person Project Role and Responsibilities
Electrical Department Purchase material, organize work and perform work.
Road Works Department All civil work, assist with standing poles and setting bases.
Pictures
Wiring Buried Directly In the Ground, No Conduit. No Ground Wire.
Old Base. No Conduit in concrete, a hole was hammer drilled on a 45 deg angle and the wires run through it.
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 25 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Proposed Conduit Layout. One road crossing on MacKenzie Ave, two on fourth, two on fifth, two on sixth and two on seventh.
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 26 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Nichol Road Reconstruction – 125m West of Hay Rd. To Camozzi Rd. intersection.
Project ID ENG -
Project Priority 1
Date 28/07/2014.
Project Description
Project Purpose To replace failing section of road.
Improve the quality of the city’s road network.
Results Improved traffic flow and pedestrian/bike safety.
Scope of Project
Construct 385m of 9.2m wide paved roadway with 3m wide driving lanes, 1.6m wide bike lanes and 0.5m gravel shoulders . Excavate and reconstruct subbase and base. Possibly install geotextile fabric. On Nichol road from approximately 125m west of Hay Road to Camozzi Road,
Justification Asset Management Policy – Statement 1 – “The City of Revelstoke will maintain and manage infrastructure assets at defined levels to support public safety, community well-being and community goals”.
Cost
Estimated Cost $370 000
Method of Financing Capital
Estimate Quality Pre-design
Schedule
Project Milestone Date
Survey/ Design 2014
Construction 2015
Personnel
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 27 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Person Project Role and Responsibilities
Derek Low Survey/Design
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 28 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Pavement Condition Assessment and Pavement Management System
Project ID ENG
Project Priority 1
Date 10 August 2014 v1.1
Project Description
Project Purpose Update and standardize the City’s pavement condition assessment data and paving prioritization procedures.
Results 1. Updated pavement condition data 2. Pavement Management Policy
Scope of Project
Procure special ist consultant services to measure the pavement condition on al l streets in Revelstoke using truck mounted equipment to develop a standardized pavement condition assessment.
Develop a Pavement Management System based on current best practice.
Justification
The City’s existing pavement condition data has been collected manually over the past six years. Manual collection is time-consuming and is prone to differences in collection accuracy.
Municipali ties must decide how to divide scarce financial resources for pavement maintenance and rehabil i tation judiciously among various projects. Historically, most maintenance and rehab decisions are based on the experiences of engineering and public works staff, rather than on documented procedures.
A pavement management system (PMS) is a decision support system to integrate pavement activities with roadway evaluations and predictions to achieve the best possible use of available funds by comparing investment alternatives and coordinating design, construction and maintenance.
Cost
Estimated Cost $80,000
Method of Financing Engineering Capital
Estimate Quality Based on budget level quote from supplier
Comment [MT1]: Need cost from Tetratech
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 29 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Schedule
Project Milestone Date
RFP
Pavement Survey
Data Delivery
PMS operational
January 2015
May/June 2015
July/August 2015
September/October 2015
Personnel
Person Project Role and Responsibi l i ties
Mike Thomas P.Eng. ENV SP
Derek Low – Engineering Tech
Consultant
Consultant or Staff
Project Director
Project Manager
Survey and Data Preparation
PMS configuration
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 30 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Public Works Shop HVAC Upgrades
Project ID ENG -
Project Priority 1
Date June 24,2014
Project Description
Project Purpose Make-up air to be added for offices and reception will ensure CO2 levels are adequate. The mechanic and welder shop ventilation system currently transfers some fumes into other workspaces. This project would eliminate this risk.
Results Improved air quality and office comfort.
Scope of Project Design system, install make up air unit with controls.
Justification Workplace health and safety
NOTE: This project must have a design and justification completed prior to committing to the installation. (MT 8/14/14)
Cost
Estimated Cost $25,000
Method of Financing General Revenue
Estimate Quality Pre-design, written quote
Schedule
Project Milestone Date
Completion October 2015
Personnel
Person Project Role and Responsibilities
Electrical/Building Dept. Project Manager
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 31 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Public Works Shop Electrical Upgrades
Project ID ENG
Project Priority 3
Date August 14, 2014 v1.0
Project Description
Project Purpose Upgrade existing lighting in storage equipment barn and yard. Lumen levels are lower than industry standards. Modern lighting will reduce maintenance and reduce energy.
Results Upgraded lights with better lighting levels.
Scope of Project Removal of existing lights and installation of new and additional lights.
Justification Workplace Health and Safety
Cost
Estimated Cost $ 7,000
Method of Financing General revenue
Estimate Quality written quote
Schedule
Project Milestone Date
Personnel
Adam Kidd Project Role and Responsibilities
Electrical/Buildings Dept. Purchase material and perform work
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 32 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Excavations
Project Title Shoring
Project ID Capital
Project Priority 5
Date 14 August 2014
Project Description
Project Purpose
The current shoring owned is 20’ long and non-adjustable, and requires heavy equipment to move. The old equipment cannot be used in tight alleyways where there is lots of infrastructure in the ground. The new aluminum shoring is able to be moved and assembled by hand and moved in a pick-up truck. It is essential to life safety to use shoring when excavating in a narrow space with high walls, it is mandated by WCB. The weight reduction with using aluminum creates a user friendly product that is easy to use, so in turn will be used more frequently. Currently if this shoring is required it must be rented out of Calgary and shipping on it is not cost-effective.
Results More versatile aluminum shoring to replace old steel shoring.
Scope of Project Purchase new aluminum shoring
Justification Worksafe BC Requirements and operational efficiency
Cost
Estimated Cost $16,500
Method of Financing General Revenues
Estimate Quality Written Quote
Schedule
Project Milestone Date
2015
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 33 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Street Lights PHOTO
Project Title Old streetlight removal
Project ID Capital GL #
Project Priority 2
Date June 6 2014
Project Description
Project Purpose
To remove potentially dangerous wiring at the entrance way to the elementary school. Currently we are responsible for maintenance on these old poles/lights where they are not needed as the entrance way is lit by brand new lighting on the opposite side of the road. These are city owned poles and lights and are our responsibility. The school district has been contacted as well as BCHydro as they were initially thought to be BCHydro’s poles.
Results Removal of dangerous over head lines in close proximity to trees
Scope of Project Removal of 3 wooden poles and associated electrical.
Justification Safety and Cost Savings
Cost
Estimated Cost $5,000
Method of Financing General Revenue
Estimate Quality Internal Quote
Schedule
Project Milestone Date
Personnel
Person Project Role and Responsibilities
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 34 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Photos
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 35 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Streetlight Replacement
Project ID ENG -
Project Priority 1
Date Date that this document was last modified.
Project Description
Project Purpose To upgrade degrading streetlight infrastructure. Old steel poles are rusting at the base creating structural issues with the poles. While upgrading the pole hardware the fixture is also upgraded to a modern full cut-off fixture to eliminate light pollution.
Results Removal of all dangerous streetlight poles that pose a hazard within the next 5 years.
Scope of Project A number of poles will be replaced each year to upgrade old green poles to new galvanized poles as well as replacement of any damaged revite light poles in the downtown core, as outlined in the 2014 counsel report.
Justification Danger to public from degrading poles. Major rust on bases of poles resulting in a reduction of structural integrity. A pro-active approach by replacing prior to any incident.
Cost
Estimated Cost $35,000
Method of Financing General Revenues
Estimate Quality Internal quote
Schedule
Project Milestone Date
Personnel
Person Project Role and Responsibilities
Jason Zimmer Carry out work with a RMP
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 36 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Tool Budget
Project ID
Project Priority 5
Date
Project Description
Project Purpose Locator – Concrete chain saw
Results
Scope of Project Replace old locator that has been rebuilt once and is unreliable. Concrete chainsaw is an addition to the tool list and can cut deeper and faster.
Justification Locator is for use by all departments, concrete chain saw can also be used by all departments.
Cost
Estimated Cost 10,000
Method of Financing
Estimate Quality
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 37 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Victoria Road Resurfacing – Wright to Kootenay
Project ID ENG -
Project Priority 2
Date 06/08/2014.
Project Description
Project Purpose To replace failing section of road and improve the quality of the city’s road network. This is phase three of the Victoria Road paving renewal project, addressing Wright to Kootenay.
Results Improved ride comfort, decreased annual maintenance. More efficient snow removal.
Scope of Project Mill out existing asphalt, re-grade and repave with 75mm of new asphalt.
Justification Asset Management Policy – “The City of Revelstoke will maintain and manage infrastructure assets at defined levels to support public safety, community well-being and community goals.”
Cost
Estimated Cost $353 000
Method of Financing Capital
Estimate Quality Pre-design
Schedule
Project Milestone Date
Survey/ Design 2014
Construction
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 38 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Personnel
Person Project Role and Responsibilities
Derek Low Survey/Design
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 39 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Engineering
Project Title Wash bay/.filling station ground pad
Project ID
Project Priority 1
Date June 18, 2014
Project Description
Project Purpose
In 2013 the heated water piping was completed for a wash bay/filling station located at the public works yard. The piping was used this past winter for the mixing of salt brine. Funding is now being requested to install a concrete and asphalt pad so the bay can be utilized for washing equipment. Currently the dirt ground makes it impossible for washing. The completion of the pad will give operators the ability to wash off equipment after each use. This practise helps reduce maintenance costs especially in winter conditions with the removal of sand and salt. The bay is equipped with multi outlets to allow up to three pieces of equipment to be cleaned or filled simultaneously. This reduces operator time.
Results Efficiency in cleaning equipmnent
Scope of Project Except for the application of asphalt all work would be done in house.
Justification Operational Efficiency and Environmental
Cost
Estimated Cost $40,000.00
Method of Financing General revenue
Estimate Quality Method of estimating –, pre-design, in house
Schedule
Project Milestone Date
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 40 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Sewer
Project Title Downie Forcemain Replacement
Project ID SEW -
Project Priority 3
Date 10-Aug-14 v1.0
Project Description
Project Purpose
The Downie forcemain carries all of the sewer collected from Columbia Park, Lower Town, Downtown and most of Southside to the Sewer Treatment Plant. The forcemain was installed in 1976, constructed from Asbestos Cement Pipe. In 2012, a significant spill was experienced due to failure of the forcemain material, prompting a review of the design.
Over several years, this project will review route options for a replacement forcemain, (as the existing main will need to stay in operation during construction), design the forcemain, and provide tender ready drawings and documents.
Results
2015 – Route selection complete
2016 – Detailed design
2018 – Construction complete
Scope of Project In 2015 the route selection, survey and conceptual design will be completed by an engineering consultant.
Justification ICSP – 4. Resilient Infrastructure
Liquid Waste Management Plan – Stage 2 – Identified as a priority with upgrading Downie Lift station (complete).
Cost
Estimated Cost 2015 - $50,000
2016-2018 estimated to be $1,000,000 or more
Method of Financing
2015 – DCC’s and General Revenue
2016-2018 General Revenue, DCCs, and Grants
Estimate Quality Pre design
Schedule
Project Milestone Date
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 41 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Sewer
Project Title UPS Upgrades
Project ID SEW
Project Priority 1
Date June 4 2014
Project Description
Project Purpose To extend the amount of run time the water and waste water sites can communicate with city hall on a power outage.
Results One hour battery backup at all sites on a power outage
Scope of Project Install 8 new UPS systems at sites that have existing 12V battery backup systems
Justification
The current battery back-up systems only give 20-30min of run time at the sites. The city hall server room has battery backup for 50 min. The sites should have battery backup equal to or grater than that at city hall. In the event the scada servers eventually have generator backup, it would be beneficial to have as much battery back-up at the sites without generators as possible. The average UPS system can keep a site online for over an hour.
Cost
Estimated Cost $10,000
Method of Financing Sewer Funds
Estimate Quality Written quote on material (subject to change)
Schedule
Project Milestone Date
Personnel
Person Project Role and Responsibilities
Electrical Department Purchase material and perform work.
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 42 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Sewer
Project Title WWTP 2ND Screen
Project ID SEW -
Project Priority 3
Date 14 August 2014
Project Description
Project Purpose
Screening is the primary treatment process at the Sewer Treatment Plant. When maintenance is required on screen one, the un-degradable solids are bypassed into the lagoon, creating maintenance issues in the lagoons as they get the un-degradable solids directly. This creates a need to clean the lagoons at a high cost and decreases efficiency. It breaks down the turn over times in the lagoons. This would allow a backup screen for servicing, resulting in less down time and no bypassing of un-degradable material
Results Continued treatment of sewer.
Scope of Project Install 2nd screen in WWTP channels.
Justification Asset Management Policy: 1. The City of Revelstoke will maintain and manage infrastructure assets at defined levels to support public safety, community well-being and community goals.
Cost
Estimated Cost $340,000
Method of Financing Sewer
Estimate Quality Written Quote
Schedule
Project Milestone Date
2018
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 43 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Sewer
Project Title Sewer Treatment Plant HVAC Upgrades
Project ID SEW -
Project Priority 2
Date 14 August 2014
Project Description
Project Purpose To change the airflow in the blower rooms to be more efficient. Possibly add an A/C unit. Poor airflow resulting in high heat in the blower room. This results in motor failure from extreme temperatures.
Results Mechanical engineer’s report on airflow.
Scope of Project Mechanical Engineer’s Report
Justification Asset Management Policy – “The City of Revelstoke will maintain and manage infrastructure assets at defined levels to support public safety, community well-being and community goals”
Cost
Estimated Cost $17,000
Method of Financing Sewer
Estimate Quality pre-design,
Schedule
Project Milestone Date
Personnel
Person Project Role and Responsibilities
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 44 of 64
City of Revelstoke - Capital Project Data Sheet 2016
Project Data
Project Area Sewer
Project Title Burke lift station
Project ID SEW -
Project Priority 3
Date 10 August 2014
Project Description
Project Purpose
To upgrade the lift station to submersible pumps from surface assisted-prime pumps. This project would improve the lift station efficiency by using less power, greater reliability, less frequent downtown and blockages, and improved operational safety and access. It is likely that the project would also remove the direct overflow to the river, (infrequently used in lengthy power outages or pump failure only).
Results Pump station design and tender documents
Scope of Project Procurement of design and tender services for a replacement or rebuilt sewer lift station.
Justification ICSP 4. – Resilient Infrastructure
Cost
Estimated Cost $60,000 in 2016
Method of Financing Sewer Revenue
Estimate Quality Pre-tender
Schedule
Project Milestone Date
Design
Construction
2016
2019
Personnel
Person Project Role and Responsibilities
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 45 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Water
Project Title Greeley WTP - Chlorine automatic shut-off
Project ID WAT
Project Priority 3
Date July 30, 2014 v1.0
Project Description
Project Purpose
Chlorine represents one of the greatest workplace hazards for the water utility staff. While the City does have chlorine handling procedures that meet Worksafe BC requirements, the installation of automatic shut-offs would reduce exposure to chlorine gas in the event of a leak or failure in the treatment plant and minimise the need to re-enter the building to turn off the chlorine source.
Results A safer working environment. Chlorine “tonners” will be shut off automatically in case of a leak
Scope of Project Chlorine detection and automatic shutoff valves would be, specified, installed and tested
Justification ICSP 4.2 Priority Actions – Water – “Update the Emergency Response Plan for a failure at the water treatment plant or convert the existing backup chlorination system from gas to sodium hypochlorite.”
Cost
Estimated Cost 35,000
Method of Financing Water
Estimate Quality written quote
Schedule
Project Milestone Date
2015 May - June
Personnel
Person Project Role and Responsibilities
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 46 of 64
City of Revelstoke - Capital Project Data Sheet 2019
Project Data
Project Area Water
Project Title Greeley WTP Filter Replacement
Project ID WAT
Project Priority 1
Date July 30 2014 v1.0
Project Description
Project Purpose
To maintain the Greeley Creek Water Treatment Plant operation by the replacement of membrane filters. The Greeley Creek Water Treatment Plant is a membrane filtration system that as part of the lifecycle of the plant, filters are to be replaced every 8 to 10 years. Failure to replace the filters within the recommended timeframe may impact treatment operations and water quality.
Results Continued provision of clean drinking water
Scope of Project There are 450 filter elements that are replaced as part of the project, which will involve contracted support and city crews. The Project should be completed as a whole.
Justification
Greeley Creek Water Treatment Plant Operating Manual
ICSP 4.2 Resilient Water Infrastructure
ICSP 2.4 Financial Well-being – “Prepare and implement a long term City Infrastructure and Asset Management Plan.”
Asset Management Policy –
1. The City of Revelstoke will maintain and manage infrastructure assets at defined levels to support public safety, community well-being and community goals.
Cost
Estimated Cost $615,000
Method of Financing Water Capital
Estimate Quality written quote from supplier/installer
Schedule
Project Milestone Date
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 47 of 64
City of Revelstoke - Capital Project Data Sheet 2019
Installation May 2019
Personnel
Utilities operators
2 installers from Evoqua water tech Installation
Utilities Foreman Project Manager
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 48 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Water
Project Title Water Treatment Plant - Hypo transfer pump
Project ID WAT -
Project Priority 5
Date 13 August 2014
Project Description
Project Purpose To construct a means of safely transferring hypochlorite from totes to holding tank
Results Safer work practices
Scope of Project 2 days work, installation of pumps and tote stands.
Justification Safety
Cost
Estimated Cost $5,000
Method of Financing Capital
Estimate Quality Written Quote
Schedule
Project Milestone Date
Installation April-May 2015
Personnel
Person Project Role and Responsibilities
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 49 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Water
Project Title Greeley Creek Flow Monitoring
Project ID WAT
Project Priority 4
Date June 10, 2014
Project Description
Cost
Estimated Cost $10,000
Method of Financing Water
Estimate Quality Written quote
Schedule
Project Milestone Date
Personnel
Project Purpose
To collect and monitor steam flow data for Greeley Creek. Collection of flow data allows for a better understanding of spring peak flows and the creeks capacity to supply drinking water for the City. Understanding creek flows and monitoring changes in flow rates also allows for supply and demand, and adaptive management of the City’s drinking water. Currently a city staff member is manually taking periodic measurements of creek flow. The use of an ultrasonic flow meter allows for consistent collection of data done remotely.
Results Collection of data to monitor changes in flow of the creek
Scope of Project The installation of an ultrasonic area velocity flow meter on Greeley creek to collect steam flow and peak flow data.
Justification Greeley Creek Source Protection Plan,
ICSP 4.2 - Water DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 50 of 64
City of Revelstoke - Capital Project Data Sheet 2016
Project Data
Project Area Water
Project Title Water Treatment Plant - Dosing System
Project ID WAT -
Project Priority 3
Date 11 August 2014
Project Description
Project Purpose To upgrade Chemical dosing pumps and storage as the existing pumps are 14 years old and have priming issues. Typically, these pumps require replacement every 15-20 years.
Results Continued efficient operation of the Water Treatment Plant
Scope of Project Procurement of replacement chemical dosing pumps
Justification
ICSP – 4.2 Water – “Improve water quality and encourage efficient water use”
Asset Management Policy – Policy Statements - “1. The City of Revelstoke will maintain and manage infrastructure assets at defined levels to support public safety, community well-being and community goals”.
Cost
Estimated Cost $15,000
Method of Financing Water Capital
Estimate Quality Pre-tender
Schedule
Project Milestone Date
Personnel
Person Project Role and Responsibilities
Water Operator Project Manager
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 51 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Water
Project Title Water Treatment Plant - Turbidity meter replacement
Project ID Capital
Project Priority 5
Date 13 August 2014
Project Description
Project Purpose To replace existing turbidity meters with new meters that are serviceable. The existing meters are not able to be serviced due to limited parts availability.
Results Improved reliability of equipment
Scope of Project Procurement of turbidity meters
Justification Interior Health Operating Permit and Canadian Drinking Water Guidelines
Cost
Estimated Cost 33,000
Method of Financing Water
Estimate Quality Written Quote
Schedule
Project Milestone Date
2015
Personnel
Person Project Role and Responsibilities
Contractor
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 52 of 64
City of Revelstoke - Capital Project Data Sheet 2016
Project Data
Project Area Water
Project Title Kiosk Access Stairway
Project ID WAT -
Project Priority 4
Date 11 August 2014
Project Description
Project Purpose
Access to heat tape kiosk vital to ensuring that the lines across the Illecillewaet bridge do not freeze up in the winter is not possible in the winter. The river bank is too steep to use for an access in the winter months. A stairway is required down the bank to the kiosk to ensure safe access during winter. It would be possible to maintain a clear access on a set of stairs down to the kiosk.
Results Proper, safe, access to the power kiosk for the heat tape on the bridge,
Scope of Project Installation of new stairway to kiosk
Justification Safety, ability to maintain heat tape in winter months when it is needed most.
Cost
Estimated Cost $20,0000
Method of Financing Water Fund
Estimate Quality Previous Quote.
Schedule
Project Milestone Date
Personnel
Person Project Role and Responsibilities
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 53 of 64
City of Revelstoke - Capital Project Data Sheet 2016
Photos
View down to heat tape kiosk
View of area where stair would be located
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 54 of 64
City of Revelstoke - Capital Project Data Sheet 2016
View of Kiosk
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 55 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Water
Project Title Historian Re-Configuration
Project ID WAT -
Project Priority 1
Date June 6 2014
Project Description
Project Purpose
The City’s data for control and operation of the water utility is stored in a server called the Historian. Currently the Historian does not acquire data properly from all of the water and waste water sites. This data is valuable for projecting future consumption and current draw on the system.
Results Fully operational historian server/client system with access to all data past and present.
Scope of Project New hardware and new configuration of our existing system to create easy access to historical data, with proper data back-up.
Justification
Asset Management Policy – Policy Statements
1. The City of Revelstoke will maintain and manage infrastructure assets at defined levels to support public safety, community well-being and community goals.
2. The City of Revelstoke will monitor standards and service levels to ensure that they meet/support community and Council goals and objectives.
Cost
Estimated Cost $12,000
Method of Financing Water Funds
Estimate Quality pre-tender,
Schedule
Project Milestone Date
Personnel
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 56 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Water
Project Title Hydrant Replacement Program
Project ID Capital GL #
Project Priority 1
Date July 11, 2014 – v0.1
Project Description
Project Purpose To upgrade existing hydrant infrastructure - 31 high priority hydrants have been identified for replacement from 2014-2018.
Results The replacement of deficient fire hydrants with compliant installations.
Scope of Project Installation of Hydrants
Justification Council Goals and Objectives
Council Report - January 21, 2014 “Hydrant Replacement Program”
Cost
Estimated Cost $60,000 in 2015
Method of Financing Water Funds
Estimate Quality Internal Budget for parts and labour
Schedule
Project Milestone Date
2015 Project Scope Complete September 2015
Personnel
Person Project Role and Responsibilities
Doug Pendergast Water Utility Operator and Project Manager
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 57 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Water
Project Title Illecillewaet River Water Crossing
Project ID Capital GL #
Project Priority 1
Revision and Date v0.1 July 10, 2014
Project Description
Project Purpose To replace the existing, exposed 16 inch water line crossing the Illecillewaet River with a new directional-drilled crossing.
Results Construction of a new water crossing of the Illecillewaet River:
- Improved water security for Arrow Heights and the Resort Area - A water line installed that would have an 80 year or more lifespan.
Scope of Project
The City would procure, through a competitive process, directional drilling services for the installation of a new watermain crossing of the Illecillewaet River. The existing main would be abandoned. Design work is being undertaken by Opus Dayton and Knight, Directional Drilling works will be completed by a contractor, water main tie-in’s will be undertaken by City Crews or a Contractor.
Justification Interior Health Permit to Operate, DWP Act Section 6
ICSP – Resilient Infrastructure – Water 4.2.4
Cost
Estimated Cost $600,000
Method of Financing Water Funds
Estimate Quality Budget Level Estimate by Consultant
Schedule
Project Milestone Date
Design Complete September 2014
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 58 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Interior Health Approval
Procurement Process
Construction
Commissioning and Tie-In
Disconnection and Abandonment of Existing Main
October 2014
January 2015
April 2015
April 2015
May 2015
Personnel
Person Project Role and Responsibilities
Mike Thomas P.Eng. ENV SP
Derek Low
Opus Dayton and Knight
Contractor
Doug Pendergast
Project Director
Project Manager
Design Engineer
Installation of directional drilled conduit
Water Operator and installation of tie-ins
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 59 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Water
Project Title Drinking Water Emergency Response Plan
Project ID WAT -
Project Priority 1
Date June 10, 2014
Project Description
Project Purpose Emergency response planning is an essential part of managing a drinking water system to ensure safe and reliable drinking water. The City’s current drinking water emergency response plan has not been updated since 2001 and requires review and updating.
Results Permit to Operate compliance for drinking water emergency response planning
Scope of Project
Emergency response planning assists the City in preparing for and responding to emergency situations. A revised plan is required that explores potential emergency situations and how they may impact the different parts of the water system and the system’s ability to deliver safe drinking water. The plan will contain contact information, detailed procedures and other information required to effectively respond to a set of identified emergency situations.
Justification
Interior Health Permit to Operate, DWP Reg. Section 13, DWP Act Section 10 & 15
Greeley Creek Source Protection Plan
ICSP – Resilient Infrastructure 4.2.4
Cost
Estimated Cost $15,000
Method of Financing Water Funds
Estimate Quality Pre Tender
Schedule
Project Milestone Date
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 60 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Project Data
Project Area Water
Project Title West Laforme Fire flow Upgrade
Project ID WAT
Project Priority 5
Date 13 August 2014
Project Description
Project Purpose To supply adequate fire flow to the properties on Laforme Blvd. west of Columbia Park Drive. There are ten properties in this area, excluding the golf course parcels. Eight developed parcels have between 300m to 500m to the nearest hydrant.
Results Improved domestic and fire flow to residents.
Scope of Project Replace 85m of existing 100mm AC and 490m of 50mm pvc water main with 150mm pvc main.
Justification The water supply in this area does not meet the fire flow requirements of the City of Revelstoke.
Cost
Estimated Cost $330,000
Method of Financing Water Capital
Estimate Quality Pre-design, unit price only.
Schedule
Project Milestone Date
Survey/ Design 2014
Construction 2015
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 61 of 64
City of Revelstoke - Capital Project Data Sheet 2015
Personnel
Person Project Role and Responsibilities
Derek Low
Contractor
Survey/Design
Construction
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 62 of 64
City of Revelstoke - Capital Project Data Sheet 2017
Project Data
Project Area Water
Project Title
Water Treatment Plant – Biomass fueled heating system
Project ID WAT -
Project Priority 5
Date 11 August 2014
Project Description
Project Purpose This project aids in moving the City toward a local more sustainable heating source. The use of wood waste to heat the Water Treatment plant compared with current propane can save in operating cost and reduce greenhouse gas emissions.
Results
A biomass heating system at the Water Treatment plant resulting in an annual reduction of $12,700 in operating cost, a reduction of 42 tonnes of greenhouse gas emissions, and a reduction in the amount of wood waste needing to be trucked out of Revelstoke.
Scope of Project
Installation of a biomass system for the Water Treatment plant, including a boiler plant, distribution system and fuel storage. A fully funded business case completed by Wood Waste 2 Rural Heat indicates the conversion of the heating of the water treatment plant from propane to a biomass heating could result in an annual savings of $12,700 in operating costs based on current propane pricing. The project has a 13.5 year simple payback, which is reduced to 10.8 with 20% grant funding.
Justification Corporate Green House Gas Emissions Reduction Strategy, Community Energy and Emissions Plan (CEEP)
Cost
Estimated Cost $172,000
Method of Financing Water, Grant, Gas Tax, Carbon Tax Reserve fund,
Estimate Quality Consultant Estimate - Greeley Water Treatment Plant Biomass Business Case
Schedule
DRAFT
AGENDA ITEM #7.a.
2015-2019 Engineering and Utilities Capital Projects Page 63 of 64