  • Navigating the Prop 39 MazePart 2

    February 6, 2014

    Presented by:

    Rick Brown, PresidentTerraVerde Renewable Partners, LLC

    Tyler B. Dockins, Attorney at LawLozano Smith

  • Table of ContentsProposition 39: Current StatusEnergy Project Scoping IssuesProp 39 Sole Source ProhibitionQ & A*

  • Proposition 39 UpdateFundingAllocation of funding the 2013-14 State Budget allocated $381 M in Prop 39 funds to K-12 School Districts. Funds are being distributed to Districts on a per-student basis plus a weighting for Free and Reduced Price Meals ADA, with small school minimum guarantees. Annual allocations through FY 2018-19 are yet to be determined; Prop 39 funds count towards the States Prop 98 requirement.

    Rollover Schools will be able to roll over their allocation year to year in order to pay for larger projects.The smallest LEAs will be able to bundle funding in years one and two.

    Planning Allocations-Districts were eligible to apply for planning dollars as of November 1; second round in January 31st; third round later in the spring.

    Energy Project Loans--Allocates $28 million to State Energy Conservation Account at CEC for low interest and no-interest loans for eligible projects and technical assistance.

    Workforce Development--Provides $3 million for competitive grants to community based organizations for job training and workforce development.

    Energy Audit--Allocates $5 million to Conservation Corps for workforce training and development.

    Entitlements: http://www.cde.ca.gov/fg/fo/r14/prop39cceja13result.asp

    *

  • Proposition 39 UpdateProcessApplication Guidelines--Required California Energy Commission (CEC), in consultation with the California Dept. of Education (CDE) and the California Public Utilities Commission (CPUC), to develop guidelines for project expenditures and applications, including energy benefit estimates, energy savings cost assumptions, benchmarks, energy surveys and audits, and cost-effectiveness determination. Draft Guidelines were released Sept 28thFinal Guidelines were released Nov. 19th CEC approved final guidelines Dec. 19thApplication Materials released Jan. 31st

    Accountability Schools will be subject to front-end project verification and back-end reporting.

    Required Prop 39 DeliverablesExpenditure Plan and ApplicationExpenditure Plan General Form A: a financial summary of how the District intends to spend its Proposition 39 award fundsExpenditure Plan Project Summary Form B(s): the eligible energy project(s) proposed at each of the Districts schools or sitesUtility Data Release Authorization form(s)Back-up documentation: additional information providing justification for the Expenditure Plan

    Project Expenditures Report

    *

  • Prop 39 Funding and Project Development Process*Project Scoping: TerraVerde Energy Report CardConduct on all sites and systems: energy benchmarking, usage, and cost analysesDetermine the highest potential energy and cost savings opportunitiesProject Asset ManagementMonitor and analyze performance dataConduct necessary O&M and warranty managementComplete Prop 39 Project Expenditures Report

  • Prop 39 Eligible Project Examples*Lighting Energy Efficiency Measures:Replace incandescent light with compact fluorescent (CFL)Replace incandescent/down light/flood with lightemitting diode (LED) lightReplace incandescent Exit Sign to LED Exit signReplace CFL Exit Sign to LED Exit signConvert T12 fluorescent lamps to T8 with electronic ballastConvert T12 or T8 fluorescent lights to linear LED lampsReplace 32 Watt T8 lamps with 28 Watt T8 LampsReplace exterior mercury vapor lights with induction or LED lightsReplace exterior high pressure sodium lights with induction or LED lightsInstall occupancy control for intermittently occupied rooms

    HVAC/Mechanical Efficiency Measures:Replace incandescent light with compact fluorescent (CFL)Replace old packaged/split HVAC unit with highefficiency HVACReplace old heat pump with highefficiency heat pumpReplace boiler or furnace with high efficiency condensing typeSeal existing leaky ductInstall premium efficiency motorsInstall variable speed drive for pumps and fansInstall new programmable/set back thermostatReplace storage water heater with instantaneous water heaterPlugLoad Efficiency Measures:Install smart strip/PC management to control computers/printersInstall vending machine occupancy control.Simple PV SelfGeneration Project:Schoolowned Solar PV systemSolar PPA

  • Application and Expenditure PlanThere were no big surprises; the application requirements did not vary in an meaningful way from what was described in the Guidelines adopted by the CEC in December.However, the application requirements are sufficiently detailed that completion will take a good bit of focused effort.Good news: there are more online calculators provided than were anticipated, narrowing the scope of what is needed from an energy audit to get your application approved. More good news: one important new clarification included in the materials is that Bond proceeds or any local capital funds (e.g. developer fees) that dont require some form of payback can be considered grant funding for the purposes of reducing the denominator in the Savings to Investment Ratio. This could help bring up the SIR of energy conservation measures that might otherwise not meet the required 1.05 threshold.*

  • BenchmarkingMeasuring and comparing the energy use intensity of buildings per square footkBTU = Thousand British Thermal UnitsCombination of kWH: thousand watt hours of electricity andTherms: units of energy for natural gas, propane, fuel oil.

    *

  • Benchmarking Example*

  • Strategic Audit Scoping*

  • Online Calculators*LightingEnergyEfficiencyMeasures:ECM1 ReplaceincandescentlightwithcompactfluorescentECM2 Replaceincandescentlightwithlightemittingdiode(LED)lightECM3&4 Convertincandescent/CFLexitsigntoLEDexitsignECM5&6 ConvertT12fluorescenttoT8withelectronicballastorLEDlampsECM7 Replace32wattT8lampswith28wattT8lampsECM8&9 Replaceexteriormercuryvapor/HPSwithLED/inductionlightsECM10 InstalloccupancycontrolforintermittentlyoccupiedroomsHVAC/MechanicalEfficiencyMeasures:ECM11 Replaceoldpackaged/splitHVACunit(upto65 kBTU)withhighefficiencyHVACECM12 Replaceoldheatpump(upto65kBTU)withhighefficiencyheatpumpECM13A ReplaceboilerwithhighefficiencycondensingboilerECM13B Replace furnace with highefficiency condensing furnaceECM14 SealexistingleakyductECM15 InstallvariablespeeddriveforpumpsandfansECM16 ReplacemanualthermostatwithprogrammablethermostatECM17 ReplaceoldmotorwithpremiumefficiencymotorECM18 Replacestoragewaterheaterwithgasfiredtanklesswaterheater

    PlugLoadEfficiencyMeasures:ECM19 Installsmartstrip/PCmanagementtocontrolcomputers/printersECM20 InstallvendingmachineoccupancycontrolSimplePhotovoltaic(PV)SelfGenerationProjectECM21 InstallPVSystem

  • Prop 39 S.I.R. Formula*

    SIR (Savings to Investment Ratio) is defined as follows:Non Energy Benefits are to be calculated as 5% of project cost.

    Rebates and other grants will vary by utility company and technology.

    This calculation will need to be done for each individual Energy Conservation or Clean Energy Measure and again for the combined Project or Portfolio.

    An SIR of 1.05 is the threshold a project or portfolio must meet to receive approve in your Expenditure Plan

  • S.I.R. Portfolio Estimate Example*

    Energy Conservation MeasureEnergy SavingsMaint. SavingsNumeratorProject CostLess Grants & RebatesLess Non Energy BenefitsDenominatorS.I.RUpgrade existing Energy Management System$238,484 $31,098 $269,582 $103,661 ($20,251)($3,110)$80,301 3.36Upgrade T8 light fixtures/lamps from 32W to 28W$362,733 $21,087 $383,820 $210,870 ($12,570)($6,326)$191,974 2.00Install Occupancy Sensors$78,797 $11,643 $90,440 $72,770 ($4,087)($2,183)$66,499 1.36Replace HVAC units $970,146 $792,540 $1,762,686 $2,641,800 $0 ($79,254)$2,562,546 0.69Totals / Weighted Average SIR$1,650,160 $856,369 $2,506,528 $3,029,101 ($36,908)($90,873)$2,901,320 0.86

    Economic/Effective Useful LifeYearsEnergy Management System15Interior Fixture15Interior Lamps4Occupancy Sensors8HVAC Units (packaged/split)15

  • The Energy Project ChallengeHow does a School DistrictAchieve actual cost savings results that match expectations?Conduct a transparent procurement process that gets the benefits of competitive bidding without a lot of administrative hassle?Achieve net positive cash flow savings without upfront expense; minimize balance sheet impact?

    *

  • Q & AIf you have any questions, please ask using the Questions pane as shown below.

    *

  • Contact InformationRick Brown, PresidentTerraVerde Renewable Partners, LLC1100 Larkspur Landing Circle, Suite155Larkspur, CA 94939T: [email protected] B. Dockins, Attorney at Law Lozano Smith 4 Lower Ragsdale Drive, Ste. 200 Monterey,CA93940 T:831.646.1501| F: 831.646.1801 [email protected] www.lozanosmith.com

    *

    *****