CCPM - HK - Revised With SSP Examples

Embed Size (px)

Citation preview

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    1/12

    Copyright 2009 The Boeing Company. All rights r eserved.

    CCPM Project Management- A Proven Method for Dramatically Improving Project Performance -

    Henry Kunkel

    The Boeing Company

    May, 2009Copyright 2009 The Boeing Company. All rights r eserved.

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    2/12

    pg. 2Copyright 2009 The Boeing Company. All rights r eserved.

    Discussion Topics

    The Program Managers Dilemma

    CCPM Project Management - A Different Focus

    Comparison of Tradit ional PM to CCPM

    Buffer Management

    Space Shuttle CCPM Projects Software Development

    Hardware Development

    Engineering Technical Document Development

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    3/12

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    4/12

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    5/12

    pg. 5Copyright 2009 The Boeing Company. All rights r eserved.

    Traditional vs. CCPM Project Management Comparison

    A1 AB1 B1

    C1

    B2 B3

    B4AB2

    A2B6B5

    Get ReadyNotifications

    Buffer

    Buffer

    25

    Weeks

    1 3 4 6 7 8 10 11 129

    AB3

    A1AB1

    B1

    C1

    B2 B3B4

    AB3AB2 A2

    B6B5

    1 23

    4 5 67

    8 9 1011

    Critical Path =Longest sequence of activities in a network

    Resources start as early

    As possib leResource

    Conflicts

    Ignored

    Lean PM Schedule View

    Traditional Critical Path Schedule View

    Critical Chain =Longest set of dependent activities, with explicitconsideration of resource availability

    This buffer is needed to

    protect the project for normal

    task variation.

    Pooled Safety Margin

    Critical Chain is Primary Focus

    No Resource Conflicts

    12

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    6/12

    pg. 6Copyright 2009 The Boeing Company. All rights r eserved.

    CCPM Management Project Buffer Status Report

    Percentage Project Buffer Consumed vs. Percent CC Complete

    Team members actively workto recover buffer

    Mitig

    ation

    plan

    sareidentifie

    d

    Management action takenTo assist team recover

    100

    1000

    Team members actively workto recover buffer

    Mitigat

    ionplansare

    identifi

    ed

    Management action takenTo assist team recover

    50

    50

    Percentage of Critical Chain Completed

    Percen

    tageofSafetyMarginConsumed

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    7/12

    pg. 7Copyright 2009 The Boeing Company. All rights r eserved.

    Space Shuttle CCPM Software Development Project

    Problem

    Prattle code is a software product used to develop heating environments for the SpaceShuttles wing.

    Prior to completing the Prattle CCPM project, an Excel based spreadsheet was used todevelop the environments.

    This process was labor intensive, hard to error check and subject to process escapes.

    Resolution Approach Develop software code and put the program under Configuration Management

    Execute project using Critical Chain Project Management

    Results

    Project completed 12-42% ahead of schedule

    Chief Engineer praised the quality of the software program and supportspecification and verification documents

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    8/12

    pg. 8Copyright 2009 The Boeing Company. All rights r eserved.

    Space Shuttle CCPM Software Development Project

    Critical Chain, %

    ProjectBuffe

    r,%

    Reflects Special Cause variation Team

    chose not to re-baseline the project.

    Perform ahead of ideal schedule and Finish up

    in GREEN for project

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    9/12

    pg. 9Copyright 2009 The Boeing Company. All rights r eserved.

    Space Shuttle CCPM Hardware Development Project

    Problem

    Customer required cargo integration hardware be delivered in a reduced schedule tomeet Space Shuttle flight manifest

    Cargo Integration Hardware team had been having challenges meeting previouscommitments due to late customer changes, vendor reliability and competingpriorities

    Project involved over twenty-two different functional areas and two outside vendors

    Resolution Approach

    CIH team identified potential execution issues and mitigated them

    All functional managers and team members were introduced to CCPM and theirsupport to use this method was obtained

    Team established Execution Run Rules to ensure the team stayed focused

    Team members subordinated their work to the effort on the critical chain andactively managed the buffers

    Results Hardware delivered early, under budget and exceeded quality expectations

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    10/12

    pg. 10Copyright 2009 The Boeing Company. All rights r eserved.

    Space Shuttle CCPM Hardware Development Project

    Project finished ~36% ahead of schedule and ~20% under budget

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    11/12

    pg. 11Copyright 2009 The Boeing Company. All rights r eserved.

    Space Shuttle Engineering Document Development Project

    Problem

    In April, 2008, our customer required the Space Shuttle design data books be updated by theend of September to avoid a significant impact to our award fee.

    Due to higher customer priorities, many of these documents had not been updated since theReturn to Flighteffort in 2003, and therefore represented a significant effort.

    Preliminary projections using traditional project management methods indicated it could take upto a year before all of these books would be completed.

    Resolut ion Approach

    Team adopted CCPM believing it offered them the best opportunity for finishing on schedule All of the required updates were identified for each data book

    Knowledge resources were identified for each data book update in order to establish aggressivedurations and define the critical chain for the project

    All resources were trained on CCPM processes and procedures

    Execution Run Rules were established and executed by the team

    Weekly buffer management meetings were conducted and actions taken as needed

    Results

    All data book updates completed within five months, a 58% schedule reduction. Customer expectations were exceeded

  • 7/28/2019 CCPM - HK - Revised With SSP Examples

    12/12

    pg. 12Copyright 2009 The Boeing Company. All rights r eserved.

    Space Shuttle Engineering Document Development Project

    When project was ~65% complete team realized they were going to finish significantlyearly and elected to add more content to the product than originally promised to increaseaward fee.