Saving time with CCPM Critical Chain Project Management Freek de Ruiter Presentatie nog te geven xx juni 2013

Saving time with CCPM

Embed Size (px)

Citation preview

Page 1: Saving time with CCPM

Saving time with CCPMCritical Chain Project Management

Freek de Ruiter

Presentatie nog te geven

xx juni 2013

Page 3: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

Product life cycles are getting shorter

Improving due date performance and reducing lead time enlarges financial benefits

Finishing a project ASAP means:

• Reduced Time to Market

• Cost reduction

CCPM promises:

• 80% due date performance in a portfolio

• 25% lead time reduction of a project

No. 3Saving time with Critical Chain Project Management

Why saving time (and money!) withCCPM ?

Page 4: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

Freek de Ruiter is a member of the NL TOC Network and has become a passionate andambitious expert on Critical Chain Project Management.

Working as Time Management Consultant for his own company, he specializes on the domains planning, scheduling and tracking

No. 4Saving time with Critical Chain Project Management

Presented to you by Freek de Ruiter

Page 5: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• What is CCPM?

• Improving portfolio performance

• How does CCPM work?

• Plenty of time to save

• CCPM planning and execution

• Multi-project CCPM

• When or why will CCPM not work

• Results

No. 5Saving time with Critical Chain Project Management

Agenda

Page 6: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• An IT development method like Agile/SCRUM

• An improvement method like Lean and SixSigma

• A project management method like PRINCE 2

• A program management method like MSP

• Just a planning “trick”

• A way to solve all your problems (“Haarlemmer oil” / “Silver Bullit”)

No. 6Saving time with Critical Chain Project Management

What CCPM is not:

Page 7: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

The elaboration of the TOC body of thought on project management:

TOC = Theory of Constraints

Books by Eli Goldratt:

• The goal

• Critical Chain

• Inherent Simplicity The Choice

Books by Robert Newbold

• Project Management in the Fast Lane

• The Billion Dollar Solution

No. 7Saving time with Critical Chain Project Management

What is CCPM ?

Isaac Newton: “Nature is exceedinglysimple and

harmoniouslywithin itself”

Page 8: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

The 5 focussing steps:

0. Define the system

1. Identify the constraint (the resource or policy that prevents the organization fromobtaining more of the goal)

2. Decide how to exploit the constraint (get the most capacity out of the constrainedprocess)

3. Subordinate all other processes to above decision (align the whole system ororganization to support the decision made above)

4. Elevate the constraint (make other major changes needed to break the constraint)

5. If, as a result of these steps, the constraint has moved, return to step 1, don’t let inertia become the constraint)

No. 8Saving time with Critical Chain Project Management

What is TOC ?

Page 9: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

Clear thinking requires these starting points (convictions? beliefs?):

1. Never say I know, it will obstruct you from gaining more knowledge

2. If confronted with something that looks complex, remember that everything is simple

3. If confronted with something that looks a contradiction, remember that it willturn out to be in harmony (a paradox?), if you are willing to think hard and long enough

4. Do not blame someone or something else, if you really feel you need someone to blame, blame yourself

No. 9Saving time with Critical Chain Project Management

What is TOC ? (continued)

Page 10: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

“Doing the right things right”

1) Select the right (order of) projects:

“Front end” PPM: portfolio alignment with company business objectives, is notcovered in this presentation, but probably is the most import factor in improvingportfolio performance

2) Execute the projects as efficiently as possible:

• By providing max. throughput of the system using “Multi-project” CCPM

• This flow is the one and only consideration!

• If you manage to keep projects on time and budget, you do not need to change orstop projects (based on predictions Earned Value Analysis can provide)

No. 10Saving time with Critical Chain Project Management

Improving portfolio performance

Page 11: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Plan projects with buffers

• Reducing work in progress (WIP)

• Active execution of projects

• Monitoring the right points of attention

• Unambiguous priority system

“Plan tasks as late as possible to avoid unnessecary work in progress, but monitor the start of planned tasks and the finish of tasks in progress daily, by means of the buffer penetration mechanism.”

No. 11Saving time with Critical Chain Project Management

How does CCPM work ?

Page 12: Saving time with CCPM

Plenty timeto save

Page 13: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Safety too high

• Tasks start too late

• Tasks end too late

• Productivity loss of bad multi-tasking

• Waiting on decisions

No. 13Saving time with Critical Chain Project Management

Time to save

Page 14: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

Project member estimates: minimum of 3 days work and tells his team lead: “ready in a week!”

Another project member estimates for a follow up action a week too

Team lead schedules the activities and tells his project manager that he needs 12 days, to prevent that delay of the 1st activity causes delay of the 2nd activity.

Project manager reports to the steering committy to count on 3 weeks for thatcluster, because before the activities can start first another cluster……

No. 14Saving time with Critical Chain Project Management

Safety too high (addition to Eli’s heritage)

Page 15: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

A deadline influences in a negative way

3 days work? 5 days available?

I can postpone working on this task, which I do not like to start, to the day aftertomorrow!

On day 4 Murphy strikes: 2 days extra needed!

Possibly increasing the lead time of the project

No. 15Saving time with Critical Chain Project Management

Tasks start too late (student syndrome)

Page 16: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

Time planned will always be filled with work

3 days work? 5 days available?

I immediately start working on this task that I like to work on

Ready after 3 days, no reward for being ready, adding all kinds of “nice to haves” for2 days

Loss of productivity and possibly waisting an opportunity to reduce the lead time of the project

No. 16Saving time with Critical Chain Project Management

Tasks end too late (Parkinsons lawNo. 1)

Page 17: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved No. 17Saving time with Critical Chain Project Management

Productivity loss of bad multi-tasking

Task A

Task B

Task C

Tasks assigned to person

3 days

3 days

3 days

Ideally: Task A Task B Task C

3 days 3 days 3 days

OK? B BA AC C

6 days

6 days

6 days

In reality minimally

BBA AC C

7 days

7 days

7 days

Productivityloss

Shift of end date task A

Shift of end date task B

Page 18: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Not much space in management agendas

• Disagreement on priorities

But on top of that:

• Menzo de Muinck Keizer: Managers miss information because the decision making process is not enough known to the non-decisionmakers

Consequences:

• More waiting on decisions

• More loss of productivity

• More increase of the project lead time

• More loss of motivation

Looking back in retrospective, any decision, always based on the knowledge at a certain time, could possibly better have been replaced by another, unfortunately never enabling a 100% certain analysis of the consequences of that replacement

No. 18Saving time with Critical Chain Project Management

Waiting on decisions (addition to Eli’s heritage)

Page 19: Saving time with CCPM

CCPM planningSingle project

Page 20: Saving time with CCPM

No. 20© Kwantitijd BV 2013 All rights reserved

Start with basic planning on skill level

Saving time with Critical Chain Project Management

Page 21: Saving time with CCPM

No. 21© Kwantitijd BV 2013 All rights reserved

Critical Path

Saving time with Critical Chain Project Management

Page 22: Saving time with CCPM

No. 22© Kwantitijd BV 2013 All rights reserved

Resource allocation of individuals

Saving time with Critical Chain Project Management

Page 23: Saving time with CCPM

No. 23© Kwantitijd BV 2013 All rights reserved

Overallocation!

Saving time with Critical Chain Project Management

Page 24: Saving time with CCPM

No. 24© Kwantitijd BV 2013 All rights reserved

Also overallocation in the skill based planning

Saving time with Critical Chain Project Management

Page 25: Saving time with CCPM

No. 25© Kwantitijd BV 2013 All rights reserved

Overallocation solved, but multitasking means more work!

Saving time with Critical Chain Project Management

Page 26: Saving time with CCPM

No. 26© Kwantitijd BV 2013 All rights reserved

Resource leveling can cause switching more than once

Saving time with Critical Chain Project Management

Page 27: Saving time with CCPM

No. 27© Kwantitijd BV 2013 All rights reserved

Multi-tasking eliminated, resource contention removed, ready to apply CCPM planning

Saving time with Critical Chain Project Management

Page 28: Saving time with CCPM

No. 28© Kwantitijd BV 2013 All rights reserved

Critical Chain is not Critical Path

Saving time with Critical Chain Project Management

Page 29: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Plan projects with buffers

• Reducing WIP

• Active execution of projects

• Monitoring the right points of attention

• Unambiguous priority system

“Plan tasks as late as possible to avoid unnessecary work in progress, but monitor the start of planned tasks and the finish of tasks in progress daily, by means of the buffer penetration mechanism.”

No. 29Saving time with Critical Chain Project Management

How does CCPM work ? (repeated)

Page 30: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Only with buffers and daily monitoring setbacks can be compensated by pleasantsurprises

• Where protection needed?

• How much?

No. 30Saving time with Critical Chain Project Management

Plan projects with buffers

Page 31: Saving time with CCPM

No. 31© Kwantitijd BV 2013 All rights reserved

Step 1:Remove 50% safety from the individual tasks

Saving time with Critical Chain Project Management

Page 32: Saving time with CCPM

No. 32© Kwantitijd BV 2013 All rights reserved

Step 2:Add buffers with 50% of the removed safety

Saving time with Critical Chain Project Management

Page 33: Saving time with CCPM

No. 33© Kwantitijd BV 2013 All rights reserved

Step 3:Start non-critical tasks ALAP

Saving time with Critical Chain Project Management

Page 34: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Plan projects with buffers

• Reducing WIP

• Active execution of projects

• Monitoring the right points of attention

• Unambiguous priority system

“Plan tasks as late as possible to avoid unnessecary work in progress, but monitor the start of planned tasks and the finish of tasks in progress daily, by means of the buffer penetration mechanism.”

No. 34Saving time with Critical Chain Project Management

How does CCPM work ? (repeated)

Page 35: Saving time with CCPM

No. 35© Kwantitijd BV 2013 All rights reserved

Result of the 3 CCPM planning steps

Saving time with Critical Chain Project Management

Page 36: Saving time with CCPM

No. 36© Kwantitijd BV 2013 All rights reserved

Cautious?Result of removing only 25% safety from tasks

Saving time with Critical Chain Project Management

Page 37: Saving time with CCPM

No. 37© Kwantitijd BV 2013 All rights reserved

Very cautious?Result of not removing any safety at all

Saving time with Critical Chain Project Management

Page 38: Saving time with CCPM

No. 38© Kwantitijd BV 2013 All rights reserved

50% - 50% 50% approach is proven best CCPM practice in a multiproject arena!

Saving time with Critical Chain Project Management

Page 39: Saving time with CCPM

CCPM executionSingle project

Page 40: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Plan projects with buffers

• Reducing WIP

• Active execution of projects

• Monitoring the right points of attention

• Unambiguous priority system

“Plan tasks as late as possible to avoid unnessecary work in progress, but monitor the start of planned tasks and the finish of tasks in progress daily, by means of the buffer penetration mechanism.”

No. 40Saving time with Critical Chain Project Management

How does CCPM work ? (repeated)

Page 41: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Resource allocation of individuals

• Buffer management

• The following scenario is an example of possible events

No. 41Saving time with Critical Chain Project Management

Execution

Page 42: Saving time with CCPM

No. 42© Kwantitijd BV 2013 All rights reserved

Start of project on 9/11/09

Saving time with Critical Chain Project Management

Page 43: Saving time with CCPM

No. 43© Kwantitijd BV 2013 All rights reserved

Monday 16/11: Analist 1 reports status finished with 4 hoursextra work done, Designer 1 reports 4 hours extra work to do.

Saving time with Critical Chain Project Management

Progress in week 1

Page 44: Saving time with CCPM

No. 44© Kwantitijd BV 2013 All rights reserved

Analyst 2 and Designer 2 report work finish conform schedule, Developer reports having started 1 day later because of sickness.

Saving time with Critical Chain Project Management

Progress in week 1

Page 45: Saving time with CCPM

No. 45© Kwantitijd BV 2013 All rights reserved

Feedbuffer consumption 50% with branche 80% complete, Projectbuffer consumption 13% with Critical Chain 30% complete.

Saving time with Critical Chain Project Management

Progress in week 1

Page 46: Saving time with CCPM

No. 46© Kwantitijd BV 2013 All rights reserved

Monday 23/11: Designer 1 reports work finished conform new schedule, Developer reports finished product 2 with 8 hours extra work done and 16

extra hours to be done on product 1.

Saving time with Critical Chain Project Management

Progress in week 2

Page 47: Saving time with CCPM

No. 47© Kwantitijd BV 2013 All rights reserved

Feedbuffer consumption 50% with branch 100% complete, Projectbuffer consumption 50% with Critical Chain 50% complete

Saving time with Critical Chain Project Management

Progress in week 2

Page 48: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Plan projects with buffers

• Reducing WIP

• Active execution of projects

• Monitoring the right points of attention

• Unambiguous priority system

“Plan tasks as late as possible to avoid unnessecary work in progress, but monitor the start of planned tasks and the finish of tasks in progress daily, by means of the buffer penetration mechanism.”

No. 48Saving time with Critical Chain Project Management

How does CCPM work ? (repeated)

Page 49: Saving time with CCPM

No. 49© Kwantitijd BV 2013 All rights reserved

Developer reports 1 day later “probably ready middle next week”, whichmeans projectbuffer consumption 75% with Critical Chain 50% complete.

Saving time with Critical Chain Project Management

Progress in week 2 + 1 day

Page 50: Saving time with CCPM

No. 50© Kwantitijd BV 2013 All rights reserved

Projectmanager helps Developer with problem and skippingsuperfluous work , project buffer consumption back on 50%

Saving time with Critical Chain Project Management

Progress in week 2 + 1 day

Page 51: Saving time with CCPM

No. 51© Kwantitijd BV 2013 All rights reserved

Monday 30/11: Developer reports progress according to new schedule, project buffer consumption 50% with Critical Chain 75% complete

Saving time with Critical Chain Project Management

Progress in week 3

Page 52: Saving time with CCPM

No. 52© Kwantitijd BV 2013 All rights reserved

Monday 7/12, integration test finished with 8 hours extra work, acceptance test starting today.

Saving time with Critical Chain Project Management

Progress in week 4

Page 53: Saving time with CCPM

No. 53© Kwantitijd BV 2013 All rights reserved

Wednesday 9/12: Acceptance test finished after 2 days, project buffer consumption of 66,67%

Saving time with Critical Chain Project Management

Progress in week 5

Page 54: Saving time with CCPM

No. 54© Kwantitijd BV 2013 All rights reserved

Project finished before deadline

Saving time with Critical Chain Project Management

Page 55: Saving time with CCPM

No. 55© Kwantitijd BV 2013 All rights reserved

Project finished in less hours than baselines

Saving time with Critical Chain Project Management

Page 56: Saving time with CCPM

No. 56© Kwantitijd BV 2013 All rights reserved

Project finished under budget

Saving time with Critical Chain Project Management

Page 57: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

Requirements for a succesful implemenation:

1. Enthusiastic, professional, believing Project Manager

2. Co-operating, open-minded team members

3. Not too much external dependencies

4. Reliable enough estimates

5. “Full Kit” preparations

6. Tooling

Saving time with Critical Chain Project Management

CCPM in a single project

Page 58: Saving time with CCPM

Multi-project CCPM

Page 59: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

Staggering:

• Single CCPM planned projects

• Projects in order of finish date (or other priority)

• Indentify drum tasks/resources (= key resources)

• Remove resource contention of key resources on drum tasks

• Replan all tasks of all projects before and after tasks of key resources, but onlymove the buffers of the newly released project

Priorities:

Only an algorithm can determine the right priority of the tasks and projects in execution

No. 59Saving time with Critical Chain Project Management

Multi project CCPM planning

Page 60: Saving time with CCPM

No. 60© Kwantitijd BV 2013 All rights reserved

Single CCPM planned projects

Saving time with Critical Chain Project Management

Page 61: Saving time with CCPM

No. 61© Kwantitijd BV 2013 All rights reserved

Staggering step 1:Identify drum tasks/resources

Saving time with Critical Chain Project Management

Page 62: Saving time with CCPM

No. 62© Kwantitijd BV 2013 All rights reserved

Staggering step 2: Remove resource contention of keyresources on drum tasks

Saving time with Critical Chain Project Management

Page 63: Saving time with CCPM

No. 63© Kwantitijd BV 2013 All rights reserved

Staggering step 3: Replan all tasks of all projectsbefore/after tasks of key resources

Saving time with Critical Chain Project Management

Page 64: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Project organization with competence pools:

• Taskmanagers are working for more than 1 project

• Resources are working for a taskmanager

• Unambigous priority rules

• Highest priority for task which causes highest penetration of the projectbuffer of the project with the highest priority

• Highest priority for project with highest penetration of its projectbuffer in relation to itscompleteness of the Critical Chain

• The project waiting with the highest priority (decided by humans, instead of the abovepriority algorithm for projects in execution) in the pipeline is only to be started when the drum assignments of one of the projects in execution is finished

No. 64Saving time with Critical Chain Project Management

Multi-project CCPM execution

Page 65: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Plan projects with buffers

• Reducing WIP

• Active execution of projects

• Monitoring the right points of attention

• Unambiguous priority system

“Plan tasks as late as possible to avoid unnessecary work in progress, but monitor the start of planned tasks and the finish of tasks in progress daily, by means of the buffer penetration mechanism.”

No. 65Saving time with Critical Chain Project Management

How does CCPM work ? (repeated)

Page 66: Saving time with CCPM

No. 66© Kwantitijd BV 2013 All rights reserved

Highest prority for which project ?

Saving time with Critical Chain Project Management

T1 T2 T3

PBProject W18: 60% penetration

T1

PB Project W14: 90% penetration

T2

Page 67: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved No. 67Saving time with Critical Chain Project Management

Overview of portfolio (fever chart)

W18

Page 68: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

Frans Jan Buters: “do not wait for drum assignments of a project to be finished, but simply wait to release a new project until another one is ready”

Michel Stijlen: “indeed: ‘one out, one in’ but also use, when choosing which project to release, the forecasted resource load as an extra criterium do decide uponpriority”

Jan Willem Tromp: “do not stagger and reschedule, release a new project wheneverthe CEO wants, but if the forecasted resource load predicts expected delays beyondthe buffers: pause another project”

Kees Vermeulen: “stagger and reschedule based on more identified key resource groups”

Jan Willem Tromp: “do not focus on due date performance and lead time reductiondirectly, but focus on output improvement of resources”

Harry Barendse: “consider Agile/SCRUM sprints as tasks in a CCPM planning, whilescheduling the rest of the tasks in the planning as well”

No. 68Saving time with Critical Chain Project Management

Other additions to Eli’s heritage

Page 69: Saving time with CCPM

Summary

Page 70: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Plan projects with buffers (feed buffers and project buffers)

• Reducing WIP (starting tasks ALAP)

• Active execution of projects

• Monitoring the right points of attention (with buffermanagement)

• Unambiguous priority system

“Plan tasks as late as possible to avoid unnessecary work in progress, but monitor the start of planned tasks and the finish of tasks in progress daily, by means of the buffer penetration mechanism.”

Every day:

How much time is needed to complete this task in progress?

No progress? Where is this task waiting on?

No. 70Saving time with Critical Chain Project Management

How does CCPM work ? (summary)

Page 71: Saving time with CCPM

No. 71© Kwantitijd BV 2013 All rights reserved

Buffermanagement is the key element

Saving time with Critical Chain Project Management

Okay Plan Act

0% 33% 66% 100%

Percentage Use of Buffer

Percentage (Non) Critical Chain to go

100% 67% 33% 0%

Traffic light status Buffers in combination with %-CC to go

x x

?

Page 72: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

No wait time on the Critical Chain

Only safety where it is neededDo not question the priority algorithm

Right mindset

Preferred implementation for single-project CCPM:

• Estimates and safety in consultation with team members (e.g. tasks have only 50% chance to finish on time)

• Reward the right performance (which is not always finishing your task on the time estimated on a 50% chance to do that!)

Preferred implementation for multi-project CCPM:

• Take 50% safety from tasks, put 50% of this safety in buffers• Consider portfolio performance as achievement of all the resources

No. 72Saving time with Critical Chain Project Management

Focus on the project/portfolio, noton the tasks

Page 73: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• If you keep believing “this is too good to be true”

• With the attitude “not invented here”

• Because companies generally do not want/need to change

• Not enough sense of urgency

• If there is no business need for project due date performance improvements and project lead time reductions

• Because CCPM needs professional planning practises to start with

• No reliable enough estimates

• No “Full Kit” preparations

• No adequate tooling

• Too slow implementation process

• Not enough committment from management

No. 73Saving time with Critical Chain Project Management

When or why does CCPM not work ?

Page 74: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

Saving time and money:

Projects theoretically always ready on due date or earlier

On-site observed average due date performance: 80%

Theoretical lead time reduction is 33%

On-site observed average lead time reduction: 25%

No. 74Saving time with Critical Chain Project Management

Results after breaking the layers of resistance

Page 75: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

Logica project managed by Marten Schröder: “Inname en Mengerij Denkavit Frankrijk”, realised margin 41,2%, planned margin 15,6%, delivery 3 weeks earlier than planned

Implementations by partner Blue Jonah, most impressive (see figures last slide): Nationale Nederlanden IT divison (http://www.bluejonah.com)

Implementations by software company Realization (Concerto tooling) (http://www.realization.com)

Implementations by consulting and software company ProChain

(http://www.prochain.com)

Numerous other implementations to be found on the internet

No. 75Saving time with Critical Chain Project Management

References

Page 76: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

1) Say what you will do, do what you have promised and show that you have donewhat you have said that you would do

2) Implement Project (Portfolio) Management processes and tools !

E.g. using the EPM tooling:

• Microsoft’s PPM Solution EPM (Enterprise Project Management), consisting of MS Project server and SharePoint

• ASP/hosted/SaaS/Cloud delivered by Perrit, branding by Kwantitijd: EPM-AAA, supplemented with documentation, training, coaching-on-the-job, helpdesk services, and Extra Features

• Necessary Extra Features represent condensed expertise since 2004 with i-BMS, the former Logica internal implementation of EPM

No. 76Saving time with Critical Chain Project Management

Professional planning practices ?

Page 77: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved No. 77Saving time with Critical Chain Project Management

Professional planning practises ? (continued)

3) Discipline !

Page 78: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Lynx (supplied by [email protected])

• Flow MPM (supplied by Glow Management)

• Concerto (supplied by Realization)

• Prochain

• PS8 (supplied by Sciforma)

No. 78Saving time with Critical Chain Project Management

Recommended CCPM software

Page 79: Saving time with CCPM

© Kwantitijd BV 2013 All rights reserved

• Read “The billion dollar solution” by Newbold

• Follow the CCPM Webcasts on TOC TV

• Join LinkedIn groups “CriticalChain” and “Critical Chain Professional”

• Follow training at the TOC Academy (http://www.tocacademy.nl)

No. 79Saving time with Critical Chain Project Management

Interested in more ?