City of Raleigh
Pleasant Valley Road Widening ProjectMarch 15, 2018
Public Meeting Presentation
Pleasant Valley RD2016
Pleasant Valley Rd. Widening Project
Project Location
Purpose of ProjectPleasant Valley RD2016
• Reconstruct Damaged Pavement
• Widen to a Three-Lane Section (According to Comprehensive Plan)
• Add Facilities For Pedestrians and Bicycles on both sides of the road
• Add pedestrian refuge at signalized intersections (where applicable)
Project ChallengesPleasant Valley RD2016
• Minimize Property Encroachment
• Proximity Parking Lots
• Existing Utilities
• Stormwater
Proposed DesignPleasant Valley RD2016
6’ CONCRETE
SIDEWALK
VARIABLE WIDTH
PLANTING STRIP
TWO-WAY LEFT TURN
CENTER LANE
6’ CONCRETE
SIDEWALK
5’ BIKE LANE
Stormwater DesignPleasant Valley RD2016
Water Quantity Management• Oversized pipes for
additional storage• 30” RCP along Commercial
Avenue
Landscaping/Planting PalettePleasant Valley RD2016
Planting Objectives• Coordinate with Parks and Recreation• Select plants that foster design cohesion and
uniformity• Mitigate undesirable views• Maintain site lines for safety
Work Zone Traffic ControlPleasant Valley RD2016
Temporary Closure• Maintaining access to
properties• Allows flexibility to contractor• Coordination with Fire Station
No. 17 and Barnhill• Short detour
Public MeetingsPleasant Valley RD2016
• First Public Meeting was held on October 19, 2016
• Second Public Meeting scheduled for March 15, 2018
Funding & SchedulePleasant Valley RD2016
On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT for design , SUE, survey, landscaping, and geotechnical services.
Estimated Project Cost
$4.3 Million Including Construction and Right of Way
Project Schedule:
• Complete Right of Way Acquisition – Fall 2018 (6-8 Month Duration)
• Award Construction Contract – Winter 2018
• Complete Construction – Fall 2019
Pleasant Valley RD2016
Thank you