17
Welcome to our OPEN HOUSE BC HYDRO’S COLUMBIA OPERATIONS

FINAL Revelstoke Columbia Operations 2015

Embed Size (px)

DESCRIPTION

Presentation on BC Hydro's Columbia River operations for Mica, Revelstoke and Arrow Lakes.

Citation preview

  • Welcome to our OPEN HOUSE BC HYDROS COLUMBIA OPERATIONS

  • 2

  • 3

    COLUMBIA RIVER BASIN

    Columbia River is the fourth largest in North America and the most powerful.

    Canada has 15% of the basin area. The Canadian portion of the basin is mountainous, with much snow. On average, it produces 30-35% of the run-off for the entire basin. During flood years Canada has produced as much as 50% of the flows recorded at Portland.

    Most hydropower production, and need for flood control is in the USA. The best storage dam sites are in Canada.

    COLUMBIA RIVER TREATY Canada United States

    Required to construct the Mica, Arrow and Duncan storage reservoirs on the Columbia River system.

    Required to pay Canada 50% of the estimated value of future flood control benefits in the U.S.

    Required to operate these reservoirs for optimum power generation and flood control downstream in both countries.

    Required to deliver to Canada 50% of the increased power capability at downstream U.S. plants due to upstream regulation this is called the Downstream Benefit.

    Canada did not turn over control of its reservoirs to the U.S. Rather, the Treaty requires specific operations for specific conditions.

    Permitted to construct and operate the Libby project on the Kootenai River flooding some Canadian land, but also providing power and flood control benefits for Canada.

  • 4

    Mica Dam

    Both countries realize significant flood control and power benefits from the Treaty.

    U.S. paid Canada for 50% of the U.S. flood control benefits provided by Treaty reservoirs until 2024.

    Canada receives its 50% share of electricity benefits directly from the U.S., typically worth between $100 to $150 million per year depending on the electricity market and water supply. Called the Downstream Benefit, this goes directly to the B.C. government.

    Treaty has a minimum term of 60 years. It can be terminated by either country with 10 years notice.

    Canada will continue to provide a minimum amount of flood protection (Called Upon Flood Control) for U.S. as long as the Canadian dams exist.

    COLUMBIA RIVER TREATY 2014 REVIEW The Province is currently consulting with Basin residents during its review of the

    Columbia River Treaty. Website: www.gov.bc.ca/ColumbiaRiverTreaty

    COLUMBIA RIVER TREATY BENEFITS

  • 5

    Non-Treaty Storage Agreement (NTSA) Non-treaty storage is additional water stored in Kinbasket Reservoir not

    coordinated under the terms of the Columbia River Treaty.

    New long-term Non-Treaty Storage Agreement (NTSA) executed April 2012 to coordinate use of 5 million acre feet of non-treaty storage. Agreement expires September 2024 with early termination provisions. Short term Bridge Agreement in place from September 2011 through March 2012.

    Water transactions by mutual agreement on a weekly basis. All flow changes made at the Hugh L. Keenleyside Dam.

    Canadian benefits of the new NTSA Power benefits estimated over $50 million to BC Hydro from September 2011

    to September 2015.

    More control of BC Hydro reservoirs. In 2012, BC Hydro used NTSA agreement to reduce Hugh L. Keenleyside dam outflows by 50,000 to 60,000 cubic feet per second during a critical three week period and provide additional downstream flood protection to Castlegar and Trail.

    Greater system flexibility to meet existing Columbia Water Use Planning objectives.

    2014/15 Non-Power Uses Agreement Protects Canadian fish (trout and whitefish) during spawning.

    Protects U.S. salmon during spawning migration.

    BC Hydros operation of our Columbia facilities is governed by the terms of the Columbia River Treaty that sets out strict rules for water releases over the Canadian/U.S. border.

    Periodically, the Treaty Operating Committee negotiates other (supplemental) operating agreements when there are mutual benefits to modify water releases specified by Treaty terms.

    COLUMBIA OPERATING AGREEMENTS

  • 6

    2015 RAINFALL Winter precipitation fell largely as rain due to warmer than normal temperatures:

    Resulting runoff directly entered reservoirs and passed through the system as prescribed by Columbia River Treaty.

    More winter rainfall resulted in below normal spring snowpack with very low snowpack in the southern part of the Columbia basin.

    Spring precipitation (April and May) was below normal.

    Cumulative Monthly Precipitation for Arrow, Duncan, and Revelstoke

    The red line indicates the average cumulative precipitation for each month in the 2014-2015 water year and the blue line shows the actual precipitation.

  • 7

    OPERATING CONDITIONS Based on snowpack levels Near to below normal in the

    Upper Columbia and the Kootenay region.

    Well below normal in the U.S.

    Water supply forecast assumes average rainfall from May through September.

    May water supply forecast (February to September 2015) as % of normal

    Kinbasket Reservoir 95%

    Revelstoke Reservoir 96%

    Arrow Lakes Reservoir 99%

    Duncan Reservoir 99%

    Kootenay Lake 97%

    Entire Columbia Basin (April - August)

    72%

    2014 & 2015 BC SNOWPACK

    2014 2015

  • 8

    WATER SUPPLY FORECAST COLUMBIA BASIN

    Forecast determines Arrow Lakes Reservoir discharges under the Columbia River Treaty.

    Significantly below normal forecast triggers additional releases.

    Additional Arrow releases result in lower summer water levels (happening this year).

    The water supply forecast for the entire Columbia River Basin has steadily declined since January 2015 from about average to currently 72 per cent of normal.

    Fourth driest year in 55 years of record.

    Very low forecast throughout the entire U.S. portion of the basin.

  • 9

    EXPECTED 2015 OPERATIONS Arrow Lakes Reservoir Expected maximum level is between 1,423 feet and 1,428 feet in late

    June/early July. Normal full pool is 1,444 feet (licence maximum). In 2014, the peak water level was 1,440.6 on July 3.

    Below average Arrow Lakes Reservoir water level forecast due to a number of factors: o Mild winter (lower than normal electricity demand) meant less

    generation from Mica/Revelstoke dams and lower than normal inflows into Arrow.

    o Higher than average late spring releases called for by operating agreements with U.S. in response to dry conditions: Columbia River Treaty Proportional Draft Provisions triggered

    during very dry years. Accounts for ~15 feet draft from Arrow. NTSA Dry Release Provision - triggered during the lowest 20% of

    water conditions for salmon migration in the lower Columbia River. Bonneville Power Administration requested the dry release provision on May 8, 2015. Although this will result in ~4 feet of draft from Arrow by July 1, more water is currently stored under the NTSA (~21 feet at Arrow) than will be released.

    o Summer releases for fish Flow Augmentation Storage - 1 million acre foot (equivalent to ~8

    feet) at Arrow was stored in January to meet Canadian and U.S. fish objectives under the Non Power Uses agreement. This stored water is expected to be released across June and July to benefit fish. This has no impact on the July month end elevation, but a deeper draft from Arrow reservoir is expected to occur when the water is released in June resulting in lower than normal June reservoir levels.

    Note that the actual summer water levels depend on Upper Columbia generation, market, load and inflow conditions.

  • 10

    Arrow Lakes Reservoir

    EXPECTED 2015 OPERATIONS

    Hugh L. Keenleyside Dam

  • 11

    EXPECTED 2015 OPERATIONS Kinbasket Reservoir Mica/Revelstoke generation ran harder than normal from March to May for

    system requirements and to help support Arrow water levels. Kinbasket Reservoir is not expected to fill this year and the expected maximum

    water level is between 2,465 feet and 2,475 feet in August 2015. In 2014, the peak level was 2,473.7 feet on November 9.

    Additional water releases from Mica dam are possible depending on inflow conditions.

    Actual levels depend on market, electricity load and inflows.

  • 12

    EXPECTED 2013 OPERATIONS

    Revelstoke dam outlets

    Revelstoke Dam Discharges Minimum flow of 142 cubic metres per second (5,000 cubic feet per second)

    from dam required under Columbia River Water Use Plan. Expect to benefit fish and fish habitat. In 2015, occasional small volume spills at Revelstoke dam during low demand

    periods to maintain minimum flow and/or Revelstoke Reservoir water levels.

    Revelstoke Reservoir Typically BC Hydro maintains water level within 1.5 metres (5 feet) of full pool

    water level of 573.0 metres (1,880 feet) to maintain head at Revelstoke dam. Expect to operate reservoir above normal minimum operating water level of

    571.5 metres (1,875 feet) for remainder of recreation season.

  • 13

    Revelstoke Forebay

    EXPECTED 2015 OPERATIONS

  • 14

    Reservoir water levels are very difficult to forecast due to the unpredictability of weather patterns, inflows, domestic load demand and electricity prices.

    HOW TO STAY INFORMED Sign up to receive regular reservoir email updates and biannual summary of BC

    Hydros Columbia Operations

    Reservoir level information through bchydro.com

    Reservoir level phone line: 1-877-924-2444

    Contact a BC Hydro Community Relations Representative:

    Mary Anne Coules Jen Walker-Larsen Castlegar Revelstoke 250-365-4565 250-814-6645 [email protected] [email protected]

    CONDITIONS CHANGE

  • 15

    ADDING TWO NEW GENERATING UNITS BC Hydro is currently working to install the

    sixth generating unit at Mica Generating Station. The new fifth generating unit has been completed.

    Each generating unit will provide approximately 500 megawatts of capacity during peak demand periods.

    New turbines manufactured in Germany and transported over 18,000 kilometres to Mica Dam.

    More than 1,500 individual workers have been hired so far to help with project work.

    MICA PROJECTS

    AGING SWITCHGEAR EQUIPMENT REPLACED BC Hydro has replaced Micas gas-

    insulated switchgear equipment that delivers electricity from Micas underground generating units to the above-ground transmission lines.

    Lowering Mica 5 turbine into place.

    Loading new turbine at port of Rotterdam

    Install new switchgear at Mica switchgear building

    NEW CAPACITOR STATION A new series capacitor station needed to

    deliver the additional power generated to BC Hydros grid was constructed near Seymour Arm.

  • 16

    BC HYDRO CONSIDERING SIXTH UNIT AT REVELSTOKE DAM Based on current electricity load forecasts,

    BC Hydro expects Revelstoke Unit 6 will not be needed until about 2029.

    If the future does not unfold as we expect, additional resources may be needed sooner. As a contingency, BC Hydro has started planning work to allow the Revelstoke Unit 6 Project to be constructed as early as 2020 if it is needed.

    The sixth generating unit would add approximately 500 megawatts of capacity to BC Hydros system.

    A new series capacitor station west of the Summerland area and upgrades to the Nicola substation would also be needed in order to reliably deliver the additional generation.

    BC Hydro has convened a Revelstoke Unit 6 Core Committee to help identify project impacts and recommend mitigation measures.

    REVELSTOKE UNIT 6

    Penstock installation for Revelstoke Unit 5 Project

  • 17

    Approved in 2007, the Columbia River Water Use Plan calls for a large number of monitoring programs and projects to be implemented on the mainstem Columbia River from Kinbasket Reservoir downstream to the Canada/United States border over 12 years.

    Programs and projects expected to benefit recreation, wildlife, fish, vegetation, and archaeology.

    Revelstoke area projects/programs: Revelstoke dam minimum flow to benefit fish

    and fish habitat

    Kinbasket and Revelstoke Reservoir productivity study

    Annual juvenile sturgeon releases and white sturgeon research

    Monitoring of shorebird, waterbird, and songbird use of Arrow Lakes Reservoir and drawdown zone

    Revelstoke wildlife enhancement projects

    Revelstoke Western painted turtle study

    Monitoring of amphibians and reptiles in drawdown zone

    Monitoring of tributary access in Arrow Lakes Reservoir for spawning fish

    COLUMBIA RIVER WATER USE PLAN

    Shelter Bay sturgeon release

    Baby Western painted turtle

    Willow flycatcher nest

    Retrieving Columbia River sampling equipment

    Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17