Car parking project

Embed Size (px)

Citation preview

  • 7/28/2019 Car parking project

    1/12

    2013

    A Plan by Aiman Jan Chowdhury

    3/18/2013

    A Project Plan on Multi-Storey Car Parking

  • 7/28/2019 Car parking project

    2/12

    Assignment

    On

    Project Plan

    Course Code: 503

    Prepared for :

    Md. Mosharref Hossain

    Assistant. Professor,

    Bangladesh Institute of Bank Management.

    Prepared by:

    Aiman Jan Chowdhury 161227

    Batch- 16th

    ,BIBM

    Bangladesh Institute of Bank Management, Mirpur-2,Dhaka

    Date of Submission- March 18, 2013

  • 7/28/2019 Car parking project

    3/12

    Executive Summary

    Now a days car parking has been one of the major problems urban areas have been confronting

    with. For example in Dhaka city number of cars are increasing day by day. But the parking lots

    or parking areas are not increasing proportionally. As a reason traffic jam is getting severe and

    the overall traffic condition is deteriorating. This calls for multi storey car parking system which

    can be extremely beneficial in this situation. A multi-storey car-park (also called a parking

    garage, parking structure, parking ramp, parkade, parking building or parking deck) is a building

    designed for car parking and where there are a number of floors or levels on which parking takes

    place. It is essentially a stacked car park.

    Many car parks are independent buildings dedicated exclusively to that use. The design loads for

    car parks are often less than the office building they serve (50 psf versus 80 psf), leading to long

    floor spans of 5560 feet that permit cars to park in rows without supporting columns in

    between. The most common structural systems in the United States for these structures are either

    prestressed concrete concrete double-tee floor systems or post-tensioned cast-in-place concrete

    floor systems. In recent times, car parks built to serve residential and some business properties

    have been built as part of a larger building, often underground as part of the basement, such as at

    the Atlantic Station redevelopment in Atlanta. This saves land for other uses (as opposed to a

    parking lot), is cheaper and more practical in most cases than a separate structure, and is hidden

    from view. It protects customers and their cars from weather such as rain, snow, or hot summer

    sunshine that raises a vehicle's interior temperature to extremely high levels. Underground

    parking of only two levels was considered an innovative concept in 1964. Car parks which serve

    shopping centres can be built adjacent to the centre for easier access at each floor between shops

    and parking. One example is Mall of America in Bloomington, Minnesota, USA, which has twolarge car parks attached to the building, at the eastern and western ends. A common position for

    car parks within shopping centres in the UK is on the roof, around the various utility systems,

    enabling customers to take lifts straight down into the centre. Examples of such are The Oracle

    in Reading and Festival Place in Basingstoke. Parking structures are subjected to the heavy and

    shifting loads of moving vehicles, and must bear the associated physical stresses. Expansion

    joints are used between sections not only for thermal expansion but to accommodate the flexing

    of the structure's sections due to vehicle traffic. Seismic retrofits can be applied where

    earthquakes are an issue.

    Some parking structures have partly collapsed, either during construction or years later. In July2009 a fourth-floor section failed at the building in midtown Atlanta, pancaking down and

    destroying more than 30 vehicles but injuring no-one. In December 2007, a car crashed into the

    wall of the deck at the SouthPark Mall in Charlotte, North Carolina, weakening it and causing a

    small collapse which destroyed two cars below. On the same day, one under construction in

    Jacksonville, Florida collapsed as concrete was being poured on the sixth floor.In November

    2008, the sudden collapse of the middle level of a deck in Montreal was preceded by warning

  • 7/28/2019 Car parking project

    4/12

    signs some weeks before, including cracks and water leaks.Parking structures are generally not

    subject to building inspections after being checked for their initial occupancy permit.

    So far there is no automated, full fledged multi storey car parking in our country which is very

    essential for busy, densely populated urban areas with exuberance of vehicles, more precisely in

    industrial/commercial areas. If we succeed to establish a well designed and well maintained

    multi-storey car parking, it will be beneficiary for the traffic system of the country at the same

    time will lead to considerable profit.

    Project Background

    General Company Description

    Company: Auto Bank Car Parking

    Business type: Service

    Location: Banani TAG: You are not a hustler Goal: Reduce the unsystematic car parking in order to restore the free space of Dhaka

    city

    Management and organization:-

    1. Aiman Jan Chowdhury (CFO)2. Golam Rifat Bhuiyan (Consultant)3. Mohi Uddin Sabbir (Management)

    Present Parking Situation:-

    Cars parked in front of high-rise buildings and commercial establishments. Commercial establishments with no parking facilities or limited facilities. Parking spaces are being used for commercial purposes

    Deadlock traffic situation

    Sadeque Hossain Khoka :-"If the Dhaka City Corporation sets up some car parkingcenters in some commercial areas across the city, it will definitely help ease traffic

    congestions.

    Reduction in illegal Parking

  • 7/28/2019 Car parking project

    5/12

    Opportunity in parking business

    Reduction in illegal Parking Ensuring maximum use of road

    Opportunity in parking business

    A Developing county and its capital city Scarcity of parking space Lack of parking security Ensuring the traffic law Demand for the systematic car parking

    Marketing Plan

    Market research Segmentation and targeting Detailed outline of the product or service Unique selling points Chosen pricing strategy Promotional plans Distribution strategy (including online) Customer service strategy Market Structure and Analysis

    Target Customer

    Corporate Organization Car Owner

  • 7/28/2019 Car parking project

    6/12

    Guests and any Individual Taxi Cab Company Delivery Van Private universities Marketing plan

    Features:-

    Car parking facility Roof top Restaurant Online booking facility Online car tracking Permanent rental parking service Automated Car wash facility CC Camera for better security

    Promotional Plans

    Environmental project (going green). Public and private partnership. Promotional strategy. The organization will have their own Web Site to contact with their entire target customer

    by giving mail.

    Online Booking Marketing Strategy

    Space Distribution Strategy

  • 7/28/2019 Car parking project

    7/12

    On the spot 50% Fixed 20% By online (Maximum 30% car)

    Market size and Potential

    The potentiality of the multistoried car parking is very high and the market is very biglike for our project our target market is

    Banani, Gulshan, Mohakhali, Motijheel and other commercial areas. Financial Plan

    Financial Analysis

    Per day income

    1st hour = 50 tk * 170 = 8500 tk 2nd hour = 30 tk * 170 = 5100 tk 3rd hour = 20 tk * 170 = 3400 tk 4th hour = 10 tk * 170 = 1700 tk. Rest of hour will be charge 10 tkTotal earning = 18700 tk per floor

    Source Of Financial Investment

    The project will financed by Lanka Bangla Finance and Government of Bangladesh.(PPP- Public Private Partnership)

    Ratio: 50% : 50% Share. The project duration : 2 years Financial Plan 1 katha = 720 sft

  • 7/28/2019 Car parking project

    8/12

    Land for the the project = 20 katha So the total sft. is => 20 *720 =14400 sft. Leave space => 14400 * 20% = 2880. Total space => 14400-2880=11520 sft

    Financial Plan

    Common space, rest room, waiting room, restaurant, stairs, lift for public = 3000 sft. Total space for project = 2880+3000- 14400= 8520 sft. Per car required space = 50 sft Total capacity = 8520/50= 170 (50car)

    Financial Plan (Cont.) Per car required space = 50 sft Total car parking capacity = 8520/50= 170 (50car) Cost for making per sft. is = 3500 So total cost = 11520*3500= 40320000*(6 floor)=241920000 BDT 2 Lift cost = 2 core Total decoration= 1 core Financial Plan (Cont.) So total earning in 6 floor 18700 * 6 = 112200tk Earning from 240 (1 year) day = 112200*240= 26928000 tk. Maintenance Per year = 5000000tk. Total earning = 26928000 - 5000000 = 21928000tk Return on asset = 11.034 year

    Particulars

    Amount in Taka

  • 7/28/2019 Car parking project

    9/12

    a) Fixed cost 2000000

    b) Variable cost/ operating cost/ working capital 3000000

    Grand total 5000000

    Total fixed cost over the entire project period as per the following table:

    Heads of expenditures/

    Items of costAmount in Taka Total

    i) Pre-construction expenditures:a) Land lease value 200000b) Preliminary expenses 50000c) Preoperative expenses 50000

    Sub-total of I 300000

    ii)Construction works:a) Building Structure 200000

    b) land development 200000

    c) Site development 100000

    Sub-total of II 500000

    iii)Machinery and Equipmenta) Imported machineries 500000b) Local machineries 250000

    c) Installation and testing cost 50000

    Sub-total of III 800000

    iv) Other costs

    a) Furniture 300000b) Fan, lighting, fittings 100000

    Sub-total of IV 400000

    Grand Total fixed cost (Total of I,II,III,IV) 2000000

    Total variable/operating/recurring cost or working capital as per table below:

  • 7/28/2019 Car parking project

    10/12

    Heads of expenditures/

    Items of costAmount in Taka Total

    i) Raw materials/ imputes:

    a) Cotton fiber 1000000b) Dye staff 200000

    Sub-total of I 1200000ii) Human resource and training cost:

    a) Technician 500002b) Operators 2000010c) Assistants 100005d) Driver 100001e) Storekeeper 200001f) Guards 100001g) Training cost 10000

    Sub-total of II 400000

    iii) Utilities (fuel, power, water etc.)

    a) Electricity 238500b) Water 7500c) Lubricant oil 4000

    Sub-total of III 250000

    iv)Other costsa) Packaging cost of cotton 250000

    b) Conveyance 250000

    d) Miscellaneous 300000e) Spare and Maintenance 350000

    Sub-total of IV 1150000

    Total variable cost (Total of I,II,III,IV) 3000000

    Means / source of finance:

    a) Fund available from own resources

    10,000,00.00

    b) Bank loan 40,000,00.00

    Employment generation (Expected number of employment)

  • 7/28/2019 Car parking project

    11/12

    Types of employee Number of employees

    a) Technician 02b) Operators 10c) Assistants 05d) Driver 01e) Storekeeper 01f) Guards 01

    Total 20

    Who will be Benefited

    General public. Government. Private Organizations. Entire Society.

    Environment:-

    Play ground for children will be free from parking Law Enforcement. Insurance company. Additional Features Roof top Restaurant. Car wash at ground floor. Security by close CC camera. Insurance of asset. Signs and way finding - color coding, numbering, visual cues and even machines for

    making your ticket with your exact location to locate your car for easy retrieval.

  • 7/28/2019 Car parking project

    12/12

    FAQ for Investors

    Risk Involved People are not used to with this kind of service Political situation and government decision is unpredictable Unstable power supplysolar solution going green This kind of project is not familiar in our country.

    Possible Gains

    Every year number of car increasing Land Price Safety of valuable vehicles from possible damages and theft. Per capital income Future plan: Make it as a shopping center. No one is certain about the future every one can predict

    Conclusion

    Its not just only a business that aims to make profit. First movers advantage is there.

    The project is expected to earn considerable profit and simultaneously socially beneficiary. So,

    weve told about the business, our team, the opportunity, etc. Now, we need qualified investors

    like you to invest. The bus spacious and roads will support the society to make our capital city

    free from traffic jam and will make it more livable.