  • Central Catholic High School Msgr. Tim Murphy Center

    Portland, OR

  • Technical Information Project Completion Date: August 26, 2015

    Project Location: Portland, OR

    Size of Project: 1,000 + cubic yards; 8,600 square feet building footprint with slab-on-grade and 2 floors of slab-on-metal-deck, accented by exterior courtyard.

    Concrete Strength Requirements: 4,000 – 5,000 psi

    Water/Cement Ratio: 0.43 – 0.49

    Placement Challenges or Unique Techniques: Access to the job site was one of the more difficult aspects of this project. A large portion of the project took place while school was in session, with a single project entrance crossing through a main pedestrian traffic area used during school classroom breaks. Concrete delivery and traffic control coordination were of utmost importance. Due to job site logistics, the courtyard was also formed and placed after the main building expansion had been erected offering no access for a forklift or concrete boom pump truck. Materials were hand packed and many of the courtyard concrete placements were done utilizing concrete buggies in tight areas on significantly sloped grades.

    Central Catholic High School Msgr. Tim Murphy Center

  • Central Catholic High School Msgr. Tim Murphy Center

    The Central Catholic High School Monsignor Tim Murphy Center

    project added a total square footage of 27,000 sq ft and consisted of an extensive

    renovation including a two-story addition, new classrooms, counseling center and new

    commons area.

  • Central Catholic High School Msgr. Tim Murphy Center

    Boora Architects set their sights on maximizing the potential of Central Catholic High School’s constrained urban setting and modernizing the existing building. The new and renovated spaces create an optimal learning environment through improved

    access to natural light, larger classrooms, break out areas, and technology upgrades.

  • Central Catholic High School Msgr. Tim Murphy Center

    Space-conscious expansion strategies included a new 3-story building wing that encloses the underutilized east side of a central courtyard. All design solutions

    supported the school’s goals of being responsible stewards of the earth’s resources. The design focused on sustainable landscaping and stormwater management,

    superior indoor air quality and efficient mechanical systems.

  • Central Catholic High School Msgr. Tim Murphy Center

    Project logistics demanded for in-time deliveries and creative scheduling to limit impact to the students as well as overcome the new addition’s tight corridors.

  • Central Catholic High School Msgr. Tim Murphy Center

    Project logistics demanded for in-time deliveries and creative scheduling to limit impact to the students as well as overcome the new addition’s tight corridors.

  • Central Catholic High School Msgr. Tim Murphy Center

    Project logistics demanded for in-time deliveries and creative scheduling to limit impact to the students as well as overcome the new addition’s tight corridors.

  • Central Catholic High School Msgr. Tim Murphy Center

    After the building’s basement walls and slab-on-grade were completed, two floors of slab on metal deck were placed and tied into the existing building corridors

    thus completing the new structure’s concrete scope.

  • Central Catholic High School Msgr. Tim Murphy Center

    A focal point of the project was an eye catching addition to the school’s central courtyard.

  • Central Catholic High School Msgr. Tim Murphy Center

    The courtyard build was highlighted by complex tiered planter walls, radius steps, and a new stairway leading up to the new Monsignor

    Tim Murphy Center.

  • Central Catholic High School Msgr. Tim Murphy Center

    The Central Catholic addition offered a variety of schedule and logistical challenges that were met head on with creative thinking and coordination providing new space for

    anticipated growth over the next 25 years.