CAPSTONE PROJECT
F.AID TEAM – HIS PROJECT
INTRODUCTIONDAT TRAN -
LEADERTOAN DANGSON NGUYENTHANH LEHUNG TOHAI NGUYENTHANH TRAN
F.Aid Team CustomerMr. Nam vu
MentorMs. Chau ly
AGENDAPROJECT BACKGROUNDPROCESS & PLANNINGDEVELOPMENTPROJECT MANAGEMENTREFLECTIONDEMO
PROJECT BACKGROUNDGOAL
HIS HOSPITAL NEED SOFTWARE TO SOLVE SOME CURRENT PROBLEMS AND FUTURE AS:• EVERY DAY, HOSPITAL HAVE ABOUT 1000 PATIENT TO EXAMINE WITH 1200
TIME. ACCORDING TO THE PREDICTION OF PATIENT GO TO HEALTH CARE MAY INCREASE 3 TIME IN 5 YEARS
• CURRENTLY, THE HOSPITAL HAVE 12 CLINICS, 3 UNITS PERFORM PRECLINICAL, 2 UNITS RECEIVING PATIENT AND HAVE EXPANSION NEED IN THE FUTURE
THE PURPOSE OF SOFTWARE IS INCREASE PERFORM IN THE HEALTHCARE, IMPROVE PRODUCTIVITY OF DOCTOR, NURSE AND STAFF OF HOSPITAL
PROJECT BACKGROUNDSCOPE
SOFTWARE WILL USING BY 12 CLINICS, THE ROOM PERFORM CLINICAL SERVICES. THE COMPUTER HAVE BEEN INSTALL SOFTWARE CAN USING IN DATABASE VIA LOCAL NETWORK, TO CONNECT AND SYCE DATA BETWEEN DEPARTMENTS
PROCESS & PLANNING
PROCESS DEVELOPMENT PROCESS
PROCESS & PLANNING
MILESTONES
Task name Start Finish
F.Aid Project 05/30/2013 12/20/2013
- Initial 05/30/2013 06/03/2013
- Requirement 06/10/2013 08/19/2013
- Architecture 07/08/2013 08/26/2013
- Incremental 1 09/02/2013 10/28/2013
- Incremental 2 10/28/2013 11/25/2013
- Incremental 3 11/25/2013 12/09/2013
- Integration Test 12/2/2013 12/9/2013
DEVELOPMENT - REQUIREMENT
REQUIREMENT PROCESS
DEVELOPMENT - REQUIREMENT
Security Availability
Performance Usability
Quality Attributes
DEVELOPMENT - REQUIREMENT
BUSINESS CONSTRAINTS ID Name Description
BC.01 Schedule Team develops should system within 6 month
BC.02 Resource Team have 6 main member and 1 support member
DEVELOPMENT - REQUIREMENT
TECHNICAL CONSTRAINTS
ID Name Description
TC.01 Database SQL Server 2008
TC.02 Tools and methods Microsoft Visual Studio 2010
TC.03 Computer language C#
TC.04 Server configurationOS: Window Server 2003
CPU: Intel X3210
TC.05 PC configurationCPU: Core 2 dual (1,8 GHz) over
RAM: 1GB HDD: 80 GB OS: Win XP
TC.06 Type System develop base on Application
TC.07 PrinterCyber Tech TM200, SATO Cx400, Canon L11121E, Samsung SCX-4X21 seres
TC.08 Reader barcode Cyber Tech DS09X, Biroh BS 360B
DEVELOPMENT - ARCHITECTURE
ARCHITECTURE PROCESS ACTIVITIES
DEVELOPMENT - ARCHITECTURE
PHYSIC VIEW
DEVELOPMENT - ARCHITECTURE
STATIC VIEW
DEVELOPMENT - ARCHITECTURE
DYNAMIC VIEW
DEVELOPMENT - TESTINGPROCESS Test plan
Design test
Perform integration test
Perform system test
Perform acceptance test
E value test
DEVELOPMENT - TESTINGDate Proposed Active Resolve Close
10/18/2013 3 14 8 140
10/19/2013 1 0 10 154
11/21/2013 0 0 0 161
Date High Med Low Very low
10/18/2013 4 3 3 8
10/19/2013 1 0 0 0
2
1
1
1 HighMedLowVery low
Bug summary of incremental 1
Bug severity status of incremental 1
BUG REPORT TEST
DEVELOPMENT - TESTING
60%20%
20%
System Test Report
Pass
Fail
Untest
Closed
Total 110
Pass 66
Fail 0
Untested 22
Closed 22
DEVELOPMENT - TESTING
Total Test Cases 94
Pass 87
Fail 0
Untested 793%
7%
Acceptance Test Report
PassFailUntest
DEVELOPMENT - TESTING
Total Test Cases 5
Pass 4
Fail 1
Untested 0
80%
20%
Non-functional Test Report
PassFailUntested
PROJECT MANAGEMENT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 280.001000.002000.003000.004000.005000.006000.007000.008000.00
Earn Value
BCWSBCWPACWP
Week
PROJECT MANAGEMENT
W1 W2 W3 W4 W5 W6 W7 W8 W9W10W11W12W13W14W15W16W17W18W19W20W21W22W23W24W25W26W27W28W29W30
050
100150200250300350
Team productivity
StandardActualLower bound
REFLECTIONProblems Solutions
At the beginning of the project, the timing of team members are not the same, it is difficult to stabilize team meeting schedule
Division of work for members perform at home. Review the work after the next steam meeting
The ability of the members is limited so work progress is often slower than the proposed plan
Learn, study the relevant documents at each phase of the project
Some cases, team member also distracts in working so late deadline
Leader regularly remind members complete the work on time. Members support each other’s to complete the work
Late meetings affect the performance of the team Leader remind members to attend meetings on time
This is the capstone project so team members have certain difficulties such as pressure Mentor and members enthusiastically help each other
REFLECTION
Actual Planned0
62727260
0
Overall Time Spent
THANKS FOR YOUR LISTENING!
F.AID TEAM – HIS PROJECT