3
Project No: GK002 Date: Drawings No: Location: Check List Number: Equipment Description: Sub-System Number: Test Package Number: No. Description YES NO N.A 1. Check correctness of equipment tag 2. Check and record nameplate data in Test Memo 3. Check correctness of cable tag 4. Check tightness of mounting bolts 5. Check correctness and tightness of cable gland 6. Check correctness and tightness of cable lug 7. Check tightness of terminals 8. Check correct number of cell 9. Check correctness of electrolyte being filled, if any 10. Check correctness of warning sign being displayed 11. Check correctness of service description being displayed 12. Check cleanliness of battery 13. Check continuity and insulation resistance (line to line and line to earth) of cable. Record the lowest Page 1 of 3 ELECTRICAL COMPLETION REPORT (EC) Battery

Check List EI-CL-12 Battery

  • Upload
    andyngo

  • View
    215

  • Download
    1

Embed Size (px)

DESCRIPTION

puo

Citation preview

Page 1: Check List EI-CL-12 Battery

Project No: GK002 Date:

Drawings No: Location:

Check List Number: Equipment Description:

Sub-System Number: Test Package Number:

No. Description YES NO N.A

1. Check correctness of equipment tag

2. Check and record nameplate data in Test Memo

3. Check correctness of cable tag

4. Check tightness of mounting bolts

5. Check correctness and tightness of cable gland

6. Check correctness and tightness of cable lug

7. Check tightness of terminals

8. Check correct number of cell

9. Check correctness of electrolyte being filled, if any

10. Check correctness of warning sign being displayed

11. Check correctness of service description being displayed

12. Check cleanliness of battery

13.Check continuity and insulation resistance (line to line and line to earth) of cable. Record the lowest value.

Page 1 of 2

ELECTRICAL COMPLETION REPORT (EC)

Battery

Page 2: Check List EI-CL-12 Battery

No. Cable Tag Continuity Insulation Resistance Line to Line (Mohm)

Insulation Resistance Line to Earth (Mohm)

1.

Remarks:

PVMS QC/ Subcontractor QC

PVMS QA Client Surveyor

Name

Signature

Date

Page 2 of 2

ELECTRICAL COMPLETION REPORT (EC)

Battery