Upload
dawit-bogale-mce-pe-pmp
View
22
Download
0
Tags:
Embed Size (px)
Citation preview
Norwich University
Direct Connector between I-10 and Highway-99
2012
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
1919 lenora ct. katy Tx. 77493
8/12/2012
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
1
Direct Connector between I-10 and Highway 99
Table of Contents
Acknowledgement ….......................................................................................................I
Nomenclature.....………………………………………………………………….........II
List of Tables………………………………………………………………………......III
List of Figures……………………………………………………………………........ IV
Abstract…...................................................................................................................... VI
1. Introduction ........................................................................................................10
1.1 Background…………………………………………………………………...10
1.2 Objective ……………………………………………………………………...11
1.3 Thesis Content ………………………………………………………………..11
1.4 Application of the study and limitations………………………………….......11
2. Bridge Structure .................................................................................................13
2.1. General……………………………………………………………………......13
2.2. Precast pre-stressed concrete Bridge……………………………………........13
2.2.1. Description…………………………………………………………….13
2.3. Importance of Bridges in Architecture…………………………………..….14
2.4 Design task ....................…………………….. …………….………..………15
3. Structural Analysis and Design of Pre-stressed Concrete Bridges........................18
3.1. Bridge loading……………………………………………………………..…18
3.1.1. Dead Load.....……….…………... …………………….………………19
3.1.2. Live Load...................……………....…….…………………………….19
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
2
3.1.3. Dynamic load allowance..............................……..........……………….20
3.1.4. Wind load..………................................………….…………………….20
3.1.5. Earth quake Load ………………………………………………………21
3.1.6 Earth pressure…........................................................................................21
3.2. Bridge design and analysis…………………………………………………...22
3.2.1Super-structure Analysis and Design……………………………….……22
3.2.1.1 Slab Analysis and Design………………………………………....24
3.2.1.2 Girder Analysis and Design……………………………………....33
3.2.2 Sub-structure Analysis and Design……………………………………...64
3.2.2.1 Abutment Analysis and Design.............. …………………………64
3.2.2.1.1 Design Abutment Heel…………….………………..…….82
3.2.2.1.2 Design Abutment Toe…………………………………….84
3.2.2.1.3 Design Abutment Stem ………………..…………………87
4. Project Management……………………….................................................................97
4.1. Project Scope Management…………………………………………………...97
4.1.1 Define Scope……………………………………………………………99
4.1.2 Create Work Break Down Structure……………………………………100
4.2. Project Time Management. ………..................................................................102
4.2.1 Define Activities, Sequence Activities, and Develop Schedule………..102
4.2.2 Schedule Changes and Thresholds….………………………………….104
4.2.3 Schedule Control…………….…………………………………………104
4.3. Project Cost Management................................................................................107
4.3.1 Estimate Cost ………………………………………………………….107
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
3
4.3.2 Determine Budget………………………………………………………107
4.3.3 Project Cost and Schedule Performance………………………………..111
4.4. Project Quality Management …………………………………………………115
4.4.1Project quality measurement……………………………………………..115
4.5. Project Human Resource Management……………………………………….115
4.6. Project Communication Management………………………………………..116
4.7. Risk Management.............................................................................................116
4.8. Project Procurement Management……………………………………………117
5 Conclusions and Summary................................................................................................118
6. References…....................................................................................................................119
7. Appendix A......................................................................................................................120
8. Appendix B.......................................................................................................................129
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
4
I. Acknowledgements
First of all, I would like to thank God for each and every success in my life. Then I would like to
extend my love and heart felt appreciation to Meskerem Eshete, Elias Manyazewal, and my
families not only for their encouragement but also for their being with me in all ups and downs.
My deepest gratitude goes to my thesis advisor Mr. Dave Mukerman, Mr. Nick Marianos, and all
the staff of Norwich University for their professional, genuine guidance and valuable advice to
accomplish the thesis.
At last, but not least, I would like to express my profound and special thanks to those engineers
who have collaborated during site visit.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
5
II. Nomenclature
Symbol Definition
⍺ Depth of equivalent rectangular stress block in concrete
As* Area of pre-stressing steel (in2)
Ast Total area of longitudinal reinforcement (in2)
A’s Area of compression reinforcement (in2)
Av Area of shear reinforcement (in2)
E Earth pressure (lbf/ft2)
D Dead load (lbf)
B Width of footing (ft.)
ρ Ratio of steel reinforcement
ρ’ Ratio of compression reinforcement
ρmax Maximum permitted reinforcement ratio
β Coefficients applied to actual loads for service load and load factor designs
β1 Factor for concrete strength
I Moment of inertia (in4)
I Live load impact (lbf)
Tf Temperature force due to friction at bearing (lbf).
FSo Factor of safety against overturning
FSs Factor of safety against sliding
g Centroid of pre-stressing strand pattern (in)
R Reaction (lbf)
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
6
III. List of Tables
TABLES Page
Table 1 Section Properties of AASHTO Type IV Girder.........................................................36
Table 2 Properties of Composite Section..................................................................................38
Table 3 Summary of service loads and moments…………………..........................................77
Table 4 Stability and Bearing Pressures…………………………………................................77
Table 5 Factored Vertical Loads………………………………...............................................79
Table 6 Moment resulted from Factored Vertical Loads.........................................................79
Table 7 Factored Horizontal Loads .........................................................................................79
Table 8 Moment resulted from Factored Horizontal Loads………........................................80
Table 9 Factored Bearing Pressures…….................................................................................80
Table 10 Factored Vertical Loads……...................................................................................89
Table 11 Factored horizontal loads………………………………………………………….89
Table 12 Factored Moment at stem base resulting from vertical and horizontal Loads…….89
Table 13 Factored Vertical Loads……................................................................................. 90
Table 14 Factored Horizontal Loads………………………………………………………..90
Table 15 Factored Moment at stem base resulting from vertical and horizontal Loads…….90
Table 16 Project Budget…………………………………………………………………….108
Table 17 Project Cost Performance………………………………………………………….113
Table 18 Cash Flow………………………………………………………………………….129
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
7
IV. List of Figure
Figure Page
Fig. 1 Project Location……………....................................................................................... 10
Fig. 2 Plan view of Bridge…….............................................................................................. 16
Fig. 3 Sectional view of Bridge……………………………………………………………...23
Fig. 4.Sectional view of slab, curb and parapet, and slab reinforcement detail….…………..32
Fig. 5 Section Geometry AASHTO Type IV Girder………………………………………...35
Fig. 6 Sectional view of Composite Section and properties…………………....................... 40
Fig. 7 Maximum live load shear……………………………………………………………..47
Fig. 8 Sectional view and strand arrangement of Girder…………………………………….52
Fig. 9 Sectional view of Abutment…………………………………………………………..65
Fig. 10 Sectional view of Live load and Earth pressure on Abutment………………………69
Fig. 11 Sectional view of pressure on Footing………………………………………………81
Fig. 12 Reinforcement detail of Abutment.............................................................................95
Fig. 13 Summary of Project Schedule…………….................................................................105
Fig. 14 Project Schedule…………..........................................................................................121
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
8
V. Abstract
The existing signalized intersection and travel corridor between IH 10 and SH 99 is insufficient
to cycle the anticipated volume of traffic. Hence, the purpose of this project is to improve traffic
flow by providing a Direct Connector between IH 10 and SH 99. It connects northbound and
southbound movements along SH 99 from IH 10 and westbound and eastbound movements
along IH 10 from SH 99.
The scope of work for this project will focus both on structural engineering and Project
Management from initiation to execution of the proposed direct connectors. This project will
perform the design of Pre stressed Concrete IV Girder, Abutment, and Concrete deck slabs. The
design is guided by the American Association of State Highway and Transportation Officials
(AASHTO) Standard Bridge Design Specifications and Texas department of Transportation’s
manuals. The analysis will be performed using traditional method. In addition scheduling, Gantt
bar chart, cost estimation is performed using Microsoft project.
In conclusion, in addition to design and analysis of concrete slab, concrete girders, and abutment,
this project clearly demonstrates the advantage of using precast concrete products to construct
cost effective, complex long span structure where aesthetic and urban geometric are significant
design consideration.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
9
CHAPTER ONE:
INTRODUCTION
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
10
1. Introduction
1.1. Background
The project is located at the intersection of State Highway (SH) 99 and Interstate Highway (IH)
10 in Harris County, Texas. These two high-speed highways intersect at a grade separated
interchange. The existing frontage roads provide northbound and southbound movements along
SH 99 from IH 10 and westbound and eastbound movements along IH 10 from SH 99. This
project would provide fully directional direct connectors (DCs) between these two facilities in
addition to the existing frontage road system. In order to connect between IH 10 and SH 99,
motorists are required to travel through at grade signalized intersection. The existing signalized
intersection and travel corridor is insufficient to cycle the anticipated volume of traffic. Hence,
there is a delay and interrupted connection that reduces local and regional transportation system
mobility [8]. Highway 99 N
I-10 W I-10 E
Highway 99 S
Fig. 1 Project Location
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
11
1.2. Objective
The importance of this project is to improve traffic flow by providing a Direct Connector that
enhances transportation continuity regionally and locally. It helps to connect northbound and
southbound movements along SH 99 from IH 10 and westbound and eastbound movements
along IH 10 from SH 99. The main objective of the thesis is to develop analysis and design of
slab, girder, and abutment of concrete bridge.
1.3. Thesis Content
The study of the thesis mainly focuses on application of the knowledge gained through different
courses on design and analysis of bridges. Based on the main objective of the thesis, the study
has focused on developing analysis and design of pre-stressed concrete bridge between I-10 and
Highway 99 using AASHTO Standard Bridge Specification. In addition to this, the project
management concept like project time, cost, quality, risk, human resource, and procurement
management will be included. Beside the above objective, the thesis helps to promote the
importance of precast pre-stressed concrete bridge for beauty of the city.
1.4. Applications and Limitations
The study shall benefit the client, public, and constructors as these bridges would only take a
short time to produce and assemble. This enables the quick restoration of traffic. The scope of
the study has been limited to the preparation of analysis and design for slab, girder, and abutment
only. This research may be used as a basis for future study to include the design of other parts of
the bridge so that the whole bridge could be designed and analyzed.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
12
CHAPTER TWO:
BRIDGE STRUCTURE
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
13
2. Bridge Structure
2.1. General
A bridge structure is divided into super structure and substructure. The superstructure (upper
part), which consists of the slab, the floor system, the girders, and the substructure (lower part),
which are piers, footings, piles and abutments. The super structure provides horizontal spans
such as deck and girders and carries the traffic loads directly where as the function of sub
structure is to support the superstructure of the bridge. The following factors are taken into
account and the type that is most economical and can give maximum service is designed. Some
of the factors considered to be the main criteria for the selection of type of bridge studied in the
thesis are:
Existing structures.
Availability of fund.
Time available for construction of the bridge.
Appearance of bridge from aesthetic point of view.
2.2. Pre-stressed Concrete Bridge
2.2.1. Description
Pre-stressed concrete structures are shallower in depth than concrete reinforced structure for the
same span and loading condition. In conventional reinforced concrete, the high tensile strength
of steel is combined with concrete's great compressive strength to form a structural material that
is strong in both compression and tension. The principle behind pre-stressed concrete is that
compressive stresses induced by high-strength steel tendons in a concrete member before loads
are applied will balance the tensile stresses imposed in the member during service. Pre-stressing
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
14
removes a number of design limitations conventional concrete places on span and load and
permits the building of bridges with longer unsupported spans. This allows designing and
building lighter and shallower concrete structures without sacrificing strength. [2]
Pre-stressed concrete structure can be produced through pre-tensioning or post-tensioning. In
pre-tensioning, the steel is stretched before the concrete is placed. High-strength steel tendons
are placed between two abutments and stretched to percentage required of their ultimate strength.
Concrete is poured into molds around the tendons and allowed to cure. Once the concrete reaches
the required strength, the stretching forces are released. As the steel reacts to regain its original
length, the tensile stresses are translated into a compressive stress in the concrete. In post-
tensioning, the steel is stretched after the concrete hardens. Concrete is cast around, but not in
contact with steel. In many cases, ducts are formed in the concrete unit using thin walled steel
forms. Once the concrete has hardened to the required strength, the steel tendons are inserted and
stretched against the ends of the unit and anchored off externally, placing the concrete into
compression. [2]
2.3 Importance of Bridges in Archtecture
The fact that bridges last many generations and become symbols of a particular city makes them
special for their designers and users. During the design, sizes and aesthetic appearance are
chosen carefully because it shows the culture of the time and the ambition of the civilizations
which built them. Bridges have a significant place in human civilization. Hence, the design of
bridge is not as easy as the design of an ordinary structure. The success of the bridge comes not
only with its function but its visual beauty. Bridges are highly visible elements in city life. The
function, stability, stiffness and strength were the primary concerns of the designer. However,
with the advancement of civilization, aesthetic parameters started to be considered. When an
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
15
engineer builds a bridge, he/she creates a visible object in the environment. The location and size
of the major structural features of the bridge, its piers, girders, and abutments, are its major
aesthetic features; because of their size, they have a major role in the aesthetic impact of the
bridge.
2.4 Design Task
In this capstone project, the task focuses both on structural engineering and Project Management
from initiation to execution of the proposed direct connectors.
Structural design and analysis: This project has precast pre-stressed Concrete girder, Concrete
deck slabs, and Abutment. It is designed using the American Association of State Highway and
Transportation Officials (AASHTO) Standard Bridge Design Specifications. Most of the data are
assumed by visiting the site.
Project Management: The project management concept like project time, cost, quality, risk,
human resource, and procurement management will be included.
The project Management section includes all connectors: Bridge on highway 99 bypass over I-10
and Direct Connector A, B, C, D, E, F, G, and H. However, the structural design and analysis
section includes only bridge on highway 99 bypass over I-10. Look Fig. 2 in the next page.
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
17
CHAPTER THREE:
STRUCTURAL ANALYSIS AND DESIGN
OF PRESTRESSED CONCRETE BRIDGE
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
18
3. Structural Analysis and Design of pre-stressed concrete Bridges
3.1. Bridge Loading
The design of any component of bridge is based on a set of loading conditions which the
component must withstand. The various types of loading which need to be considered can
broadly be classified as permanent, or temporary.[1] Permanent loads are those due to the weight
of the structure itself and of any other immovable loads that are constant in magnitude and
permanently attached to the structure. They act on the bridge throughout its life. Temporary
loads are those loads that vary in position and magnitude and act on the bridge for short period of
time such as live loads, wind loads and water loads etc. [4]. Some of these are:
1. Permanent loads
dead load of structure
superimposed dead loads
2. Temporary loads
vehicular live loads
pedestrian live loads
impact loads
wind loads
earth quake loads
In order to form a consistent basis for design, AASHTO has developed a set of standard loading
condition, which is taken in to account while designing a bridge. These loads are factored and
combined to produce extreme adverse effect on the member being designed.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
19
3.1.1 Dead Load
The dead load from superstructure is the aggregate weight of all structural elements and
nonstructural parts of the bridge above the bearing. This would include the main supporting
girders, the deck, parapets and road surfacing. The dead load from substructure is the weight of
all structural elements of the bridge between the lowest levels of the structure till the bearing.
This would include the abutment, foundation, and pier.
3.1.2 Live Loads
The live load for bridges means a load that moves along the length of the span that consists of
the weight of the applied moving load of vehicles and pedestrians. The traffic over a highway
bridge consists of a multitude of different types of vehicles. To form a consistent basis for
design, standard loading conditions are applied to the design model of structure. These standard
loadings are specified in Standard specification of American Association of State Highway and
transportation Officials (AASHTO).
The highway live loadings on bridge consist of standard trucks or lane loads that are equivalent
to truck trains. Two systems of loading are provided: H-loading and HS loading. The number
after H or HS indicates the gross weight in tons of the truck or tractor. The design truck is
designated as HS 25 consisting of 10 kip front axle and two 40 kip rear axles. The design
tandem consists of a pair of 32-kip axles spaced 4 ft. apart. However, for spans longer than 40 ft.
the tandem loading do not govern, thus only the truck load is investigated [1].
The lane load consists of a load of 0.8klf uniformly distributed in the longitudinal direction. The
design of the deck slab is based on HS 25 loading; hence, 20 kip wheel load will govern the
design.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
20
3.1.3 Dynamic Load Allowance (Impact)
The truckloads on bridges are applied not gently and gradually but rather violently, causing
stress increase. In order to account the dynamic effect of sudden loading of vehicle on to a bridge
structure, additional loads called impact loads must be considered. These are taken into account
by increasing the static effects of design truck or tandem, with the exceptions of centrifugal and
breaking forces, by the Dynamic Load Allowance. The factor to be applied to the static load shall
be taken as: (1 + IM/100). The dynamic load allowance shall not be applied to pedestrian loads
or to the design lane load. [3]
3.1.4 Wind Load
Wind forces are extremely complicated, but through a series of simplifications are reduced to an
equivalent static force applied uniformly over the exposed faces of the bridge (both super and
sub-structures) that are perpendicular to the longitudinal axis. AASHTO specifies that the
assumed wind velocity should be 100 mph. For a common slab-on-stringer bridge this is usually
a pressure of 50psf, and a minimum of 300p/lf. These forces are applied at the center of gravity
of the exposed regions of the structure.
AASHTO recommends the following for common slab-on-stringer bridges:
1) Wind force on structures (W): a) transverse loading = 50psf b) longitudinal loading = 12psf
2) Wind force on live load (WL): a) transverse loading = 100psf b) longitudinal loading = 40psf
The transverse and longitudinal loads are placed simultaneously for both the structure and the
live load (AASHTO 3.15.2.1.3).
For the usual girder having span lengths less than 125ft, the transverse wind loading on the
superstructure can be taken as 50lbf/ft2, and the longitudinal wind loading can be taken as
12lbf/ft2. [AASHTO 3.15.2.1.3]
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
21
Wind forces are resisted by the bracing systems for a through bridge. The bracing systems are
neither analyzed nor designed in this thesis since the load is considered insignificant.
3.1.5 Earthquake Loading
When earthquakes occur, bridges can be subject to large lateral displacements from the ground
movement at the base of the structure. In many areas of the United States, the risk of earthquakes
is low. Since city of Houston lies not within the seismic zone, the risk of earthquakes is less.
Bridge earthquake loads depend on a number of factors, including the earthquake magnitude, the
seismic response of soil at the site, and the dynamic response characteristics (stiffness and
weight distribution) of the structure. Hence, it can be ignored for this capstone project.
3.1.6 Earth Pressure
In this capstone project, earth pressure is the lateral pressure generated by fill material acting on
abutments. The magnitude of earth pressure depends on the physical properties of the soil, the
interaction at the soil-structure interface, and the deformations in the soil-structure system. From
AASHTO 5.5.2, an equivalent fluid weight of 35lb/ft3 is more commonly used (sandy backfill
with a unit weight of approximately 120lb/ft3). The earth pressure acting on abutment is
increased when vehicle live loads occur in the vicinity of the structure. When vehicle traffic can
come within a horizontal distance from the top of a retaining structure equal to one-half its
height, a live load surcharge of 2 feet of fill is added to compensate for vehicle loads (AASHTO
3.20.3). The resulting load distribution on the structure is trapezoidal is as shown in drawing no.
10. [1]
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
22
3.2. Bridge design and analysis
The Direct Connector between I-10 and highway 99 projects has eight connectors with different
span length. In this project, structural design of slab, girder, and abutment that connects north
and south of I-10 on highway 99 is considered. The calculation used in design of girder in this
project connects north and south of I-10 on Highway 99. In this project, to obtain optimum
design longest span of 80 ft. single span bridge is considered. The design is based on the
AASHTO Standard Bridge Design Specifications. The sectional view of the bridge is shown in
the next page, Fig. 3.
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
24
3.2.1. Super-structure Analysis and Design
DESIGN PARAMETERS
The bridge considered for this design has a span length of 80 ft. (center-to-center (c/c) pier
distance), a total width of 42 ft. and total roadway width of 39 ft. The bridge superstructure
consists of slab design, five AASHTO IV Girders spaced 9 ft. center-to-center, designed to act
compositely with 9 in. thick cast-in-place (CIP) concrete deck. The wearing surface thickness is
0.5 in., which includes the thickness of any future wearing surface.
3.2.1.1 Slab Analysis and Design
The overall width of the bridge is 42ft. The clear road way width is 39ft. The road way is a
concrete slab 9 in thick, with a concrete strength of fc’=4 kips/in2 and steel reinforcement equal
to Fy= 60 kips/in2. The top width of girder spaced 9 ft. apart is 20 in. The future wearing surface
is 0.03 kips/ft3.
Determine the effective slab span length:
The effective slab span length S is the clear span plus one half the stringer top widths
[AASHTO 3.24.1.2(b)] S = 9 ft. + 10/12 ft. =9.83 ft.
Determine minimum thickness of the slab:
[AASHTO Table 8.9.2] tmin = (S+10)/30 = (9.83+10)/30 *12 in/ft. = 7.9 in
Assumed slab thickness is t= 7.9 +.5=8.4
Use 9 in
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
25
Determine factored load
Group loading combinations for load factor design are
[AASHTO Table 3.22.1A] Group I =ɤ*(βD*D + βL(L+I))
= 1.3(1*D+1.67(L+I))
= 1.3D + 2.17(L+I)
Determine the factored dead loads
WD= 1.3(deck slab + FWS)
= 1.3(9in*(1/12)*.15kip/ft3 + 0.03kip/ft
2)
= 0.185kip/ft2
WD = 0.185kip/ft per foot of width of slab
WC+P = 1.3(curb and parapet)
= 1.3*3.37ft2*(0.15kip/ft
3)
= 0.657 kip/ft.
Determine the factored live plus impact loads.
The design truck is designated as HS 25 consisting of 10 kip front axle and two 40 kip rear axles.
The design tandem consists of a pair of 32-kip axles spaced 4 ft. apart. However, for spans
longer than 40 ft. the tandem loading does not govern, thus only the truck load is investigated.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
26
The lane load consists of a load of 0.8klf uniformly distributed in the longitudinal direction. The
design of the deck slab is based on HS 25 loading; hence, 20 kip wheel load will govern the
design.[1]
[AASHTO 3.8.2] The live load impact is:
I= 50/ (L+125) = 50/ (9ft + 125) = 0.37
The maximum impact load allowed is 0.3.
The factored wheel plus impact load is
PL+I = 2.17(L+I) = 2.17*(20kips + 0.3*20kips) = 56.4 kips
Analyze for factored moment.
For continuous spans, the factored positive and negative dead load moments are assumed to be
MD= (WD S2)/10 = ((0.185 Kip/ft
2)*(9.83ft)
2)/10
MD =1.79ft-kips/ft. width of slab
Based on AASHTO 3.24.3.1 in slabs continuous over three or more supports, a continuity factor
of 0.8 is applicable. The factored positive and negative live load plus impact moments are:
[AASHTO 3.24.3.1 & Equation 3-15 ] ML+I= O.8*((S+2)/32)*PL+I
= 0.8((9.83+2)/32)*56.4
= 16.68 ft.-kips/ft. width of slab
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
27
The total factored positive and negative moments are:
Mu = MD+ML+I
= 1.79ft-kips + 16. 68 ft.-kips
= 18.47 ft.-kips/ft. width of slab
[AASHTO3.24.5.] For cantilever spans, the factored negative dead load moment is;
MD= ((WDS2)/2) + MC+P*L
AASHTO 3.24.1.2 S= 3ft – (10/12) ft. = 2.17ft
L= 2.17ft-0.66ft = 1.51ft
MD= (((0.185 kips/ft2)*(2.17ft)
2)/2) +(0.657 kip/ft
2)*1.51ft
= 1.43 ft.-kips/ft. width of slab
[AASHTO 3.24.2.1] The center line of the wheel will be placed 1 ft. from the face of the curb.
[AASHTO 3.24.5] Each wheel on the slab perpendicular to traffic is distributed over a width of
[AASHTO Equation 3.17] E= 0.8X + 2.17 = (0.8*(0.58ft.)) + 2.17 ft. = 2.63 ft.
Where X= distance in feet from wheel load to point of support
X= I [2.17ft. - ((12+2+7+12)/12)] I = 0.58 ft.
[AASHTO 3.24.5.1] The factored negative wheel load plus impact moment is
ML+I = PL+ I(X/E)
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
28
= (56.4 kip)*(0.58ft/2.63)
= 12.44ft.-kips/ft. width of slab
The total factored negative moment is
Mu= MD + ML+ I
= 1.43 ft.-kips + 12.44 ft.-kips
= 13.87ft.-kips/ft. width of slab
Due to the short overhang, the live load acting at a distance on one foot from the barrier face
does not act on the overhang. Therefore, this case need not be investigated.
Design for moment
The compressive strength of the concrete at 28 days is f’c = 4000lbf/in2. The specified minimum
yield point of the steel is Fy = 60000lbf/in2. Determine the maximum and minimum steel
reinforcement needed.
[AASHTO 8.16.3.1 & 8.16.3.2] The maximum ratio of tension reinforcement is
[AASHTO 8.16.3.1.1] ρ max = 0.75ρb = 0.75* ρb
Where, β =0.85-0.025= 0.825; fc’=4000lbf/in2 [AASHTO 8.16.2.7]
ρb =( (0.85β1fc’)/Fy)*(87000/(87000+Fy) [AASHTO 8.16.3.2.2]
ρb =( (0.85*0.825*4000)/60000)*(87000/(87000+60000)
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
29
ρb =0.028
ρ max = 0.75ρb = 0.75*0.028 = 0.021
Determine the areas of positive and negative steel. [AASHTO 8.16.3.2 & Equation 8-16]
ΦMn = ΦAs Fy(d- (⍺/2))
⍺= (As*Fy)/ (0.85*fc’*b)
⍺= (As*60kips/in2)/ (0.85*4kips/in
2 *12in)
⍺= 1.47*As
Assume No. 7 steel rebar,
d= 9in – 0.5in for integral wearing surface – 2.0 in for cover – 0.44in
d= 6.06in
[AASHTO 8.16.1.2] Φ=0.9 for flexure
Mu= Φ*Mn for continuous spans
Mu= 18.47*12(in/ft.)= Φ*Mn = 0.9*As*(60kips/in2)*(6.06in-(1.47/2)*As)
221.64= 327.24As - 39.69As2
As2-8.245*As + 5.584 = 0
As=0.745 in2/ft. of slab width
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
30
Use #7@9in (As= 0.8in2/ft.)
ρ= As/bd = 0.8in2/(12in*6.06in)= 0.011< ρmax=0.021 ok
Check moment capacity
⍺=(As*Fy)/(0.85*fc’*b)= (0.8in2*60kips/in
2)/(0.85*4 kips/in
2*12in)
= 1.18in
⍺/2 = 0.588in
ΦMn= 0.9*0.8*60*(6.06in-0.588in)(1ft/12in)
= 19.7 ft-kips/ft of slab width
Mu= 18.47 ft-kips/ft of slab width [ < ΦMn, so ok]
Check minimum steelIn a flexure member where tension reinforcement is required by analysis,
the minimum reinforcement provided shall be adequate to develop a moment capacity at least
1.2times the cracking moment. [AASHTO 8.17.1]
[AASHTO Equation 8-62] ΦMn≥1.2 Mcr
[AASHTO 8.13.3 & Equation 8-2] Mcr= fr*Ig/yt
fr=modulus of rupture= 7.5(√fc') for normal weight concrete
fc= 4000lbf/in2
Ig= moment of inertia
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
31
Yt= distance from centroidal axis to extreme fiber in tension
ΦMn≥ 1.2Mcr
Mcr= fr*Ig/yt= (7.5 ) *((12in)(9in)3)/4.5in)*(1ft/12in)(1kip/ft)
Mcr= 6.404 ft.-kips/ft.
1.2 Mcr=1.2*6.404ft-kips = 7.68ft-kips/ft. [≤ΦMn=19.47 ft.-kips/ft. ok
Distribution Reinforcement
Reinforcement traverse to main steel reinforcement is placed in the bottom of all slabs. The
amount shall be a percentage of the main reinforcement required as determined in the following
formula. [AASHTO 3.24.10]
[AASHTO 3.24.10.2 & Equation 3-22] The percentage is 220/ (√S), with a maximum of 67%
= 220/ (√9.83ft) =70.17% [67%maximum allowed]
As= 0.67*0.7in2 = 0.47 in
2/ ft.
Use #6@9in (As= 0.59in2/ft.) in the bottom and perpendicular to the main reinforcement in the
middle half of the slab span. 50% of the specified distribution reinforcement is used in the outer
quarters of the slab span. [AASHTO 3.24.10.3]
5. Design for shear and bond
Slabs designed for bending moment in accordance with AASHTO sec.3.24.3 (wheel loads) are
considered satisfactory in bond and shear. Fig. 4 shows slab and curb detail in the next page.
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
33
3.2.1.2 Girder Analysis and Design
Considering the bridge connects north and south of highway 99 that pass over I-10 as simply
supported span 80 ft. There are five pre-stressed AASHTO standard IV beams with compressive
strength f’c= 5500 psi at initial pre-stress and f’cg = 6500 psi at 28 days. The roadway is 9 in
slab three lanes wide. The dead load of curb and parapet is 0.506 kips/ft. Pre-stress is to be
provided by ½ in strand(seven-wire) steel with an area of 0.153in2 and ultimate stress of pre-
stressing steel of f’s= 270 kips/in2. For HS 25 loading, use load factor design method to design
AASHTO standard IV beams.
Span Length (c/c piers) = 80 ft.-0 in.
Overall girder length = 80'-0" – 2(2") = 79'-8" = 79.67 ft.
Design Span = 80'-0" – 2(9") = 78'-6" = 78.5 ft. (c/c of bearing)
Cast-in-place slab:
Thickness, ts = 9.0 in.
Concrete strength at 28 days, fc′ = 4000 psi
Thickness of asphalt wearing surface (including any future wearing surface), tw = 0.5 in.
Unit weight of concrete, wc = 150 pcf
Precast girders:
Concrete strength at release, fc′i = 5500 psi
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
34
Concrete strength at 28 days, fc′g = 6500 psi
Concrete unit weight, wc = 150 pcf
Pre-tensioning strands: ½ in. diameter, seven wire low relaxation
Area of one strand = 0.153 in.2
Ultimate stress, fpu = 270,000 psi
Yield strength, fpy = 0.9fpu = 243,000 psi
Stress limits for prestressing strands:
Before transfer, fpi ≤ 0.75 fpu = 202,500 psi
At service limit state (after all losses) fpe ≤ 0.80 fpy = 194,400 psi
Modulus of Elasticity, Ep = 28,500 ksi
Non pre-stressed reinforcement:
Yield strength, fy = 60,000 psi
Modulus of Elasticity, Es = 29,000 ksi
Look the cross sectional drawing of Type IV Girder Fig. 5 in the next page.
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
36
A.2.4 CROSS SECTION PROPERTIES FOR A TYPICAL GIRDER
A.2.4.1 NON-COMPOSITE SECTION
The section properties of an AASHTO Type IV girder are provided in the following table.
Table 1 Section Properties of AASHTO Type IV Girder
yt (in) yb (in) Area(in2) I (in4) Wt/lf (lbs)
29.25 24.75 788.4 260403 821
Where:
I = Moment of inertia about the centroid of the non-composite precast girder = 260,403 in.4
yb = Distance from centroid to the extreme bottom fiber of the non-composite precast girder =
24.75 in.
yt = Distance from centroid to the extreme top fiber of the non-composite precast girder = 29.25
in.
Sb = Section modulus referenced to the extreme bottom fiber of the non-composite precast
girder, in.3 = I/yb = 260,403/24.75 = 10,521.33 in.3
St = Section modulus referenced to the extreme top fiber of the non-composite precast girder,
in.3 = I/ yt = 260,403/29.25 = 8902.67 in.3
COMPOSITE SECTION
Effective Flange Width
[AASHTO 9.8.3.2] The effective flange width is lesser of:
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
37
Case 1: 0.25 span length of girder:
= 80(12 in. /ft.)/ 4 = 240 in.
Case 2: 12 × (effective slab thickness) + (greater of web thickness or one half top flange width):
= 12(9) + 0.5(20) = 118 in.
[0.5 × (girder top flange width) = 10 in. > web thickness = 8 in.]
Case 3: Average spacing of adjacent girders:
= (9 ft.)(12 in. /ft.) = 108 in. (controls)
Effective flange width = 108 in.
A.2.4.2.2Modular Ratio between Slab and Girder Concrete
The modular ratio between the slab and girder concrete is used for service load design
calculations. For the flexural strength limit design, shear design, and deflection calculations, the
actual modular ratio based on optimized concrete strengths is used.
n = Ecs for slab/ Ecg for girder
where n is the modular ratio between slab and girder concrete, and
Ec is the elastic modulus of concrete.
Slab concrete fcs’ = 4000lbf/ft2,
[AASHTO Equation 10-68] Ecs = Wc1.5
*33*√fcs'
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
38
Ecs = (150lbf/ft3)1.5
*33*√ (4000lbf/in2) = 3.83 x 10
6lbf/in
2
Girder fcg’ = 6500lbf/ft2, fci’ = 5500lbf/ft2,
Ecg = Wc1.5
*33*√fcg' = (150lbf/ft3)1.5*
33*√ (6500lbf/in2) = 4.89 x 106lbf/in
2
n= Ecg/Ecs = 4.89/3.83 = 1.28
A.2.4.2.3 Transformed Section Properties
Transformed flange width = n × (effective flange width) = (1.28)(108) = 138.24 in.
Transformed Flange Area = n × (effective flange width)(ts) = (1.28)(108)(9) = 1244.16 in.2
Table 2 Properties of Composite Section.
Transformed
Area( in2)
yb
( in)
A*yb A(ybc – yb)2
I
(in4)
I + A(ybc - yb)2
(in4)
Girder 788.4 24.75 19512.9 336517.19 260403 596920.19
Slab 1244.16 58.5 72783.36 213184.45 6561 219745.45
Total 2032.56 92296.26 816665.64
Note
Ac = Total area of composite section
Ac= Ab + flange area = 788.4 + 1244.16 = 2032.56 in.2
hc = Total height of composite section
hc = 54 + 9 = 63 in.
Ic = Moment of inertia about the centroid of the composite section
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
39
= 260403+788.4*(45.41-24.75)2 +6561+ 1244.16*(8.59+4.5)
2
= 260403+336517.19+6561+213184.45 in.4
= 816665.64 in4
ybc = Distance from the centroid of the composite section to extreme bottom fiber of the
precast girder, in. = 92296.26/2032.56 = 45.41 in.
ytg = Distance from the centroid of the composite section to extreme top fiber of the
precast girder, in. = 54 – 45.41 = 8.59 in.
ytc = Distance from the centroid of the composite section to extreme top fiber of the slab
= 63 – 45.41 = 17.59 in.
Sbc = Section modulus of composite section referenced to the extreme bottom fiber of the
precast girder, in.3 = Ic/ybc = 816665.64 /45.41 = 17984.27 in.3
Stg = Section modulus of composite section referenced to the top fiber of the precast
girder, in.3 = Ic/ytg = 816665.64 /8.59 = 95071.67in.3
Stc = Section modulus of composite section referenced to the top fiber of the slab, in.3
= Ic/ytc = 816665.64 /17.59 = 46427.84 in.3
Look the composite sectional drawing shown in the next page Fig. 6.
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
41
SHEAR FORCES AND BENDING MOMENTS
The self-weight of the girder and the weight of the slab act on the non-composite simple span
structure, while the weight of the barriers, future wearing surface, live load, and dynamic load
act on the composite simple span structure. [2]
Shear Forces and Bending Moments due to Dead Load
Dead Loads
Dead loads acting on the non-composite structure:
Self-weight of the girder = 0.821 kip/ft.
Weight of cast-in-place deck on each girder = (0.150kcf) (9 in.) (9 ft.)/ (12 in./ft.)
= 1.012 kips/ft.
Total dead load on non-composite section = 0.821 + 1.012 = 1.833 kips/ft.
Superimposed Dead Loads
The superimposed dead loads placed on the bridge, including loads from railing and wearing
surface can be distributed uniformly among all girders.
Weight of 0.5 in. wearing surface = 0.03 kips/ft2. This load is applied over the entire clear
roadway width of 39 ft.-0 in.
DFWS= (FWS)*9ft
= (0.03kip/ft2)*9ft
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
42
= 0.27 kip/ft. /girder
WC+P = (curb and parapet) for one girder
= 3.37ft2*(0.15kip/ft3)*2/5
= 0.202 kip/ft. / girder
Total superimposed dead load = 0.202(Wc+p) + 0.27(WD) = 0.472 kips/ft.
Wind load
Wind Forces (W and WL).
Wind forces are extremely complicated, but through a series of simplifications are reduced to an
equivalent static force applied uniformly over the exposed faces of the bridge (both super and
sub-structures) that are perpendicular to the longitudinal axis.
AASHTO specifies that the assumed wind velocity should be 100 mph. For a common slab-on-
stringer bridge this is usually a pressure of 50psf, and a minimum of 300p/lf. These forces are
applied at the center of gravity of the exposed regions of the structure.
AASHTO recommends the following for common slab-on-stringer bridges:
1) Wind force on structures (W): a) transverse loading = 50psf b) longitudinal loading = 12psf
2) Wind force on live load (WL): a) transverse loading = 100psf b) longitudinal loading = 40psf
The transverse and longitudinal loads are placed simultaneously for both the structure and the
live load (AASHTO 3.15.2.1.3).
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
43
Determine the wind load, Wsuper, on the superstructure transmitted to the substructure. For the
usual girder having span lengths less than 125ft, the transverse wind loading on the
superstructure can be taken as 50lbf/ft2, and the longitudinal wind loading can be taken as
12lbf/ft2. [AASHTO 3.15.2.1.3]
The height exposed to wind is
= 54 in (girder) + 9in (slab) + 32in (curb and parapet)
=95 in or 7.92ft
The longitudinal wind loading is
= 80 ft. * 7.92 ft. * 0.012 kip/ft2
= 7.6kips (at 7.92/2= 3.96 ft.)
The longitudinal (horizontal) wind loading of the superstructure is
WH= 7.6 kips/80ft
= 0.095 kips/ft. (including wind load on the girder)
The vertical wind loading of the superstructure is
= 7.6 kips*3.96ft/80ft
= 0.376 kips (including wind load on girder)
WV = 0.376 kips/ 80 ft. = 0.0047 kip/ft. [negligible]
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
44
The height exposed to wind is
= 54 in (girder) + 9in (slab) + 6ft (wind load on vehicle acts)
=11.25 ft.
The longitudinal wind loading is
= 80 ft. * 0.04 kip/ft.
= 3.2kips (at 11.25/2= 5.625 ft.)
The longitudinal (horizontal) wind loading of the superstructure is
WLH= 3.2 kips/80ft
= 0.04 kips/ ft. (including wind load on the girder)
The vertical wind loading of the superstructure is
WLV = 3.2 kips*3.96ft/80ft
= 0.079 kips (including wind load on girder)
the maximum lateral moment due to the factored wind loading is computed as follows:
M = WL2/10 =
A longitudinal force of 5% of the live load in all lanes is located 6ft above floor slab. For HS 25
loading, the longitudinal force is
= 3 lanes*[80ft*(0.64kip/ft.*1.25) +(26kips*1.25)]*0.05
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
45
= 14.475 kips
The horizontal force is
LFH = 14.475 kip/80 ft. =0.18 kip/ft.
Determine the live load distribution
[AASHTO 3.12.1]
The reduction in load intensity for three traffic lanes loaded is 90%. The transverse distribution
of wheel loads for beam design for an interior beam is
= S/5.5 [AASHTO Table 3.23.1]
= 9ft. /5.5 = 1.45
This distribution factor will be applied for HS loading.
Determine impact load [AASHTO 3.8.2]
I= 50/ (L+125) = 50/(80+125) = 0.244 [3]
Determine service loads moment and shear
The moment at mid span due to the weight of the beam is
M0 = WL2/8 = (0.821 * 80
2)/8 = 656.8 ft.-kips
The moment at mid span due to the slab dead load per beam is
MD = (WD*L2)/8 = (1.012*80
2)/8 = 809.6 ft.-kips
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
46
The moment mid span due to the superimposed dead load per beam is
Ms = WSL2/8 = (0.472*80
2)/8 = 377.6 ft.-kips
The maximum live load moment due to the HS 25 truck can be determined through the influence
line method.
The live load reaction at A is
= 40kips*(28.33ft. +42.33ft.) / 80ft. + (10kips*56.33 ft.) /80 ft.
= 42.37 kips
The live load moment, ML, is
= 42.37 kips*(14ft. + 23.67 ft.) - (10kips*14 ft.)
= 1456.07 ft.-kips for all wheels
The maximum live load moment with impact for each beam is
ML+ I = (1456.07 ft.-kips/2 wheel lines)*1.45*1.244
= 1313.23 ft.-kips
The maximum dead load shear is
VD= (0.821kip/ft. + 1.012kip/ft. + 0.472kip/ft.)*40ft.
= 92.12 kips at each support
The maximum live load shear due to the HS 25 truck is
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
47
40kips 40kips 10kips
14ft. 14 ft. 52ft.
Fig. 7 Maximum live load shear
The live load reaction at A is
= 40 kips + (40kips*(52 ft. + 14ft.) + 10kips*(52ft.))/80ft.
= 79.5 kips
For an HS lane loading
W=0.64 kips/ft *1.25 = 0.8 kips/ft
Axel load= 26 kips*1.25 = 32.5 kips
Max. R= 32.5 kips + 0.8*80/2 = 64.5 kips
Therefore, HS 25 truck loading controls the maximum reaction, which is 79.5kips/lane.
The maximum live load shear with impact for each beam is
VL+I = (79.5 kips/2 wheel lines)*1.45*1.244
= 71.7 kips
Factored loads are used for designing structural members using the load factor concept. Group
loading combinations for load factor design are given by [AASHTO 3.22.1A; and foot notes]
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
48
Group I =1.3(1D + (1.67) (L+I))
Group II =1.3(1D + 1W)
Group III =1.3(1D + 1L+0.3W+1WL)
Group IV =1.3(1D + 1L)
Group V =1.25(1D + 1W)
Group VI =1.25(1D + 1L+0.3W+1WL)
For the strength limit state, wind on the structure is considered for the Strength III and Strength
V Limit States. Due to the magnitude of the live load stresses, Strength III will clearly not
control for this design. Therefore, for this design, group I control the design factor load.
Calculate the factored moment and shear
Mu = 1.3(1D + (1.67) (L+I))
= 1.3*[656.8+809.6+377.6+ (1.67)*(1313.23)]
=5248.22 ft.-kips
Vu = 1.3(1D +1.67*(L+I))
= 1.3(92.12 kips + 1.67*(71.7kips))
= 275.42 kips
Allowable concrete stresses for I-beam girders [AASHTO 9.15.2]
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
49
[AASHTO 9.15.2.1 & 9.15.2.2]
Compression (pretension members) before losses due to creep and shrinkage,
fci=0.6 f’ci= 0.6*5500lbf/in2 = 3300psi
Tension (with no bonded reinforcement) before losses due to creep and shrinkage,
fti =200lbf/in2 or )
[AASHTO 9.15.2.2]
Compression stresses after losses, fcs= 0.4f’cg= 0.4*6500lbf/in2 = 2600lbf/in
2
Tension after losses, fts = ) = √ ) = 483.7 lbf/in2
For severe corrosive exposure conditions, fts= ) = 241.87 lbf/in2
Calculate pre-stress force and eccentricity
The temporary stress limits before losses due to creep and shrinkage are as follows.
For compression,
fcs= 0.4f’cg= 0.4*6500lbf/in2 = 2600lbf/in
2
For tension,
fts= ) = √ )= 556 lbf/in2
Allowable stresses after losses are as follows.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
50
For compression,
fcs= 0.4f’cg= 0.4*6500lbf/in2 = 2600lbf/in
2
For tension,
fts= )= √ )= 242 lbf/in2
N.B: A 25% loss of pre-stress force is assumed in the straight tendons. It will be assumed that the
critical stresses are the initial tensile stress at the top of the beam at the bearing and the final
tensile stress at the bottom of the beam at mid-span.
For initial tensile stress at the top of beam at bearing,
fti= Pi/Ab + Pie/St
Substituting values for the stresses and section properties gives
300 lbf/in2= -Pi/788.4 + Pi *e/8902.67 -------------------------------------------------------Equation 1.
For final tensile stress at the bottom of the beam at midspan,
fts = (-Pe/Ab) – (Pe* e/Sb) +( MO+D/Sb) +(( Ms+ML+I)/Sbc)
242= (-0.75Pi/ 788.4) – (0.75Pi*e/10,521.33) + [((656.8 ft.-kips+809.6 ft.-kips)/ 10,521.33) +
((377.6 kip- ft. +1313.23 kip- ft.) / 17984.27 in.3)]*12*1000 -----------------------------Equation 2.
Solving Equation 1 and 2 simultaneously gives
Pi=1,348,630 lbf; e= 13.27 in
[AASHTO 9.15.1] The amount of force taken by one ½ in, seven-wire strand at 70% of ultimate
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
51
stress f’s is
F=As*fsi
Where, fsi = 0.7*f’s
F= O.153 in2*0.7*270000 = 28920lbf
The number of strands required is
N = 1348630/28920 = 46.63 ≅ [USE 47 STRANDS]
For 47 strands, the initial pre-stressing force is
Pi = 28920lbf*47 = 1359240lbf
Try the following pattern
Number of strands 5 5 5 5 3 3 3 2 2 2 2 2 2 2 2 2
Distance from
bottom fiber
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32
Strand eccentricity at mid-span after strand arrangement
ec = 24.75 –[(5(2 + 4 + 6+8) +3(10+12+14)+ 2(16+18+20+22+24+26+28+30+32))/47]
= 24.75- 13.62 in. = 11.11 in
Look Fig. 8 cross sectional view drawing no.8 strand arrangement in the next page.
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
53
Check the assumed pre-stress loss
The loss of pre-stress will be determined using the modified Bureau of Public Roads formula.[1]
Total loss of pre-stress is
=6000lbf/in2 + 16fcs + 0.04fsi
fsi = 0.7*f’s = 0.7*270000 = 189,000 lbf/in2
fcs= Pi/Ab + (Pi*e2 – Mo*e)/IB
fcs=[1359240lbf / 788.4in2] +[ [(1359240kips*11.112) – (656.8 ft.-kips*12000*11.11in)]/
260403in4]
fcs=1724.05 + 308.02 = 2032.07lbf/in2
Total loss of pre-stress is
=6000lbf/in2 +16*2032.07lbf/in2 +0.04*189000lbf/in2 =46073.1lbf/in2
The percentage loss is =(46073.1/189000)*100% = 24.4% < 25% assumed; therefore minimum
loss of 25% assumed is conservative.
The effective pre-stress loss force after losses is
Pe = (1-0.25)*1359240lbf = 1019430lbf
Determine the critical stresses at support and mid-span
Initial stresses before losses at support for the basic beam section are
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
54
Pi/Ab = 1359240lbf/788.4 in2 = -1724.47lbf/in2 [compression]
Pi*e/St = 1359240lbf * 11.11in/8902.67 in3m= 1696.25lbf/in2 [tension]
Pi*e/Sb = 1359240lbf*11.11in / 10521.33 in3 = -1435.29lbf/in2 [compression]
Check the allowable stresses
[AASHTO 9.15.2.1 &9.15.2.2]
For compression at the beam base, allowable concrete stress = fci
Fci= 0.6*f’ci = 0.6*5500lbf/ in2 = 3300lbf/in2 [> -3159.76 lbf/in2 = (-1724.47-1435.29) lbf/in2,
ok]
For tension, to be conservative, allowable concrete stress fti lesser of 200lbf/in2 or
√ = 222.5 lbf/in2
fti=200lbf/in2 [>-28.22 lbf/in2 =( -1724.47+1696.25) lbf/in2]
Final stresses after losses at mid span are as follows.
The stress in the basic beam section at girder base is
= -Pe/Ab – Pe*e/Sb
= -1019430/788.4 – 1019430*11.11/10521.33
= -1293.04 – 1076.47
= -2369.51 lbf/in2 [compression]
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
55
The stress at the top of the girder is
f= -Pe/Ab + Pe*e/St
= -1293.04 + 1019430*11.11/8902.67
= -20.85lbf/in2 [compression]
Due to the beam and slab weight, the stress at the top of the girder is
=-MO+D/St = -((656.8 +809.6)/8902.67)*12*1000 = -1976.58lbf/in2 [compression]
The stress at the girder base is
= MO+D/Sb = -((656.8 +809.6)/10521.33)*12*1000 = 1672.49lbf/in2 [tension]
Due to the superimposed dead load (parapet and curb) plus live load, the stress in the composite
section at slab top is
f= -Ms+ML+I/Stc = - ((377.6 +1313.23)/ 46427.84)*12*1000 = -437.02lbf/in2 [compression]
The stress in the composite section at the girder base is
f=Ms+ML+I/Sbc = ((377.6 +1313.23)/ 17984.27)*12*1000 = 1128.21lbf/in2 [compression]
Check the allowable stresses in the girder after losses.
[AASHTO 9.15.2.2] For compression at the beam base, allowable concrete stress =
fcs= 0.4*f’cg = 0.4*5500lbf/ in2 = 2600lbf/in2 [> -2210.85lbf/in2 , ok]
[AASHTO 9.15.2.2] For tension,
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
56
fts= 6√(f’cg = 6√(6500 lbf)/in2 = 483.7lbf/in2(>431.19lbf/in2 ok)
Check the stress in the slab
[AASHTO 8.15.2.1.1] fcs allowable compressive stress in concrete (slab)
fcs= 0.4*f’cs= 0.4*4000 = 1600 lbf/in2
fslab = (Ms +ML+I)/Stc = -((377.6 +1313.23)/ 46427.84)*12*1000 = -437.02 lbf/in2
[compression]
[<1600lbf/in2, so ok]
Check moment capacity by Load factor design. First, determine whether the beam section is
flanged or rectangular.
[AASHTO 9.17.2] ⍺= As*f*su/0.85fc,slab b
f’c,slab= f’cs=4000lbf/in2
[AASHTO 9.17.4.1] f*su=average stress in pre-stressing steel at ultimate load
f*su=f’s(1-(ɤ/β1)(ρ*f’s/f’c))
[AASHTO 9.1.2] ɤ*= 0.4 for steel relieved steel [AASHTO 9.1.2]
[AASHTO 8.16.2.7] β1=0.85-0.05*(500/1000)=0.825 [AASHTO 8.16.2.7]
f’s=270000lbf/in2
ρ*=As/bd = 47*0.153/(108*(63-13.62)) = 0.00135
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
57
f*su=(270000lbf/in2)*(1-[(0.4/0.825)*(0.00135*270000/4000)])
= 258070.91lbf/in2
⍺= (47*0.153*258070.91)/(0.85*4000*108)
= 5.05 in
Since ⍺<9 in, the effective thickness of the slab, the beam is rectangular.
The moment capacity by load factor design is
ΦMn= Φ(A*sf*su d(1-0.6(ρ*fsu*/f’c))) [AASHTO 9.1.7.2]
[AASHTO 9.14] Φ=1 for flexure in pre-stressed concrete members for load factor design
ΦMn= 1(47*0.153*258070.91*(63-13.63)(1-0.6(0.00135*258070.91*/4000)))
= 104420290.04in-lbf
= 8701.69ft-kips
Determine the design moment by the load factor method (Group I loading)
Mu=1.3D + 2.17(L+I)
= 1.3(Mo+MD+Ms) + 2.17(ML+I)
= 1.3(656.8+809.6+377.6) + 2.17(1313.23)
= 5246.91 ft-kips [<ΦMn =8701.69ft-kips ok]
[AASHTO 9.18.1] The pre-stress steel’s reinforcement index cannot exceed 0.36β1.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
58
Ρ*f*su/f’c = 0.00135*258070.91/4000
= 0.087 [<0.36β1=0.36*0.825=0.297, ok]
Determine the minimum amount of pre-stressing steel that will be necessary.
[AASHTO 9.18.2] The total amount of pre-stressing reinforcement shall be adequate to develop
an ultimate moment at the critical section of at least 1.2 times the cracking moment M*cr.
ΦMn≥ 1.2 M*cr
M*cr= (fr+fpe)Sbc – Md/nc((Sc/Sb) -1)
Md/nc = non-composite dead load moment
= Mo + MD + Ms
= 656.8+809.6+377.6
= 1844 ft-kips
[AASHTO 9.15.2.3] fr= √ = = 604.67lbf/in2
fpe= Peffect/Ab + Peffect*e/Sb – Mo/Sb
Peffect = Pi*0.75 = (0.7f’sA*s)*0.75
= 0.7*270*0.153*42*0.75
= 910.89kips
fpe = 910.89/788.4 + 910.89*11.11/10521.33 – 656.8*12/10521.33
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
59
= 1.155 + 0.962 -0.749
= 1.37kips/in2
M*cr. = (0.6047+1.37)* 17984.27 – 1844*((17984.27 /10521.33) -1)
= 2959.46 – 1307.98
= 1651.48 ft-kips
1.2M*cr. = 1.2*1651.48 = 1981.776 ft.-kips [<ΦMn = 8701.69ft-kips, ok]
Design for shear
Shear design for straight fully bonded strands pre-stressed beams will be in accordance with
Article 9.20 of the AASHTO Specifications.
Vu ≤ Φ*(Vc + Vs) [AASHTO Equation 9-26]
The shear stress at the support is
The maximum live load and impact load shear is
VL+I= (79.5 kips/ 2 wheel lines)*1.45*1.244= 71.7kips
The maximum dead load shear is
VO+D+S = (0.821kip/ft. + 1.012kip/ft. + 0.472kip/ft.)*40ft.
= 92.12 kips at each support
Calculate shear stress at the quarter point
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
60
[AASHTO 9.20.2.1 & 9.20.2.2] The shear strength of concrete, Vc, shall be the lesser of Vci or
Vcw.
Vci= 0.6(√’fc) b’ d + Vd + ViMcr/Mmax
b’= 8in
d= yt+e= 29.25 in + 11.11 in = 40.39 in
From shear force diagram, since dead load is uniform, the shear force at quarter point equals half
of the support shear force.
Vd= ½(92.12) = 46.06 kips
The factored shear force due to externally applied loads occurring simultaneously with Mmax is
Vi= 1.3*1.67(L+I)
= 1.3*1.67*53.69
= 116.56 kips
Mcr = (Ic/yb)( 6√f’cg + fpe – fd)
Moments at quarter point are (Wo+WD = WL). For beam weight (W) and slab weight (WD),
MO+D = (WL/2)(L/4) – (WL/4)(L/8)
= WL2/8 – WL
2/32
= 3(WL) 2 /32
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
61
= (3/32)*(0.821 + 1.012)*802
= 1099.8 ft.-kips
For the superimposed dead load, Ws(parapet/curb),
Ms= (3/32)*(Ws) 2
= (3/32)*(0.472)* 802
= 283.2 ft-kips
fpe= 1.37 kips.in2
The stress due to the un-factor dead load at the quarter point in the beam span is
fd= (MO+D/Sb) + (Ms/Sbc)
= (1099.8/10521.33 + 283.2/17984.27)*12in/ft
= 1.44 kips/in2
Mcr = (816665.64 /45.41)*[( 6√6500 *1/1000) +1.37 – 1.44]*1/12
= 620.06 ft- kips
The maximum factored moment due to externally applied load at quarter point is
Mmax = ML+I
= 1.3*1.67(L+I)
= 2.17*(1012.73)
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
62
= 2197.62 ft.-kips
Vci= (0.6*(√6500)* 8*40.39)*1/1000 + 46.06 + 116.56*620.06/2197.62
= 15.63 + 46.06 + 32.89
= 94.58 kips
Vc = Vci = 94.58 kips
Vc, min = 1.7*√f’c *b’ *d
= 1.7*((√6500)*1/1000)*8*40.39
= 44.27 kips
d≥ 0.8h = 0.8*54 in = 43.2 in [ d=40.39 ≅ 0.8h, hence so close ok]
Vu ≤ Φ(Vc +Vs)
Vu= 1.3(1D +1.67(L+I))
= 1.3(46.06 + 1.67(53.69))
= 176.44 kips
For load factor design, Φ=0.9 for shear[AASHTO 9.14]
Vu/Φ = 176.44/0.9 = 196.04 kips
Vs= Vu/Φ – Vc = 196.04 – 94.58 = 101.46 kips
[AASHTO 9. 20.3.1] Check Vs ≤ 8*√f’cg b’ *d = 8*(√6500* 1/1000)*8*40.39 = 208.41 kips
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
63
Vs= 101.46 kips ≤ 208.41kips ok
For grade 60 No. 4 vertical stirrups, the spacing required
[AASHTO Equation 9-30] S = (Av * fsy * d) / Vs
= 0.4*60*40.39/ 101.46
= 9.55 in [use 10 in spacing]
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
64
3.2.2. Sub-structure Analysis and Design
DESIGN PARAMETERS
The abutments are a part of the substructure or foundation of the bridge. They act at end
supports. Abutments provide vertical support to the bridge and lateral support to the soil at the
ends of the roadway. The abutment has 16 ft. height and 42 ft. length, and it has spread footing
and no back wall. Assuming it has placed on gravel and sandy soil with a safe bearing capacity
of 8.5 kips/ft2. The density of the compacted earth fill is 120lbf/ft
3, and the lateral earth pressure
35lbf/ft3. The load that must be considered in this analysis are dead load, live load, earth
pressure, wind load on structure, wind load on live load, longitudinal force from live load, and
longitudinal friction load due to temperature. Centrifugal force does not exist for straight
structure. Whereas impact load and earthquake load are not considered. A live surcharge of 2ft.
of soil is placed on the bridge approach (AASHTO 3.20.3 and 5.5.2). Service loads are used in
determining if the abutment is safe against overturning about the toe of the footing, against
sliding on the footing base, and against crushing of the foundation material at the point of
maximum pressure.
3.2.2.1 Reinforced concrete Abutment and Footing
From AASHTO load combination for service load design for abutment and footing, group I, II,
III, IV, V, and VI will be the only ones considered in checking for stability and bearing pressure
for the abutment. Group I, II, III, IV, V, and VI factored load group are considered in designing
structural members using the load factor concept. In the next page Fig. 9 shows sectional view of
Abutment.
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
66
Dead loads of super structure on the abutment:
Self-weight of the girder = 0.821 kip/ft.
Weight of cast-in-place deck on each girder = (0.150kcf) (9 in.) (9 ft.) / (12 in./ft. )
= 1.012 kips/ft.
For the end block and diaphragm,
= 42ft*2.75ft*1.5ft*0.15kip/ft3
= 25.99 kip
Future wearing surface
DFWS= (FWS)*9ft
= (0.03kip/ft2)*9ft
= 0.27 kip/ft./girder
WC+P = (curb and parapet) for one girder
= 3.37ft2*(0.15kip/ft3)*2/5
= 0.202 kip/ft. / girder
Total dead load of super structure
=([0.821(beam) + 1.012(slab) + 0.27(wearing surface) + 0.202(curb and parapet)]*5*80/2) +
25.99(end block and diaphragm)
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
67
=486.99 kips
The dead load weight per foot of the abutment is
D= 486.99/42 =11.6 kips/ft.
Determine the live load weight on the superstructure. Use HS 25 loading.
The maximum live load shear due to the HS 25 truck (HS 20 loading x 1.25) is
40kips 40kips 10kips
14ft. 14 ft. 52ft.
The maximum live load reaction occurs due to truck loading
= 40 kips + (40kips*(52 ft. + 14ft.) + 10kips*(52ft.))/80ft.
= 79.5 kips/lane
For an HS lane loading
W=0.64 kips/ft. *1.25 = 0.8 kips/ft.
Axel load= 26 kips*1.25 = 32.5 kips
Max. R= 32.5 kips + 0.8*80/2 = 64.5 kips
Therefore, HS 25 truck loading controls the maximum reaction, which is 79.5kips/lane.
The maximum live load per foot of abutment
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
68
= (3lanes * 79.5 kips/lane)/42ft.
=5.68 kips/ft.
Determine the lateral earth pressure
An equivalent fluid weight of 35lbf/ft3
is assumed for determining the lateral earth pressure. The
effect of passive pressure due to soil in front of the abutment is neglected.
[AASHTO 3.20.3 &5.5.2] Alive load surcharge pressure equal to 2 ft. of earth will be added to
the approach.[1]
= 2ft*35lbf/ft3 = 70lbf/ft
2
A lateral pressure due to the earth back fill is
= (5.37ft + 16ft)*35lbf/ft3 = 747.95lbf/ft
2
The load due to earth and live load surcharge is as follows
Ls= 0.07*21.37 =1.5 kips/ft.
E = 0.5*0.748*21.23 = 7.98 kips/ft.
In the next page, Fig. 10 shows Sectional view of Live load and Earth pressure on Abutment.
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
70
Wind load (W and WL).
Wind forces are extremely complicated, but through a series of simplifications are reduced to an
equivalent static force applied uniformly over the exposed faces of the bridge (both super and
sub-structures) that are perpendicular to the longitudinal axis.
AASHTO specifies that the assumed wind velocity should be 100 mph. For a common slab-on-
stringer bridge this is usually a pressure of 50psf, and a minimum of 300 plf. These forces are
applied at the center of gravity of the exposed regions of the structure.
AASHTO recommends the following for common slab-on-stringer bridges:
1) Wind force on structures (W): a) transverse loading = 50psf b) longitudinal loading = 12psf
2) Wind force on live load (WL): a) transverse loading = 100psf b) longitudinal loading = 40psf
The transverse and longitudinal loads are placed simultaneously for both the structure and the
live load (AASHTO 3.15.2.1.3).
Determine the wind load, Wsuper, on the superstructure transmitted to the substructure. For the
usual girder having span lengths less than 125ft, the transverse wind loading on the
superstructure can be taken as 50lbf/ft2, and the longitudinal wind loading can be taken as
12lbf/ft2. [AASHTO 3.15.2.1.3]
The height exposed to wind is
= 54 in (girder) + 9in (slab) + 32in (curb and parapet)
=95 in or 7.92ft
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
71
The distance of the center of gravity of the superstructure area above the top of the abutment is
= (7.92ft/2) +0.12(bearing) = 4.08 ft
The longitudinal wind loading is
= 80 ft. * 7.92 ft. * 0.012 kip/ft2
= 7.6kips (at 7.92/2= 3.96 ft.)
This force transmitted to the substructure through the bearings.
[AASHTO 3.15.2.1.3] The longitudinal (horizontal) wind loading of the superstructure is
W super (H) = 7.6 kips/42ft abutment width
= 0.18 kips/ft
The vertical wind loading of the superstructure is
= 7.6 kips*4.08ft/80ft
= 0.388 kips (including wind load on girder)
Wsuper(V) = 0.388 kips/ 42 ft. = 0.009 kip/ft. [negligible]
[AASHTO 3.15.2.2] Determine the wind load on sub-structure, Wsub.
A wind loading of 40ft/ft2 will act perpendicular to the exposed stem of the abutment. The
horizontal wind loading at 10ft(= (12ft/2)+2ft+2ft) above the base of the abutment footing is
Wsub(H)= (0.04kip/ft2)*12ft = 0.48kip/ft. [exposed stem=12ft]
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
72
[AASHTO 3.15.3] Determine the upward wind load, Wup.
The upward force will be 20 lbf/ft2 of horizontal area for group II and V combinations and 6
lbf/ft2 for group III and VI combinations.
For group II and V, the uplift is
Wup= (80ft*39ft*0.02kip/ft2)/(2*42) = 0.743kip/ft
Whereas, roadway width =39ft
Slab width= 42ft = abutment width
Overall beam length = 80ft\
For groups III and VI, the uplift is
Wup= (80ft*39ft*0.006kip/ft2)/(2*42) =0.222 kip/ft
[AASHTO 3.15.2.1.2 & 8.3.15.2.1.3] Determine the wind load, WL, transmitted to the
substructure by the wind load on the moving live load.
The longitudinal wind loading on the live load is taken as 0.04 kip/ft and acts at a point 6ft.
above the deck.
The height exposed to wind is
= 54 in (girder) + 9in (slab) + 6ft (wind load on vehicle acts)+ 0.12(bearing)
=11.37 ft
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
73
The longitudinal wind loading is
= 80 ft. * 0.04 kip/ft
= 3.2kips (at 11.37/2= 5.685 ft.)
The longitudinal (horizontal) wind loading of the superstructure transmitted through bearing.
The reaction at support
= 3.2kips*11.37/80ft = 0.455kip
The horizontal wind loading at the top of the abutment,
WLH= 3.2 kips/42ft
= 0.076 kips/ ft. (including wind load on the girder)
The vertical wind loading at the top of the abutment is
WLV = 0.455 kips/42ft
= 0.011 kips/ft width
[AASHTO Fig. 3.7.6B & 8.3.9] A longitudinal force of 5% of the live load in all lanes is located
6ft above floor slab. For HS 25 loading, the longitudinal force is
= 3 lanes*[80ft*(0.64kip/ft*1.25)+(26kips*1.25)]*0.05
= 14.475 kips
The horizontal force is
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
74
LFH = 14.475 kip/42 ft. =0.345 kip/ft.
The reaction at support is
= 14.475*11.37/80 = 2.057kips
The vertical force at the top of the abutment is
LFV= 2.057/42 = 0.049 kip/ft width [negligible]
[AASHTO 3.16] Determine the temperature force, Tf, due to friction.
The longitudinal force due to friction at expansion bearings, which is transmitted to both
abutments through the superstructure, is assumed to be 10% (coefficient of friction) of the dead
load reaction.
The friction force is
Tf =( 0.1)*(6.55 kips/ft)= 0.655kip/ft.
The service loads and moments due to the loads are summarized in Table 1.
Perform a stability analysis and bearing pressure check (service load design).
[AASHTO 3.3.6] The density of the normal weight concrete is 150lbf/ft3. The density of the
compacted earth fill is 120lbf/ft3. To compensate for incidental field adjustments in the location
of bearings, a 2 in longitudinal eccentricity from the theoretical centerline of bearing will be
used.
Ls= lateral pressure from 2 ft of soil for live load surcharge
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
75
= 2 ft.*0.035kip/ft3 * 21.37ft
=1.5kips/ft.
E= lateral earth pressure
= 21.37ft*0.035kip/ft3*21.37ft*0.5
= 7.98kips/ft.
To create the maximum pressure under the toe and the minimum pressure under the heel of the
footing, an eccentricity of 2in to the left for vertical forces will be used.
Check against sliding and overturning.
The factor of safety against sliding is
[AASHTO 5.5.5 & Table 5.5.2B]
FSs= f*∑V/∑H= 0.6*∑V/∑H≥1.5 [Assuming friction factor of 0.6]
The minimum factor of safety against sliding is 1.5.
The factor of safety against overturning is 2 for footings set on soil.
The location of the resultant soil pressure from the toe is given by
Ẋ= ((∑Mv,toe - ∑MH)/∑V)
The eccentricity of the resultant soil pressure is given by
eB= (B/2)-Ẋ
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
76
For eB < B/6, the pressure under the footing is given by
qt=(∑V/B)(1+(6*eB/B)) at toe
qt=(∑V/B)(1-(6*eB/B)) at heel
[AASHTO 5.5.5 & 4.4.7] For footing set on soil, the location of the resultant soil pressure should
be with in the middle one-third of the base.
The safe bearing capacity of the gravel sand foundation material is assumed to be 8.5 kips/ft2.
Table 3 shows service loads and service load moments at the toe of the footing in the next page.
Table 4 shows stability and bearing pressure in the next pressure.
The minimum values of the factor of safety against sliding and overturning from Table 4 are:
FSs, min= 2.11 from group V loading [>1.5, ok]
FSo, min= 2.43 from group VI loading [>2, ok]
The eccentricity of the resultant soil pressure, ∑V, is
eB, max = 2.24 ft from group VI loading [> B/6 = 11/6=1.83FT]
Check soil pressure qt, max = 8.16 kips/ft2 from group VI loading
[<safe bearing capacity = 8.5 kips/ft, ok]
V Lever arm from toe Mv, toe
calculation kips/ft ft ft-kips/ft
1.00 concrete D 11*2*0.15 3.30 5.50 18.15
2.00 concrete D 14*1.5*0.15 3.15 3.75 11.81
3.00 concrete D 0.5*14*1.17*0.15 1.23 4.89 6.01
4.00 soil E 0.5*14*1.17*0.12 0.98 5.28 5.19
5.00 soil E 14*5.33*0.12 8.95 8.33 74.59
6.00 soil E 6.5*5.37*0.12 4.19 7.75 32.46
7.00 live load surcharge Ls 6.5*2*0.12 1.56 7.75 12.09
8.00 superstructure D 11.60 3.75 43.50
9.00 live load L 5.68 3.75 21.30
10.00 wind upward Wup group II &V -0.74 3.75 -2.79
0.3Wup group III &VI -0.22 3.75 -0.84
load type H
Lever arm from
footing base Mv, toe
kips/ft ft ft-kips/ft
11.00 LS Live load surcharge 1.50 10.69 16.03
12.00 E 7.98 7.12 56.82
13.00 LF 0.35 16.00 5.52
14.00 Tf 0.66 16.00 10.48
15.00 WLH 0.08 16.00 1.22
16.00 Wsuper(H) group II &V 0.18 16.00 2.88
17.00 0.3Wsuper(H) group III &VI 0.05 16.00 0.86
18.00 Wsub group II &V 0.48 10.00 4.80
19.00 0.3Wsub group III &VI 0.14 10.00 1.44
Group
loading ∑V ∑H ∑Mv, toe ∑M H FSs Fso Ẋ eb qt qh
kips kips ft-kips/ft ft-kips/ft
I 40.64 9.48 225.10 72.85 2.57 3.09 3.75 1.75 7.23 0.16
II 32.66 8.64 188.92 64.50 2.27 2.93 3.81 1.69 5.71 0.23
III 40.42 10.10 224.26 81.89 2.40 2.74 3.52 1.98 7.64 -0.29
IV 40.64 10.14 225.10 83.33 2.41 2.70 3.49 2.01 7.75 -0.36
V 32.66 9.30 188.92 74.98 2.11 2.52 3.49 2.01 6.23 -0.29
VI 40.42 10.75 224.26 92.37 2.26 2.43 3.26 2.24 8.16 -0.81
Item
Number
Item
Number
Table 1. Summary of sercice loads and moments
(at the toe of footing, Mv and MH)
Table 2 Stability and Bearing Pressures
Vertical Loads
Description
load type
Horizontal Loads
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
78
3.2.2.1 Analyze and design for footing (Load factor design)
Factored loads and moments resulting from the factored loads are given in Tables 5-8 .The
factored bearing pressure under the footing at toe qt and heel qh for various group loading
combinations are summarized in Table 9.
Group I loading is critical for the toe of the footing. The factored shear and moment at the front
of the stem for this loading are assuming d=21.37in or 1.63 ft
Vu= (((10.94+9.55)/2)-0.39)*(3-1.63)
= 13.5kips/ft [at a distance d from the face of the stem]
Mu= (((7.9-0.39)*3*1.5 + 0.5*(10.94-7.9)*3*2
= 52.035 ft-kips/ft
Design the footing using strength criteria for concrete and steel of f’c=3000lbf/in2 and Fy =
60000lbf/in2.
[AASHTO 8.16.2.7 & 8.16.3] Calculate the maximum and minimum steel reinforcement
ρb= ((0.85β1f’c/Fy)*(87000/(87000+Fy))
= ((0.85*0.85*3000/60000)*(87000/ (87000+60000))
= 0.02138
ρmax= 0.75*ρb = 0.75*0.02138 = 0.016
V
Lever arm
from toe
calculation kips/ft ft I II III IV V VI
1.00 concrete D 11*2*0.15 3.30 5.50 4.29 4.29 4.29 4.29 4.13 4.13
2.00 concrete D 14*1.5*0.15 3.15 3.75 4.10 4.10 4.10 4.10 3.94 3.94
3.00 concrete D 0.5*14*1.17*0.15 1.23 4.89 1.60 1.60 1.60 1.60 1.54 1.54
4.00 soil E 0.5*14*1.17*0.12 0.98 5.28 1.28 1.28 1.28 1.28 1.23 1.23
5.00 soil E 14*5.33*0.12 8.95 8.33 11.64 11.64 11.64 11.64 11.19 11.19
6.00 soil E 6.5*5.37*0.12 4.19 7.75 5.45 5.45 5.45 5.45 5.24 5.24
7.00
live load
surcharge Ls 6.5*2*0.12 1.56 7.75 3.39 2.03 2.03 1.95
8.00 superstructure D 11.60 3.75 15.08 15.08 15.08 15.08 14.50 14.50
9.00 live load L 5.68 3.75 12.33 7.38 7.38 7.10
10.00 wind upward Wup group II &V -0.74 3.75 -0.97 -0.29 -0.93 -0.28
∑V 59.14 42.46 52.55 52.84 40.83 50.53
V
Lever arm
from toe
calculation kips/ft ft I II III IV V VI
1.00 concrete D 11*2*0.15 3.30 5.50 23.60 23.60 23.60 23.60 22.69 22.69
2.00 concrete D 14*1.5*0.15 3.15 3.75 15.36 15.36 15.36 15.36 14.77 14.77
3.00 concrete D 0.5*14*1.17*0.15 1.23 4.89 7.81 7.81 7.81 7.81 7.51 7.51
4.00 soil E 0.5*14*1.17*0.12 0.98 5.28 6.75 6.75 6.75 6.75 6.49 6.49
5.00 soil E 14*5.33*0.12 8.95 8.33 96.97 96.97 96.97 96.97 93.24 93.24
6.00 soil E 6.5*5.37*0.12 4.19 7.75 42.20 42.20 42.20 42.20 40.58 40.58
7.00
live load
surcharge Ls 6.5*2*0.12 1.56 7.75 26.25 0.00 15.72 15.72 0.00 15.11
8.00 superstructure D 11.60 3.75 56.55 56.55 56.55 56.55 54.38 54.38
9.00 live load L 5.68 3.75 46.24 0.00 27.69 27.69 0.00 26.63
10.00 wind upward Wup group II &V -0.74 3.75 0.00 -3.62 -1.09 0.00 -3.48 -1.04
∑V 321.71 245.60 291.54 292.63 236.16 280.33
Table 3. Factored Vertical Loads
Description
load type
Table 4. Moment resulted from Factored Vertical Loads
Description
Item
Number
Factored V(kips/ft)
Item
Number
Factored Mv, toe(ft-kips/ft)
load type
load type service lever arm I II III IV V VI
11.00 LS Live load surcharge 1.50 10.69 3.26 1.95 1.95 1.88
12.00 E 7.99 7.12 10.39 10.39 10.39 10.39 9.99 9.99
13.00 LF 0.35 16.00 0.45 0.43
14.00 Tf 0.66 16.00 0.85 0.82 0.82
15.00 WLH 0.08 16.00 0.10 0.10
16.00 Wsuper(H) group II &V 0.18 16.00 0.23 0.07 0.23 0.07
18.00 Wsub group II &V 0.48 10.00 0.62 0.19 0.60 0.18
∑H 13.64 11.25 13.14 13.19 11.63 13.46
load type service lever arm I II III IV V VI
11.00 LS Live load surcharge 1.50 10.69 34.80 20.84 20.84 20.03
12.00 E 7.98 7.12 73.96 73.96 73.96 73.96 71.11 71.11
13.00 LF 0.35 16.00 7.18 6.90
14.00 Tf 0.66 16.00 13.62 13.10 13.10
15.00 WLH 0.08 16.00 1.58 1.52
16.00 Wsuper(H) group II &V 0.18 16.00 3.74 1.12 3.60 1.08
18.00 Wsub group II &V 0.48 10.00 6.24 1.87 6.00 1.80
∑MH 108.75 83.94 106.54 108.42 93.81 115.55
Group
loading ∑V ∑H ∑Mv, toe ∑M H FSs Fso Ẋ eb qt qh
kips kips ft-kips/ft ft-kips/ft
I 59.14 13.64 321.71 108.75 2.60 2.96 3.60 1.90 10.95 -0.19
II 42.46 11.25 245.60 83.94 2.27 2.93 3.81 1.69 7.42 0.30
III 52.55 13.14 291.54 106.54 2.40 2.74 3.52 1.98 9.93 -0.38
IV 52.84 13.19 292.63 108.42 2.40 2.70 3.49 2.01 10.08 -0.47
V 40.83 11.63 236.16 93.81 2.11 2.52 3.49 2.01 7.79 -0.36
VI 50.53 13.46 280.33 115.55 2.25 2.43 3.26 2.24 10.20 -1.02
Table 7 Factored Bearing Pressures
Item
Number
Factored Mv, toe(ft-kips/ft)
Item
Number
Factored V(kips/ft)
5. Factored Horizontal Loads
6. Moment resulted from Factored Horizontal Loads
description
description
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
82
3.2.2.1.1 Design for the toe.
It will be safe and conservative to neglect compression reinforcement in the design calculation.
For a singly reinforced section, the ultimate moment is
ΦMn = ΦAsFy(d-(⍺/2))
[AASHTO 8.16.1.2.2] Φ=0.9 for flexure
⍺= ((As*Fy)/ (0.85*f’c*b))
[AASHTO 8.22.1] Use d= 24in- 4 in cover – 0.5 in for 0.5 diameter of steel assumed =
19.5 in.
⍺= ((As*60)/(0.85*3*12))= 1.96 As
⍺/2 = 0.98As
Mu = ΦMn
(52.035 ft-kip/ft)*12 in/ft = 0.9 As*60(19.5in- 0.98As)
As2 – 19.9As + 11.8 = 0
As=19.29 in2 or 0.61 in2 [Since As should be less than 1, As=0.61 in2 is correct answer]
ρ= As/bd = 0.61/12*19.5 = 0.0026 [<ρmax = 0.016 ok]
Use #8@15 in( As= 0.62in2)
Check minimum steel
[AASHTO 8.17.1] The minimum reinforcement provided shall be adequate to develop a factored
moment capacity at least 1.2 times the cracking moment, unless the area of reinforcement
provided is at least one third greater than that required by analysis.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
83
ΦMn ≥ 1.2Mcr
⍺= ((0.62*60)/(0.85*3*12)) = 1.216 in
⍺/2 = 0.608 in
ΦMn = 0.9*0.62*60*(19.5-0.608)/12 =52.71ft-kips/ft
The cracking moment, Mcr, is determined by the transformed area method.
Mcr = fr*I/ c
fr=modulus of rupture= 7.5(√fc') for normal weight concrete wc=150 lbf/ft3
fc= 4000lbf/in2
I= Icg= moment of inertia
c= distance from centroid axis to extreme fiber in tension
[AASHTO 8.7.1 & 8.7.2] Ec = 33*wc 1.5
(√fc')
= 33 1501.5
(√3000)
= 3,320,560.95lbf/in2
Es = 29,000,000 lbf/in2
n= 29,000,000 / 3,320,560.95 = 8.7 ≅ 9
The transformed area is
(n-1)*As= (9-1)*0.62 = 4.96 in2
Ac +As = 12*24 + 4.96 = 292.96 in2
Taking moment about the bottom and solving the equation,
292.96*yb = 288*12 +4.96*4.5
yb = 11.87in from bottom
The moment of inertia about the neutral axis is
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
84
Icg= (1/12)(12*243) + 288*(12-11.87)
2 + 4.96(11.87 – 4.5)
2 = 14100 in4
[AASHTO 8.15.2.1.1] fr=modulus of rupture= 7.5(√fc') = 7.5(√3000) =410.79lbf/in2
Mcr = fr*I/ c = (0.411*14100/11.87) /(12) = 40.68 ft.-kips/ft.
1.2Mcr = 1.2*40.68 = 48.82 ft.-kips/ft. [< ΦMn = 52.71 ft- kips/ft., ok]
Use #8@ 15 in.
[AASHTO 8.16.1.2.2 & Equation 8-49] Check shear at a distance d from the face of the stem.
The ultimate shear capacity without shear reinforcement is
ΦVc=Φ*2(√fc') *bw*d
= 0.85*2(√3000) *12*19.5 in
= 21788.4 lbf [> Vu from group I loading (=13.5kips/ft.) at a distance d from face of stem,
ok]
3.2.2.1.2 Design for the heel
Group VI loading is critical for the heel of the footing. The factored shear and moment at the
back of the stem for this loading are as follows.
w=1.25(21.35ft)(0.12) + 2ft* 0.15= 3.506
Vu = (3.506kips/ft2)*5.33ft – 0.5*4.424*4.341
= 9.082 kips/ft
Mu =3.506*4.341*2.67 – 0.5*4.424*4.341*(4.341/3)
= 26.74 ft-kips/ft
[AASHTO 8.22.1] For the heel steel design, use d= 24-3-0.5in for ½ diameter of steel
assumed=20.5in
⍺= ((As*60)/(0.85*3*12)) = 1.96As
⍺/2 = 0.98As
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
85
The moment in the heel at the back of the stem from group VI loading was 26.74ft-kips/ft
Mu = ΦMn = ΦAsFy(d-(⍺/2))
26.74ft-kips*12in/ft = 0.9*As*60*(20.5-0.98As)
As2 – 20.918As + 6.063 = 0
As= 20.624 in2 or 0.294 in2
As= 0.294 in2/ft
ρ= 0.294/12*20.5 = 0.0012[<ρmax = 0.016 ok]
Try 7@16in, As= 0.45 in2
Check minimum steel
⍺= ((0.45*60)/(0.85*3*12)) = 0.882 in
⍺/2 = 0.441 in
ΦMn = 0.9*0.45*60*(20.5-0.441)/12 =40.62ft-kips/ft
The transformed area is
(n-1)*As= (9-1)*0.45 = 3.6 in2
Ac +As = 12*24 + 3.6 = 291.6 in2
Taking moment about the top and solving the equation,
291.6*yt = 288*12 +3.6*3.5
yb = 11.895 in from top
The moment of inertia about the neutral axis is
Icg= (1/12)(12*243) + 288*(12-11.895)
2 + 3.6(11.895 – 3.5)
2 = 14080.89 in
4
fr=modulus of rupture= 7.5(√fc') = 7.5(√3000) =410.79 lbf/in2
Mcr = fr*I/ c = (0.411*14080.89/11.895) / (12) = 40.54 ft-kips/ft
1.2Mcr = 1.2*40.54 = 48.65 ft-kips/ft [> ΦMn = 40.62 ft- kips/ft, not ok, increase the amount of
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
86
stee]
Try #8@ 15 in., As =0.62 in2
⍺= ((0.62*60)/(0.85*3*12)) = 1.216 in
⍺/2 = 0.608 in
Mu = ΦMn = ΦAsFy(d-(⍺/2))
= 0.9*0.62*60*(20.5-0.608)
= 55.5 ft-kips/ft
The transformed area is
(n-1)*As= (9-1)*0.62 = 4.96 in2
Ac +As = 12*24 + 4.96 = 292.96 in2
Taking moment about the top and solving the equation,
292.96*yt = 288*12 +4.96*3.5
yb = 11.86 in from top
The moment of inertia about the neutral axis is
Icg= (1/12)(12*243) + 288*(12-11.86)2 + 4.96*(11.86 – 3.5)2 = 14176.3 in4
fr=modulus of rupture= 7.5(√fc') = 7.5(√3000) =410.79 lbf/in2
Mcr = fr*I/ c = (0.411*14176.3/11.86) /(12) = 40.94 ft-kips/ft
1.2Mcr = 1.2*40.94 = 49.13 ft-kips/ft [< ΦMn = 55.5 ft- kips/ft, ok]
Use 8@15 in, As= 0.62 in2
Check shear in the heel at the back of the stem. The ultimate shear capacity without shear
reinforcement is [AASHTO 8.16.1.2.2]
ΦVc=Φ*2(√fc') *bw*d
= 0.85*2(√3000) *12*20.5 = 22900lbf/ft = 22.9 kips/ft [> Vu from group VI loading
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
87
(=9.082kips/ft) at a distance d from face of stem, ok]
3.2.2.1.3 Design for stem
Analyze for the stem
The stem will be designed for combined axial load and bending. To compensate for incidental
field adjustments in the location of bearings for for vertical loads, a 2in longitudinal eccentricity
from the theoretical centerline of bearing will be used. This 2 in eccentricity will produce the
maximum or minimum moment at the stem base.[1]
Determine the minimum axial load and maximum moment with a 2 in eccentricity toward the
stem front face from the bearing point as follows.
Factored loads are used for designing structural members using the load factor concept. Group
loading combinations for load factor design are given by AASHTO 3.22.1A; and foot notes
βD = 0.75 because of designing members for minimum axial load and maximum moment, and
βE = 0.75 for lateral earth pressure.
Group I =1.3(0.75*D +0.75EVERTICAL+ 1.67(L+LS) +1.3ELATERAL)
Group II =1.3(0.75*D +0.75EVERTICAL+ 1W +1.3ELATERAL)
Group III =1.3(0.75*D +0.75EVERTICAL+ 1L+LS+0.3W+1WL+1.3ELATERAL +1LF)
Group IV =1.3(0.75*D +0.75EVERTICAL +1L+LS +1T+1.3ELATERAL)
Group V =1.25(0.75*D +0.75EVERTICAL+ 1W+1W +1T+0.75ELATERAL)
Group VI =1.25(0.75*D +0.75EVERTICAL+ 1L+LS +0.3W+1WL+1T+0.75ELATERAL +1LF)
The minimum axial load and corresponding moment are
∑V= Pu= 15.68 kips/ft see Table
∑M = Mu= 95.51 ft- kips/ft see Table
The maximum moment and corresponding axial load are
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
88
∑V= Pu= 23.78 kips/ft see Table
∑M = Mu= 119.34 ft- kips/ft see Table
The maximum shear is
∑H= Vu= 14.06 kips/ft see Table
Determine the maximum axial load and minimum moment with a 2 in eccentricity toward the
stem rear face from the bearing point. [AASHTO Table 3.22.1A]
βD = 1 because of designing members for maximum axial load and minimum moment, and
βE = 1 for vertical earth pressure
βE = 0.75 for lateral earth pressure.
Group I =1.3(1D +1EVERTICAL+ 1.67(L+LS) +1.3ELATERAL)
Group II =1.3(1D +1EVERTICAL+ 1W +1.3ELATERAL)
Group III =1.3(1D +1EVERTICAL+ 1L+LS+0.3W+1WL+1.3ELATERAL +1LF)
Group IV =1.3(1D +1EVERTICAL +1L+LS +1T+1.3ELATERAL)
Group V =1.25(1D +1EVERTICAL+ 1W +1T+1.3ELATERAL)
Group VI =1.25(1D +1EVERTICAL+ 1L+LS +0.3W+1WL+1T+1.3ELATERAL +1LF)
The maximum axial load and corresponding moment are
∑V= Pu= 35.97 kips/ft see Table
∑M = Mu= 110.94 ft- kips/ft see Table
The minimum moment and corresponding axial load are
∑V= Pu= 21.22 kips/ft see Table
∑M = Mu= 54.82 ft- kips/ft see Table
The maximum shear is
∑H= Vu= 14.06 kips/ft see Table
V
Lever arm from center
of stem base
Description kips/ft ft I II III IV V VI
2 concrete D 14*1.5*0.15 3.15 0.58 3.07 3.07 3.07 3.07 2.95 2.95
3 concrete D 0.5*14*1.17*0.15 1.23 -0.56 1.20 1.20 1.20 1.20 1.15 1.15
4 soil E 0.5*14*1.17*0.12 0.98 -0.94 0.96 0.96 0.96 0.96 0.92 0.92
5 soil E 5.37*1.17*0.12 0.75 -0.75 0.74 0.74 0.74 0.74 0.71 0.71
7
live load
surcharge Ls 1.7*2*0.12 0.28 -0.75 0.61 0.37 0.37 0.35
8 superstructure D 11.60 0.75 11.31 11.31 11.31 11.31 10.88 10.88
9 live load L 5.68 0.75 12.33 7.38 7.38 7.10
10 wind upward Wup group II &V -0.74 0.75 -0.97 -0.29 -0.93 -0.28
∑V 30.21 16.31 24.73 25.02 15.68 23.78
service lever arm I II III IV V VI
11 LS Live load surcharge 1.36 9.69 2.95 1.77 1.77 1.70
12 E Lateral 6.57 6.46 11.10 11.10 11.10 11.10 10.68 10.68
13 LF 0.35 14.00 0.45 0.43
14 Tf 0.66 14.00 0.85 0.82 0.82
15 WLH 0.08 14.00 0.10 0.10
16 Wsuper(H)group II &V 0.18 14.00 0.23 0.07 0.23 0.07
18 Wsub group II &V 0.48 8.00 0.62 0.19 0.60 0.18
∑H 14.06 11.96 13.68 13.72 12.32 13.97
V
Lever arm from center
of stem base
kips/ft ft I II III IV V VI
2 concrete D 14*1.5*0.15 3.15 0.58 1.78 1.78 1.78 1.78 1.71 1.71
3 concrete D 0.5*14*1.17*0.15 1.23 -0.56 -0.67 -0.67 -0.67 -0.67 -0.64 -0.64
4 soil E 0.5*14*1.17*0.12 0.98 -0.94 -0.90 -0.90 -0.90 -0.90 -0.87 -0.87
5 soil E 5.37*1.17*0.12 0.75 -0.75 -0.55 -0.55 -0.55 -0.55 -0.53 -0.53
7
live load
surcharge Ls 1.7*2*0.12 0.28 -0.75 -0.46 -0.27 -0.27 -0.26
8 superstructure D 11.60 0.75 8.48 8.48 8.48 8.48 8.16 8.16
9 live load L 5.68 0.75 9.25 5.54 5.54 5.33
10 wind upward Wup group II &V -0.74 0.75 -0.72 -0.22 0.00 -0.70 -0.21
∑V 16.93 7.42 13.19 13.41 7.13 12.68
service lever arm I II III IV V VI
11 LS Live load surcharge 1.36 9.69 28.61 17.13 17.13 16.47
12 E Lateral 6.57 6.46 71.73 71.73 71.73 71.73 68.97 68.97
13 LF 0.35 14.00 6.28 6.04
14 Tf 0.66 14.00 11.92 11.46 11.46
15 WLH 0.08 14.00 1.38 1.33
16 Wsuper(H)group II &V 0.18 14.00 3.28 0.98 3.15 0.95
18 Wsub group II &V 0.48 8.00 4.99 1.50 4.80 1.44
∑H 100.34 80.00 99.00 100.78 88.38 106.66
∑Total Moment stem 117.27 87.41 112.19 114.19 95.51 119.34
Table 8. Factored vertical loads
Table 9. Factored Horizontal Loads
Table 10. Factored Moment at stem base resulting from Vertical and Horizontal Loads
Description
Description
Item
Number
Factored Moment V(kips/ft)
Item
Number
Factored V(kips/ft)
Item
Number
Factored H(kips/ft)
Item
Number
Factored Moment V(kips/ft)
V
Lever arm from center
of stem base
kips/ft ft I II III IV V VI
2.00 concrete D 14*1.5*0.15 3.15 0.58 4.10 4.10 4.10 4.10 3.94 3.94
3.00 concrete D 0.5*14*1.17*0.15 1.23 -0.56 1.60 1.60 1.60 1.60 1.54 1.54
4.00 soil E 0.5*14*1.17*0.12 0.98 -0.94 1.28 1.28 1.28 1.28 1.23 1.23
5.00 soil E 5.37*1.17*0.12 0.75 -0.75 0.98 0.98 0.98 0.98 0.94 0.94
7.00
live load
surcharge Ls 1.7*2*0.12 0.28 -0.75 0.61 0.37 0.37 0.35
8.00 superstructure D 11.60 0.42 15.08 15.08 15.08 15.08 14.50 14.50
9.00 live load L 5.68 0.42 12.33 7.38 7.38 7.10
10.00 wind upward Wup group II &V -0.74 0.42 -0.97 -0.29 -0.93 -0.28
∑V 35.97 22.06 30.49 30.78 21.22 29.32
service lever arm I II III IV V VI
11.00 LS Live load surcharge 1.36 9.69 2.95 1.77 1.77 1.70
12.00 E 6.57 6.46 11.10 11.10 11.10 11.10 10.68 10.68
13.00 LF -0.35 14.00 -0.45 -0.43
14.00 Tf -0.66 14.00 -0.85 -0.82 -0.82
15.00 WLH -0.08 14.00 -0.10 -0.10
16.00 Wsuper(H) group II &V -0.18 14.00 -0.23 -0.07 -0.23 -0.07
18.00 Wsub group II &V -0.48 8.00 -0.62 -0.19 -0.60 -0.18
∑H 14.06 10.25 12.07 12.02 9.03 10.78
V
Lever arm from center
of stem base
kips/ft ft I II III IV V VI
2.00 concrete D 14*1.5*0.15 3.15 0.58 2.38 2.38 2.38 2.38 2.28 2.28
3.00 concrete D 0.5*14*1.17*0.15 1.23 -0.56 -0.89 -0.89 -0.89 -0.89 -0.86 -0.86
4.00 soil E 0.5*14*1.17*0.12 0.98 -0.94 -1.20 -1.20 -1.20 -1.20 -1.15 -1.15
5.00 soil E 5.37*1.17*0.12 0.75 -0.75 -0.74 -0.74 -0.74 -0.74 -0.71 -0.71
7.00
live load
surcharge Ls 1.7*2*0.12 0.28 -0.75 -0.46 -0.27 -0.27 -0.26
8.00 superstructure D 11.60 0.42 6.33 6.33 6.33 6.33 6.09 6.09
9.00 live load L 5.68 0.42 5.18 3.10 3.10 2.98
10.00 wind upward Wup group II &V -0.74 0.42 -0.41 -0.12 -0.39 -0.12
10.60 5.47 8.58 8.71 5.26 8.25
H
service lever arm I II III IV V VI
11.00 1.36 9.69 28.61 0.00 17.13 17.13 0.00 16.47
12.00 E 6.57 6.46 71.73 71.73 71.73 71.73 68.97 68.97
13.00 LF 0.35 14.00 -6.28 -6.04
14.00 Tf 0.66 14.00 -11.92 -11.46 -11.46
15.00 WLH 0.08 14.00 -1.38 -1.33
16.00 Wsuper(H) group II &V 0.18 14.00 -3.28 -0.98 -3.15 -0.95
18.00 Wsub group II &V 0.48 8.00 -4.99 -1.50 -4.80 -1.44
100.34 63.46 78.72 76.94 49.56 64.23
110.94 68.93 87.30 85.64 54.82 72.48
∑H moment
∑Total Moment stem
Table 11. Factored Vertical Loads
Description
Description
Description
Description
Table 12. Factored Horizontal Loads
Table 13. Factored Moment at stem base resulting from Vertical and Horizontal Loads
∑V moment
Item
Number
Factored Moment H(kips/ft)
Item
Number
Factored V(kips/ft)
Item
Number
Factored H(kips/ft)
Item
Number
Factored Moment V(kips/ft)
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
91
Design for stem f’c= 3000 lbf/in2 and Fy= 60000lbf/in
2
Reinforcement for stem will be designed for bending only as a singly reinforced beam. The
section will then be checked for combined axial force and bending, neglecting the front faces
reinforcing steel.
Use d= 32in – 3 in cover – 0.5 in for ½ steel assumed= 28.5 in
d’’ =(32/2)-3.5 = 12.5 in
⍺= ((As*60)/(0.85*3*12)) = 1.96As
⍺/2 = 0.98As
Mu = ΦMn = ΦAsFy(d-(⍺/2))
119.34ft-kips*12in/ft = 0.9*As*60*(28.5-0.98As)
As2 – 29.08As + 27.06 = 0
As= 28.12 in2 or 0.96 in
2
As= 0.96 in2/ft
Try #8@9 in, As= 1.05 in2
ρ= 0.96/12*28.5 = 0.0028[<ρmax = 0.016 ok]
Use, #8@ 9 in, As= 1.05 in
Check for the combined axial force and bending.
The AASHTO equations for pure compression and balanced conditions neglect the slight change
of location for plastic centroid when compression steel is used. The footing and wing walls brace
the abutment stem, so slenderness effects will not have to be considered.
[AASHTO 8.16.4.2.1, Equation 8-31 & 8-30]
For pure compression (As=Ast),
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
92
ΦPo= Φ(0.85*f’c*(Ag-Ast)+Ast*Fy)
= Φ (0.85*f’c*(Ag-Ast)+Ast*Fy)
= 0.7[0.85*3[12*32-1.05] + 1.05*60]
= 715.49 kips/ft
ΦPn(max)= 0.8*715.49 = 572.39 kips/ft [0.8 is the minimum eccentricity for a tied column]
[AASHTO 8.16.4.2.3, Equation 8-32 & 8-33]
For balanced conditions,
ΦPb= Φ(0.85*f’c*b*ab +Asf’s - Ast*Fy)
ΦMb= (0.85*f’c*b*ab[d - d’’- (ab/2)] +A’s*f’s[d- d’ – d’’] + As*Fy*d’’)
ab= (87000/(87000+Fy))β1d [AASHTO Equation 8-34]
fs= 87000(1-(d’/d)[(8700+Fy)/87000]) ≤ Fy
As= 1.05 in2
A’s= f’s=0 [assumed a singly reinforced stem section]
ab = (87000/(87000+60000)*0.85*28.5
= 14.34 in
ΦPb= 0.7*(0.85*3*12*14.34 +0 – 1.05*60)
= 263.06 kips/ft.
ΦMb= (0.85*f’c*b*ab[d - d’’- (ab/2)] +A’s*f’s[d- d’ – d’’] + As*Fy*d’’)
= 0.7(0.85*3*12*14.34*(28.5-12.5- (14.34/2)) + 1.05*60*12.5)
= 3263.5in- kips/ft
[AASHTO 8.16.4.2.2, Equation 8-16 &17]
For pure bending,
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
93
⍺= AsFy/0.85*f’c*b = 1.05*60/0.85*3*12 = 2.06 in
⍺/2 = 1.03 in
ΦMn = 0.9*1.05*60*(28.5-0.75)/12
= 131.12 ft-kips/ft
Check minimum steel for bending
The transformed area is
(n-1)*As= (9-1)*1.05 = 8.4 in2
Ac +As = 12*32 + 8.4 = 392.4 in2
Taking moment about the bottom and solving the equation,
392.4*yb = 384*16 + 8.4*3.5
yb = 15.73 in from bottom
The moment of inertia about the neutral axis is
Icg= (1/12)(12*323) + 384*(16-15.73)
2 + 4.96*(15.73 – 3.5)
2 = 34052.41 in
4
fr=modulus of rupture= 7.5(√fc') = 7.5(√3000) =410.79 lbf/in2
Mcr = fr*I/ c = (0.411*34052.41/15.73) /(12) = 74.14 ft-kips/ft
1.2Mcr = 1.2*74.14 = 88.97 ft-kips/ft [< ΦMn = 131.12 ft- kips/ft, ok]
Use #8@9 in, As= 1.05 in2
Check for shear in the stem. The ultimate shear capacity without shear reinforcement is
ΦVc=Φ*2(√fc') *bw*d
= 0.85*2(√3000) *12*28.5 in
= 31844.59 lbf/ft
= 31.84 kips/ft
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
94
[> ∑H for group I loading (=14.06 kips/ft), ok]
Determine temperature and shrinkage reinforcement
[AASHTO 8.20.1] Reinforcement should be provided near exposed surfaces not otherwise
reinforced. The area provided shall be As (temperature and shrinkage)= 0.125 in2/ft. in each
direction.
Use # 4@ 15 in (As= 0.16 in2).
Fig. 12 shows the abutment reinforcement detail.
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
96
CHAPTER FOUR:
PROJECT MANAGEMENT
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
97
Project Management
“Project management has five process groups as mentioned in PMBOK Gide, namely: project
initiation, project planning, project execution, project monitoring and control, and project
closure.” [7] Success of any project depends upon how best the activities are managed from
conception till completion. To be successful in a project management, a project manager must
achieve the project objectives by managing the four basic elements of a project: resource, time,
money, and scope. Hence, to manage this direct connector project, the assigned project manager
has to manage by combing effectively the following key elements:
Resources: people, equipment, material
Time: task durations, dependencies, critical path
Money: costs, contingencies, profit
Scope: project size, goals, requirements
4.1. Project Scope Management
Project scope management clearly defines all roles and responsibilities. For this direct connector
project the role and responsibilities of the Executives Sponsors, Resource Manager, Program
Manager, Project Manager, Customer Service, Team Leader, and Project Team is defined as
shown below which plays key roles in managing the scope of this project. All the teams and
responsible personnel must be aware of their responsibilities in order to ensure that work
performed on the project is within the established scope throughout the entire duration of the
project.
The following table summarizes the roles and responsibilities of the scope management of this
project.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
98
Role Role and Responsibilities
Executive sponsor Oversees project delivery from a business perspective.
Signs off on results during project delivery, project planning, and
quality assurance reporting.
Approve or deny scope change requests as appropriate
Evaluate need for scope change requests
Accept project deliverables
Resource manager Assign resources to projects.
Program manager
Works to ensure project requirements are being met.
Responsible for business planning and administration of the
overall project.
Responsible for coordinating, monitoring and reporting status of
the project and deliverables to appropriate parties.
Oversees project delivery from a customer business process
service perspective.
Project Manager Responsible for coordinating and reporting project status
Measure and verify project scope
Facilitate scope change requests
Facilitate impact assessments of scope change requests
Organize and facilitate scheduled change control meetings
Communicate outcomes of scope change requests
Update project documents upon approval of all scope changes
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
99
Customer
representative
Attend design sessions
Review and comment on draft system.
Participate as needed in other project related meetings.
Team Lead Measure and verify project scope
Validate scope change requests
Participate in impact assessments of scope change requests
Communicate outcomes of scope change requests to team
Facilitate team level change review process
Team Member Participate in defining change resolutions
Evaluate the need for scope changes and communicate them to the
project manager as necessary
The Project Manager, Sponsor and Stakeholders will establish and approve documentation for
measuring project scope which includes deliverable quality checklists and work performance
measurements. Proposed scope changes may be initiated by the Project Manager, Stakeholders or
any member of the project team. The Project Manager will submit the scope change request to
the Change Control Board and Project Sponsor for acceptance. After approval of scope changes,
the Project Manager will update all project documents and communicate the scope change to all
stakeholders. The Project Sponsor is responsible for the acceptance of the final project
deliverables and project scope. [6]
4.1.1 Define Scope
The scope of the project management in the Direct Connector between I-10 and highway 99
Bridge project includes:
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
100
Direct Connector Connects Facilities
From To
AA West bound IH 10 North bound SH99
B B East bound IH 10 North bound SH99
CC South bound SH99 East bound IH 10
DD South bound SH99 West bound IH 10
EE East bound IH 10 South bound SH99
FF North bound SH99 West bound IH 10
GG West bound IH 10 South bound SH99
HH North bound SH99 East bound IH 10
However this thesis would not design pier, foundation and cross beams. Instead, it would
structurally design on abutment, girder, and slab on north and south highway 99 that pass over I-
10. The quantities for each direct connector is assumed in order to apply the project management
knowledge for this thesis. In order to minimize impacts to the traveling public, the project will be
constructed under traffic using staged construction.
4.1.2 Create Work Break down Structure
A comprehensive Work Breakdown Structure is essential for the proper communication of cost
estimating and scheduling data between all participants in Project. The Work Breakdown must
include all phases of the project life cycle, from conception, through development, engineering,
construction, operations, maintenance and transfer. To be manageable the project scope should
be subdivided in to manageable level of work. Hence, work break down structure (WBS) is
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
101
important for project manager and project team because it provides the basis for planning and
managing project schedules, costs, resources, and changes. In WBS, project team will know what
is expected from them and will see their big picture, and where their portions of the project. If
the whole team acts together, it reduces or eliminate that could cause change. Hence, WBS will
make better quality, easier management, and everyone see the whole project. [7]
Description Represent
Bridge Work Break down structure
substructure A
Foundation Excavation A.1
Footing A.2
Pier A.3
Abutment A.4
Abutment back fill A.5
Superstructure B
IV Girder B.1
Deck Forms B.2
Shear Connectors B.3
Deck B.4
Curbs and Parapets B.5
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
102
4.2. Project Time Management
In this capstone project, project time management of bridge demands that manager to reorient all
the resources in such a way that the project is completed without any time/cost overrun. Project
Schedule is prepared based Critical Path Method (CPM) along with major milestone and Bar
Charts. [7] The project schedule is an important part of any project as they provide the project
team, sponsor, and stakeholders a picture of the project’s status at any given time.
Using work break down structure created previously, the project schedules is prepared with MS
Project 2007. After developing a preliminary project schedule, it will be reviewed by the project
team and any resources assigned to project tasks. The project team and resources must agree to
the proposed work package assignments, durations, and schedule. Once this is achieved the
project sponsor will review and approve the schedule and it will then be base lined.
4.2.1 Define Activities, Sequence Activities, and develop schedule
The project manager will be responsible for facilitating work package definition, sequencing, and
estimating duration and resources with the project team. The activities listed in this capstone
bridge project are mentioned as follows:
Activities Definition
Bridge Work Break down structure
substructure Structure below the bearing of bridge
Foundation Excavation Excavation and disposal of Unsuitable Material
in and below confined excavations
Footing Reinforced concrete for foundation that
contains both concrete and reinforced steel
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
103
Pier Reinforced concrete for pier that contains both
concrete and reinforced steel
Abutment Reinforced concrete for abutment stem that
contains both concrete and reinforced steel
Abutment back fill Backfill with select backfill material at the
back of abutment.
Superstructure Bridge structure above bearing.
IV Girder AASHTO standard Pre-stressed concrete I
girders, supply on Site.
Deck Forms Forms for Reinforced concrete deck slab that
cast on site.
Shear Connectors To rearrange and supply shear connector.
Deck Reinforced concrete deck slab that contains
both concrete and reinforced steel.
Curbs and Parapets Reinforced concrete in parapet and curbs.
The above bridge activities sequencing will be used to determine the order of work packages and
assign relationships between project activities. Activity duration estimating will be used to
calculate the number of work periods required to complete work packages. It needs to assign
resources to work packages in order to estimate the number of days required and complete
schedule development. For this project, the schedule is developed by rough assumption of
number of days required to complete the activities.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
104
The project is scheduled using MS Project 2007 and validate the schedule with the project team,
stakeholders, and the project sponsor. The project team is responsible for participating in work
package definition, sequencing, and duration and resource estimating.
4.2.2 Schedule Changes and Thresholds
In this project the threshold limit are set by the project sponsor to establish the schedule
parameters within which the project is expected to operate. The activities which may potentially
cause a schedule change which exceeds these boundary conditions must have a schedule change
request submitted and approved by the sponsor before the schedule change is made. Any change
requests that do not meet these thresholds may be submitted to the project manager for approval.
Once the change request has been reviewed and approved the project manager is responsible for
adjusting the schedule and communicating all changes and impacts to the project team, project
sponsor, and stakeholders. [6]
4.2.3 Schedule Control
In this project, the status of the project will be reviewed and raised in the meeting on a bi-weekly
basis reporting schedule status in accordance with the project’s communications plan. The
project sponsor will maintain awareness of the project schedule status and review/approve any
schedule change requests submitted by the project manager.[6]
IDTask N
ame
Duration
Start
Finish
1D
irect Connectors
between I-10 and
Highw
ay 99
480days
Sat 9/1/12
Fri7/4/14
2B
ridge on highway
99 bypass over I-10160days
Mon
9/3/12Fri
4/12/13
3substructure
90days
Mon
9/3/12Fri
1/4/139
Superstructure70
daysM
on1/7/13
Fri4/12/13
15D
irect Connector A
160days
Mon
9/3/12Fri
4/12/13
16substructure
90days
Mon
9/3/12Fri
1/4/1322
Superstructure70
daysM
on1/7/13
Fri4/12/13
28D
irect Connector B
160days
Mon
9/3/12Fri
4/12/13
29substructure
90days
Mon
9/3/12Fri
1/4/1335
Superstructure70
daysM
on1/7/13
Fri4/12/13
41D
irect Connector C
160days
Mon
4/15/13Fri
11/22/13
42substructure
90days
Mon
4/15/13Fri
8/16/1348
Superstructure70
daysM
on8/19/13
Fri11/22/13
54D
irect Connector D
160days
Mon
4/15/13Fri
11/22/13
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
ep2nd H
alf1st H
alf2nd H
alf1st H
alf2nd H
alf12
20132014
Task
Critical Task
Milestone
Sum
mary
Rolled U
p Task
Rolled U
p Critical Task
Split
Project S
umm
ary
Deadline
Project S
chedule for Direct C
onnector between I-10 and highw
ay 99
Norw
ich University
1
Prepared by: D
awit B
ogale
Approved by: Pascarella B
ryan
IDTask N
ame
Duration
Start
Finish
55substructure
90days
Mon
4/15/13Fri
8/16/1361
Superstructure70
daysM
on8/19/13
Fri11/22/13
67D
irect Connector E
160days
Mon
4/15/13Fri
11/22/13
68substructure
90days
Mon
4/15/13Fri
8/16/1374
Superstructure70
daysM
on8/19/13
Fri11/22/13
80D
irect Connector F
160days
Mon
11/25/13Fri
7/4/14
81substructure
90days
Mon
11/25/13Fri
3/28/1487
Superstructure70
daysM
on3/31/14
Fri7/4/14
93D
irect Connector G
160days
Mon
11/25/13Fri
7/4/14
94substructure
90days
Mon
11/25/13Fri
3/28/14100
Superstructure70
daysM
on3/31/14
Fri7/4/14
106D
irect Connector H
160days
Mon
11/25/13Fri
7/4/14
107substructure
90days
Mon
11/25/13Fri
3/28/14113
Superstructure70
daysM
on3/31/14
Fri7/4/14
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
ep2nd H
alf1st H
alf2nd H
alf1st H
alf2nd H
alf12
20132014
Task
Critical Task
Milestone
Sum
mary
Rolled U
p Task
Rolled U
p Critical Task
Split
Project S
umm
ary
Deadline
Project S
chedule for Direct C
onnector between I-10 and highw
ay 99
Norw
ich University
2
Prepared by: D
awit B
ogale
Approved by: Pascarella B
ryan
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
107
4.3. Project Cost Management plan
The project cost management plan clearly defines how the costs on a project will be managed
throughout the project’s lifecycle. It sets the format and standards by which the project costs are
measured, reported and controlled. In this project as one of government work the manager will
get his budget fixed on monthly basis and performance will be measured using earned
value. The Project Manager is responsible for accounting for cost deviations and presenting the
Project Sponsor with options for getting the project back on budget. [7]
4.3.1 Estimate Cost
The project cost is estimated using the amount of resources required to accomplish the work
required to be performed. For this project, it needs a lot of cost to find out the cost estimation
based on output and current market condition. However, from the previous similar projects,
rough work is done as shown in the Table.
4.3.2 Project Budget
The budget for this project is detailed below. It includes fixed Costs, Material Costs, total
Project Cost, and management Reserve (7 % indirect costs and 10% contingency costs). This
project expected to receives fund from the federal and state highway administrations. Table 16
shows Project Budget in the next page.
PROJECT BUDGET
DIRECT CONNECTOR BETWEEN I-10 AND HIGHWAY 99
Description Fixed Cost Total Cost Baseline Variance Actual Remainng
Direct Connectors between I-10 and Highway
99 0 105116800 0 105116800 0 105116800
Bridge on highway 99 bypass over I-10 0 17775200 0 17775200 0 17775200
substructure 0 6826400 0 6826400 0 6826400
Foundation Excavation 0 35200 0 35200 0 35200
Footing 2000000 2044800 0 2044800 0 2044800
Pier 2000000 2060800 0 2060800 0 2060800
Abutment 2000000 2060000 0 2060000 0 2060000
Abutment backfill 600000 625600 0 625600 0 625600
Superstructure 0 10948800 0 10948800 0 10948800
IV Girder 6000000 6108800 0 6108800 0 6108800
Deck Forms 0 60000 0 60000 0 60000
Shear Connectors 0 20000 0 20000 0 20000
Deck 4000000 4112000 0 4112000 0 4112000
Curbs and Parapets 600000 648000 0 648000 0 648000
Direct Connector A 0 9175200 0 9175200 0 9175200
substructure 0 3526400 0 3526400 0 3526400
Foundation Excavation 0 35200 0 35200 0 35200
Footing 1000000 1044800 0 1044800 0 1044800
Pier 1000000 1060800 0 1060800 0 1060800
Abutment 1000000 1060000 0 1060000 0 1060000
Abutment backfill 300000 325600 0 325600 0 325600
Superstructure 0 5648800 0 5648800 0 5648800
IV Girder 3000000 3108800 0 3108800 0 3108800
Deck Forms 0 60000 0 60000 0 60000
Shear Connectors 0 20000 0 20000 0 20000
Deck 2000000 2112000 0 2112000 0 2112000
Curbs and Parapets 300000 348000 0 348000 0 348000
Direct Connector B 0 9175200 0 9175200 0 9175200
substructure 0 3526400 0 3526400 0 3526400
Foundation Excavation 0 35200 0 35200 0 35200
Footing 1000000 1044800 0 1044800 0 1044800
Pier 1000000 1060800 0 1060800 0 1060800
Abutment 1000000 1060000 0 1060000 0 1060000
Abutment backfill 300000 325600 0 325600 0 325600
Superstructure 0 5648800 0 5648800 0 5648800
IV Girder 3000000 3108800 0 3108800 0 3108800
Deck Forms 0 60000 0 60000 0 60000
Shear Connectors 0 20000 0 20000 0 20000
Deck 2000000 2112000 0 2112000 0 2112000
Curbs and Parapets 300000 348000 0 348000 0 348000
Direct Connector C 0 9175200 0 9175200 0 9175200
substructure 0 3526400 0 3526400 0 3526400
Foundation Excavation 0 35200 0 35200 0 35200
Footing 1000000 1044800 0 1044800 0 1044800
Pier 1000000 1060800 0 1060800 0 1060800
Abutment 1000000 1060000 0 1060000 0 1060000
Abutment backfill 300000 325600 0 325600 0 325600
Superstructure 0 5648800 0 5648800 0 5648800
IV Girder 3000000 3108800 0 3108800 0 3108800
Deck Forms 0 60000 0 60000 0 60000
PROJECT BUDGET
DIRECT CONNECTOR BETWEEN I-10 AND HIGHWAY 99
Shear Connectors 0 20000 0 20000 0 20000
Deck 2000000 2112000 0 2112000 0 2112000
Curbs and Parapets 300000 348000 0 348000 0 348000
Direct Connector D 0 9175200 0 9175200 0 9175200
substructure 0 3526400 0 3526400 0 3526400
Foundation Excavation 0 35200 0 35200 0 35200
Footing 1000000 1044800 0 1044800 0 1044800
Pier 1000000 1060800 0 1060800 0 1060800
Abutment 1000000 1060000 0 1060000 0 1060000
Abutment backfill 300000 325600 0 325600 0 325600
Superstructure 0 5648800 0 5648800 0 5648800
IV Girder 3000000 3108800 0 3108800 0 3108800
Deck Forms 0 60000 0 60000 0 60000
Shear Connectors 0 20000 0 20000 0 20000
Deck 2000000 2112000 0 2112000 0 2112000
Curbs and Parapets 300000 348000 0 348000 0 348000
Direct Connector E 0 9175200 0 9175200 0 9175200
substructure 0 3526400 0 3526400 0 3526400
Foundation Excavation 0 35200 0 35200 0 35200
Footing 1000000 1044800 0 1044800 0 1044800
Pier 1000000 1060800 0 1060800 0 1060800
Abutment 1000000 1060000 0 1060000 0 1060000
Abutment backfill 300000 325600 0 325600 0 325600
Superstructure 0 5648800 0 5648800 0 5648800
IV Girder 3000000 3108800 0 3108800 0 3108800
Deck Forms 0 60000 0 60000 0 60000
Shear Connectors 0 20000 0 20000 0 20000
Deck 2000000 2112000 0 2112000 0 2112000
Curbs and Parapets 300000 348000 0 348000 0 348000
Direct Connector F 0 9175200 0 9175200 0 9175200
substructure 0 3526400 0 3526400 0 3526400
Foundation Excavation 0 35200 0 35200 0 35200
Footing 1000000 1044800 0 1044800 0 1044800
Pier 1000000 1060800 0 1060800 0 1060800
Abutment 1000000 1060000 0 1060000 0 1060000
Abutment backfill 300000 325600 0 325600 0 325600
Superstructure 0 5648800 0 5648800 0 5648800
IV Girder 3000000 3108800 0 3108800 0 3108800
Deck Forms 0 60000 0 60000 0 60000
Shear Connectors 0 20000 0 20000 0 20000
Deck 2000000 2112000 0 2112000 0 2112000
Curbs and Parapets 300000 348000 0 348000 0 348000
Direct Connector G 0 9175200 0 9175200 0 9175200
substructure 0 3526400 0 3526400 0 3526400
Foundation Excavation 0 35200 0 35200 0 35200
Footing 1000000 1044800 0 1044800 0 1044800
Pier 1000000 1060800 0 1060800 0 1060800
Abutment 1000000 1060000 0 1060000 0 1060000
Abutment backfill 300000 325600 0 325600 0 325600
Superstructure 0 5648800 0 5648800 0 5648800
IV Girder 3000000 3108800 0 3108800 0 3108800
Deck Forms 0 60000 0 60000 0 60000
Shear Connectors 0 20000 0 20000 0 20000
Deck 2000000 2112000 0 2112000 0 2112000
PROJECT BUDGET
DIRECT CONNECTOR BETWEEN I-10 AND HIGHWAY 99
Curbs and Parapets 300000 348000 0 348000 0 348000
Direct Connector H 0 9175200 0 9175200 0 9175200
substructure 0 3526400 0 3526400 0 3526400
Foundation Excavation 0 35200 0 35200 0 35200
Footing 1000000 1044800 0 1044800 0 1044800
Pier 1000000 1060800 0 1060800 0 1060800
Abutment 1000000 1060000 0 1060000 0 1060000
Abutment backfill 300000 325600 0 325600 0 325600
Superstructure 0 5648800 0 5648800 0 5648800
IV Girder 3000000 3108800 0 3108800 0 3108800
Deck Forms 0 60000 0 60000 0 60000
Shear Connectors 0 20000 0 20000 0 20000
Deck 2000000 2112000 0 2112000 0 2112000
Curbs and Parapets 300000 348000 0 348000 0 348000
10 % Contigency cost 8200000 8200000 0 8200000 0 8200000
7 % Indirect cost 5740000 5740000 0 5740000 0 5740000
99940000 105116800
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
111
4.3.3 Project Cost and Schedule Performance
Using Microsoft project Earned Value measurements, Schedule Variance (SV), Cost Variance
(CV), Schedule Performance Index (SPI) and Cost Performance Index (CPI), will be performed
to check the status. Appling these four measurements will provide enough insight for effective
management. Cost variances of +/- 0.1 in the cost and schedule performance indexes will change
the status of the cost to cautionary; since cost variances of +/- 0.2 in the cost and schedule
performance indexes will change the status of the cost to an alert stage, it will require corrective
action from the Project Manager in order to bring the cost and/or schedule performance indexes
below the alert level.[6]
Schedule Variance (SV) is a measurement of the schedule performance for a project. It’s
calculated by taking the Earned Value (EV) and subtracting the Planned Value (PV).
If SV is zero, then the project is perfectly on schedule.
If SV is greater than zero, the project is earning more value than planned thus it’s ahead
of schedule.
If SV is less than zero, the project is earning less value than planned thus it’s behind
schedule.
Cost Variance (CV) is a measurement of the budget performance for a project. CV is calculated
by subtracting Actual Costs (AC) from Earned Value (EV).
If CV is zero, then the project is perfectly on budget.
If CV is greater than zero, the project is earning more value than planned thus it’s under
budget.
If CV is less than zero, the project is earning less value than planned thus it’s over
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
112
budget.
Schedule Performance Index (SPI) measures the progress achieved against that which was
planned. A well performing project should have its SPI as close to 1 as possible, or maybe even
a little less than 1. SPI is calculated as EV/PV.
If EV is equal to PV the value of the SPI is 1.
If EV is less than the PV then the value is less than 1, which means the project is behind
schedule.
If EV is greater than the PV the value of the SPI is greater than one, which means the
project is ahead of schedule.
Cost Performance Index (CPI) measures the value of the work completed compared to the actual
cost of the work completed. CPI is calculated as EV/AC.
If CPI is equal to 1 the project is perfectly on budget.
If the CPI is greater than 1 the project is under budget.
If it’s less than 1 the project is over budget.
Table 17 shows the performance cost and schedule in the next page.
Table 17. PROJECT COST PERFORMANCE
Description
Planned Value,
PV (BCWS)
Earned
Value, EV
(BCWP)
Actual Cost,
AC ( ACWP)
Schedule
Variance, SV Cost Variance, CV
Earned Actual Cost,
EAC
Budgeted Actual
Cost, BAC
Variance Actual Cost,
VAC
Direct Connectors between I-10 and
Highway 99 $0.00 $0.00 $0.00 $0.00 $0.00 $105,116,800.00 $0.00 ($105,116,800.00)
Bridge on highway 99 bypass over I-
10 $0.00 $0.00 $0.00 $0.00 $0.00 $17,775,200.00 $0.00 ($17,775,200.00)
substructure $0.00 $0.00 $0.00 $0.00 $0.00 $6,826,400.00 $0.00 ($6,826,400.00)
Foundation Excavation $0.00 $0.00 $0.00 $0.00 $0.00 $35,200.00 $0.00 ($35,200.00)
Footing $0.00 $0.00 $0.00 $0.00 $0.00 $2,044,800.00 $0.00 ($2,044,800.00)
Pier $0.00 $0.00 $0.00 $0.00 $0.00 $2,060,800.00 $0.00 ($2,060,800.00)
Abutment $0.00 $0.00 $0.00 $0.00 $0.00 $2,060,000.00 $0.00 ($2,060,000.00)
Abutment backfill $0.00 $0.00 $0.00 $0.00 $0.00 $625,600.00 $0.00 ($625,600.00)
Superstructure $0.00 $0.00 $0.00 $0.00 $0.00 $10,948,800.00 $0.00 ($10,948,800.00)
IV Girder $0.00 $0.00 $0.00 $0.00 $0.00 $6,108,800.00 $0.00 ($6,108,800.00)
Deck Forms $0.00 $0.00 $0.00 $0.00 $0.00 $60,000.00 $0.00 ($60,000.00)
Shear Connectors $0.00 $0.00 $0.00 $0.00 $0.00 $20,000.00 $0.00 ($20,000.00)
Deck $0.00 $0.00 $0.00 $0.00 $0.00 $4,112,000.00 $0.00 ($4,112,000.00)
Curbs and Parapets $0.00 $0.00 $0.00 $0.00 $0.00 $648,000.00 $0.00 ($648,000.00)
Direct Connector A $0.00 $0.00 $0.00 $0.00 $0.00 $9,175,200.00 $0.00 ($9,175,200.00)
substructure $0.00 $0.00 $0.00 $0.00 $0.00 $3,526,400.00 $0.00 ($3,526,400.00)
Foundation Excavation $0.00 $0.00 $0.00 $0.00 $0.00 $35,200.00 $0.00 ($35,200.00)
Footing $0.00 $0.00 $0.00 $0.00 $0.00 $1,044,800.00 $0.00 ($1,044,800.00)
Pier $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,800.00 $0.00 ($1,060,800.00)
Abutment $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,000.00 $0.00 ($1,060,000.00)
Abutment backfill $0.00 $0.00 $0.00 $0.00 $0.00 $325,600.00 $0.00 ($325,600.00)
Superstructure $0.00 $0.00 $0.00 $0.00 $0.00 $5,648,800.00 $0.00 ($5,648,800.00)
IV Girder $0.00 $0.00 $0.00 $0.00 $0.00 $3,108,800.00 $0.00 ($3,108,800.00)
Deck Forms $0.00 $0.00 $0.00 $0.00 $0.00 $60,000.00 $0.00 ($60,000.00)
Shear Connectors $0.00 $0.00 $0.00 $0.00 $0.00 $20,000.00 $0.00 ($20,000.00)
Deck $0.00 $0.00 $0.00 $0.00 $0.00 $2,112,000.00 $0.00 ($2,112,000.00)
Curbs and Parapets $0.00 $0.00 $0.00 $0.00 $0.00 $348,000.00 $0.00 ($348,000.00)
Direct Connector B $0.00 $0.00 $0.00 $0.00 $0.00 $9,175,200.00 $0.00 ($9,175,200.00)
substructure $0.00 $0.00 $0.00 $0.00 $0.00 $3,526,400.00 $0.00 ($3,526,400.00)
Foundation Excavation $0.00 $0.00 $0.00 $0.00 $0.00 $35,200.00 $0.00 ($35,200.00)
Footing $0.00 $0.00 $0.00 $0.00 $0.00 $1,044,800.00 $0.00 ($1,044,800.00)
Pier $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,800.00 $0.00 ($1,060,800.00)
Abutment $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,000.00 $0.00 ($1,060,000.00)
Abutment backfill $0.00 $0.00 $0.00 $0.00 $0.00 $325,600.00 $0.00 ($325,600.00)
Superstructure $0.00 $0.00 $0.00 $0.00 $0.00 $5,648,800.00 $0.00 ($5,648,800.00)
IV Girder $0.00 $0.00 $0.00 $0.00 $0.00 $3,108,800.00 $0.00 ($3,108,800.00)
Deck Forms $0.00 $0.00 $0.00 $0.00 $0.00 $60,000.00 $0.00 ($60,000.00)
Shear Connectors $0.00 $0.00 $0.00 $0.00 $0.00 $20,000.00 $0.00 ($20,000.00)
Deck $0.00 $0.00 $0.00 $0.00 $0.00 $2,112,000.00 $0.00 ($2,112,000.00)
Curbs and Parapets $0.00 $0.00 $0.00 $0.00 $0.00 $348,000.00 $0.00 ($348,000.00)
Direct Connector C $0.00 $0.00 $0.00 $0.00 $0.00 $9,175,200.00 $0.00 ($9,175,200.00)
substructure $0.00 $0.00 $0.00 $0.00 $0.00 $3,526,400.00 $0.00 ($3,526,400.00)
Foundation Excavation $0.00 $0.00 $0.00 $0.00 $0.00 $35,200.00 $0.00 ($35,200.00)
Footing $0.00 $0.00 $0.00 $0.00 $0.00 $1,044,800.00 $0.00 ($1,044,800.00)
Pier $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,800.00 $0.00 ($1,060,800.00)
Abutment $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,000.00 $0.00 ($1,060,000.00)
Abutment backfill $0.00 $0.00 $0.00 $0.00 $0.00 $325,600.00 $0.00 ($325,600.00)
Superstructure $0.00 $0.00 $0.00 $0.00 $0.00 $5,648,800.00 $0.00 ($5,648,800.00)
IV Girder $0.00 $0.00 $0.00 $0.00 $0.00 $3,108,800.00 $0.00 ($3,108,800.00)
Deck Forms $0.00 $0.00 $0.00 $0.00 $0.00 $60,000.00 $0.00 ($60,000.00)
Shear Connectors $0.00 $0.00 $0.00 $0.00 $0.00 $20,000.00 $0.00 ($20,000.00)
Deck $0.00 $0.00 $0.00 $0.00 $0.00 $2,112,000.00 $0.00 ($2,112,000.00)
Curbs and Parapets $0.00 $0.00 $0.00 $0.00 $0.00 $348,000.00 $0.00 ($348,000.00)
Direct Connector D $0.00 $0.00 $0.00 $0.00 $0.00 $9,175,200.00 $0.00 ($9,175,200.00)
substructure $0.00 $0.00 $0.00 $0.00 $0.00 $3,526,400.00 $0.00 ($3,526,400.00)
Foundation Excavation $0.00 $0.00 $0.00 $0.00 $0.00 $35,200.00 $0.00 ($35,200.00)
Footing $0.00 $0.00 $0.00 $0.00 $0.00 $1,044,800.00 $0.00 ($1,044,800.00)
Pier $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,800.00 $0.00 ($1,060,800.00)
Abutment $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,000.00 $0.00 ($1,060,000.00)
Table 17. PROJECT COST PERFORMANCE
Abutment backfill $0.00 $0.00 $0.00 $0.00 $0.00 $325,600.00 $0.00 ($325,600.00)
Superstructure $0.00 $0.00 $0.00 $0.00 $0.00 $5,648,800.00 $0.00 ($5,648,800.00)
IV Girder $0.00 $0.00 $0.00 $0.00 $0.00 $3,108,800.00 $0.00 ($3,108,800.00)
Deck Forms $0.00 $0.00 $0.00 $0.00 $0.00 $60,000.00 $0.00 ($60,000.00)
Shear Connectors $0.00 $0.00 $0.00 $0.00 $0.00 $20,000.00 $0.00 ($20,000.00)
Deck $0.00 $0.00 $0.00 $0.00 $0.00 $2,112,000.00 $0.00 ($2,112,000.00)
Curbs and Parapets $0.00 $0.00 $0.00 $0.00 $0.00 $348,000.00 $0.00 ($348,000.00)
Direct Connector E $0.00 $0.00 $0.00 $0.00 $0.00 $9,175,200.00 $0.00 ($9,175,200.00)
substructure $0.00 $0.00 $0.00 $0.00 $0.00 $3,526,400.00 $0.00 ($3,526,400.00)
Foundation Excavation $0.00 $0.00 $0.00 $0.00 $0.00 $35,200.00 $0.00 ($35,200.00)
Footing $0.00 $0.00 $0.00 $0.00 $0.00 $1,044,800.00 $0.00 ($1,044,800.00)
Pier $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,800.00 $0.00 ($1,060,800.00)
Abutment $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,000.00 $0.00 ($1,060,000.00)
Abutment backfill $0.00 $0.00 $0.00 $0.00 $0.00 $325,600.00 $0.00 ($325,600.00)
Superstructure $0.00 $0.00 $0.00 $0.00 $0.00 $5,648,800.00 $0.00 ($5,648,800.00)
IV Girder $0.00 $0.00 $0.00 $0.00 $0.00 $3,108,800.00 $0.00 ($3,108,800.00)
Deck Forms $0.00 $0.00 $0.00 $0.00 $0.00 $60,000.00 $0.00 ($60,000.00)
Shear Connectors $0.00 $0.00 $0.00 $0.00 $0.00 $20,000.00 $0.00 ($20,000.00)
Deck $0.00 $0.00 $0.00 $0.00 $0.00 $2,112,000.00 $0.00 ($2,112,000.00)
Curbs and Parapets $0.00 $0.00 $0.00 $0.00 $0.00 $348,000.00 $0.00 ($348,000.00)
Direct Connector F $0.00 $0.00 $0.00 $0.00 $0.00 $9,175,200.00 $0.00 ($9,175,200.00)
substructure $0.00 $0.00 $0.00 $0.00 $0.00 $3,526,400.00 $0.00 ($3,526,400.00)
Foundation Excavation $0.00 $0.00 $0.00 $0.00 $0.00 $35,200.00 $0.00 ($35,200.00)
Footing $0.00 $0.00 $0.00 $0.00 $0.00 $1,044,800.00 $0.00 ($1,044,800.00)
Pier $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,800.00 $0.00 ($1,060,800.00)
Abutment $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,000.00 $0.00 ($1,060,000.00)
Abutment backfill $0.00 $0.00 $0.00 $0.00 $0.00 $325,600.00 $0.00 ($325,600.00)
Superstructure $0.00 $0.00 $0.00 $0.00 $0.00 $5,648,800.00 $0.00 ($5,648,800.00)
IV Girder $0.00 $0.00 $0.00 $0.00 $0.00 $3,108,800.00 $0.00 ($3,108,800.00)
Deck Forms $0.00 $0.00 $0.00 $0.00 $0.00 $60,000.00 $0.00 ($60,000.00)
Shear Connectors $0.00 $0.00 $0.00 $0.00 $0.00 $20,000.00 $0.00 ($20,000.00)
Deck $0.00 $0.00 $0.00 $0.00 $0.00 $2,112,000.00 $0.00 ($2,112,000.00)
Curbs and Parapets $0.00 $0.00 $0.00 $0.00 $0.00 $348,000.00 $0.00 ($348,000.00)
Direct Connector G $0.00 $0.00 $0.00 $0.00 $0.00 $9,175,200.00 $0.00 ($9,175,200.00)
substructure $0.00 $0.00 $0.00 $0.00 $0.00 $3,526,400.00 $0.00 ($3,526,400.00)
Foundation Excavation $0.00 $0.00 $0.00 $0.00 $0.00 $35,200.00 $0.00 ($35,200.00)
Footing $0.00 $0.00 $0.00 $0.00 $0.00 $1,044,800.00 $0.00 ($1,044,800.00)
Pier $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,800.00 $0.00 ($1,060,800.00)
Abutment $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,000.00 $0.00 ($1,060,000.00)
Abutment backfill $0.00 $0.00 $0.00 $0.00 $0.00 $325,600.00 $0.00 ($325,600.00)
Superstructure $0.00 $0.00 $0.00 $0.00 $0.00 $5,648,800.00 $0.00 ($5,648,800.00)
IV Girder $0.00 $0.00 $0.00 $0.00 $0.00 $3,108,800.00 $0.00 ($3,108,800.00)
Deck Forms $0.00 $0.00 $0.00 $0.00 $0.00 $60,000.00 $0.00 ($60,000.00)
Shear Connectors $0.00 $0.00 $0.00 $0.00 $0.00 $20,000.00 $0.00 ($20,000.00)
Deck $0.00 $0.00 $0.00 $0.00 $0.00 $2,112,000.00 $0.00 ($2,112,000.00)
Curbs and Parapets $0.00 $0.00 $0.00 $0.00 $0.00 $348,000.00 $0.00 ($348,000.00)
Direct Connector H $0.00 $0.00 $0.00 $0.00 $0.00 $9,175,200.00 $0.00 ($9,175,200.00)
substructure $0.00 $0.00 $0.00 $0.00 $0.00 $3,526,400.00 $0.00 ($3,526,400.00)
Foundation Excavation $0.00 $0.00 $0.00 $0.00 $0.00 $35,200.00 $0.00 ($35,200.00)
Footing $0.00 $0.00 $0.00 $0.00 $0.00 $1,044,800.00 $0.00 ($1,044,800.00)
Pier $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,800.00 $0.00 ($1,060,800.00)
Abutment $0.00 $0.00 $0.00 $0.00 $0.00 $1,060,000.00 $0.00 ($1,060,000.00)
Abutment backfill $0.00 $0.00 $0.00 $0.00 $0.00 $325,600.00 $0.00 ($325,600.00)
Superstructure $0.00 $0.00 $0.00 $0.00 $0.00 $5,648,800.00 $0.00 ($5,648,800.00)
IV Girder $0.00 $0.00 $0.00 $0.00 $0.00 $3,108,800.00 $0.00 ($3,108,800.00)
Deck Forms $0.00 $0.00 $0.00 $0.00 $0.00 $60,000.00 $0.00 ($60,000.00)
Shear Connectors $0.00 $0.00 $0.00 $0.00 $0.00 $20,000.00 $0.00 ($20,000.00)
Deck $0.00 $0.00 $0.00 $0.00 $0.00 $2,112,000.00 $0.00 ($2,112,000.00)
Curbs and Parapets $0.00 $0.00 $0.00 $0.00 $0.00 $348,000.00 $0.00 ($348,000.00)
10 % Contigency cost $0.00 $0.00 $0.00 $0.00 $0.00 $8,200,000.00 $0.00 ($8,200,000.00)
7 % Indirect cost $0.00 $0.00 $0.00 $0.00 $0.00 $5,740,000.00 $0.00 ($5,740,000.00)
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
115
4.4. Project Quality Management
The Quality Management Plan is an integral part of any project management plan. The purpose of the
Quality Management Plan is to describe how quality will be managed throughout the lifecycle of the
project. It ensures quality planning, assurance, and controls are all conducted [7]. All stakeholders should
be familiar with how quality will be planned, assured, and controlled. Training to staff should be provided
to update the quality control measure and it should become part of the work culture. At site laboratory be
established to check the quality of concrete. Tests are analyzed at site to produce the concrete of desirable
strength. Compaction of concrete is given more attention before final setting. Quality assurance on ground
improves the aesthetic of structures and must always be planned into a project in order to prevent
unnecessary rework, waste, cost, and time. The Texas department of transportation has a standardized
approach to quality; however, the approach must be defined and communicated to all project responsible
personnel’s.
4.4.1 Quality Control Measurements
In this project Quality Management Plan should contain a sample or useable table/log to be used in taking
tests and comparing them against Texas department of transportation standards/requirements. The most
important aspect of this log is to provide documentation of the findings. If actual measurements do not
meet the standards or requirements then some action must be taken.
4.5. Project Human Resource Management
Manager should put the engineers or responsible personnel’s to activities they can perform
better. The characteristic of each individual should be studied in detail to assign the suitable job.
The project is full of staff that will collect data, design the project, and construct the project.
There will be an office on the site equipped with computer, meeting halls, and required facility as
required by specification. It should provide a general description of what the plan includes and
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
116
explain how the project manager and project team can use the plan to help them manage the
project effectively.
In the human resources management plan, the project will use MS- project as a tool to aid in the
management of the project’s human resource activities throughout the project. Using project
organizational chart the Human Resource Plan provides a graphic display of the project tasks and
team members. The project manager will review each team member’s assigned work activities at
the onset of the project and communicate all expectations of work to be performed.
4.6. Project Communication Management
The purpose of the Communications Management Plan is to define the communication
requirements for the project and how information will be distributed [7]. In this project, there
should be good communication between the client, contractor and consultant for solving
problems that would occur throughout design or construction stage.
Most of a Project Manager’s time is spent communication. To communicate well in this project,
the project manager spent his time measuring and reporting on the performance of the project,
composing and reading emails, conducting meetings, writing the project plan, meeting with team
members, overseeing work being performed. It will serve as a guide for communications
throughout the life of the project and will be updated as communication needs change. Project
communication conducts meeting twice a month. It has a guide that explains communications
rules and how the meetings will be conducted, ensuring successful meetings. As a Project
Manager, it is best to take a proactive role in ensuring effective communications on this project.
4.7. Risk Management
The purpose of the risk management plan is to establish the framework in which the project team
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
117
will identify risks and develop strategies to mitigate or avoid those risks [7]. Risk managers will
provide status updates on their assigned risks in the bi-weekly project team meetings. In order to
determine the severity of the risks identified, a probability and impact factor was assigned to
each risk. During the bi-weekly project team meeting the Risk Manager for each risk will discuss
the status of that risk. Each risk manager will provide the status of their assigned risk at the bi-
weekly project team meeting for their risk’s planned timeframe.
4.8. Project Procurement Management
The purpose of the Procurement Management Plan is to define the procurement requirements for
the project and how it will be managed from developing procurement documentation through
contract closure. Better documentation will avoid any disputes during the currency and after
completion of contract. The Procurement Management Plan defines items to be procured with
justification statements and timelines, type of contract to be used, contract approval process,
decision criteria, establishing contract deliverables and deadlines, vendor Management, and
performance metrics for procurement activities. It will serve as a guide for managing
procurement throughout the life of the project and will be updated as acquisition needs change. It
clearly identifies the necessary steps and responsibilities for procurement from the beginning to
the end of a project [7].
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
118
5. Summary and Conclusion
With regard to structural engineering, this project will perform the design and analysis of Pre
stressed Concrete AASHTO Type IV Girder, Abutments, and Concrete deck slabs using
AASHTO Standard Specification. In addition from project management point of view this thesis
layout the plan to manage this project from initiation till completion with respect to the Project
Communication Management, Project Time Management, Project Cost Management, and Project
Quality Management. Project management basically is a tool to complete the project effectively
by balancing cost, time, resource, and scope. Manager should have knowledge sequence of all
the activities. In this project, decision making for both sides the contractor and the client needs to
be fast and time bound otherwise the project will get delayed which will have cost overrun. In
this project, the project management techniques that help to manage effectively throughout the
project are explained well.
In conclusion, in addition to design and analysis of AASHTO IV girders, abutments, and
concrete slab, this project clearly explains the advantage of using pre-stressed concrete products
to construct cost effective, complex long span structure where aesthetic and urban geometric are
significant design consideration.
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
119
6. References:
1. Bridge Design for the Civil and Structural Professional Engineering Exams, Second Edition
By Robert H. Kim, MSCE, PE and Jai B. Kim, PH.D, PE.
2. Prestressed Concrete, A Fundamental Approach, Fifth Edition, By Professor Edward G.
Nawy.
3. Structural Dynamics, Theory and Computation, Fifth Edition Updated with SAP2000, By
Mario Paz and William Leigh
4. Civil Engineering Reference Manual for the PE Exam, Thirteenth Edition, By Michael R.
Lindeburg, PE.
5. Project Management, A System Approach to Planning, Scheduling, and Controlling, By
Harold Kerzner 2009, PH.D.
6. A Guide to the Project Management Body of Knowledge (PMBOK Guide), Fourth Edition,
2008.
7. Proposed Direct Connectors at State Highway 99/ Interstate Highway 10 Interchange by
Federal Highway Administration and Texas Department of Transportation, Retrieved from
http://www.grandpky.com/downloads/segmentd/CE%20For%20Proposed%20Direct%20Con
nectors%20at%20State%20Highway%2099%20%20Interstate%20Highway%2010%20Interc
hange.pdf
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
120
7. APPENDIX A
FIG.14 PROJECT SCHEDULE
IDTask N
ame
Duration
Start
Finish
1D
irect Connectors
between I-10 and
Highw
ay 99
480days
Sat 9/1/12
Fri7/4/14
2B
ridge on highway
99 bypass over I-10160days
Mon
9/3/12Fri
4/12/13
3substructure
90days
Mon
9/3/12Fri
1/4/134
FoundationE
xcavation10
daysM
on9/3/12
Fri9/14/12
5Footing
20days
Mon
9/17/12Fri
10/12/126
Pier
20days
Mon
10/15/12Fri
11/9/127
Abutm
ent30
daysM
on11/12/12
Fri12/21/12
8A
butment
backfill10
daysM
on12/24/12
Fri1/4/13
9Superstructure
70days
Mon
1/7/13Fri
4/12/1310
IV G
irder20
daysM
on1/7/13
Fri2/1/13
11D
eck Forms
15days
Mon
2/4/13Fri
2/22/1312
Shear
Connectors
5 daysM
on2/25/13
Fri3/1/13
13D
eck20
daysM
on3/4/13
Fri3/29/13
14C
urbs andP
arapets10
daysM
on4/1/13
Fri4/12/13
excavator[200%],G
eneral super intendent,labourer[500%],site engineer,Trucks[350%
]
bar bender[300%],concrete expert[300%
],concrete trucks[300%],G
eneral super intendent,project engineer
bar bender,concrete expert,concrete trucks,General super intendent,heavy load trucks,site engineer
bar bender,concrete trucks,General super intendent,labourer,concrete expert
excavator,General super intendent,project engineer,labourer
bar bender,concrete expert,concrete trucks,crane,heavy load trucks
bar bender,General super intendent,labourer,crane
bar bender,crane,labourer,General super intendent
bar bender,concrete expert,concrete trucks,crane,General super intendent,labourer,project e
bar bender,concrete expert,concrete trucks,crane,labourer
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Hal
122013
20142015
Task
Critical Task
Milestone
Sum
mary
Rolled U
p Task
Rolled U
p Critical Task
Split
Project S
umm
ary
Deadline
Project S
chedule for Direct C
onnector between I-10 and highw
ay 99
Norw
ich University
1
Prepared by: D
awit B
ogale
Approved by: Pascarella B
ryan
IDTask N
ame
Duration
Start
Finish
15D
irect Connector A
160days
Mon
9/3/12Fri
4/12/13
16substructure
90days
Mon
9/3/12Fri
1/4/1317
FoundationE
xcavation10
daysM
on9/3/12
Fri9/14/12
18Footing
20days
Mon
9/17/12Fri
10/12/1219
Pier
20days
Mon
10/15/12Fri
11/9/1220
Abutm
ent30
daysM
on11/12/12
Fri12/21/12
21A
butment
backfill10
daysM
on12/24/12
Fri1/4/13
22Superstructure
70days
Mon
1/7/13Fri
4/12/1323
IV G
irder20
daysM
on1/7/13
Fri2/1/13
24D
eck Forms
15days
Mon
2/4/13Fri
2/22/1325
Shear
Connectors
5 daysM
on2/25/13
Fri3/1/13
26D
eck20
daysM
on3/4/13
Fri3/29/13
27C
urbs andP
arapets10
daysM
on4/1/13
Fri4/12/13
28D
irect Connector B
160days
Mon
9/3/12Fri
4/12/13
29substructure
90days
Mon
9/3/12Fri
1/4/1330
FoundationE
xcavation10
daysM
on9/3/12
Fri9/14/12
excavator[200%],G
eneral super intendent,labourer[500%],site engineer,Trucks[350%
]
bar bender[300%],concrete expert[300%
],concrete trucks[300%],G
eneral super intendent,project engineer
bar bender,concrete expert,concrete trucks,General super intendent,heavy load trucks,site engineer
bar bender,concrete trucks,General super intendent,labourer,concrete expert
excavator,General super intendent,project engineer,labourer
bar bender,concrete expert,concrete trucks,crane,heavy load trucks
bar bender,General super intendent,labourer,crane
bar bender,crane,labourer,General super intendent
bar bender,concrete expert,concrete trucks,crane,General super intendent,labourer,project e
bar bender,concrete expert,concrete trucks,crane,labourer
excavator[200%],G
eneral super intendent,labourer[500%],site engineer,Trucks[350%
]
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Hal
122013
20142015
Task
Critical Task
Milestone
Sum
mary
Rolled U
p Task
Rolled U
p Critical Task
Split
Project S
umm
ary
Deadline
Project S
chedule for Direct C
onnector between I-10 and highw
ay 99
Norw
ich University
2
Prepared by: D
awit B
ogale
Approved by: Pascarella B
ryan
IDTask N
ame
Duration
Start
Finish
31Footing
20days
Mon
9/17/12Fri
10/12/1232
Pier
20days
Mon
10/15/12Fri
11/9/1233
Abutm
ent30
daysM
on11/12/12
Fri12/21/12
34A
butment
backfill10
daysM
on12/24/12
Fri1/4/13
35Superstructure
70days
Mon
1/7/13Fri
4/12/1336
IV G
irder20
daysM
on1/7/13
Fri2/1/13
37D
eck Forms
15days
Mon
2/4/13Fri
2/22/1338
Shear
Connectors
5 daysM
on2/25/13
Fri3/1/13
39D
eck20
daysM
on3/4/13
Fri3/29/13
40C
urbs andP
arapets10
daysM
on4/1/13
Fri4/12/13
41D
irect Connector C
160days
Mon
4/15/13Fri
11/22/13
42substructure
90days
Mon
4/15/13Fri
8/16/1343
FoundationE
xcavation10
daysM
on4/15/13
Fri4/26/13
44Footing
20days
Mon
4/29/13Fri
5/24/1345
Pier
20days
Mon
5/27/13Fri
6/21/1346
Abutm
ent30
daysM
on6/24/13
Fri8/2/13
bar bender[300%],concrete expert[300%
],concrete trucks[300%],G
eneral super intendent,project engineer
bar bender,concrete expert,concrete trucks,General super intendent,heavy load trucks,site engineer
bar bender,concrete trucks,General super intendent,labourer,concrete expert
excavator,General super intendent,project engineer,labourer
bar bender,concrete expert,concrete trucks,crane,heavy load trucks
bar bender,General super intendent,labourer,crane
bar bender,crane,labourer,General super intendent
bar bender,concrete expert,concrete trucks,crane,General super intendent,labourer,project e
bar bender,concrete expert,concrete trucks,crane,labourer
excavator[200%],G
eneral super intendent,labourer[500%],site engineer,Trucks[350%
]
bar bender[300%],concrete expert[300%
],concrete trucks[300%],G
eneral super intendent
bar bender,concrete expert,concrete trucks,General super intendent,heavy load trucks
bar bender,concrete trucks,General super intendent,labourer,concrete expert
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Hal
122013
20142015
Task
Critical Task
Milestone
Sum
mary
Rolled U
p Task
Rolled U
p Critical Task
Split
Project S
umm
ary
Deadline
Project S
chedule for Direct C
onnector between I-10 and highw
ay 99
Norw
ich University
3
Prepared by: D
awit B
ogale
Approved by: Pascarella B
ryan
IDTask N
ame
Duration
Start
Finish
47A
butment
backfill10
daysM
on8/5/13
Fri8/16/13
48Superstructure
70days
Mon
8/19/13Fri
11/22/1349
IV G
irder20
daysM
on8/19/13
Fri9/13/13
50D
eck Forms
15days
Mon
9/16/13Fri
10/4/1351
Shear
Connectors
5 daysM
on10/7/13
Fri10/11/13
52D
eck20
daysM
on10/14/13
Fri11/8/13
53C
urbs andP
arapets10
daysM
on11/11/13
Fri11/22/13
54D
irect Connector D
160days
Mon
4/15/13Fri
11/22/13
55substructure
90days
Mon
4/15/13Fri
8/16/1356
FoundationE
xcavation10
daysM
on4/15/13
Fri4/26/13
57Footing
20days
Mon
4/29/13Fri
5/24/1358
Pier
20days
Mon
5/27/13Fri
6/21/1359
Abutm
ent30
daysM
on6/24/13
Fri8/2/13
60A
butment
backfill10
daysM
on8/5/13
Fri8/16/13
61Superstructure
70days
Mon
8/19/13Fri
11/22/1362
IV G
irder20
daysM
on8/19/13
Fri9/13/13
excavator,General super intendent,project engineer,labourer
bar bender,concrete expert,concrete trucks,crane,heavy load trucks
bar bender,General super intendent,labourer,crane
bar bender,crane,labourer,General super intendent
bar bender,concrete expert,concrete trucks,crane,General super intendent
bar bender,concrete expert,concrete trucks,crane,labourer
excavator[200%],G
eneral super intendent,labourer[500%],site engineer,Trucks[350%
]
bar bender[300%],concrete expert[300%
],concrete trucks[300%],G
eneral super intendent
bar bender,concrete expert,concrete trucks,General super intendent,heavy load trucks
bar bender,concrete trucks,General super intendent,labourer,concrete expert
excavator,General super intendent,project engineer,labourer
bar bender,concrete expert,concrete trucks,crane,heavy load trucks
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Hal
122013
20142015
Task
Critical Task
Milestone
Sum
mary
Rolled U
p Task
Rolled U
p Critical Task
Split
Project S
umm
ary
Deadline
Project S
chedule for Direct C
onnector between I-10 and highw
ay 99
Norw
ich University
4
Prepared by: D
awit B
ogale
Approved by: Pascarella B
ryan
IDTask N
ame
Duration
Start
Finish
63D
eck Forms
15days
Mon
9/16/13Fri
10/4/1364
Shear
Connectors
5 daysM
on10/7/13
Fri10/11/13
65D
eck20
daysM
on10/14/13
Fri11/8/13
66C
urbs andP
arapets10
daysM
on11/11/13
Fri11/22/13
67D
irect Connector E
160days
Mon
4/15/13Fri
11/22/13
68substructure
90days
Mon
4/15/13Fri
8/16/1369
FoundationE
xcavation10
daysM
on4/15/13
Fri4/26/13
70Footing
20days
Mon
4/29/13Fri
5/24/1371
Pier
20days
Mon
5/27/13Fri
6/21/1372
Abutm
ent30
daysM
on6/24/13
Fri8/2/13
73A
butment
backfill10
daysM
on8/5/13
Fri8/16/13
74Superstructure
70days
Mon
8/19/13Fri
11/22/1375
IV G
irder20
daysM
on8/19/13
Fri9/13/13
76D
eck Forms
15days
Mon
9/16/13Fri
10/4/1377
Shear
Connectors
5 daysM
on10/7/13
Fri10/11/13
78D
eck20
daysM
on10/14/13
Fri11/8/13
bar bender,General super intendent,labourer,crane
bar bender,crane,labourer,General super intendent
bar bender,concrete expert,concrete trucks,crane,General super intendent
bar bender,concrete expert,concrete trucks,crane,labourer
excavator[200%],G
eneral super intendent,labourer[500%],site engineer,Trucks[350%
]
bar bender[300%],concrete expert[300%
],concrete trucks[300%],G
eneral super intendent
bar bender,concrete expert,concrete trucks,General super intendent,heavy load trucks
bar bender,concrete trucks,General super intendent,labourer,concrete expert
excavator,General super intendent,project engineer,labourer
bar bender,concrete expert,concrete trucks,crane,heavy load trucks
bar bender,General super intendent,labourer,crane
bar bender,crane,labourer,General super intendent
bar bender,concrete expert,concrete trucks,crane,General super intendent
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Hal
122013
20142015
Task
Critical Task
Milestone
Sum
mary
Rolled U
p Task
Rolled U
p Critical Task
Split
Project S
umm
ary
Deadline
Project S
chedule for Direct C
onnector between I-10 and highw
ay 99
Norw
ich University
5
Prepared by: D
awit B
ogale
Approved by: Pascarella B
ryan
IDTask N
ame
Duration
Start
Finish
79C
urbs andP
arapets10
daysM
on11/11/13
Fri11/22/13
80D
irect Connector F
160days
Mon
11/25/13Fri
7/4/14
81substructure
90days
Mon
11/25/13Fri
3/28/1482
FoundationE
xcavation10
daysM
on11/25/13
Fri12/6/13
83Footing
20days
Mon
12/9/13Fri
1/3/1484
Pier
20days
Mon
1/6/14Fri
1/31/1485
Abutm
ent30
daysM
on2/3/14
Fri3/14/14
86A
butment
backfill10
daysM
on3/17/14
Fri3/28/14
87Superstructure
70days
Mon
3/31/14Fri
7/4/1488
IV G
irder20
daysM
on3/31/14
Fri4/25/14
89D
eck Forms
15days
Mon
4/28/14Fri
5/16/1490
Shear
Connectors
5 daysM
on5/19/14
Fri5/23/14
91D
eck20
daysM
on5/26/14
Fri6/20/14
92C
urbs andP
arapets10
daysM
on6/23/14
Fri7/4/14
93D
irect Connector G
160days
Mon
11/25/13Fri
7/4/14
94substructure
90days
Mon
11/25/13Fri
3/28/14
bar bender,concrete expert,concrete trucks,crane,labourer
excavator[200%],G
eneral super intendent,labourer[500%],site engineer,T
bar bender[300%],concrete expert[300%
],concrete trucks[300%],G
ene
bar bender,concrete expert,concrete trucks,General super intenden
bar bender,concrete trucks,General super intendent,labourer,co
excavator,General super intendent,project engineer,labourer
bar bender,concrete expert,concrete trucks,crane,heavy loa
bar bender,General super intendent,labourer,crane
bar bender,crane,labourer,General super intendent
bar bender,concrete expert,concrete trucks,crane,Gene
bar bender,concrete expert,concrete trucks,crane,labo
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Hal
122013
20142015
Task
Critical Task
Milestone
Sum
mary
Rolled U
p Task
Rolled U
p Critical Task
Split
Project S
umm
ary
Deadline
Project S
chedule for Direct C
onnector between I-10 and highw
ay 99
Norw
ich University
6
Prepared by: D
awit B
ogale
Approved by: Pascarella B
ryan
IDTask N
ame
Duration
Start
Finish
95FoundationE
xcavation10
daysM
on11/25/13
Fri12/6/13
96Footing
20days
Mon
12/9/13Fri
1/3/1497
Pier
20days
Mon
1/6/14Fri
1/31/1498
Abutm
ent30
daysM
on2/3/14
Fri3/14/14
99A
butment
backfill10
daysM
on3/17/14
Fri3/28/14
100Superstructure
70days
Mon
3/31/14Fri
7/4/14101
IV G
irder20
daysM
on3/31/14
Fri4/25/14
102D
eck Forms
15days
Mon
4/28/14Fri
5/16/14103
Shear
Connectors
5 daysM
on5/19/14
Fri5/23/14
104D
eck20
daysM
on5/26/14
Fri6/20/14
105C
urbs andP
arapets10
daysM
on6/23/14
Fri7/4/14
106D
irect Connector H
160days
Mon
11/25/13Fri
7/4/14
107substructure
90days
Mon
11/25/13Fri
3/28/14108
FoundationE
xcavation10
daysM
on11/25/13
Fri12/6/13
109Footing
20days
Mon
12/9/13Fri
1/3/14110
Pier
20days
Mon
1/6/14Fri
1/31/14
excavator[200%],G
eneral super intendent,labourer[500%],site engineer,
bar bender[300%],concrete expert[300%
],concrete trucks[300%],G
ene
bar bender,concrete expert,concrete trucks,General super intenden
bar bender,concrete trucks,General super intendent,labourer,co
excavator,General super intendent,project engineer,labourer
bar bender,concrete expert,concrete trucks,crane,heavy loa
bar bender,General super intendent,labourer,crane
bar bender,crane,labourer,General super intendent
bar bender,concrete expert,concrete trucks,crane,Gene
bar bender,concrete expert,concrete trucks,crane,labo
excavator[200%],G
eneral super intendent,labourer[500%],site engineer,T
bar bender[300%],concrete expert[300%
],concrete trucks[300%],G
ene
bar bender,concrete expert,concrete trucks,General super intenden
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Hal
122013
20142015
Task
Critical Task
Milestone
Sum
mary
Rolled U
p Task
Rolled U
p Critical Task
Split
Project S
umm
ary
Deadline
Project S
chedule for Direct C
onnector between I-10 and highw
ay 99
Norw
ich University
7
Prepared by: D
awit B
ogale
Approved by: Pascarella B
ryan
IDTask N
ame
Duration
Start
Finish
111A
butment
30days
Mon
2/3/14Fri
3/14/14112
Abutm
entbackfill
10days
Mon
3/17/14Fri
3/28/14113
Superstructure70
daysM
on3/31/14
Fri7/4/14
114IV
Girder
20days
Mon
3/31/14Fri
4/25/14115
Deck Form
s15
daysM
on4/28/14
Fri5/16/14
116S
hearC
onnectors5 days
Mon
5/19/14Fri
5/23/14117
Deck
20days
Mon
5/26/14Fri
6/20/14118
Curbs and
Parapets
10days
Mon
6/23/14Fri
7/4/14119
10 %C
ontigency cost0 days
Sat 9/1/12
Sat
9/1/12120
7 % Indirect
cost0 days
Sat 9/1/12
Sat
9/1/12
bar bender,concrete trucks,General super intendent,labourer,co
excavator,General super intendent,project engineer,labourer
bar bender,concrete expert,concrete trucks,crane,heavy loa
bar bender,General super intendent,labourer,crane
bar bender,crane,labourer,General super intendent
bar bender,concrete expert,concrete trucks,crane,Gene
bar bender,concrete expert,concrete trucks,crane,labo
9/1
9/1
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
May
JulS
epN
ovJan
Mar
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Half
2nd Half
1st Hal
122013
20142015
Task
Critical Task
Milestone
Sum
mary
Rolled U
p Task
Rolled U
p Critical Task
Split
Project S
umm
ary
Deadline
Project S
chedule for Direct C
onnector between I-10 and highw
ay 99
Norw
ich University
8
Prepared by: D
awit B
ogale
Approved by: Pascarella B
ryan
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
129
8. APPENDIX B
TABLE 18. CASH FLOW
Direct C
onnectors between I-10 and H
ighway 99
Bridge on highw
ay 99 bypass over I-10substructure
Foundation Excavation
$35,200.00Footing
$1,036,800.00$1,008,000.00
Pier
$1,339,520.00$721,280.00
Abutm
ent$1,030,000.00
$1,030,000.00A
butment backfill
$375,360.00$250,240.00
Superstructure
IV G
irder$5,803,360.00
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector A
substructureFoundation E
xcavation $35,200.00
Footing$536,800.00
$508,000.00P
ier$689,520.00
$371,280.00A
butment
$530,000.00$530,000.00
Abutm
ent backfill$195,360.00
$130,240.00S
uperstructureIV
Girder
$2,953,360.00D
eck Forms
Shear C
onnectors D
eckC
urbs and Parapets
Direct C
onnector Bsubstructure
Foundation Excavation
$35,200.00Footing
$536,800.00$508,000.00
Pier
$689,520.00$371,280.00
Abutm
ent$530,000.00
$530,000.00A
butment backfill
$195,360.00$130,240.00
Superstructure
IV G
irder$2,953,360.00
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapets
Septem
berO
ctoberN
ovember
Decem
berJanuary
February
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 1
Direct C
onnector Csubstructure
Foundation Excavation
FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector D
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector E
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector F
Septem
berO
ctoberN
ovember
Decem
berJanuary
February
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 2
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector G
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector H
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapets 10 %
Contigency cost
$8,200,000.00 7 %
Indirect cost$5,740,000.00
Septem
berO
ctoberN
ovember
Decem
berJanuary
February
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 3
Total$16,156,000.00
$4,742,560.00$3,553,840.00
$2,856,080.00$12,220,800.00
Septem
berO
ctoberN
ovember
Decem
berJanuary
February
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 4
Direct C
onnectors between I-10 and H
ighway 99
Bridge on highw
ay 99 bypass over I-10substructure
Foundation Excavation
FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
$305,440.00D
eck Forms
$60,000.00S
hear Connectors
$16,000.00$4,000.00
Deck
$4,112,000.00C
urbs and Parapets
$648,000.00D
irect Connector A
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
$155,440.00D
eck Forms
$60,000.00S
hear Connectors
$16,000.00$4,000.00
Deck
$2,112,000.00C
urbs and Parapets
$348,000.00D
irect Connector B
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
$155,440.00D
eck Forms
$60,000.00S
hear Connectors
$16,000.00$4,000.00
Deck
$2,112,000.00C
urbs and Parapets
$348,000.00
FebruaryM
archA
prilM
ayJune
July
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 5
Direct C
onnector Csubstructure
Foundation Excavation
$35,200.00Footing
$110,240.00$934,560.00
Pier
$265,200.00$795,600.00
Abutm
ent$176,666.67
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector D
substructureFoundation E
xcavation $35,200.00
Footing$110,240.00
$934,560.00P
ier$265,200.00
$795,600.00A
butment
$176,666.67A
butment backfill
Superstructure
IV G
irderD
eck Forms
Shear C
onnectors D
eckC
urbs and Parapets
Direct C
onnector Esubstructure
Foundation Excavation
$35,200.00Footing
$110,240.00$934,560.00
Pier
$265,200.00$795,600.00
Abutm
ent$176,666.67
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector F
FebruaryM
archA
prilM
ayJune
July
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 6
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector G
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector H
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapets 10 %
Contigency cost
7 % Indirect cost
FebruaryM
archA
prilM
ayJune
July
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 7
Total$844,320.00
$8,348,000.00$1,780,320.00
$3,599,280.00$2,916,800.01
FebruaryM
archA
prilM
ayJune
July
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 8
Direct C
onnectors between I-10 and H
ighway 99
Bridge on highw
ay 99 bypass over I-10substructure
Foundation Excavation
FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector A
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector B
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapets
JulyA
ugustS
eptember
October
Novem
berD
ecember
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 9
Direct C
onnector Csubstructure
Foundation Excavation
FootingP
ierA
butment
$812,666.67$70,666.67
Abutm
ent backfill$325,600.00
Superstructure
IV G
irder$1,554,400.00
$1,554,400.00D
eck Forms
$44,000.00$16,000.00
Shear C
onnectors $20,000.00
Deck
$1,478,400.00$633,600.00
Curbs and P
arapets$348,000.00
Direct C
onnector Dsubstructure
Foundation Excavation
FootingP
ierA
butment
$812,666.67$70,666.67
Abutm
ent backfill$325,600.00
Superstructure
IV G
irder$1,554,400.00
$1,554,400.00D
eck Forms
$44,000.00$16,000.00
Shear C
onnectors $20,000.00
Deck
$1,478,400.00$633,600.00
Curbs and P
arapets$348,000.00
Direct C
onnector Esubstructure
Foundation Excavation
FootingP
ierA
butment
$812,666.67$70,666.67
Abutm
ent backfill$325,600.00
Superstructure
IV G
irder$1,554,400.00
$1,554,400.00D
eck Forms
$44,000.00$16,000.00
Shear C
onnectors $20,000.00
Deck
$1,478,400.00$633,600.00
Curbs and P
arapets$348,000.00
Direct C
onnector F
JulyA
ugustS
eptember
October
Novem
berD
ecember
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 10
substructureFoundation E
xcavation $31,200.00
FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector G
substructureFoundation E
xcavation $31,200.00
FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector H
substructureFoundation E
xcavation $31,200.00
FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapets 10 %
Contigency cost
7 % Indirect cost
JulyA
ugustS
eptember
October
Novem
berD
ecember
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 11
Total$2,438,000.01
$5,852,000.01$4,795,200.00
$4,543,200.00$3,038,400.00
JulyA
ugustS
eptember
October
Novem
berD
ecember
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 12
Direct C
onnectors between I-10 and H
ighway 99
Bridge on highw
ay 99 bypass over I-10substructure
Foundation Excavation
FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector A
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector B
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapets
Decem
berJanuary
FebruaryM
archA
prilM
ay
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 13
Direct C
onnector Csubstructure
Foundation Excavation
FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector D
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector E
substructureFoundation E
xcavation FootingP
ierA
butment
Abutm
ent backfillS
uperstructureIV
Girder
Deck Form
s S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector F
Decem
berJanuary
FebruaryM
archA
prilM
ay
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 14
substructureFoundation E
xcavation $4,000.00
Footing$892,400.00
$152,400.00P
ier$1,060,800.00
Abutm
ent$706,666.67
$353,333.33A
butment backfill
$325,600.00S
uperstructureIV
Girder
$155,440.00$2,953,360.00
Deck Form
s $12,000.00
Shear C
onnectors D
eckC
urbs and Parapets
Direct C
onnector Gsubstructure
Foundation Excavation
$4,000.00Footing
$892,400.00$152,400.00
Pier
$1,060,800.00A
butment
$706,666.67$353,333.33
Abutm
ent backfill$325,600.00
Superstructure
IV G
irder$155,440.00
$2,953,360.00D
eck Forms
$12,000.00S
hear Connectors
Deck
Curbs and P
arapetsD
irect Connector H
substructureFoundation E
xcavation $4,000.00
Footing$892,400.00
$152,400.00P
ier$1,060,800.00
Abutm
ent$706,666.67
$353,333.33A
butment backfill
$325,600.00S
uperstructureIV
Girder
$155,440.00$2,953,360.00
Deck Form
s $12,000.00
Shear C
onnectors D
eckC
urbs and Parapets
10 % C
ontigency cost 7 %
Indirect cost
Decem
berJanuary
FebruaryM
archA
prilM
ay
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 15
Total$2,689,200.00
$3,639,600.00$2,120,000.01
$2,503,119.99$8,896,080.00
Decem
berJanuary
FebruaryM
archA
prilM
ay
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 16
Direct C
onnectors between I-10 and H
ighway 99
Bridge on highw
ay 99 bypass over I-10substructure
Foundation Excavation
$35,200.00Footing
$2,044,800.00P
ier$2,060,800.00
Abutm
ent$2,060,000.00
Abutm
ent backfill$625,600.00
Superstructure
IV G
irder$6,108,800.00
Deck Form
s $60,000.00
Shear C
onnectors $20,000.00
Deck
$4,112,000.00C
urbs and Parapets
$648,000.00D
irect Connector A
substructureFoundation E
xcavation $35,200.00
Footing$1,044,800.00
Pier
$1,060,800.00A
butment
$1,060,000.00A
butment backfill
$325,600.00S
uperstructureIV
Girder
$3,108,800.00D
eck Forms
$60,000.00S
hear Connectors
$20,000.00D
eck$2,112,000.00
Curbs and P
arapets$348,000.00
Direct C
onnector Bsubstructure
Foundation Excavation
$35,200.00Footing
$1,044,800.00P
ier$1,060,800.00
Abutm
ent$1,060,000.00
Abutm
ent backfill$325,600.00
Superstructure
IV G
irder$3,108,800.00
Deck Form
s $60,000.00
Shear C
onnectors $20,000.00
Deck
$2,112,000.00C
urbs and Parapets
$348,000.00
TotalM
ayJune
JulyA
ugust
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 17
Direct C
onnector Csubstructure
Foundation Excavation
$35,200.00Footing
$1,044,800.00P
ier$1,060,800.00
Abutm
ent$1,060,000.01
Abutm
ent backfill$325,600.00
Superstructure
IV G
irder$3,108,800.00
Deck Form
s $60,000.00
Shear C
onnectors $20,000.00
Deck
$2,112,000.00C
urbs and Parapets
$348,000.00D
irect Connector D
substructureFoundation E
xcavation $35,200.00
Footing$1,044,800.00
Pier
$1,060,800.00A
butment
$1,060,000.01A
butment backfill
$325,600.00S
uperstructureIV
Girder
$3,108,800.00D
eck Forms
$60,000.00S
hear Connectors
$20,000.00D
eck$2,112,000.00
Curbs and P
arapets$348,000.00
Direct C
onnector Esubstructure
Foundation Excavation
$35,200.00Footing
$1,044,800.00P
ier$1,060,800.00
Abutm
ent$1,060,000.01
Abutm
ent backfill$325,600.00
Superstructure
IV G
irder$3,108,800.00
Deck Form
s $60,000.00
Shear C
onnectors $20,000.00
Deck
$2,112,000.00C
urbs and Parapets
$348,000.00D
irect Connector F
TotalM
ayJune
JulyA
ugust
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 18
substructureFoundation E
xcavation $35,200.00
Footing$1,044,800.00
Pier
$1,060,800.00A
butment
$1,060,000.00A
butment backfill
$325,600.00S
uperstructureIV
Girder
$3,108,800.00D
eck Forms
$48,000.00$60,000.00
Shear C
onnectors $20,000.00
$20,000.00D
eck$528,000.00
$1,584,000.00$2,112,000.00
Curbs and P
arapets$208,800.00
$139,200.00$348,000.00
Direct C
onnector Gsubstructure
Foundation Excavation
$35,200.00Footing
$1,044,800.00P
ier$1,060,800.00
Abutm
ent$1,060,000.00
Abutm
ent backfill$325,600.00
Superstructure
IV G
irder$3,108,800.00
Deck Form
s $48,000.00
$60,000.00S
hear Connectors
$20,000.00$20,000.00
Deck
$528,000.00$1,584,000.00
$2,112,000.00C
urbs and Parapets
$208,800.00$139,200.00
$348,000.00D
irect Connector H
substructureFoundation E
xcavation $35,200.00
Footing$1,044,800.00
Pier
$1,060,800.00A
butment
$1,060,000.00A
butment backfill
$325,600.00S
uperstructureIV
Girder
$3,108,800.00D
eck Forms
$48,000.00$60,000.00
Shear C
onnectors $20,000.00
$20,000.00D
eck$528,000.00
$1,584,000.00$2,112,000.00
Curbs and P
arapets$208,800.00
$139,200.00$348,000.00
10 % C
ontigency cost$8,200,000.00
7 % Indirect cost
$5,740,000.00
TotalM
ayJune
JulyA
ugust
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 19
Total$1,788,000.00
$5,378,400.00$417,600.00
$105,116,800.03Total
May
JuneJuly
August
Cash Flow
as of Sun 8/12/12
Direct C
onnector between I-10 and highw
ay 99D
awit B
ogale
Page 20
Prepared by: Dawit Bogale Submitted to: Dave Mukerman
Capstone project 2012
151