FOR THE DEVELOPMENT OF CILAMAYA PORT
SCOPE OF WORKS FOR THE DEVELOPMENT OF CILAMAYA PORT CONSIST OF :
1. Breakwater, Seawall and Revetment Construction2. Dredging (Access Channel and Port Basin) and Reclamation Works3. Container Terminal Wharf Construction4. Car Carrier Terminal Wharf Construction5. Government Service Boats Wharf Construction6. Oil Jetty Construction7. Navigation Aids Facilities8. Power and Water Supply Facilities9. Port Backup Area Development10. Container Handling Equipments and Operation Systems
CONTINUED .
TOTAL OF BACKUP AREA 205 HA
Width : 380 mLength : 9 kmDepth : 17 mVolume : 16.8 million m3
PHASE I
TOTAL INVESTMENT PHASE I : 2.4 BILLION US$
1. BREAKWATER2. OUTER SEAWALLS/REVETMENT3. DREDGING4. QUAYWALL RECLAMATION & SOIL
IMPROVEMENT (BERTH NO. 1, 2,3,7,8 & PETROLEUM JETTY)
5. YARD PAVEMENT & BUILDING6. REVETMENT FOR PHASE II7. BACKUP AREA (ONLAND)8. ROAD & BRIDGE9. CONTAINER HANDLING EQUIPMENT10. NAVIGATIONAL AIDS11. TRAINING DYKE
1. QUAYWALL RECLAMATION & SOIL IMPROVEMENT (BERTH NO. 4, 5, 6 & 9)
2. YARD PAVEMENT & BUILDING3. ROAD & BRIDGE4. CONTAINER HANDLING EQUIPMENT
TOTAL INVESTMENT PHASE II : 1.1 BILLION US$
PROCESS 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
FS
EIA
LOAN AGREEMENT
DED
LOAN AGREEMENT
TENDERING PROCESS
CONSTRUCTION
OPERASIONAL
TIME SCHEDULE FOR CILAMAYA PORT DEVELOPMENT
LAND ACQUISITION(AGRICULTURAL LAND CONVERSION FOR ACCESS
ROAD)
OIL AND GAS FACILITIES(EXISTING AND DEVELOPMENT OF OIL AND GAS
FACILITIES OF PHE ONWJ)
Parking areaFor the vehicle on the toll road CapacitySemi-trailer: 6Large vehicle: 3Small vehicle: 1
Toll gate and office
Interchange,toll gate and office
Rice field shall be protected.
No extra interchangeNo pedestrianNo motorbiketo protect existing land use
ACTION PLANS FOR THE PROJECT
ACTION PLANS FOR THE BOTTLENECKINGSNO THE BOTTLENECKINGS ACTION PLANS
1 LAND ACQUISITION 1. Hearings and coordination with Ministry of Agriculture (agricultural land conversion for access road)
2. Coordination with province and regency (LARAP/Land Acquisition and Resettlement Plan and spatial plan)
3. Coordination with National Land Agency about preparations and procedures of LARAP
2 OIL AND GAS FACILITIES Preparing the consideration and recommendation about the impact of port development and access channel to the operation of oil and gas (by team task force consist of Directorat General of Sea Transportation, DirectoratGeneral of Oil and Gas, Pertamina, SKK Migas, and PHE ONWJ)
DETAIL ENGINEERING DESIGN 2014
PREPARATION OF LAND ACQUISITION 2014