Cable Presentation for Drum Project

Embed Size (px)

Citation preview

  • 7/28/2019 Cable Presentation for Drum Project

    1/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    2/143

    www.ieema.org [email protected]

    Power Delivery System Electricity from the Generating Site (the Power Plant) is delivered to residential,

    commercial and industrial customers through a system of wires (overhead) orcables (underground), switches, protection & control devices and transformers

  • 7/28/2019 Cable Presentation for Drum Project

    3/143

    www.ieema.org [email protected]

    PresentationonElectrical Cables&Accessories

  • 7/28/2019 Cable Presentation for Drum Project

    4/143

    www.ieema.org [email protected]

    Conductor

    (CU / AL)

    Wires

    Conductor

    Armoured

    Cables

    Laid Up

    Cables

    Inner

    Sheathed

    cables

    FinishedCables

    Cores

    Drawing

    Bunching

    Stranding

    Laying Up

    (For Multi Core)

    Sheathing

    Taping Armouring

    Testing and

    Packing

    Insulation

    Sheathing

    Manufacturing Process of Electrical Power Cables

  • 7/28/2019 Cable Presentation for Drum Project

    5/143

    www.ieema.org [email protected]

    Finest Electrolytic Grade 99.9 % Pure

    Copper or Aluminium

    The process reduces the wire rods to

    Specified or desired wire diameter.

    Annealing & Tinning of fine copper wires.

    Wire DrawingManufacturing Process

    Conductor

    (CU / AL)

    Wires

    Drawing

  • 7/28/2019 Cable Presentation for Drum Project

    6/143

    www.ieema.org [email protected]

    StrandingThe individual strands are bunched together

    to form a conductor of specified size.

    Manufacturing Process

    Conductor

    (CU / AL)

    Wires

    Conductor

    Drawing

    Bunching

    Stranding

  • 7/28/2019 Cable Presentation for Drum Project

    7/143www.ieema.org [email protected]

    Extruders

    Triple Extrusion line for HT cables

    Manufacturing ProcessInsulation

  • 7/28/2019 Cable Presentation for Drum Project

    8/143www.ieema.org [email protected]

    Manufacturing Process : Copper ScreeningOnly for HT Cables above 6.6 KV Grade

    Copper tape with the number/color marking is applied over the cores.

    Where required Water blocking tape can also be provided.

    Copper tape Screening & Copper wire screening.

  • 7/28/2019 Cable Presentation for Drum Project

    9/143www.ieema.org [email protected]

    Lay up to 100 cores with Extruded/taped inner sheath

    Manufacturing ProcessLaying Up

    Conductor

    (CU / AL)

    Wires

    Conductor

    Laid UpCables

    Cores

    Drawing

    Bunching

    Stranding

    Laying Up

    (For Multi Core)

    Insulation

  • 7/28/2019 Cable Presentation for Drum Project

    10/143

  • 7/28/2019 Cable Presentation for Drum Project

    11/143www.ieema.org [email protected]

    Emboss/Print on line on outer sheath.

    Manufacturing ProcessSheathing

    Conductor

    (CU / AL)

    Wires

    Conductor

    Armoured

    Cables

    Laid Up

    Cables

    Inner

    Sheathedcables

    Finished

    Cables

    Cores

    Drawing

    Bunching

    Stranding

    Laying Up

    (For Multi Core)

    Sheathing

    Taping Armouring

    Insulation

    Sheathing

  • 7/28/2019 Cable Presentation for Drum Project

    12/143www.ieema.org [email protected]

    Quality treated wooden / steel Drums for winding the finished cables

    before final testing & delivery.

    Manufacturing ProcessConductor

    (CU / AL)

    Wires

    Conductor

    Armoured

    Cables

    Laid Up

    Cables

    Inner

    Sheathed

    cables

    Finished

    Cables

    Cores

    Drawing

    Bunching

    Stranding

    Laying Up

    (For Multi Core)

    Sheathing

    Taping Armouring

    Testing and

    Packing

    Insulation

    Sheathing

  • 7/28/2019 Cable Presentation for Drum Project

    13/143www.ieema.org [email protected]

    Four major parameters of cable design to

    illustrate the proper design

    Conductor

    Insulation

    Armouring

    Sheathing

    Emphasis On Design

  • 7/28/2019 Cable Presentation for Drum Project

    14/143www.ieema.org [email protected]

    The heart of the cable is the Conductor.

    Conductor

  • 7/28/2019 Cable Presentation for Drum Project

    15/143www.ieema.org [email protected]

    Example of selection of the no of strands in a conductor.

    WHY 19 STRANDS ARE REQUIRED

    FOR 70 SQ.MM. CONDUCTOR?

    NO OF STRAND:-19 SIZE:-2.24mm1

    d =2.24mm.

    d=PITCH CIRCULAR DIAMETER

    FOR FIRST LAYER = 2X2.24mm =

    4.48mm

    NO. OF WIRES IN FIRST LAYER =

    dX3.14/d = 4.48X3.14/2.24

    6 WIRE3 1 2

    d =2Xd

    Conductor

  • 7/28/2019 Cable Presentation for Drum Project

    16/143

  • 7/28/2019 Cable Presentation for Drum Project

    17/143www.ieema.org [email protected]

    When conductors are not properly shaped, they have gaps , sharp edges

    in between the wires, which may lead to failures , after a period of time.

    Gaps also increase Conductor Resistance

    A properly designed conductor

    is smooth and compact.

    Conductor

  • 7/28/2019 Cable Presentation for Drum Project

    18/143www.ieema.org [email protected]

    If the compaction is not proper, it can lead to air gaps, which increase

    conductor resistance.

    A Bad Design of Conductor Can Cause

    3% to 9% Transmission loss,Failure due to Sharp

    Edges.

    Conductor

  • 7/28/2019 Cable Presentation for Drum Project

    19/143www.ieema.org [email protected]

    A good Insulation should have:

    High insulation resistance

    High dielectric strength

    Good mechanical properties

    Tenacity & elasticity should not be affected by

    chemicals.

    Should be non hygroscopic.

    Insulation

  • 7/28/2019 Cable Presentation for Drum Project

    20/143www.ieema.org [email protected]

    Insulation Uniformity of Insulation Thickness & Eccentricity

    Avoids increase in charging current and

    lessens the voltage drop

    If dielectric is not uniform, it leads to increase

    in the capacitance of the conductor and

    resultant higher temperature.

  • 7/28/2019 Cable Presentation for Drum Project

    21/143

    www.ieema.org [email protected]

    Laying up & Inner Sheath The cores are laid up, along with fillers & suitable

    binding tape, ensuring circularity. It is an

    international practice to have filler insertedbetween the cores, to prevent displacement of

    the cores in manufacturing as well as in laying of

    cable at site.

  • 7/28/2019 Cable Presentation for Drum Project

    22/143

    www.ieema.org [email protected]

    Laying up & Inner Sheath Many times cores are laid up with nylon/cotton

    twine, which results in cores getting damaged,

    which effects not just the insulation thickness

    but also, the overall performance of the cable.

  • 7/28/2019 Cable Presentation for Drum Project

    23/143

    www.ieema.org [email protected]

    Laying up & Inner Sheath CABLE WITH NON HYGROSCOPIC

    POLYPROPYLENE TAPE & FILLERS

    PP tape & Filler has very high melting point i.e.

    160 C.

    Has very high insulation resistance property

    i.e. 150 Mohm/km

    Works as water barrier, prevents water

    penetration inside the cable.

    Less flexibility than other types of

    polyethylene, which prevents the cores from

    displacement in the cable.

  • 7/28/2019 Cable Presentation for Drum Project

    24/143

    www.ieema.org [email protected]

    ArmouringApart from mechanical protection, an important feature of

    Armour design is to provide effective conductance of

    earth fault current. When designing an armoured cable,

    the selection of minimum number of armour wire/stripsplays a very important role

  • 7/28/2019 Cable Presentation for Drum Project

    25/143

    www.ieema.org [email protected]

    ArmouringExample : 3.5 C X 240 SQ.MM A2XFY cable.

    Min. 34 strips require for 100% coverage.

    And with this the armour resistance at 20 C

    will be 1.62 ohm/km & short circuit current

    carrying capacity will be 4.2 kA/Sec,

    where as the Max requirement as per IS 7098 part I

    is 1.64 ohm/km

    If we use 30 strips in place of 34,

    there will be a gap and the armour

    resistance will be increased to 1.79 ohm/km &

    short circuit current carrying capacity

    will come down to 3.7 kA/sec

  • 7/28/2019 Cable Presentation for Drum Project

    26/143

    www.ieema.org [email protected]

    Armouring protects the cable from mechanical damage.

    Maintain minimum 95% coverage to protect the cable from any

    mechanical damage because of sharp edges.

    Badly Armoured Cables

    Armouring

  • 7/28/2019 Cable Presentation for Drum Project

    27/143

    www.ieema.org [email protected]

    This Protects the Overall Cable

    Embossing / printing options on the outer sheath.

    Outer Sheathing

  • 7/28/2019 Cable Presentation for Drum Project

    28/143

    www.ieema.org [email protected]

    Stringent Quality checks at each and every level.

    Raw materials.

    In Process.

    Finished goods.

    Emphasis On Quality

    EMPHASIS ON QUALITY : TESTING LABS

  • 7/28/2019 Cable Presentation for Drum Project

    29/143

    www.ieema.org [email protected]

    Raw Material Testing

    The major raw materials in a Cable are :-

    Copper/Aluminium Rods

    PVC/XLPE Compounds

    Armour Wires/Strips

    Emphasis On Quality

  • 7/28/2019 Cable Presentation for Drum Project

    30/143

    www.ieema.org [email protected]

    Copper/Aluminium Rods

    Tensile Strength

    Resistivity

    Purity

    Surface Finish

    Diameter

    Aluminium Rods

    Emphasis On Quality : R.M.Testing

  • 7/28/2019 Cable Presentation for Drum Project

    31/143

    www.ieema.org [email protected]

    XLPE & PVC Compounds

    Tensile Strength & Elongation

    Hot set

    Volume Resistivity

    Ageing

    Thermal Stability

    Density Galvanized Steel Wires / Strips

    Tensile Strength & Elongation

    Dimensions

    Zinc Coating (Dip Test)

    Torsion/Winding

    Resistivity

    Emphasis On Quality : R.M.Testing

  • 7/28/2019 Cable Presentation for Drum Project

    32/143

    www.ieema.org [email protected]

    In process quality checks are performed at each and every stage of

    manufacturing

    Stage wise details of Quality checks performed are shown in the next

    set of folios.

    Diameter

    Surface finish

    Tensile/Wrapping test for Aluminium

    Annealing/Elongation test for Copper

    Resistivity

    Emphasis On Quality

    Wire Drawing : R. M. Testing

  • 7/28/2019 Cable Presentation for Drum Project

    33/143

    www.ieema.org [email protected]

    No. of strands

    Stranding Sequence

    Surface finish

    Resistance

    Conductor screening (HT)

    Thickness

    Tensile strength & Elongation

    Hot Set test

    Surface finish

    Type of Compound

    Dia. Over conductor

    Dia. Over insulation & Insulation screening (HT)

    Stranding : Quality Checks

    Insulation : Quality Checks

  • 7/28/2019 Cable Presentation for Drum Project

    34/143

    www.ieema.org [email protected]

    No. of wires / Diameter of wire (Wire Screening)

    Gap between wires (Wire Screening)

    Lay length (Taping / Wire screening)

    Tape Overlap (Taping)

    Sequence of Laying

    Diameter over laid up cores

    Lay length

    Laying Up Quality Checks

    Copper Screening : Qulaity Checks

  • 7/28/2019 Cable Presentation for Drum Project

    35/143

    www.ieema.org [email protected]

    Thickness

    Diameter over inner sheath

    Surface finish

    Inner Sheath : Quality Checks

    Armouring : Quality Checks Dimension of wire/strip

    Diameter over armouring

    Gap between wires/strip

    No. of wires/Strip

    Direction of lay and lay length

  • 7/28/2019 Cable Presentation for Drum Project

    36/143

    www.ieema.org [email protected]

    Thickness

    Diameter over outer sheath

    Tensile strength & Elongation

    Surface finish & Marking/Embossing

    Colour of sheath & Type of Compound

    Outer Sheath : Quality Checks

  • 7/28/2019 Cable Presentation for Drum Project

    37/143

    www.ieema.org [email protected]

    Emphasis On Quality Checks Finished Goods testing

    Routine tests are carried out as per relevant standards on each cable

    length.

    Type tests are carried out for each LOT (One manufacturing length)

    Acceptance tests and Inspections can be arranged as per requirements ofcustomers.

    Testing Facilities should include :

    Partial Discharge

    FRLS Testing

    Oxygen Index

    Smoke Density

    Halogen Gas

    High Voltage / Impulse Voltage

  • 7/28/2019 Cable Presentation for Drum Project

    38/143

    www.ieema.org [email protected]

    Packing & Marking

    Testing of End sealing.

    Testing of packing and wooden drums

    Inspection for marking and scripts

    Emphasis On Quality Packing Drums

    Inspection of Marking on sheath

  • 7/28/2019 Cable Presentation for Drum Project

    39/143

    www.ieema.org [email protected]

    CABLE LAYING&INSTALLATION

  • 7/28/2019 Cable Presentation for Drum Project

    40/143

    www.ieema.org [email protected]

    Cable installation involves selection of cable route, mode of installation

    i.e. underground, in duct or cable ladder/ trays, associated accessories and

    man power

    For cable laying it is very essential to get acquainted with the visible as

    well as hidden obstacles and following activities are recommended prior tothe actual laying work

    Inspection of cable route

    Trial holes to check thermal resistivity & underground

    obstacles.

    Excavation (Trenching) & preparation of cable bed Laying of necessary pipes

    Drum handling & cable pulling equipment including pay

    off jacks

    Arrangement of filling.

    Back filling

    Planning

  • 7/28/2019 Cable Presentation for Drum Project

    41/143

    www.ieema.org [email protected]

    Inspection of cable route :The cable route is first inspected as per the main plan for visibleobstruction such as trees, manholes, road crossing etc.

    Trial Holes:After inspection of the cable route, it is advisable to have theknowledge of the underground obstruction. Trial holes are generally

    taken at every 50 meters interval along the planned cable route up to

    10 cm below the planned depth of laying. The route is then inspected

    for underground obstruction e.g. water lines, drainage lines,

    telephone cables, power cables or other utilities etc.

    After this the cable route is finalized keeping in view that it should

    be straight as far as possible and proper depth is permissible. It is

    then marked suitably for trenching

  • 7/28/2019 Cable Presentation for Drum Project

    42/143

  • 7/28/2019 Cable Presentation for Drum Project

    43/143

    www.ieema.org [email protected]

    Clearances : The desired minimum clearances are as under- Power to Control cables : 0.2 m

    Power to communication cables : 0.3 m

    Power cables to gas/water main : 0.3 m

    Inductive influence on sensitive control cable on account of near

    by power cable should also be checked.

    Width of trench : The width of trench depends on no & diameter of cables to be laid. For

    HV & EHV cables the width of excavation is generally as under-

    No. of Cables HV Cables EHV Cables

    3 0.65 m 0.8 m

    4 0.85 m 1.05 m

  • 7/28/2019 Cable Presentation for Drum Project

    44/143

    www.ieema.org [email protected]

    Sand bedding: Sand bedding of minimum 10 cm is provided for the cables laid

    directly in ground for protection. The grain size of sand should

    preferably be less than 8 mm. The material with high volume weight

    ratio has a good distribution among grain sizes and it has normally

    low thermal resistivity, even when it has lower moisture.

    Laying of Ducts/ pipes: Steel, cast iron, plastics, cements or earthenware ducts or

    cable ducting blocks are used for cables crossing

    roads/railway tracks. Spare ducts for future expansions

    should also be provided and should be properly sealed off.Buried ducts or ducting blocks should project into footpath

    or up to the edge of road, where there is no footpath, to

    permit smooth entry of cable without un-due bending. The

    duct/pipe should be mechanically strong to withstand the

    impact due to traffic when laid across road/railway tracks.

  • 7/28/2019 Cable Presentation for Drum Project

    45/143

    www.ieema.org [email protected]

    Laying of Ducts/ pipes (Continued): The pipe/duct are generally laid at depth 1.0 & 1.2 metres

    across road and railway racks respectively. The diameter of

    duct or pipe should be at least 1.5 times the outer diameter of

    cable.

    Single core cable should never be laid individually in steel

    ducts. However, it is permissible to lay all three cables of same

    system in one duct.

  • 7/28/2019 Cable Presentation for Drum Project

    46/143

    www.ieema.org [email protected]

    Transportation of cable drum: The cable drum must be handled properly to avoid any damageto cable during transportation. It is important that cable drum

    stands on the flanges during transportation, well fixed to the

    transport vehicle. Loading of drum should be done by crane or

    forklift. A ramp or crane should be used for unloading cabledrums from vehicle. Where it is not possible, a temporary ramp

    with approx. inclination 1:3 to1:4 should be constructed and

    cable drums should then be rolled over the ramp by means of

    ropes and winches. An additional sand bed at foot of the ramp is

    also helpful to brake the rolling of cable drum. Where it is

    necessary to roll the cable on ground, it should be done slowly

    and carefully. The drum should always be rolled in the direction

    of arrow marked on the drum to avoid unwinding & loosening of

    cable in the drum as shown in the figure.

  • 7/28/2019 Cable Presentation for Drum Project

    47/143

    www.ieema.org [email protected]

    Transportation of cable drum:

  • 7/28/2019 Cable Presentation for Drum Project

    48/143

    www.ieema.org [email protected]

    Pulling of cable: The cable drum shall be placed such that there is minimum inconvenience.

    Cable drum is normally placed on jacks at starting point, in such a way that

    direction arrow points to the opposite direction of the pulling, and a wire

    winch at the other end of the pulling distance of the trench. The pulling wire

    can be connected to the cable either by a cable stocking or directly to the

    conductor in such a manner that water or soil cannot enter the cable. Except

    for wire armoured cables, the cable is normally pulled by the conductor with

    pulling force limiting to the following -

    Aluminum conductor : 30 N/mm2

    Copper conductor : 50 N/mm2

    The cable should be pulled from the top of the drum. To prevent crossing of

    turns on the drum due to sudden stop in pulling, a brake should be arranged

    at the cable drum as shown in figure and a man should be placed there to

    operate this brake rapidly.

  • 7/28/2019 Cable Presentation for Drum Project

    49/143

    www.ieema.org [email protected]

    Pulling of cable drum:

  • 7/28/2019 Cable Presentation for Drum Project

    50/143

    www.ieema.org [email protected]

    Pulling of cable: With temperature below 30C, the cables should be warmed before the

    laying out, otherwise the bending can damage the insulation/protective

    covering of cables. The cable laying should be carried out swiftly so that

    the cable does not cool down too much.

    Warming of cable may be achieved by storing the cable drum for

    adequately longer period, not less than 24 hours, in a heated building or in

    a tent with hot air heaters

    To protect the cable from damage during pulling out, cablerollers should be used, placed at suitable intervals. Bends

    must be arranged very carefully and cable is not allowed to

    bend beyond the limit specified as mention here under.

    Closely spaced and well fixed angle rollers are skid plates

    should be used at all corners

  • 7/28/2019 Cable Presentation for Drum Project

    51/143

    www.ieema.org [email protected]

    MINIMUM PERMISSIBLE BENDING RADIUS

    PILC Cables PVC/XLPE Cables

    Cable Voltage single Multi single Multi

    rating core core core core

    Up to 1.1 kV 20 D 15 D 15 D 12 D

    3.3 kV to 11 kV 20 D 15 D 15 D 12 D

    22 kV & 33 kV 25 D 20 D 20 D 15 D

    Above 33 kV - - 20 D

    - D = outer diameter of cable

    Pulling of cable:

  • 7/28/2019 Cable Presentation for Drum Project

    52/143

    www.ieema.org [email protected]

    Filling:After laying the cable, sand should be filled in the trench to completelysurround the cable. The grain size of sand shall be less than 8 mm. The

    thickness of sand in all direction of the cable surface should normally not

    be less than 10 cm.Backfilling:Normally the backfill consists of material excavated earlier from the trench.However, bigger stones or pieces of rock should be removed.

    Extra protection:Important feeders and cables at places where high digging activity is

    expected can be further protected by means of tubes, slabs or troughs

    The tubes of non-magnetic material are mainly used at road crossing etc.

    The tube diameter should not be less than 2 times the cable diameter. The

    current rating of cables laid in tube is reduced up to 80% of the cable

    rating in ground. The tubes can be filled with material e.g. Bentonite,

    having thermal resistivity equal to the ground, to avoid reduction in ground

    rating.

  • 7/28/2019 Cable Presentation for Drum Project

    53/143

    www.ieema.org [email protected]

    In trenches, normally extra protection is achieved by providing flat

    concrete slabs of size selected according to the expected damage.

    Generally slab is 50 mm thick and of sufficient width to cover the

    cables. The slabs are placed directly on the sand as shown here

    below

  • 7/28/2019 Cable Presentation for Drum Project

    54/143

    www.ieema.org [email protected]

    A very efficient protection against cable damage can be obtained by

    using concrete troughs. The trough should be completely filled with

    the sand.

  • 7/28/2019 Cable Presentation for Drum Project

    55/143

    www.ieema.org [email protected]

    Warning tape (Specially for EHV cables):A pre warning tape, e.g. of yellow PVC, should be laid in the ground

    around o.2 to 0.4 metre under the surface and at least o.4 mm above the

    cable. In a trench with several cables, the warning tape should not be

    spaced more than 0.15 metres apart and the outermost cable should

    always be covered by warning tapes.

    Special precautions for single core cables:Except for EHV cables, the spacing between three cables laid in one

    plane should generally be not less than the cable diameter. When the

    cables are arranged in a duct or on rack, the cables should be secured by

    non-magnetic, non-corrosive clamps.When the cable run is several kilometer long, the cable should be

    transposed at 1/3rd and 2/3rd of the total route length.

    For cables in trefoil formation, non-magnetic clamps are not essential

    and steel, copper, Aluminum or plastic tape may be used to bind the cable

    trefoil

  • 7/28/2019 Cable Presentation for Drum Project

    56/143

  • 7/28/2019 Cable Presentation for Drum Project

    57/143

    www.ieema.org [email protected]

    BIRD CAGING

  • 7/28/2019 Cable Presentation for Drum Project

    58/143

    www.ieema.org [email protected]

    If the drum is kept on the flange or lifted from one

    side & cable unwound, there is all likelihood of twists

    in the armour, which would cause deformation

    of cores & outer-sheath.

    This process of deformation is called

    BIRD CAGING &

    is normally perceived as a manufacturing defect

    which is normally a HANDLING defect.

  • 7/28/2019 Cable Presentation for Drum Project

    59/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    60/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    61/143

    www.ieema.org [email protected]

    This can be prevented by unwinding the cable by loading the

    drum on jacks & pulling in the proper direction with stocking

    or pulling eye.

    Proper Handling of cables is very important, both from

    safety as well as long life of the installation.

    The most common causes of cable failure are due to

    mishandling of the product at installation stage.

    In the following slides we show you some of the effects

    of mishandling of the cables.

  • 7/28/2019 Cable Presentation for Drum Project

    62/143

    www.ieema.org [email protected]

    Recommendation for Installation

  • 7/28/2019 Cable Presentation for Drum Project

    63/143

    www.ieema.org [email protected]

    GROUP RATING FACTOR FOR SINGLE CORE

    CABLES LAID IN TREFOIL FORMATION

    B. Cables laid on Racks/Trays in covered trench withremovable covers where air circulation is restricted, trefoilsare separated by 2 cable dia. horizontally and the traysare in tiers with 300 mm. gap between them.

    NO. OFRACKS/TRAYS IN

    TIERS

    NO. OF TREFOILS IN HORIZONTAL FORMATION

    1236

    1 2 3

    0.950.900.880.86

    0.900.850.830.81

    0.880.830.810.79

    NUMBER OFTREFOILS IN

    GROUP

    SPACING BETWEEN TREFOILS3.3 TO 22 KV CABLES

    33 KV CABLES

    TOUCH

    ING

    15

    cm

    30

    cm

    45

    cm

    TOUCH

    ING

    15

    cm

    30

    cm

    45

    cm

    2345

    0.780.680.610.56

    0.810.710.650.61

    0.850.770.720.68

    0.880.810.760.73

    0.800.680.620.57

    0.820.710.650.60

    0.850.760.710.67

    0.880.790.750.72

    A. Cables laid in ground in horizontal formation

    C. Cables laid as in 'B' but in open air

    NO. OFRACKS/TRAYS IN

    TIERS

    NO. OF TREFOILS IN HORIZONTAL FORMATION

    1

    2

    3

    6

    1 2 3

    1.0

    1.0

    1.0

    1.0

    0.98

    0.95

    0.94

    0.93

    0.96

    0.93

    0.92

    0.90

  • 7/28/2019 Cable Presentation for Drum Project

    64/143

    www.ieema.org [email protected]

    GROUP RATING FACTOR MULTICORE CABLES

    NO. OFRACKS/TRAYS IN

    TIERS

    NO. OF CABLES

    12

    36

    1 2 3

    0.950.90

    0.880.86

    6 9

    0.900.85

    0.830.81

    0.880.83

    0.810.79

    0.850.81

    0.790.77

    0.840.80

    0.780.76

    B. Cables laid on cable trays exposed to air, the cables

    spaced by one cable diameter and trays in tiers by 300 mm.The clearance between the wall and the cables is 25 mm.

    A. Cables laid inside concrete trench with removeable

    covers, on cable trays where air circulation is restricted.

    The cables spaced by one cable diameter and the trays in

    tiers by 300 mm. The clearance of the cable from the wall is 25 mm.

    NO. OF CABLETRAYS IN

    TIERS

    NO. OF CABLES

    1236

    1 2 3

    1111

    6 9

    0.980.950.940.93

    0.960.930.920.90

    0.930.900.890.87

    0.920.890.880.86

    C. Cables laid on cable trays exposed to air, the cables

    touching and trays in tiers by 300 mm. The clearance

    between the wall and the cable is 25 rnm.

    NO. OF TRAYS

    NO. OF CABLES

    12

    3

    6

    1 2 3

    1.01.0

    1.0

    1.0

    6 9

    0.840.80

    0.78

    0.76

    0.800.76

    0.74

    0.72

    0.750.71

    0.70

    0.68

    0.730.69

    0.68

    0.66

    D. Cables laid direct in ground in horizontal formation.

    NO. OFCABLES

    IN GROUP

    SPACING OF CALBLES

    23

    4

    5

    6

    0.790.69

    0.62

    0.58

    0.54

    0.820.75

    0.69

    0.65

    0.61

    0.870.79

    0.74

    0.72

    0.69

    0.900.83

    0.79

    0.76

    0.75

    TOUCHING 15 cm 30 cm 45 cm

  • 7/28/2019 Cable Presentation for Drum Project

    65/143

    www.ieema.org [email protected]

    RATING FACTOR

    GROUNDTEMPERATURE(C)

    FACTOR

    15

    1.12

    20

    1.08

    25

    1.03

    30

    1.00

    35

    0.96

    40

    0.91

    45

    0.87

    A. Rating factors for ambient air temperature variation

    AMBIENTTEMPERATURE (C)

    25

    1.14

    30

    1.10

    35

    1.04

    40

    1.00

    45

    0.95

    50

    0.90FACTOR

    B. Rating factors for ground temperature variation

    DEPTH OF LAYING (cm)

    90

    105

    120

    150

    180or more

    6 KV, 10 KV AND15 KV ALL SIZES

    1.00

    0.99

    0.98

    0.960.95

    20KV AND 30 KVALL SIZES

    ---

    1.00

    0.99

    0.970.96

    C. Rating factors for depth of laying

    ( for cables laid direct in the ground)

    THERMALRESISTIVITY

    OF SOIL(ccm/w)

    100

    1.20

    120

    1.11

    150

    1.0

    200

    0.89

    250

    0.80

    300

    0.73FACTOR

    D. Rating factors for variation in Thermal Resistivity of soil

  • 7/28/2019 Cable Presentation for Drum Project

    66/143

    www.ieema.org [email protected]

    CABLE

    ACCESSORIES

  • 7/28/2019 Cable Presentation for Drum Project

    67/143

    www.ieema.org [email protected]

    SEPARABLE CONNECTORS

    LOADBREAK

    DEADBREAK

    OTHER CONNECTORS

    CABLE JOINTS CABLE TERMINATIONS

  • 7/28/2019 Cable Presentation for Drum Project

    68/143

    www.ieema.org [email protected]

    Utilize permanently crimped connectors

    Housings/Tubings are fully insulated,

    shielded and sealed

    Direct buried, vault, submersible and other

    severe service applications

    Units designed and tested per IS/VDE/IEEE

    Standards to assure system matched

    performance and ratings equal to cable

    Cable Joints Overview

  • 7/28/2019 Cable Presentation for Drum Project

    69/143

    www.ieema.org [email protected]

    Terminations &

    Cable Basics

  • 7/28/2019 Cable Presentation for Drum Project

    70/143

    www.ieema.org [email protected]

    While Cable Basics uses the CableTermination as the base example, the

    same principles apply anywhere a

    shielded medium or high voltage cableis terminated.

    Elbows, Joints, etc.

  • 7/28/2019 Cable Presentation for Drum Project

    71/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    72/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    73/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    74/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    75/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    76/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    77/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    78/143

  • 7/28/2019 Cable Presentation for Drum Project

    79/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    80/143

    www.ieema.org [email protected]

    Conductor

  • 7/28/2019 Cable Presentation for Drum Project

    81/143

  • 7/28/2019 Cable Presentation for Drum Project

    82/143

    www.ieema.org [email protected]

    + Insulation

    + Conductor shield

    Conductor

  • 7/28/2019 Cable Presentation for Drum Project

    83/143

    www.ieema.org [email protected]

    + Semi-Con Shield

    + Insulation

    + Conductor shield

    Conductor

  • 7/28/2019 Cable Presentation for Drum Project

    84/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    85/143

  • 7/28/2019 Cable Presentation for Drum Project

    86/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    87/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    88/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    89/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    90/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    91/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    92/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    93/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    94/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    95/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    96/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    97/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    98/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    99/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    100/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    101/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    102/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    103/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    104/143

  • 7/28/2019 Cable Presentation for Drum Project

    105/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    106/143

  • 7/28/2019 Cable Presentation for Drum Project

    107/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    108/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    109/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    110/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    111/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    112/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    113/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    114/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    115/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    116/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    117/143

    www.ieema.org [email protected]

    In case of p remo ldedterminat ions

  • 7/28/2019 Cable Presentation for Drum Project

    118/143

    www.ieema.org [email protected]

    The addi t ion o f a stress contro ltube tends to smooth the

    st ress concentrat ions in case

    of heat shr ink term inat ion s

  • 7/28/2019 Cable Presentation for Drum Project

    119/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    120/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    121/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    122/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    123/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    124/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    125/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    126/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    127/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    128/143

  • 7/28/2019 Cable Presentation for Drum Project

    129/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    130/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    131/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    132/143

    www.ieema.org [email protected]

    Only in case of

    premolded terminations

  • 7/28/2019 Cable Presentation for Drum Project

    133/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    134/143

  • 7/28/2019 Cable Presentation for Drum Project

    135/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    136/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    137/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    138/143

  • 7/28/2019 Cable Presentation for Drum Project

    139/143

    www.ieema.org [email protected]

  • 7/28/2019 Cable Presentation for Drum Project

    140/143

    www.ieema.org [email protected]

    This same cone shape

    is incorporated intomost Cable Accessories

  • 7/28/2019 Cable Presentation for Drum Project

    141/143

  • 7/28/2019 Cable Presentation for Drum Project

    142/143

    www.ieema.org [email protected]

    Right angle boot is

    used in case ofHeat shrink

    Terminations

    http://www.shrinkpolymersystems.co.uk/3cPilcBeltedTermination.pdf
  • 7/28/2019 Cable Presentation for Drum Project

    143/143

    End of Session..