62
RFP NO. C1045 1 06.18.13 It would be beneficial to view the exploratory shaft as it is being excavated. Will LACMTA arrange a site visit of the exploratory shaft (Contract C1034)? Metro has made arrangements for the C1045 proposers to visit the PLE Exploratory Shaft site located at 6006 W Wilshire Blvd for the purpose of viewing the installation of the soldier piles during the week of July 15 th and July 22 nd between the hours of 7AM to 3:30PM. Visitors need to arrive at the jobsite wearing full PPE (hardhat, safety glasses, vest and boots). Visitors are to check in with the Resident Engineer for an orientation and safety briefing. Visitors are to follow the instructions of Metro staff and the contractor as related to viewing areas and safety while on the jobsite. Any statements made by Metro staff or the contractor while at the jobsite visit are not binding and do not change the contract C1045. Other jobsite visits will be scheduled in the future for viewing of the excavation/lagging process. The project requires off-street parking. Visitors are encouraged to park at the Metro-leased lot located on the southeast corner of Ogden Drive and Genesse Avenue (Opposite the Exploratory Shaft). 07.05.13 2 06.18.13 Will LACMTA make soil samples/borings available for viewing? Metro will provide a second and FINAL viewing of cores samples at the SW corner of Wilshire/Crenshaw on Wednesday and Thursday, September 25th and 26th, respectively between the hours of 9am to 4pm. July 24th and July 25th between the hours of 9:00 am and 4:00 pm, at the offices of AMEC Environment & Infrastructure, located at: 6001 Rickenbacker Road Los Angeles, CA 90040. The sample borings (refer to attached table) include soil and rock conditions encountered along the tunnel alignment, and were selected considering tunnel and station locations, depths, geologic conditions to be encountered, and the presence of tar and transition areas. If proposers would like to view additional Section 1 borings, please email Eva Rodriguez at [email protected]. See attached table for Sample Borings Availability Dates. Proposers attending this FINAL viewing must contact Eva Rodriguez via email at [email protected] to schedule a viewing time. 07.09.13 08.30.13 3 07.11.13 The Metro Rail Design Criteria states that train control and communication rooms shall be protected with an approved non-water based special extinguishing system (such as an inergen system or equivalent), that does not damage or affect the performance of installed equipment. In the latest revised specs it says that In train control and communication room, provide hydraulically designed, single interlock, fully supervised pre-action sprinkler system, with electrically activated cross zoned smoke detectors. Am I Correct to assume that for the train control and communications rooms are to have an inergen system or equivalent, with a preaction system? Also how are the electric service vaults, aux power, and traction power substation going to be protected since they are the exception to not having automatic fire sprinkler systems in them? Contractor shall provide a water-based Pre-action Fire Protection (sprinkler) System for Train Control and Communication Rooms, not both water-based and non water- based (Inergen or equivalent) systems. Paragraph 2.6.6.2 E. and 2.6.2.1 of the FLS Criteria both allow for the use of a water-based Pre-Action fire sprinkler system. Paragraph 2.6.2.4 will be revised by Metro to allow for the alternate use of a non water-based (Inergen or equivalent) Fire Protection System, subject to the approval of the Agency Having Jurisdiction (AHJ). Electric Service vaults, Aux Power and Traction Power substations shall be provided with Fire Extinguishers per Paragraph 2.6.4.of the FLS Criteria.” 07.19.13 No. Date of Question WESTSIDE SUBWAY EXTENSION PROJECT, SECTION 1 (D/B) QUESTION & ANSWER LOG Date Answer Issued Answer Question Revision 18 12/13/2013 1 OF 62

C1045 RFP Westside Subway Extension QA Log as of 12.13.13

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

1 06.18.13 It would be beneficial to view the exploratory shaft as it is being excavated. WillLACMTA arrange a site visit of the exploratory shaft (Contract C1034)?

Metro has made arrangements for the C1045 proposers to visit the PLE ExploratoryShaft site located at 6006 W Wilshire Blvd for the purpose of viewing the installation

of the soldier piles during the week of July 15th and July 22nd between the hours of7AM to 3:30PM. Visitors need to arrive at the jobsite wearing full PPE (hardhat,safety glasses, vest and boots). Visitors are to check in with the Resident Engineerfor an orientation and safety briefing. Visitors are to follow the instructions of Metrostaff and the contractor as related to viewing areas and safety while on the jobsite.Any statements made by Metro staff or the contractor while at the jobsite visit are notbinding and do not change the contract C1045. Other jobsite visits will bescheduled in the future for viewing of the excavation/lagging process. The projectrequires off-street parking. Visitors are encouraged to park at the Metro-leased lotlocated on the southeast corner of Ogden Drive and Genesse Avenue (Opposite theExploratory Shaft).

07.05.13

2 06.18.13 Will LACMTA make soil samples/borings available for viewing? Metro will provide a second and FINAL viewing of cores samples at the SW corner ofWilshire/Crenshaw on Wednesday and Thursday, September 25th and 26th,respectively between the hours of 9am to 4pm. July 24th and July 25th between thehours of 9:00 am and 4:00 pm, at the offices of AMEC Environment & Infrastructure,located at: 6001 Rickenbacker Road Los Angeles, CA 90040. The sample borings(refer to attached table) include soil and rock conditions encountered along thetunnel alignment, and were selected considering tunnel and station locations,depths, geologic conditions to be encountered, and the presence of tar and transitionareas. If proposers would like to view additional Section 1 borings, please emailEva Rodriguez at [email protected]. See attached table for Sample BoringsAvailability Dates. Proposers attending this FINAL viewing must contact EvaRodriguez via email at [email protected] to schedule a viewing time.

07.09.1308.30.13

3 07.11.13 The Metro Rail Design Criteria states that train control and communication roomsshall be protected with an approved non-water based special extinguishing system(such as an inergen system or equivalent), that does not damage or affect theperformance of installed equipment. In the latest revised specs it says that In traincontrol and communication room, provide hydraulically designed, single interlock,fully supervised pre-action sprinkler system, with electrically activated cross zonedsmoke detectors. Am I Correct to assume that for the train control andcommunications rooms are to have an inergen system or equivalent, with a preactionsystem? Also how are the electric service vaults, aux power, and traction powersubstation going to be protected since they are the exception to not having automaticfire sprinkler systems in them?

Contractor shall provide a water-based Pre-action Fire Protection (sprinkler) Systemfor Train Control and Communication Rooms, not both water-based and non water-based (Inergen or equivalent) systems. Paragraph 2.6.6.2 E. and 2.6.2.1 of the FLSCriteria both allow for the use of a water-based Pre-Action fire sprinkler system.Paragraph 2.6.2.4 will be revised by Metro to allow for the alternate use of a nonwater-based (Inergen or equivalent) Fire Protection System, subject to the approvalof the Agency Having Jurisdiction (AHJ). Electric Service vaults, Aux Power andTraction Power substations shall be provided with Fire Extinguishers per Paragraph2.6.4.of the FLS Criteria.”

07.19.13

No.Date of

Question

WESTSIDE SUBWAY EXTENSION PROJECT, SECTION 1 (D/B)

QUESTION & ANSWER LOG

Date

Answer

Issued

AnswerQuestion

Revision 1812/13/2013

1 OF 62

Page 2: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

4 07.16.13 Does the Westside Subway Extension project include an upgrade, renovation to theexisting subway operations control center?

Contact C1045 does not include any upgrades or renovations to the existing subwayoperations control center (Rail Operations Center –ROC).  The Purple LineExtension Project does include funding for upgrades and renovations to the existingRail Operations Center (ROC) to be completed by others. 

07.25.13

5 07.17.13 Will there be a new vehicle maintenance facility associated with this project? Contract C1045 does not include a new vehicle maintenance facility.  The PurpleLine Extension Project does include upgrades (additional track and a new building)within and south of the existing Metro Red Line Division 20 Yard.  This SOW will beincluded in future PLE contracts.

07.25.13

6 07.19.13 1.07 Part B states an XER file ( a primavera backup file) has been provided. CanMetro provide the referenced XER file?

The XER file will be provided at Notice of Award to the winning proposer. 08.16.13

7 07.19.13 3.3 Site Response Analysis and Free-Field Differential Displacement, last paragraph,last sentence stipulates: A revised site response analysis will be performed for theWilshire/Fairfax Station and results will be submitted as an addendum to this report".Please advise when the revision will be available?

To be provided in a future amendment. 08.16.13

8 07.19.13 1.2 Subsurface Investigations states: "As of the date of preparation of this GBR,additional subsurface investigations are planned. They will provide furtherinformation on the Fernando Formation including characterization of discontinuitieswithin the formation and their potential as a source of gas. This information will allowconsideration of a deeper profile for the tunnels, and additional characterization ofgas conditions within Section 1. The results of these investigations will be given tothe prospective Design-Build Teams as they become available." Please advise whenrevised GBR will be issued.

Results of new Geotechnical investigations will be provided in future amendment. Data from Reach 2 followed by data from the deep borings from Reach 1.

08.16.13

9 07.19.13 The tail track grade of 3.9% has been approved as a design deviation against MRDC4.1.6.4.C2 clause with respect to stub end track at the west end of the project. Sincethe tail tracks will serve as storage track (4 car per track). Also , please clarify adesign deviation against MRDC 4.1.6.4.C3 is available, or MRDC 4.1.6.4.C3 is notapplicable?

The tracks west of Wilshire/La Cienega station are considered temporary "stub endtracks" and a deviation has been approved against MRDC4.1.6.4.C2.  MRDC 4.1.6.4.C3 concerning "storage tracks" is not applicable to thissame infrastructure.

08.02.13

10 07.19.13 MRDC Fire/Life/Safety Criteria stipulates "The walkway clearance envelope abovethe walking surface shall measure 30 inches wide by 80 inches high and shall beclear of all obstructions including the tunnel handrail and the vehicle dynamicenvelope". However, Drawing Y2001 and Y-2002 show the walkway envelope is 2ftwide at the top and bottom and 2'-6" at 4'-8" above the walkway surface. However,there is not an approved design deviation. Please provide the approved designdeviation or the Proposer shall assume that a larger tunnel diameter will be requiredto satisfy the 2'-6" by 6'-8" clearance envelope requirement.

An approved deviation will be provided in future amendment. 08.23.13

Revision 1812/13/2013

2 OF 62

Page 3: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

11 07.19.13 Summary of Work, Section 1.02, Subsection 2.c.1 describes cross passagerequirements. However, the low and high level requirements for surge chamber ateach cross passage have not been provided with the contract documents. Pleaseprovide the requirements.

The Low and High levels as well as the size of the surge chamber shall bedetermined by the Final Designer based on the maximum anticipated flow.Consideration shall be given to infiltration flow, fire standpipe and deluge systems asa minimum. Infiltration flow shall be discharged into the city sewer system, whichrequires an industrial wastewater permit and may require pretreatment. Stormdrains shall be considered for discharge of deluge and standpipe water flows. Thedischarge of deluge and standpipe water flows, including the testing of systems, areexempt from NPDES guidelines per LA County MS4 Permit. Contractor shallconsider the locations and capacities of the sewer and storm drains for potentialdischarge in his design.

09.16.13

12 07.19.13 Summary of Work, Section 1.04, Subsection B mentions about advanced contractsC1048, C0155, C1056, and Division 20 Yard. Please provide these contractdocuments.

Contract  C1048 Advanced Utility Relocations Contract Wilshire/La Brea Station wasprovided as a reference document in Amendment 1.  Subject to availability otherrelated contracts will be provided with future amendments.

08.02.13

13 07.19.13 Clause 2.02.J.1.a.3 states “…to maximize potential and kinematic energy …” Pleaseclarify the intent or meaning of this clause. Does it mean that the vertical alignmentbetween stations is fixed and cannot be amended, refined, and optimized?

To be clarified in future amendment. 08.16.13

14 07.19.13 The General Requirements limit the change in profile from the PE design to 5’, andnotes the traction power efficiencies of having stations at high points. Please clarify asag profile between stations is mandatory.

To be clarified in future amendment. 08.16.13

15 07.19.13 The Building & Adjacent Structure Protection Report included as part of TechnicalReports describes tunneling impact on the building and structures along thealignment. However, the report does not cover the excavation impact on the buildingand structures adjacent to station sites. The Proposer wonders if Metro has done asimilar impact evaluation for station excavation. If yes, please provide the impactassessment.

The report will be provided in future amendment. 08.16.13

16 07.19.13 Will LACMTA make bulk soil samples of the tar sand excavated from the test pitavailable for contractors to test?

Proposers may request soil samples from the Exploratory Shaft construction site.Arrangements and pick up times must be coordinated with Eva Rodriguez at (213)922-1034 or via email at [email protected]. Metro does not warrant theaccuracy or representation of all conditions of the soil samples obtained from thesoldier pile drilling in the Wilshire/Fairfax station area or Tar Sands. Also, proposersreceiving samples assume the risk of interpretation of the samples obtained.Proposers are also reminded that the Contractor must properly dispose ofcontaminated soils at the appropriate disposal sites and comply with ContractDocument including but not limited to SP-21- Hazardous Substance Managementand GC-41 – Environmental Compliance.

08.02.13

17 07.19.13 Will Metro make BIM files available? As per LOI-RFP pg 1-4 "The CADD files for the Project Definition Drawings shall beprovided only to LACMTA Pre-Qualified Firms/Teams listed in Exhibit A of this RFPProposal Letter (Letter of Invitation)….

08.02.13

Revision 1812/13/2013

3 OF 62

Page 4: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

18 07.22.13 Looking for Metro "Metro standard drawing SS-003" as referred in referenced doc,"The Metro Seismic Criteria does not provide..., but Metro standard drawing SS-003presents a guideline for seismic earth pressure due to retained soil and due toadjoining building", where can this be found?

Support of Excavation drawings will be provided in a future amendment. 08.02.13

19 07.24.13 I notice that this project has an estimate expenditure for DBE.  However, mycompany is MBE only, not DBE. Does my company get qualified for participating thebidding process? We are manufacturing that specialize in machining precision metalparts.  Do you require any manufacturing located in United States?  Do we allow tosubcontract some work outside the United States?

MBE does not qualify for the DBE project, you need to apply the DBE certificationeither with Metro or any California DBE certifying agencies. Yes, if your firm is amanufacturing company, we require your manufacturing facility located in UnitedStates. You can subcontract some work outside the United States, but the work willnot be certified with your DBE certification.

08.21.13

20 07.24.13 Have the primes already selected their subs in preparing these designs or are weable to meet them as they are actually hiring us not Metro, correct?

The C1045 contract is a design build project delivery system therefore until design iscompleted by the design builder subcontracting opportunities may be identifiedthrough completion of the design/construction. Subcontractors are to contact thequalified proposers to inquire about possible and future opportunities.

08.23.13

21 07.24.13 Any raised deck construction type in the streets for this first segment? Please refer to Technical Requirement 01 53 05, Temporary Decking Systems,Paragraph 3.02 for information on raised decking.

08.23.13

22 07.24.13 Will BIM (building information model) be used for this project? Yes, please refer to General Requirement Section 01 31 28, Building InformationModel for BIM requirements.

08.23.13

23 07.24.13 The system component of the work was not discussed. Could you explain Metro'saspirations present and future in the area and any resolutions of the interface?

LACMTA request further clarification related to your question. Please provide moredetail.

08.02.13

24 07.24.13 Please detail the community outreach and public relations component of this RFP?Please indicate of or where this information is in the RFP.

Refer to Community Outreach Requirements are described in General Requirement01 35 95 - Public Information and Community Relations.

08.02.13

25 07.24.13 Does subconsultants (DBE's) need the same amount of insurance as the primes? Ifso, will Metro reimburse small businesses for the increase in standard insurancecosts?

The Prime Contractor is solely responsible to ensure that all Subcontractors areappropriately insured.  Subcontractors shall be enrolled under the Contractor’s CCIPunder the same terms as the Contractor unless otherwise specified in the contractdocument.  In the case of automobile liability insurance, Subcontractors mustmaintain no less than $1 million of coverage.  In the event that a Subcontractor ispermissibly excluded from the CCIP, the Contractor is responsible for theestablishment of coverage limits for Subcontractors.   The Contractor is fullyresponsible for any deficiencies resulting from insufficient coverage on the part of theSubcontractors.  Metro will not reimburse small businesses for any increases in thecost of their insurance.

08.02.13

26 07.24.13 How does SBE participation fit in with the DBE program? The SBE and DBE programs are distinct separate programs. Because this projecthas Federal funds, only the DBE program applies. SBE participation pertains only toNon-Federally funded projects. Please  reference Section 200 (page 3-14) of theInstructions to Bidders for more information regarding DBE participation.

08.02.13

27 07.24.13 Can prime D/B proposers utilize DBE firms to help/assist with GFE solicitation andidentification of RC-DBE firms interested in providing proposals for the work?

Yes proposers can; however, no DBE credit will be given for  work performed bya DBE prior to contract award.

08.02.13

Revision 1812/13/2013

4 OF 62

Page 5: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

28 07.24.13 Is there an SBE goal for design? No, there is not a SBE goal for design. The design portion of the project has a DBEgoal. Please  reference  the Letter of Invitation (page 1-23)  for more information .

08.02.13

29 07.29.13 The deadline for Questions/RFIs about the RFP is listed as 10 days prior to the duedate. However, Section IP-04 B. states that inquiries shall be received at least 21calendar days prior to the due date. Please clarify which is correct.

LACMTA will Amend Letter of Invitation Supplement (Construction) to reflect 21calendar days prior to due date. This change will be reflected in a futureamendment.

08.02.13

30 07.29.13 Can the CADD files of the Project Definition and Reference drawings be madeavailable to the Bidders?

Please refer to the answer to question no. 17 above. 08.02.13

31 07.29.13 Is it LACMTA's intention to not compensate the Contractor for any interruptionsresulting from non-availability of funds? Can LACMTA provide current status onfunding availability for the Section 1 project?

Please clarify the first part of the question. LACMTA is on schedule to execute theFFGA for the Project in early 2014, and to obtain the TIFIA loan commitments prior toFFGA execution.  Those actions will establish funding availability before contractaward and execution of the DB Contract.

08.16.13

32 07.29.13 The Schedule column for Milestone No. 3 refers to "...days after commencement ofsoldier pile installation for support of excavation and Flower Street Decking." Also,Systems Integration Testing is already included under Milestone No. 1. Pleaseclarify this Milestone.

Revisions will be provided by amendment to the RFP. 08.02.13

33 07.29.13 The Schedule column for Milestone No. 4 refers to "...days after commencement ofremoval of decking." It appears that this should say "…days after issuance of Noticeto Proceed." Please clarify.

Revisions will be provided by amendment to the RFP. 08.02.13

34 07.29.13 In GC-14, 14.1.2 refers to coordination with "other contractors". Please confirm thatthe Contractor is only to consider coordination with Work by other contractors thatare clearly foreseeable under this Contract, e.g., any third party contract interferencenot related to LACMTA work and not known to the Contractor at RFP stage cannotbe considered and would constitute a change.

In compliance with General Condition GC 14, Cooperation, Coordination andAccess, in its entirety, the Design Builder is responsible for cooperation, coordinationand access with other contractors during the period of performance of the contract.This obligation is not limited to contractors that are "clearly foreseeable”; it extends toany other contractor performing work during the DB Contract period.

08.22.13

35 07.29.13 The first sentence in IP-08 B. references "conforming proposals" and "alternateproposals" which can be submitted together as "complete separate offers".However, this article also requires that alternate proposals "must be equal to orbetter than the original requirements of the Contract Documents". In addition, anyalternative proposals accepted will be "evaluated in accordance with the evaluationcriteria in this RFP." Consequently, by definition an "alternate proposal" must also bea "conforming proposal". It's therefore not clear from the description what thedifference is between the two. We request clarification on what allowances may begranted by LACMTA for alternate proposals. Also, would alternate proposals requirea complete duplicate submittal of all Vol. I, II, and III documents or just the TechnicalApproach Submittal and Alternate Price Proposal, if applicable?

Alternate Proposals must be equal "must be equal to or better than the originalrequirements of the Contract Documents". During the design and review processalternate proposals that comply with all contract requirements may be considered.Yes, all alternate proposals are considered separate and distinct proposals mustcomply with all the RFP submittal requirements.

08.30.13

Revision 1812/13/2013

5 OF 62

Page 6: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

36 07.29.13 Page 3-48 (I. General Format) states that "Schedule plots shall be on 22 x 34 inch or24 x 36 inch paper,..." while page 3-59 (Volume II G.2.e) requires a hard copy of theCPM schedule on an 11 x 17 paper. Please clarify which is correct. Please alsoconfirm that schedules will be counted as part of the page count limitations, and thatoversize pages will count as 1 page.

Under Submittal Requirements, Volume II - Project management Submittal, sectionG2e on page 3-59 of the original RFP will be changed in a future Amendment to read22x34 inch or 24x36 inch sheets. The schedule submitted will not be included in the120 page limit count.

08.23.13

37 07.29.13 Article F. 1. refers to the Proposer's plan to "construct" stations, etc. Since thissubject is covered in depth in Vol. III - Technical Submittal and to make Article F. 1.consistent with F. 2., we respectfully suggest that this article be revised to refer to theProposer's plan to "manage the construction of the" stations, etc.

No change. 08.28.13

38 07.29.13 Article B. 2. Structures (Excluding Bored and Cut and Cover Tunnels) would seem toreference only underground stations. However, underground stations are covered indetail in B. 5. Please clarify how Section B. 2. differs from B. 5.

Refer to Section 3 of the RFP Documents, Volume III Technical Approach Submittal,Section B

08.28.13

39 07.29.13 Article 8. d) does not appear to apply to the Westside Subway Extension Project.Please clarify.

Article 8 does apply to the Westside Subway Extension Project. 08.28.13

40 07.29.13 Are there existing Record Drawings available for the Purple Line at theWilshire/Western Station?

Wilshire/Western Record Drawings were provided on Disk 3b, folder labeled:“04.Metro Red Line As-Built Drawings”

08.02.13

41 07.29.13 The last sentence states that the Committee may revise evaluation scores based onthe…BAFO. Does this mean that the Proposer's BAFO will be evaluated separatelyfrom the original Proposal and that the final scoring will be changed to reflectchanges that are presented in the Project Management, Technical Approach, andPrice Proposal sections of the BAFO documents?

The Committee may revise evaluation scores based on the information contained inthe BAFO.

08.28.13

42 07.29.13 Under the column "Weight", it appears that the superscript 1/ after 25% does notapply, since all the sub-criteria referenced by this superscript are not equallyweighted.

Subscript to be modified in amendment. 08.28.13

43 07.29.13 Section 01 11 00 – Summary of Work, Article 1.04 B. 1. mentions Contracts C1048,C1055, and C1056 as advance utility relocation contracts for the three station areasat Wilshire/La Brea, Wilshire/Fairfax and Wilshire/La Cienega. Will information forthese contracts be made available?

Please refer to the answer to question no. 12 above. 08.02.13

44 07.29.13 This section stipulates the current allowable work hours. In Section 01 71 43 Table 1,LACMTA identifies "Metro Obtained Permits", including an "After Hours ConstructionPermit". Please advise the status of these Metro Obtained Permits and their validitythroughout the period from NTP to Final Completion.

To be clarified in a future amendment. 08.19.13

Revision 1812/13/2013

6 OF 62

Page 7: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

45 07.29.13 This section states in 1.05 E 3 f 2) that the City is performing a sewer capacityanalysis. Please advise if this analysis will be available prior to Proposal submittaldue date.

Available sewer capacity for Western, La Brea and Fairfax, and conditions fordischarge are stated in the Appendix to TR 01 35 35.  Any available sewer capacityfor La Cienega will be clarified in a future Amendment.

08.19.13

46 07.29.13 This section states design life "in excess" of 100 year design life. Does "in excess"mean "equal to"?

Yes.  A minimum of 100 years. 08.19.13

47 07.29.13 Should this read "…experience in the installation of..." instead of "…experience forthe manufacture of..."? Please clarify.

To be clarified in future amendment. 08.19.13

The differences in the fan start and ramp up times used in the Fire-Life Safety BODTM and the CFD report for Fairfax will be clarified in a future amendment. The Fire-Life Safety Basis of Design (BOD) Technical Memorandum (03-27-2012) Section3.3.1 is based on the times used for the simulations in that report. These Simulationswere run allowing 90 seconds for the fans to reach full capacity after initiation. At thetime when the report was finalized, ways of improving the Time of Tenability duringthe first 4 minutes of the station fire incident were investigated, and the ramp up timewas reduced to 30 seconds. These original simulations were not rerun since thefaster ramp up time for the fans would improve conditions and at that point werealready acceptable. All CFD work going forward assumed fan activation via HeatDetector at 90 seconds, and 30 seconds for fans to reach full capacity (120 secondstotal). Table 4-1 in the BOD report was based on the initial assumptions for theproject and were based on the challenges of the Arson Based Fire.

Section 3.2 in the same report also mentions the new assumption of 90 seconds toactivate via heat detectors and 30 seconds to reach full capacity (120 seconds total).Section 01 11 01, Project Design Build Requirements will be revised to add the fanactivation and time to reach full capacity.

49 07.29.13 This section is related to deflection and distortion of the tunnel segmental lining atcross passage locations. Is LACMTA providing a quantification for deflection anddistortion?

No, Contractor to analyze tunnel based on construction methods and final tunnel andcross passage design.

08.19.13

50 07.29.13 The section states the requirement to coordinate with the Utility Owners to establishallowable settlement levels. In Item 3.02 A. 12. d of Section 31 71 19, LACMTA isproviding allowable settlements for utilities. If the requirements by the Utility Ownersare more stringent that LACMTA's levels does that constitute a change?

No. Design-Builder to verify allowable settlements prior with utility owners accordingto referenced Section 1.04 E.c.

10.02.13

51 07.29.13 If the Contractor wishes to propose steel fiber reinforcement, would this represent analternative to the Proposal?

Steel reinforcing bars are required for primary reinforcement in precast concretetunnel liners. Steel fiber may not be used as the primary reinforcement. Refer toTechnical Requirement 31 74 16, Precast Concrete Tunnel Lining, Paragraph 2.02B. 2

08.20.13

08.28.1310.09.13

48 07.29.13 Fire-Life Safety BOD TM (03-27-2012) Section 3.3.1 indicates fans start at 90seconds reaching full capacity at 180 seconds; Fire-Life Safety BOD TM (03-27-2012) Table 4-1 indicates fans start at 270 seconds reaching full capacity at 360seconds; CFD Report – Fairfax (Final) (11-20-2012) indicates fans start at 90seconds reaching full capacity at 120 seconds; Please clarify fan start and ramp uptimes used in CFD analysis.

Revision 1812/13/2013

7 OF 62

Page 8: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

52 07.29.13 LACMTA uses a Medium Fire Growth for Gold Line Eastside Extension, PasadenaGold Line, Expo Line and for Crenshaw Base Option. Is it conceivable to use aMedium Fire Growth for this design and propose an alternate design resilient for thestipulated Arson Fire Growth?

No, design for the stipulated Arson Fire Growth. 08.20.13

53 07.29.13 What is the scope and schedule of the additional planned subsurface investigations? In summary, borings have been completed to revise three Geotechnical DataReports-GDR for Wilshire/La Brea will be updated for pump test data-GDR for Wilshire/Fairfax will be revised to add two borings at entrance locations-GDR for Reach two will be revised to data from three additional borings5 Borings are to be completed to provide additional data at lower elevations in Reach1

08.20.13

54 07.29.13 What is the scope and schedule for the additional investigations on the tiebackanchorages that impact the tail track tunnels west of Wilshire/La Cienega Station?

A single (plan) location of tiebacks is planned to be investigated using Geophysicaltechniques to locate anchor plates.  If successful, additional locations may beinvestigated

08.20.13

55 07.29.13 There is an indication of artesian pressure at Wilshire/La Cienega Station. Designgroundwater is stated to be 10ft below ground surface, +/- 5 feet. Does this includethe artesian pressure?

Design groundwater levels do not need to be adjusted for additional pressures 08.23.13

56 07.29.13 Indicates a revised site response analysis will be performed for the Wilshire/FairfaxStation. Has this been performed? If so, please provide results.

Yes, the analysis is being revised for the Wilshire/Fairfax Station and will be providedin a future amendment.

08.23.13

57 07.29.13 The profile legend on K-119 shows historic high groundwater table which is notshown on drawings K-120 to K-127. Please clarify if the groundwater table shown ondrawings K-120 to K-127 is the baseline groundwater table.

To be clarified in future amendment. 08.23.13

58 07.29.13 At Station 563+00, the current high groundwater table is shown to be atapproximately Elevation 132 ft and 100 ft. Please clarify the baseline groundwatertable at this location and to the west of Station 563+00.

To be clarified in future amendment. 08.23.13

59 07.29.13 Is it possible to provide borings, CPTs, laboratory, and field test data digitally (softcopy/gINT files, Plates in GDR)?

Yes, to be provided in future amendment. 08.23.13

60 07.29.13 The Geotechnical Data Reports include summary tables of Pressuremeter tests. Canthe complete test results be provided?

Yes, to be provided in future amendment. 08.23.13

61 07.29.13 The Geotechnical Technical Memoranda (TMs) summarizes the results of siteresponse and hazard analyses. Is a more complete hazard analysis report available?

No additional reports are available, also please refer to answer to question no. 56above.

08.23.13

Revision 1812/13/2013

8 OF 62

Page 9: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

62 07.29.13 Numerous borehole logs have been provided that do not include surveyed locations.Can a complete list of all boreholes and their locations by station and offset andelevation be provided?

A list of borings and coordinates will be provided in a future amendment.  Elevationsof prior borings should be estimated from topo maps and cross sections.  Elevationsshown on some logs for prior investigations were relative to an assumed datum(refer to notes on logs).

08.30.13

63 07.29.13 Item A15: Entry in the description section suggests "three sets of DC surgearrestors", then the entry in the quantity column also states "three sets". Pleaseclarify if the required quantity is three sets x three sets, i.e. nine sets - or if there is amistake and the "three sets" should only be referred to once.

Section 34 01 03 has been deleted. Refer to the List “A” Spare Parts – TractionPower of Section 01 78 43 titled Spare Parts, Illustrated Parts Catalog, andReplacement Materials issued in Amendment #1. The required quantity is three sets.

08.28.13

64 07.29.13 Items B6. and B8. are both for anchor assemblies but contain different quantities.Please define the items more specifically and explain the difference between the two.

Section 34 01 03 has been deleted. Refer to the List “A” Spare Parts – Contact Railof Section 01 78 43 titled Spare Parts, Illustrated Parts Catalog, and ReplacementMaterials issued in Amendment #1 for quantities.

08.28.13

65 07.29.13 Center the loop in the platform so that there is one car length on either end of thewire loop as shown. Where can the presentation of arrangement be seen as it doesnot appear to be shown anywhere within the Technical Requirements document?

Per the Technical Requirement, from the center of the platform the loop shouldextend on either side a minimum one car length. A presentation an arrangement canbe found in the Reference Documents Volume 3b, Reference Drawings Volume 2,TC-013.

08.28.13

66 07.29.13 Volume II states that "The Contractor shall replace all existing ATC Equipmentlocated at Wilshire/Western Station (…)" - this contradicts the statement in Volume IIIwhich reads "in order to provide through movements from Wilshire / Western Stationto the Westside Extension project alignment, the existing Train Control Equipmentwill be modified." - Please confirm that Volume II takes precedence.

Volume II takes precedence. and the text in Volume III will be revised in a futureAmendment.

10.04.1308.28.13

67 07.29.13 Please confirm where "Rail Operations Simulation Report" (Deliverable 5.2.7 A/B)can be found within the supplied documentation. If it has not been provided, couldthis document be provided?

Yes, will be provided in future amendment as reference document. 08.23.13

68 07.29.13 Document contains the following statement: "Metro has indicated that any works andequipment provisions associated with the existing facilities and at the Rail OperationControl (ROC) center will be done by the Metro". Please confirm whether the quotedstatement still holds and to what extent.

Any Work required at the existing Central Control Facility that houses the ROC toaccommodate the Purple Line Extension will be performed by Metro outside of thescope of work of Contract C1045. C1045 scope of work is to provide support toMetro during integration testing to ROC.

09.04.13

69 07.29.13 Volume III reads "The current SCADA system (…) is TRACS. Based on theinformation received from the metro, the existing TRACS system in ROC is notexpandable (…)" Please confirm if this statement still holds and whether it should beconsidered as having impact on Contractor's scope of work.

All of  the necessary work to replace the current TRACS system to accommodate thePurple Line Extension will be performed by Metro outside of the scope of work ofContract C1045.

09.04.13

Revision 1812/13/2013

9 OF 62

Page 10: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

70 07.29.13 Volume II contains many references relating to consideration of impact of proposedworks on the Rail Operations Center (ROC). Could LACMTA provide indication aboutany passive or active provision for line expansion present at the ROC?

Any expansion (passive or active) required at the ROC to accommodate the PurpleLine Extension will be performed by Metro outside of the scope of work ContractC1045.

09.04.13

71 07.29.13 The statement lists the requirement for a train control designer to manufacture 50%of the Train Control System supplied under the contract, but earlier states that theTrain Control Designer may be train control equipment manufacturing firm or firms. Isa combination of a competent design consultant and an equipment manufactureralso acceptable?

Per the referenced Technical Requirements Section, the designated “Train ControlDesigner” for this Contract must meet all the requirements. One of the requirementsis that the designated “Train Control Designer” manufacture at least 50% of the TrainControl System equipment being supplied under this Contract.  A competentconsultant may be part of the Contractor’s overall team but cannot fulfill the role ofthe Contractor’s designated “Train Control Designer” unless the consultant satisfiesthe stated manufacturing criteria.

09.04.13

72 07.29.13 LACMTA specified the use of BIM by design consultants to execute ACE, PE andAPE Design and Construction Project in this document. Is the final BIM Data of theAPE Phase available?

Please refer to the answer to question no. 17 above. 08.02.13

73 07.29.13 This section states BIM Electronic files shall be developed to include the featuresdescribed in Section 3.04 (As-Built Model) as designed. Can LACMTA clarify "thefeatures" described in Section 3.04?

“The features” refer to specific additional model attributes and discipline-specificproperties of BIM Electronic Files that are required to create the As-Built deliverableModel, as listed in detail in subsection 3.04.C.

09.19.13

74 07.31.13 The Westside Transit partners requests your permission to collect three 5 gallonsamples of the soldier beam drill spoil currently being excavated at the future locationof the Fairfax/Wilshire station at the intersection of Wilshire and Ogden Avenue. Wewould like to obtain samples of the spoil to determine the appropriate soilconditioners to deal with the asphalt impregnated soils present in the tunnelalignment. We would like to collect the spoil from between 45’ to 60’ below groundsurface. We will provide the appropriate containers and tools to collect the samples.

Please refer to the answer to question no. 16 above. 08.02.13

75 08.02.13 Is this project only for Race Conscious DBE's, or can other DBE, WBE, SBEcompanies perform work functions and also receive DBE participation credit? Is therea separate goal for non-minority companies?

This project has a twenty percent (20%) Race Conscious DBE goal for Design and aseventeen percent (17%) Race Conscious DBE goal for Construction. Only RaceConscious DBE firm's participation is credited toward the Race Conscious DBEgoals. Participation by WBE and SBE firms are not credited toward the RaceConscious DBE goals. Participation by non-Minority women is counted towardMetro's Race Neutral goal. There is not a separate goal for non-minority companies.

08.21.19

76 08.02.13 On Page 7-9 of the Preliminary Engineering Report (Final), Deliverable No. 6.6.1.2.F(Draft Building and Adjacent Structure Protection Report,Cut‐and‐Cover Excavation, submitted October 31, 2011) ismentioned that it is summarized. Can Metro provide this full report?

Report addressing cut and cover excavations will be provided in a futureamendment.

08.19.13

77 08.02.13 Will Metro make available the latest CAD Standards to ensure proper set of projectfiles?

Metro's latest standards have been provided.  If updated, the revised standards willbe provided to proposers.

08.19.13

Revision 1812/13/2013

10 OF 62

Page 11: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

78 08.02.13 Equipment access hatches up to street level are shown 12’ wide by 17’ long on theWilshire/Fairfax Station reference drawings [see Vol. IIIb, Dwg.: S-1218]. With notmuch effort it appears they could be replaced with equipment access hatches downto track level as we have track damper openings shown at large as 15’ wide X 17’long [see Vol. IIIb, Dwg.: S1214]. What is the reason for having these equipmenthatches up to street level when other equipment access hatches are provided overthe tracks below?

The floor access hatches located in Rooms 50 and 57 to track level as shown in thecontract drawings A-2111 and A-2114 (Wilshire/La Brea Station) are meant forremoval/replacement of ventilation and auxiliary power equipment only. Theequipment access hatch located in the corridor between the Traction Power Room#47, LADWP Switch Room #44, and Metering Switchgear Room #45 is required fora joint use of removing/replacing of Metro’s traction power equipment and LA/DWPequipment from the street. Track damper openings shall not be used forremoval/replacement of any type of mechanical or electrical equipment. Similararrangement shall also apply at Fairfax and La Cienega Stations.

08.19.13

79 08.02.13 Included in the proposal documents are copies of MTA approved criteria deviations,requested by P/B during their preparation of the 30% documents (see Volume II,Section 3, ‘Deviations to Metro Design Criteria’).

There is a deviation request [WSE-2013-007 “General Architectural Design CriteriaDeviations for WSE” (submitted 5/21/20130] listed but not yet approved. CanLACMTA provide a status update and a copy of the original deviation request.

The Deviation was provided in Amendment #1 08.19.13

80 08.06.13Lab tests results from these boreholes are included in Table 4-3, but the boreholelogs are missing from Appendix A and the borehole locations are missing from Plate1. Please provide logs, locations, and ground elevations for boreholes:

A-66260 (1)A-66260 (2)A-71252 (1)A-71252 (2)A-71252 (3)A-71252 (4)A-71252 (5)A-71252 (6)

The missing information will be provided in a future amendment. Please refer tocross sections and topo maps for approximate elevations of prior borings.  Elevationsshown on some logs for prior investigations (those not for C1045 contract) wererelative to an assumed datum (refer to note on these logs).

08.23.13

Revision 1812/13/2013

11 OF 62

Page 12: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

81 08.06.13Locations of these boreholes are presented in Plate 1, but the borehole logs aremissing from Appendix A. Please provide logs, and ground elevations for boreholes:

E-108AE-108BE-109AE-110AP-304OB-305E-110BOB-306E-110CG-315

Please refer to the answer to question no. 80 above. 08.23.13

82 08.06.13 The logs for these boreholes and CPTs are included in Appendix A and D, but do notinclude the ground elevations.Please provide ground elevations for boreholes:

A-79292 (1)A-79292 (2)C-110CB-101

Please refer to cross sections for approximate elevations of prior borings.  Elevationsshown on some logs for prior investigations (those not for C1045 contract) wererelative to an assumed datum (refer to note on these logs). CPT ground elevationswill be provided in a future amendment.

08.23.13

83 08.06.13The logs for these boreholes included in Appendix A include ground elevations, butthe elevations do not agree with the expected elevations in the vicinity of the station.Please provide ground elevations for boreholes:

L89452.PBFB (1)L89452.PBFB (2)L89452.PBFB (3)L89452.AC (4)L89452.AC (5)

Please refer to cross sections and topo for approximate elevations of prior borings. Elevations shown on some logs for prior investigations (those not for C1045contract) were relative to an assumed datum (refer to note on these logs).

08.23.13

84 08.06.13Table 3-2 summarizes the pressuremeter test results, but the pressuremeter testreports are necessary to evaluate the quality of the pressuremeter test curves.Please provide pressuremeter test reports performed at boreholes:

G-112G-309

To be provided in future amendment. 08.23.13

Revision 1812/13/2013

12 OF 62

Page 13: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

85 08.06.13 Logs of these CPTs are included in Appendix D, but the digitized tabulated data isrequired to make use of the test results for interpretation purposes.Please provide digital tabulated data for CPTs:

C-110CB-101

To be provided in future amendment. 08.23.13

86 08.06.13 The stations presented in the logs for these boreholes in Appendix A do not agreewith the borehole stations inferred from Plate 1. Please provide stations forboreholes:

G-3G-4

Use Plate 1 locations for Borings. To be clarified in a future amended GDR. 08.23.13

87 08.06.13 Locations of these boreholes are presented in Plate 1, but the borehole logs aremissing from Appendix A. Please provide logs and ground elevations for boreholes:M A-78304 (4), M A-80041 (1)G-127, RC-17SV-6, A-68291-B (10)A-68291 (2), A-68291-B (8)A-68291-B (5), A-79181 (1)A-68291-B (4), A-68291-B (6)A-68291 (1), M A-69086-B (3)M A-69086-B (6), M A-69086-B (9)M A-69086-B (8), M A-79162 (2)M A-79162 (1), M A-79026 (2)M A-79026 (3), M A-79026 (1)G-8, E-123, OB-101, OB-102P-101 and M A-78304 (3)

The boring logs will be provided in a future amendment. Also, please refer to theanswer to question no. 83 above.

08.23.13

88 08.06.13 The logs for these CPTs are included in Appendix D, but do not include the groundelevations.Please provide ground elevations for boreholes:

C-112C-302C-303

To be provided in future amendment. 08.23.13

Revision 1812/13/2013

13 OF 62

Page 14: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

89 08.06.13The logs for these boreholes included in Appendix A include ground elevations, butthe elevations do not agree with the expected elevations in the vicinity of the station.Please provide ground elevations for boreholes:

M A-68291 (3)M A-68291-B (11)M A-69086-B (1)M A-69086-B (4)M A-69086-B (5)M A-68291-B (7)M A-68291-B (9)M A-69086-B (2)M A-69086-B (7)M A-78304 (1)M A-78304 (2)

Please refer to the answer to question no. 83 above. 08.23.13

90 08.06.13 Section 3.1 and Plate 1 state that pressuremeter tests were performed at theseboreholes. However, the results are not included in GDR.Please provide pressuremeter test reports performed at boreholes:

G-128G-131

To be provided in future amendment. 08.23.13

91 08.06.13 Logs of these CPTs are included in Appendix D, but the digitized tabulated data arerequired to make use of the test results for interpretation purposes.Please provide digital tabulated data for CPTs:

C-112C-303C-302

To be provided in future amendment. 08.23.13

Revision 1812/13/2013

14 OF 62

Page 15: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

92 08.06.13 Locations of these boreholes and CPTs are presented in Plate 1, but the boreholelogs are missing from Appendix A and D. Please provide logs and ground elevationsfor boreholes:

C-111G-350AP-47MW-2DG-318G-319MW-1DM L90123.ADEFO (MW-1)M L90123.ADEFO (MW-3)M L90123.ADEFO (MW-1A)MW-3DP-48RC-16

The boring logs will be provided in a future amendment. Also, please refer to theanswer to question no. 83 above.

08.23.13

93 08.06.13 The logs for these boreholes and CPTs are included in Appendix A and D, but do notinclude the ground elevations.Please provide ground elevations for boreholes:

G-W2CB-103CB-104C-350

To be provided in future amendment. 08.23.13

94 08.06.13The logs for these boreholes included in Appendix A include ground elevations, butthe elevations do not agree with the expected elevations in the vicinity of the station.Please provide ground elevations for boreholes:

M A-67263 (1)M A-67263 (2)M A-67263 (3)M A-77144 (1)M A-77144 (2)M A-79069 (1A)M A-79069 (2A)M A-79069 (3A)M A-79069 (4A)M A-81018 (1B)M A-81018 (2B)M A-81018 (3B)M A-83353 (5)M A-83353 (6)

The boring logs will be provided in a future amendment. Also, please refer to theanswer to question no. 83 above.

08.23.13

Revision 1812/13/2013

15 OF 62

Page 16: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

95 08.06.13Table 3-2 summarizes the pressuremeter test results, but the pressuremeter testreports are necessary to evaluate the quality of the pressuremeter test curves.Please provide pressuremeter test reports performed at boreholes:

G-121G-123G-312G-350G-351

To be provided in future amendment. 08.23.13

96 08.06.13 Logs of these CPTs are included in Appendix D, but the digitized tabulated data arerequired to make use of the test results for interpretation purposes. Please providedigital tabulated data for CPTs:

C-111CB-103CB-104CB-350

To be provided in future amendment. 08.23.13

97 08.06.13Locations of these boreholes are presented in Plate 1, but the borehole logs aremissing from Appendix A. Please provide logs and ground elevations for boreholes:

P-32ACWDD 15AER-8

The boring logs will be provided in a future amendment. Also, please refer to theanswer to question no. 83 above.

08.23.13

98 08.06.13 The logs for this CPT is included in Appendix D, but do not include the groundelevation.Please provide ground elevation for borehole:

C-101

To be provided in future amendment. 08.23.13

99 08.06.13 The logs for these boreholes included in Appendix A include ground elevations, butthe elevations do not agree with the expected elevations in the vicinity of the station.Please provide ground elevations for boreholes:

M-62313 (1)M-62313 (3)A-73089 (3)A-73089 (6)A-73089 (10)

The boring logs will be provided in a future amendment. Also, please refer to theanswer to question no. 83 above.

08.23.13

100 08.06.13Table 3-1 summarizes the pressuremeter test results, but the pressuremeter testreports are necessary to evaluate the quality of the pressuremeter test curves.Please provide pressuremeter test report performed at borehole:G-102

To be provided in future amendment. 08.23.13

Revision 1812/13/2013

16 OF 62

Page 17: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

101 08.06.13 Log of this CPT is included in Appendix D, but the digitized tabulated data is requiredto make use of the test results for interpretation purposes. Please provide digitaltabulated data for CPT:C-101

To be provided in future amendment. 08.23.13

102 08.06.13 The logs for these boreholes included in Appendix A include ground elevations, butthe elevations do not agree with the expected elevations in the vicinity of the station.Please provide ground elevations for boreholes:

M-62313 (1)M-62313 (2)A-73089 (3)A-73089 (6)A-73089 (10)

Please refer to the answer to question no. 82 above. 08.23.13

103 08.09.13 During the scheduled tour of the Fairfax Station test pit construction on July 24, 2013,we observed the drilling contractor applying a drying agent to the soldier beamdrilling spoil. Please identify the product being used and the manufacturer.

The product name is ZorbixTM  manufactured by Diversified Minerals Inc. 08.23.13

104 08.09.13 The original traction power simulation was conducted for the whole plannedextension between Wilshire/Western and Westwood/VA Hospital station. Pleaseconfirm the scope of the requested Traction Power simulation review. Is the bidderrequired to review and comment on the complete section only or is it necessary toconsider the Phase 1 extension as well? Or is the scope Phase 1 extension only?

The scope of the traction power simulation is limited to Section 1 only. 08.23.13

105 08.09.13 The original traction power simulation uses characteristics of a "refurbished train".There is no reference to a "refurbished train" within the technical requirements.Please confirm that rolling stock parameters included in the "Traction PowerSimulation and Analysis Report" (Deliverable No. 6.7.X) are valid for traction powersimulation purposes.

The rolling stock parameters included in the Traction Power Simulation and analysisreport are valid for Traction Power simulation purposes.

08.23.13

106 08.09.13 In order to investigate the best solution for the tail tracks, can LACMTA provide theexpected plan for operation of the trains, in particular any aspirations for trainstorage, cleaning, or joining and splitting of the trains to be carried out within the tailtracks?

The tail tracks are on the alignment of the future main line between Wilshire/LaCienega Station and Wilshire/Rodeo Station.  The length is based on having storagefor a four car reserve or crippled train in addition to safe braking distance forplatforming trains.  The space beyond the bumping post is for the ventilationequipment and a point of safety for workers in the event of a fire.  There is noanticipation of cleaning trains or coupling or uncoupling trains. 

08.23.13

107 08.09.13 In Appendix A Cost and Schedule Template on Page 01 29 76-0, it reads "ASchedule template is provided in XER format for Contractor to grasp minimumschedule structure requirements prior to bid schedule and all schedule submittalsidentified in the contract". We cannot find this template. Please clarify where canthis .XER file can be found.

Refer to Section 0129 76-0 Appendix A - Cost and Schedule Template for directionon how to create .XER format/template.

08.30.13

Revision 1812/13/2013

17 OF 62

Page 18: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

108 08.09.13 The specifications states "Minimum 12-inch thick single-pass gasketed pre-castconcrete segmental lining". If engineering calculations and design show a thicknessof less than 12-inch meets all design requirements, would this be acceptable to theLACMTA?

NO, the Contract minimum requirement is a 12-inch thick single-pass gasketed pre-cast concrete segmental tunnel lining

08.23.13

109 08.09.13 According to the GBR (Vol. II, Section 05), the zone of elevated gas conditionsextends from Wilshire Blvd. and Highland Ave to Wilshire Blvd. and Stanley Drive.This area includes all three stations – La Brea, Fairfax, and La Cienega. However,the Project Definition Drawings (Vol. II, Section 07) drawings SF-2510 to SF-2516only shows Fairfax and La Cienega stations. Is the gas venting system required in allthree stations?

Gas venting is required at Wilshire/Fairfax and Wilshire/La Cienega Stations.Wilshire/La Brea Station is outside the elevated gas zone. GBR Section 5 andgeologic profiles in GBR Appendix A will be revised in a future amendment

08.23.13

110 08.09.13 The details shown on gas venting system appears to be intended to be inaccordance with the passive system per City of Los Angeles Methane HazardMitigation Plans, prepared by LA DBS. Please confirm.

Please see Section  31 21 16.13 Sub-Article 2.01 Regulatory Requirements and Sub-Article 2.02 System Assembly. Where appropriate for the form of construction, suchas the paved areas at the entrance locations, the City of Los Angeles MethaneHazard Mitigation Plans have been implemented. Where not appropriate for the formof construction, such as the station boxes beneath the street an alternative approachhas been implemented.

09.12.13

111 08.09.13 LA DBS requires a methane site investigation to be signed off using Form 1(Certificate of compliance for methane test data) which includes a Design MethaneConcentration and a Design Methane Pressure, together with a Methane DesignLevel (Levels I through V): was such a form prepared for the GDR for this project? Ifso, please provide.

A LADBS Form 1 “Certificate of Compliance for Methane Test Data” is not required. 09.12.13

112 08.09.13 LA DBS Mitigation Plans appear to be applied to buildings at and above grade; theydo not appear to address below ground structures. Under LA DBS Mitigation Plans,dewatering is required in order to keep groundwater at least 12 inches below thelowest horizontal pipe. At all three stations (La Brea, Fairfax, and La Cienega),groundwater level is 20 to 30 ft below ground level and the drawings show the lowesthorizontal pipe to be at least 80 ft below ground level. The drawings also refer to‘submerged trench drains’ which we assume are water-filled: Can we assume thatthe gas venting system shown on the drawings could be entirely filled with waterbelow groundwater level?

See Section 31 21 16.13 Sub-Article 2.02 System Assembly for the minimumrequirements of the gas venting system. LADBS Mitigation Plans are written forbuildings and hard paved areas and the Project Requirements are written to addressbelow ground structures. It can be assumed that the gas venting system shown onthe drawings can be entirely filled with water below groundwater level.

09.12.13

113 08.09.13 Can the design basis for the sizing, layout and spacing for the underslab and verticalriser systems shown on the drawings for La Cienega and Fairfax Stations beprovided?

The design basis is from the City of Los Angeles Methane mitigation measuresmodified for Metro’s underground facilities.

09.12.13

114 08.09.13 The sidewalk vent details show risers discharging into either a below grade boxcovered by a steel grating or a landscape buffer zone detail. There are scenarioswhere such systems cannot disperse methane: for example, if the steel grated box isfilled with accumulated soil or trash or if the landscape buffer zone is filled with rainor irrigation water. Who is responsible for maintaining these vents so that theyfunction properly?

During the Project the Contractor is responsible and on Project completion, LACMTA is responsible for maintaining the vents. Both details are similar to thoseused in the City of Los Angeles and are developed from the LADBS Mitigation Plans

09.12.13

Revision 1812/13/2013

18 OF 62

Page 19: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

115 08.09.13 Are alternative methane control systems, other than the gas venting system externalto the station structure shown on the drawings, allowed? If so, what is the processand level of detail required for alternative submittals?

Refer to Section 31 21 16.13 Sub-Article 2.02, System Assembly. The gas ventingsystem shown on the Project Definition Drawings are minimum requirements. Also,please refer to the answer to question no. 155 for instructions on Modifications andAlternative Proposals.

10.03.13

116 08.09.13 The definition drawings indicate a 2000 KW emergency generator at La Brea and LaCienega Stations, but there is not one shown for Fairfax. Please confirm that anemergency generator is not required at Fairfax.

A standby generator is not required at Wilshire/ Fairfax. 09.04.13

117 08.05.13 What is the latest estimate for the construction period of Phase 1 (Section 1) - - LaBrea, Fairfax and La Cienega Sations?

Please refer to Article V - Contract Term and Period of Performance for theestimated duration of the construction period for Section 1.

08.21.13

118 8.23.13 Milestone 3 refers to the commencement of piles at Flower Street:• No Flower street on this project. (Regional Connector)• If this does refer to one of the locations at this project, then there could have aconflict between milestones. Lets say the design for the SOE and utilities is approved9 months (270 days into the project.). Utility relocation for piles is 45 cal days. ThenMilestone 3 would complete on 270 + 45 + 2920 or 3235. This is after Milestone 1.

To be revised in future amendment. 08.29.13

119 8.23.13 Milestone 4 states that demob is 3250 days AFTER removal of decking. The deckingis one of the last things to be done. Substantial completion is 3070 after NTP. Letssays decking comes out at day 2700. Then demobilization must complete by 2700 +3250 = 5950. 6950 / 365 = 16 years after NTP.

Please refer to the answer to question no. 33 above. 08.29.13

120 8.23.13 Please explain why alignment vertical profile adjustment is restricted to 5ft upwardand 30ft downward? Does the restriction apply to the top of rail elevations at eachstation?

General Requirement Section  01 11 01 Paragraph 2.20. J.1.a.3 will be revised in afuture amendment to remove the constraint on profile deviations in the vertical plane.The track alignment may be realigned from that shown so long as it remains within 5-feet from the Right-of-Way limits.  As part of Project planning and design for energyconsumption (Refer to Section  35 63 Sustainability Plan), the  track vertical profileshall be designed with a vertical profile sag between stations to minimize train energyconsumption during breaking and accelerating on approaching and leaving thestations respectively.

09.10.13

121 8.23.13 Will Metro entertain alternative technical concepts for the underground stationdesign?

No, Metro will not consider alternative technical concepts for underground stationdesign.

08.30.13

122 8.23.13 It is understood that Metro would entertain betterment to the station module approachto the ancillary spaces. Will Metro consider and accept betterment to the stationentrances, public areas, fared zones, boarding platforms, station shape and form,floor heights, etc., so long as the betterments meet Metro Rail Design Criteria? WillMetro consider anybetterments, even if they conform to all technical requirements, not responsive to theproposal solicitation?

Define “betterment(s)”. Metro would consider a “better design” that is compliant to allthe Project Definition Drawings, Technical Requirements, Metro Design Criteria,Metro Standard Drawings and all other mandatory Contract Documents. The “betterdesign” will need to be cost effective as lowest price is part of the proposalevaluation criteria. All “better designs” must conform to all technical requirementsand be responsive to the RFP solicitation.

08.30.13

Revision 1812/13/2013

19 OF 62

Page 20: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

123 8.23.13 Amendment 1 includes a design deviation approval of architectural directivedrawings. Does it imply that any design features that are not identical to the MetroDirective Drawings require deviation approval? To our understanding, the intents ofthe Metro Standard Drawings are mandatory, but the intents of the Metro DirectiveDrawings are not, except mandated contractually otherwise. Is our understandingcorrect?

Design features that are not identical to the Metro Directive Drawings DO NOTrequire deviation approval. Metro Standard Drawings are mandatory, but MetroDirective Drawings are not mandatory except if the information shown on the MetroDirective Drawing is a technical requirement elsewhere in the RFP.

08.30.13

124 8.23.13 Can Metro provide cadd files of all the geological profiles included in the GBR? Electronic files will be provided with the final GBR amendment. 09.19.13

125 8.23.13 A TBM arrival shaft is prescribed west of existing Wilshire/Western Station, inanticipation of TBM launching from Wilshire/La Brea Station eastward. However, wedon’see any prescription of an arrival shaft at the west end of the tail track. Pleaseexplain Metro’s position and intent about how to terminate bored tunnel thereof.

Please refer to Drawing G-2450 for the termination at tail tracks.   This may requireportions of TBMs (shields) to remain in place, with other components salvaged thruthe tail tracks and Wilshire/La Cienega shaft excavation.  A retrieval shaft at the westend of Section 1 was not contemplated at the time of the EIS/EIR and cannot becleared in time for Section 1.

09.04.13

126 8.23.13 Will Metro consider and accept construction methods other than cut-and-cover orbored tunneling for stations, X-overs, and tail tracks? For example, the RegionalConnector project prescribes the use of SEM for X-over cavern construction.

Metro has anticipated Sequential Excavation Methods (SEM) for cross passages inthe GBR. Westside Subway Extension stations and crossovers, to be constructed insoft ground, may not be excavated using SEM. Tail Track excavation by tunnelingmethods other than pressurized face TBMs may be acceptable subject todemonstration of meeting project requirements, such as those in TechnicalRequirements Section 31 71 16 - Mined Cross Passages. Note that Cut and Covermethods are not acceptable for tail track construction.

09.19.13

127 8.23.13 Is the 1+5 bored tunnel ring configuration mandatory? No 09.04.13

128 8.23.13 What is Metro’s position on the migration of contaminated groundwater at the stationsites, where construction dewatering would induce such a movement should soliderpile with lagging wall system is deployed as the mean of stability of excavation?

Regarding the movement of the contaminated groundwater as a result of dewatering,Contractor is responsible for the treatment and disposal of contaminatedgroundwater that is discharged from a dewatering system or from the excavation.

11.01.13

129 8.23.13 A 4 (four) inch construction tolerance is shown on the bored tunnel typical section.Are we allowed to adjust the tolerance to fit our tunneling control?

Tolerances shown are maximum allowable. Tighter tolerances are acceptable topromote better tunnel build and reduce potential need for track adjustments

08.28.13

130 8.23.13 Does Metro’s HRT vehicle dynamic envelope consider end throw? We understand the term ‘end throw’ in the question to mean the train overhang(either mid-overhang or end-overhang) as the train travels through a curve.  TheMetro Dynamic envelope does not take account of this.  For these dimensions, referto Section 4 of the Metro Design Criteria, and in particular Figure 4.16.  In addition,refer to Project Definition Document drawing Y-2005 (Sheet 233) which shows theoffset dimensions for the centerline of track from the centerline of tunnel for thecurves in the project alignment. 

08.28.13

Revision 1812/13/2013

20 OF 62

Page 21: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

131 8.23.13 The information required in Vol. 2, Section D.1 is the same information thatProposers are to provide in Section B. Due to the page limitations on Vol 2 and toeliminate duplication ofinformation, we request that LACMTA remove this requirement from Section D andonly require Proposers to provide it in Section B.

No change will be made to the submittal sequirements. Proposals must comply withall RFP submittal requirements.

08.30.13

132 8.23.13 Please clarify what information the Proposer is to provide in Vol. 3, Section B.2"Structures" that is not already included in other sections of Volume 3

Please refer to the answer to question no. 38 above. 08.30.13

133 8.23.13 Exhibit A - Minimum Qualification of Key Personnel and Functions Note 2 a) and b)appear to be minimum requirements for the Design - Build Entity and not for KeyPersonnel. Please clarify.

Refer to Section 3 of the RFP Documents, Evaluation Criteria and Process, Exhibit AMinimum Qualification of Key Personnel and Functions

08.30.13

134 8.23.13 Are all of the mitigation measures strictly mandated as a part of the GeneralRequirements?

Mitigation measures have been certified and approved by both Metro and the FTAand are legally binding. If there are alternative methods to achieve the same degreeof mitigation, those would need to be evaluated and approved by Metro’sEnvironmental Compliance Department and the FTA.

09.13.13

135 8.23.13 MRDC 4.2.11 stipulates turnouts at terminal stations shall be minimum No. 15. IsWilshire/La-Cienega Station considered a terminal station before the Purple Line isextended westward? Should the station be construed as a terminal station, hasMetro approved a design deviation for the crossover using No. 10 turnoutsimmediate east of the station?

Wilshire/La Cienega Station is not considered a terminal station. Wilshire/LaCienega is considered a temporary terminus and a design deviation to use No. 10turnouts are not required under this designation.

09.19.13

136 08.30.13 Paragraph J. 1. a. 3) states that “The track alignment may be realigned from thatshown so long as it remains within 5-feet from the Right-of-Way limits...”Please clarify if the 5-foot lateral position tolerance includes the option to have thelateral extents of permanent infrastructure to be up to 5 feet outside the Right-of-Waylimits or please confirm, in a diagram for the avoidance of uncertainty, therealignment tolerance with respect to the Right-of-Way.

Elements of the Guideway are not to be constructed outside of the ROW. Pleaseread Section 01 11 00 Summary of Work; Sub-Article 1.05 “The Project is to beconstructed within the permanent Right-of-Way and Temporary Easements that havebeen obtained for the Project, as shown on the Project Definition Drawings”. Alsorefer to Metro Design Criteria 4.1.5.1 Right-of-Way “for defining the width and depthof the ROW, necessary to fit the entire transit Guideway, including all its elements.

11.08.13

137 08.30.13 Under design-build requirements for installation, there's a specific item noting that araised decking concept has been approved for the Wilshire/Fairfax Station area.Please confirm if there's been any approval for the raised decking concept for theother two stations.

No approval has been obtained for Wilshire/La Brea or Wilshire/La Cienega raiseddecking.

09.05.13

138 08.30.13 Vertical curve reference PVI13 (Sta 575+98.39) of given length 300ft (Drawings C-031 & C-2021) appears to be consistent with a design speed of 45mph whenreviewed against Metro Rail Design Criteria Section 4.1.6.5. This design speed doesnot appear to be defined for this element. Please clarify the status of this verticalcurve with respect to the required speed.

The design speed is 45 mph. Also refer to design Deviation WSE-2013-001. 10.03.13

139 08.30.13 The RFP drawing E-0040 does not show a 34.5KV tunnel parallel feeder betweenthe existing Wilshire/Western TPSS and the new Wilshire/La Brea TPSS. Pleaseclarify or confirm that this feeder section is not required.

There are no 34.5 Kv trainway feeders between the existing Wilshire/WesternStation and the new Wilshire/La Brea Station.

10.02.13

Revision 1812/13/2013

21 OF 62

Page 22: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

140 08.30.13 The Geotechnical Design Memoranda, Section 4.6.5 refers to Metro StandardDrawing SS-003 for seismic earth pressures to be applied to both the shoring andpermanent wall design. However, Metro Standard Drawing SS-003 included in theRFP, Volume II, Section 4-Metro Standard Drawings, is labelled as “NOT USED”.Please clarify the status of Metro Standard Drawing SS-003 and the design approachfor seismic earth pressures.”

Please refer to the answer to question no. 18. (Support of Excavation drawings willbe provided in a future amendment)

09.10.13

141 08.30.13 Are CAD files available for Metro Rail Standard drawings? (specifically, StructuralStandard drawings Cut and Cover Underground Structures: SS-002 ConstructionStructures Loads and Design Criteria; SS-003 Construction Structures LateralPressures and Criteria; SS-004 Construction Structures, Tie-Back, Bracing,Excavation and Vertical Support Criteria).

CAD files are NOT available for Metro Rail Standard Drawings. 09.10.13

142 08.30.13 Replacement Page 1-4 of Amendment 1 does not appear to correspond correctly tothe existing Page 1-4. The first paragraph repeats the last paragraph of Page 1-3,and the last paragraph appears truncated.

These are not replacement pages but rather show the changes such as insertions inbold blue and/or deletions in strikethrough in red.

09.03.13

143 08.30.13 Replacement Page 2-145 of Amendment 1 does not appear to correspond correctlyto the existing Page 2-145. This affects subsequent Pages through 2-242

These are not replacement pages but rather show the changes such as insertions inbold blue and/or deletions in strikethrough in red.

09.05.13

144 08.30.13 Replacement Page 2-246 of Amendment 1 does not appear to correspond correctlyto the existing Page 2-246. This affects subsequent Pages through 2-258.

These are not replacement pages but rather show the changes such as insertions inbold blue and/or deletions in strikethrough in red.

09.05.13

145 08.30.13 Replacement Page 3-52 of Amendment 1 does not appear to correspond correctly tothe existing Page 3-52. It appears to correspond to Page 3-51.

These are not replacement pages but rather show the changes such as insertions inbold blue and/or deletions in strikethrough in red.

09.05.13

146 08.30.13 Replacement Page 3-52 adds the phrase, "…and the Illness and Injury PreventionPlan(s)." We find no requirement in the Volume II submittal requirements specifyingthe inclusion of such a plan. Please identify where this plan should be included.

Illness and Injury Prevention Plan(s) should be included with Safety submittal as perSP-21.H - Compliance with Laws.

09.18.13

147 09.04.13 EIR/EIS, page 4-160, Mitigation Measure VIB-2 - Use of a Low Impact Crossover,states "A low impact crossover, such as a movable point frog or a spring-loaded frog,will be used in the design of the Wilshire/La Brea No. 10 Double Crossover for theapartments at Site V16)". However, Project Definition Plan C-2111 shows the use ofresilient fasteners. Please clarify.

High compliance resilient rail fastener are to be used in place of the low impact frog.Design-Builder to confirm final design meets specified noise and vibration criteria.

10.03.13

148 09.04.13 Section 01 11 01 Project Design-Build Requirements, Page 8, clause E.1.a. states"Provide a minimum 12-inch thick singlepass double gasketed….". Please clarify ifthe proposer could optimize the segmental lining thickness to fit its final design.Please also clarify the minimum concrete cover of the segmental lining.

12 inches is the minimum requirement for segment thickness. 1 ½ inches isminimum clear cover on inside face and sides of segments. On the outside face(face in contact with the ground) a minimum clear cover of 2 inches is required.Technical requirements will be revised to clarify the cover requirements in a futureAmendment.

09.19.13

Revision 1812/13/2013

22 OF 62

Page 23: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

149 09.04.13 Section 01 11 01 Project Design-Build Requirements, Page 9, clause E.2.a. states"Elevated Gas zone: Design the precast segmental tunnel lining, with the provisionfor a 6-inch secondary lining……".Please clarify if the proposer can optimize thesecondary lining thickness to fit its final design. The same clause further states"...have the capability to be constructed within the pre-cast segmental tunnel lining,and while the subway system is in operation." Please clarify if one of the two tracksremains operation meets the stipulated condition.

Yes, the proposer may “optimize” secondary liner design for compatibility with FinalDesign while meeting minimum tunnel envelopes for Heavy Rail Vehicles. Should asecondary liner need to be installed after ROD, the work window given to theContractor would be from 10:00 PM to 3:00 AM Sunday through Thursday.

10.18.13

150 09.04.13 Section 01 11 01-17, Project Design-Build Requirements, clause 3.03 A.5.astipulates "Special excavation methods as defined in the GRB with no more than 6inch lifts are a project specific requirement within the Paleontological Zone……….".Since the 6 inch lifts are most likely to be executed by hand mining over weekend fullroad closure periods, it would be almost impossible to achieve a depth (about 6ft)sufficient for decking/supporting beam installation in any given weekend closure of53 hours (Friday midnight to Monday 5am), and restore surface traffic. Will Metroreconsider the lift restriction?

Due to street closure time constraints, 6 inch lifts will not be required for deck beaminstallation and utility relocation, up to a depth of 10 feet below the ground surface.Metro has assumed the use of raised decking in the design of the advance utilityrelocations. The raised deck installation reduces time of excavation in theWilshire/Fairfax area for deck beam excavation and potential disturbance ofpaleontological resources. This will be clarified in a future amendment.

10.03.13

151 09.04.13 EIS/EIR, page 4-338,first paragraph, states "In areas where gas is present, such asthe Wilshire/Fairfax Station initial support for the station wall could require a lesspermeable wall systems such as slurry walls or secant pile walls". However, GBR,page 7-4, Section 7.3 Wilshire/Fairfax Station Excavation, third paragraph, states"The excavation is to be supported by means of soldier piles and shotcrete laggingwith an internal system of walers and struts". Please clarify. Further to the inquiryabove, should the less permeable wall system is required, will be the same systemrequired for the Wilshire/La-Cienega Station for the station is also located in elevatedgas zone.

The Contractor is to design based on ground conditions described in the GBR andGDRs and select means and methods to address those conditions. The shotcreteLagging statement will be clarified in a future amendment.

09.19.13

152 09.04.13 The information required in this Vol. 2, Section D.1 is the same information thatProposers are to provide in Section B of this Volume. Due to the page limitations onVol 2 and to eliminate duplication of information, we request that LACMTA removethis requirement from Section D and only require Proposers to provide it in Section B.

This is not a duplication; the Design-Builder/Proposer must comply with RFPrequirements.

09.18.13

153 09.04.13 Please clarify what information the Proposer is to provide in this Vol. 3, Section B.2"Structures" that is not already included in other sections of Volume 3.

Please refer to the answer to question no. 38 above. 09.18.13

154 09.04.13 "Note 2: a) and b)" appears to be minimum requirements for the Design - Build Entityand not for Key Personnel. Please clarify.

This is correct. These are minimum requirements for the Design-Builder/Proposer. 09.18.13

Revision 1812/13/2013

23 OF 62

Page 24: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

155 09.04.13 Metro’s responses to Q121 and Q122 appear contradictory to each other. Can Metroelaborate the exact meaning of Response to Q121? Is flat roof (in lieu of arch roof)prohibited?

Please refer to Instructions to Proposers, IP-08 for instructions on MODIFICATIONSAND ALTERNATIVE PROPOSALS. Alternative Proposals may be submitted, butwill only be considered if the Proposer also submits a proposal conforming to therequirements of the RFP”.With respect to station roofs, the arched roof shown on the Project DefinitionDrawings considers location of the pile corridor and the advanced utility locationsand provides a clear span for the stations. Station Designs with columns onplatforms will not be accepted. This will be clarified in a future amendment.

09.19.13

156 09.04.13 27 36 00 Telephone System indicate that telephones shall be VoIP but drawingsshow all analog phones. Please clarify.

The telephone system shown on drawing CN-2907 is VoIP. The analog telephonesets are shown to provide off-hook detection and line supervision via the SCADAsystem.

10.04.13

157 09.04.13 Item 4.07 Building & Adjacent Structure Protection Report Section 4.3 Protectionfrom Ground Movements Related to Open‐Cut Construction makes reference toadditional PE Reports, namely "Adv. PE 3.07.040 series of reports (3.07.040.1through 3.07.040.4)". Are these reports included as reference documents? If not canwe be provided with copies of these reports?

The report reference numbers provide were not correct, Building and AdjacentStructure Protection Report will be provided in a future amendment

10.03.13

158 09.09.13 This section requires names of “...all subsidiaries,...” Please clarify as to whether therequirement pertains to parent companies’ subsidiaries or bidder/proposersubsidiaries.

Yes, certifications are required for all parent and subsidiary companies. Whiletechnically only the prime contractor is required to submit an ethics declaration, weprefer all subs do as well. However, in circumstances where only the prime submitsan ethics declaration, they are answering on behalf of their subs. Proposers toconduct due diligence when completing form. Yes, this requirement pertains toparent companies subsidiaries as well as bidder/proposer subsidiaries.

09.18.1310.09.1311.08.13

159 09.09.13 This states: "Public Telephone shall be provided by the local telephone company andwill not be part of the Metro Private telephone system". However, a specification forthe public telephone system is provided in Section 10 17 16 Public Telephones.Please confirm whether the installation of Public Telephones is included inContractor's scope of work.

The Telephone Company will install the actual phone only. The DB Contractorprovides the enclosure for the phone, and all the electrical, cables, wires, conduits,etc. Contractor to coordinate with Metro Please refer to Communication Drawing CN-2907 for Telephone System Block Diagram. Specifications and drawings will bemodified and included in the next Amendment.

10.02.13

160 09.09.13 This article states that: "The FACP shall transmit alarm/troublezones to the Metro'sprovided fire alarm workstation located in the rail operations control (ROC)." Pleaseconfirm whether this statement is to be read that the Metro will provide the ROCworkstation and the relevant contractor's scope.

Metro will provide the Fire Alarm Workstation at the ROC. 09.17.13

Revision 1812/13/2013

24 OF 62

Page 25: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

161 09.09.13 Item I. states: "This equipment includes a marker frequency generator that generatesthree frequencies to be applied to the appropriate markers as shown." This isfollowed by a list containing two frequencies. The Drawings also suggest that onlytwo frequencies are used. Please clarify which is correct.

Correct, only two frequencies (not three) as noted in the Technical RequirementSection and Referenced Drawings Vol2B TC-012 are needed. The TechnicalRequirement Section (34 42 13.83 2.03 I., 34 42 13.83-5) in question will be revisedin a future Amendment to read as follows “This equipment includes a markerfrequency generator that generates two frequencies to be applied to the appropriatemarkers as shown”.

09.13.13

162 09.09.13 These refer to the "Cable Plan In Contract Drawings" in regard to the system. Suchdrawings cannot be found among the drawings supplied in the RFP. Could thepreliminary design cabling plan be provided?

The Contractor is responsible for preparation of Cable Plan drawings during finaldesign. The Technical Requirement Section (34 42 16.16) in question will be revisedin a future Amendment to read as follows: “Per Cable Plan drawings prepared by theContractor”.

09.13.13

163 09.09.13 Articles 4.6.5 and 4.6.7 of the Technical Memorandum for Stations Section - 1 andArticle 5.6.4 B. (Page 5-76) of Metro Rail Design Criteria Section 5Structural/Geotechnical all refer to Standard Structural Drawings SS-002, SS-003,and SS-004 that provide design criteria for construction structures (shoring anddecking). In the package provided to us, these three drawings have been x'ed outwith the note "NOT USED" placed on them. Is LACMTA going to issue replacementdrawings for these three criteria drawings as implied by the references above?

Yes – Shoring criteria will be provided in a future amendment 09.12.13

164 09.09.13 The drawing shows no TWC loops around Wilshire/Western Station, neither existingnor proposed. Please explain whether this is an omission of the existing equipment toavoid confusion and, if there are no loops at Wilshire/Western Station, are they to beinstalled by the Contractor?

Yes, the Contractor is responsible to furnish wayside portion of the TWC system(both loops and TC&C room equipment) per the Technical Requirement Sections 3442 13.19, 34 42 13.33, 34 42 13.79 among other sections included in the RFP. As forthe reference drawing in question (TC-401), it provides only a representation of theexisting wayside equipment layout at Wilshire/Western station. Note that the existinginfrastructure does not have any TWC equipment.  However, Contractor isresponsible to field verify the existing conditions at Wilshire/Western beforeperforming final design.

09.19.13

165 09.09.13 The reference design shown only shows PSS markers for the main direction of trafficfor each track. The arrangement of the signaling devices and operational referencematerial suggests that bi-directional operation will be possible on both tracks andused in emergency situations. Please confirm that the provision of a PSS system forthe main direction only as shown on the reference drawings is sufficient.

It should be noted that reference drawings are for Information Only. Forarrangement of signaling devices, the Contractor is to comply with the TechnicalRequirements of the RFP. The ATC system shall permit following moves in bothnormal and reverse directions of travel on each track in accordance with theTechnical Requirements. However, when a train is operating against the normaldirection of travel of a particular track (also known as reverse direction) then the trainshall operate in MTO mode only with full ATP protection, including speed limittransmission and enforcement. In such reverse direction operation, the berthing oftrains will be performed manually by the train operator. Refer to TechnicalRequirement Sections 34 42 13.06, 34 42 13.19, 34 42 13.83 among other sectionsincluded in the RFP.

09.19.13

Revision 1812/13/2013

25 OF 62

Page 26: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

166 09.09.13 Drawing 408 on Track BL through La Cienega Station shows both the temporaryposition of the Programmed Station Stop (PSS) equipment for train arrival fromFairfax Station (designated **) and for the permanent condition for the full extensionfor train arrivals from Phase 2 extension. Is the Contractor expected to install PSSequipment for both conditions or just for Phase 1 extension? Similarly, formodifications at Wilshire/Western Station, is the Contractor expected to provide newequipment for PSS on Track BL or is repositioning of the existing equipmentsufficient?

It should be noted that reference drawings are for Information Only. For arrangementof signaling devices, the Contractor shall comply with the Technical Requirements ofthe RFP. At La Cienega Station, the Contractor is responsible to provide allequipment and circuitry necessary for the temporary terminal operations andprovisions (both equipment and circuitry provisions) for converting the temporaryterminal configuration to the final through station configuration. At Wilshire/WesternStation, however, Contractor is responsible to field verify the existing conditions atWilshire/Western before performing final design and provide new PSS equipment inorder to convert the temporary terminal configuration to a through stationconfiguration. Refer to Section 01 11 01 - Project Design-Build Requirements,subsection 2.02.L.2 – Provision for Future Construction, and Technical RequirementSections 34 42 13.19, 34 42 13.26, 34 42 13.33, 34 42 13.83 among other sectionsincluded in the RFP.

09.19.13

167 09.12.13 Drawing G-2401, Section A, shown tieback elevations do not match with the tiebacksketch in Vol 3b for Wilshire 8501 building. Please clarify.

Please refer to General Notes 2 and 3 on Project Definition Drawing G-2090. 10.11.13

168 09.12.13 The Tunnel and Station Ventilation Report (Deliverable No. 6.6.4.E Rev 1) does notprovide a description for the function of the emergency ventilation concept for the tailtrack as shown on Drawing G-2450. The reversible ventilation fan shown woulddirect smoke into the platform during an emergency fire condition. Therefore weconsider the concept described as not workable. Please update the ventilationreport to describe the proposed tail track ventilation scheme.

The Tail Track Ventilation System is designed to work in conjunction with theStation/Tunnel Ventilation fans at the West end of the Wilshire/La Cienega station.Evacuation away from the incident train shall always be through the cross passageand up the non-incident track.Example, if the incident train is on BR Track, evacuation will be toward the crosspassage at the end of the tail track tunnel.- Track Dampers on the BL Track are closed.- Track Dampers on the BR Track are open.- Tail Track Auxiliary Fan (TAF) moves air thru the cross passage and up BR Track.- Emergency Ventilation Fans (EF) draw air through the Track Dampers on the BR

Track and exhaust to the surface.Evacuation to the station via the BR Track will operate in the reverse.

10.03.13

169 09.12.13 Will Metro allow an ATC (Alternative Technical Concept) process similar toCrenshaw/LAX Transit Corridor Project? Or will Metro allow, at a minimum, a PAPS(Pre-Proposal Alternate Proposal Submittal) process similar to the RegionalConnector Transit Corridor Project?

Please refer to the answer to question no. 155 above. 09.20.13

Revision 1812/13/2013

26 OF 62

Page 27: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

170 09.13.13 According to the GBR, the Paleo Zone at the Wilshire/Fairfax Station is“…associated with the asphalt impacted soils…” and “…does extend into soil notimpacted with asphalt.”  According to Drawing K-125 in the GBR, this descriptionextends the entire depth of the station excavation. However, the GBR also says that“For baseline purposes, the ‘Paleo Zone’ is from the ground surface at ApproximateEl. 165 to the top of the marine sediments at El. 145 at the Wilshire/Fairfax stationexcavation site…”  This sentence seems to conflict with Drawing K-125 which showsthe Asphalt Impacted Soil extending down past El. 80 under the Wilshire/FairfaxStation. Please confirm the depth of the special excavation requirements at theWilshire/Fairfax Station.

The Paleo Zone is associated with the Tar Sands, however, it does not extend to thefull depth of the Tar Sands.  The GBR will be revised in a future amendment toclarify.

09.19.13

171 09.13.13 Metro Rail Design Criteria Section 06 Architectural Table 6.2 has specified minimumroom size requirements. Some of the room dimensions indicated on the ProjectDefinition Drawings are bigger or smaller than those stated in the Metrorequirements. If all equipment can fit in the plant room with adequate maintenanceand replacement access, please confirm if room dimensions can deviate from theMetro Rail Design Criteria.

Comply with Metro Rail Design Criteria Section 6, Table 6.2 for all minimum roomsize requirements except for those items listed in approved Deviation Requests WSE-2013-003 and WSE-2013-005, “Design Criteria Room Size Reduction for Clear SpanStations”.

09.19.13

172 09.13.13 Referring to General Requirements 01 11 00, 1.02 B. 10. Equipment provided andinstalled by Third Parties, the equipment and incoming power cables andaccessories will be provided by LADWP and SCE, respectively. However, per Note 8on Dwg. TP-2051 and Note 5 on TP-2053, Contractor shall coordinate and providemetering equipment, switchgear and conduits with DWP and SCE.

Please clarify who provides and installs this equipment.

Drawing notes on drawings are correct and Section 01 11 00, 1.02B.10 will bemodified to clarify the following:

· DWP will provide and install watt-hour demand meter and incoming power cables.Contractor to provide and install Potential Transformers (PTs), Current Transformers(CTs), incoming metering switchgear and accessories per DWP electric servicerequirements (ESR).

· SCE will provide and install watt-hour demand meter, PTs, CTs and incomingpower cables. Contractor to provide and install incoming metering switchgears andaccessories per SCE electric service requirements (ESR).

10.23.13

173 09.13.13 Technical requirement 31 74 16, 2.02 F. 2. states: “interconnect the double gasketwith a crossbar located on each radial joint face.” Our experience with crossbars /crossgaskets has been with their location on the circumferential face to avoid rollingof the gasket when the segments are positioned. Please confirm if the radialrequirement is mandatory or would the LACMTA accept location of thecrossbars/crossgaskets on the circumferential face if similar compartmentalizationcan be achieved?

Radial location is not mandatory. Please refer to Drawing Y-2011.  The TechnicalRequirement will be revised in a future amendment

09.13.13

174 09.13.13 Our understanding of Paragraph A. is that contractor JV members, which aresubsidiaries of parent companies (and use their parent companies’ projectexperience and execution capabilities), will not be required to provide a ParentGuaranty at Proposal submission, but may be required to provide one post-bid.  Isthis correct?

Not required at Proposal Due Date although IP-13 (18) Metro has the discretion torequire a Parent Guaranty.

09.18.13

Revision 1812/13/2013

27 OF 62

Page 28: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

175 09.13.13 Amendment 1 lists a number of drawings as being revised or added. We cannot findthe following drawings in Amendment 1:

Sheet 135, Drawing DC-2002Sheet 136, Drawing DC-2004Sheet 138, Drawing DC-2025Sheet 143, Drawing DC-2407Sheet 144, Drawing DC-2408Sheet 248A, Drawing K-2001Sheet 248B, Drawing K-2002Sheet 248C, Drawing K-2003

Amendment #1 cover page will be revised to correct erroneous information in afuture amendment.

10.11.13

176 09.16.13 In reference to LACMTA’s response to Question No. 16 we would like to request bulksoil samples from the exploratory shaft excavation.

Proposers may request soil samples from the Exploratory Shaft construction site.Arrangements and pick up times must be coordinated with Eva Rodriguez at (213)922-1034 or via email at [email protected]. Metro does not warrant theaccuracy or representation of all conditions of the soil samples obtained from theEXCAVATION in the Wilshire/Fairfax station area or Tar Sands.  Also, proposersreceiving samples assume the risk of interpretation of the samples obtained. Proposers are also reminded that the Contractor must properly dispose ofcontaminated soils at the appropriate disposal sites and comply with ContractDocument including but not limited to SP-21- Hazardous Substance Managementand GC-41 – Environmental Compliance.

10.03.13

177 09.20.13 After reviewing the RFP for this project, I wanted to clarify if Metro will retain thepaleontologist for this project, or would it be one of the joint ventures? From the RFPit appears that it will be Metro. If it is Metro, will there be a separate opportunity toparticipate in the bidding for the paleontology/archPBology portion of the project?

Per General Requirements 01-35-92 section 1.01.B and 1.07.B the scope of work inquestion is performed by Metro (or its agents) not the Design Builder. 

10.03.13

178 09.23.13 Is it possible to get a copy of the list of certified DBE firms that was included in theRFP in an excel format? This will assist us with our outreach efforts to the DBEcommunity on the project.

The list of certified DBE firms is only available in word format and it will be emailed toall planohoders.

10.04.13

179 09.23.13 We have compared the room sizes shown on Architectural plans with therequirements stipulated in Metro Rail Design Criteria and have found many roomsare smaller than that required by the Criteria. Please clarify if Metro intend to issuedesign deviations for those nonconforming rooms or if Metro expects that the finaldesigners shall rectify the deficiency.

Metro Rail Architectural Criteria Section 6, Table 6.2 room minimum dimensions arebased on a station with columns. Deviation Requests WSE-2013-003 for TractionPower Substation Room, and WSE-2013-005,Train Control and CommunicationsRoom, have been approved by Metro for room size reductions based on a clearspandesign.  A Request for Deviation for other room reductions based on a clearspandesign is in process. The Deviation will be included in a future Amendment.  Anyremaining rooms will need to comply to MRDC Section 6, Table 6.2 or the successfulContractor may request a Deviation, subject to Metro review and possible approval.

10.09.13

Revision 1812/13/2013

28 OF 62

Page 29: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

180 09.23.13 We could not find as-built information for 6226 Wilshire (about sta. 537+50). Pleaseprovide.

For 6226 Wilshire Design Information is only available from City of Los AngelesBuilding and Safety, and can be viewed inside their office.  The reference filenumbers were provided in Reference Documents, Building information – Section 1Spreadsheet.

10.11.13

181 09.23.13 We could not find as-built information for 5900 Wilshire (about sta. 522+75). Pleaseprovide.

Available information on the building at 5900 Wilshire found in the ReferenceDocuments (file numbers). The Los Angeles Department of Building and Safetymay have additional as-design information available but access to these files arerestricted. Metro is seeking approval from the Owner for viewing these files

10.18.13

182 09.23.13 It appears that Drawing G-2303, Section A, is not shown to reflect the most adversetie-back location for the 6500 Wilshire subsurface parking garage, and the tunnel willbe much closer to the existing tie-backs. Please clarify.

The sections indicated are based on design drawings and my not reflect as-constructed conditions. Please refer to General Notes 2 and 3 on Project DefinitionDrawing G-2090.

10.31.13

183 09.27.13 Subsequent to Metro's reply to Q123, we wish to further clarify the following: A-Seriesdrawings do not show the distance between Concourse Floor elevation and thePlatform Floor elevation while S-Series drawings, S-1133, S-1134, etc.indicate 15'-3". Metro Directive Drawings, AD-002, AD-003, AD-005, etc. indicate theminimum distance is 16'-3". Please clarify which one the proposer has to conform to.

Conform to Metro Rail Design Criteria as modified by approved design deviations,Metro Standard Drawings, and applicable A-series drawings for required minimumvertical clearances at platform and concourse areas. The minimum distance of 16’-3”shown on Metro Directive Drawings is not a specific requirement; however theminimum distance of 10’-5” from the platform finish floor to the underside of theedgelight and cantilever arm support is required, as indicated on A-series drawings.

10.18.13

184 09.27.13 Subsequent to Metro's reply to Q151, we felt that Metro has not responded to thepart of the question regarding the statement in the EIS/EIR. Does Metro imply thatthemitigation measures prescribed in the EIS/EIR can be ignored?

Clarification of excavation support requirements will be provided in next Amendment. 11.08.13

185 09.27.13 Per the "Corrosion control measures technical memorandum (Final)", the corrosionindex is severe. Are there any Metro recommendations related to reconstruction offacilities such as storm drain, sewers, water and other utilities?

Yes, please refer to the Geotechnical Data Reports. Preliminary Recommendationsfor corrosion mitigation are included in the Appendices.

10.31.13

186 09.27.13 What are the preliminary design recommendations regarding the cross passagessumps? Are the future pumps at these locations collecting only the waste water forthe tunnel areas, or the combination tunnel plus station?

The sumps at the cross passages shall have the same considerations as those inthe station. They will collect any water that infiltrates the tunnels (and stations) aswell as any water discharged from the fire standpipe system during a fire event. TheCross passage sump system shall also collect the water that is not collected in thestation sumps and continues to the tunnel low point. Also refer to the answer toquestion no. 11 above.

10.04.13

Revision 1812/13/2013

29 OF 62

Page 30: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

Is ALL tar contaminated soil required to go to a class II landfill or (dependent on testresults) is it allowable to send a portion of the material to a class III facility?-Per Environmental Procedures for Contaminated and Hazardous Materials, 01 3543-6: All tar contaminated soil shall be disposed of in a Class II landfill. However, thisconflicts with the EDR (pages 93 and 94 of 102), where it states the following: 91% ofthe tar impacted soils from the Wilshire/Fairfax Station were initially considered to beNon-RCRA Hazardous Waste (California Hazardous Waste) per CaliforniaRegulations, but later classified to be non-hazardous for disposal purposes whenthey passed the Bioassay Fish Kill Test. However, due to the presence of tar in thesoil, most of the excavated materials may require disposal at a Class II Landfill facilitysuch as McKittrick Landfill (located west of Bakersfield). It is anticipated, that aportion of the excavated material from this location can also be disposed off at aClass III Landfill facility, provided favorable test results from Bioassay test areestablished during station excavation

operations and no excessive tar balls are encountered. If the Bioas say results areunfavorable then the excavated material will require disposal to a Class II Landfillfacility such as McKittrick Landfill.

188 09.27.13 Members of our team have recently completed Metro Exhibit C Experience /Performance Questionnaire forms that were submitted for another recent Metrodesign-build proposal. Will Metro accept these same forms for the WestsideExtension proposal?

No, DB/Proposer must comply with the RFP requirements. 10.04.13

189 09.27.13 Amendment 1 adds an Illness and Injury Prevention Plan to the exclusion of the pagecount in Volume 2 - Project Management Submittal, however, the plan is not addedinto the submittal requirements. Will Metro be issuing revised submittal requirementsbased on these new additions? Please clarify.

RFP Section 3, Vol II Project Management Submittal requires the Illness and InjuryPrevention Plan(s) to be submitted as a submittal. The Health and Safety Section 0135 23 Work Site Safety Requirements requires a Project Specific Illness and InjuryPrevention Plan(s) to be submitted after award.

10.04.13

190 09.27.13 The RFQ did not require a Design Quality Manager to be submitted in the SOQ.Exhibit A - Minimum Qualifications of Key Personnel and Functions in the RFP showsthe minimum requirements that this position needs to meet. Will Metro be requiringthe submission of a Design Quality Manager in addition to those resumes submittedin the SOQ? Please Clarify.

Yes, as required in the RFP documents. 11.15.13

191 09.27.13 Will Metro be revising the Form 3’s for Design and Construction to include changesmade to columns C-G on these forms as was done for the Regional Connectorprocurement?

To be revised in future amendment. 10.04.13

The tar will likely be non-hazardous based on the bioassay test that was alreadyconducted.  However, if the soil has high VOCs, even if it is non-hazardous, it canonly go to specific facilities, such as Thermal Remediation Solutions facilities.  If soilhas low VOCs and is non-hazardous, then it can go in to a class III facility that canthat accepts that level of TPH.

10.11.1309.27.13187

Revision 1812/13/2013

30 OF 62

Page 31: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

192 09.27.13 Section 01 11 00 - 9, paragraph 1.04.B.1 states: "Prior to Contractor access to astation or shaft location, Metro will have relocated utilities inclusive of;telecommunications, electrical power, gas, sewer and water mains that run parallelto, and within the planned Pile Corridor." This statement omits "storm drain",presumably on purpose. However, the Contractor Utility Responsibility Matrixprovided in section 01 31 31 states that the 1045 contractor will only need tosuspend/protect the storm drains. Additionally, the project definition drawings call outthat the 1045 contractor is to relocate the storm drains. (See PDD Sheet 161 for anexample at La Brea Station). Please clarify who is responsible for storm drainrelocations.

To be clarified in next amendment. 10.31.13

193 09.27.13 The La Brea Station 1048 Advanced Utility Contract drawings provided inamendment 1 show a 36” HDPE sanitary sewer (SS). See sheet 082, cross section2. This SS is not shown on any of the project definition drawings in the 1045 RFPpackage at La Brea Station. It appears this 36” SS will remain in place and requiredto be hung by the DB Contractor on the 1045 contract, please confirm.

To be clarified in next amendment. 10.31.13

194 09.27.13 Section 3.03 on page 12 of 01 31 31 states that "The Contractor is responsible forthe design and construction of storm drain and sanitary sewer relocations...". This isin conflict with both the Responsibility Matrix in this same section, and also the scopeof work document, specifically section 01 11 00-9, paragraph B.1 which states that allsewer lines will be relocated ahead of time by other contracts. Please confirm thatthe contractor is not responsible for sanitary sewer relocations.

To be clarified in next amendment. 10.31.13

195 09.27.13 Sheet 161 of the project definition drawings shows an 18" sanitary sewer that is to berelocated by the DB contractor at La Brea Station. Upon reviewing the La BreaStation advanced utility contract documents, it appears the 1048 contractor is beingdirected to relocate this sewer line. Please clarify who will be relocating this sewerline.

To be clarified in next amendment. 10.31.13

196 09.27.13 It is not clear what is Mandatory in the context of GC Para 44. For instance, reading01 11 01 Project D/B Requirement Para 2.02C.1.a. it remains unclear what portion, ifany, Metro considers Mandatory. Advise if any words such as 'shall', 'will', 'are fixedas a Project Specific Requirement', Project Specific Requirements' are equivalent toMandatory. Q&A 123 may have further confused items as it defined those items inthe Directive Drawings and shown in the Technical Requirementsare now mandatory.

Words such as “shall” or “will” or phrases such as “are fixed as a Project SpecificRequirement” indicate that the item referenced is a requirement. As a general rule,the particular requirement referenced sets forth the minimum technical and/orperformance characteristics of the Work that must be met; however, in some casesthe particular requirement referenced must be met exactly, for uniformity purposes.All RFP requirements are “mandatory” as that term appears to be used in thequestion. GC- 44 will be clarified in a future amendment.

10.09.13

Revision 1812/13/2013

31 OF 62

Page 32: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

197 09.27.13 Section 01 35 63 Para 1.01.C states compliance is required for both 'Mandatorysustainability measures as well as voluntary sustainability requirements'.This conflicts with the same Section, Para 3.01.A that states 'The Sustainability goalsfor the Project, as a minimum, are to efficiently implement the mandatorysustainability measures as listed in the Sustainability Measures Checklist from theCurrent Edition of California Code of Regulations (CCR), CALGreen, Part 11 of Title24, Please clarify if only 'mandatory' or both 'mandatory and voluntary' items arerequired. If voluntary is also a requirement, confirm which Tier (Tier 1 or 2).

These paragraphs are not in conflict.  Contractor is to comply with 2013 CalGreenrequirements through the minimum implementation of the mandatory sustainabilitymeasures listed therein.  If Contractor chooses to implemented voluntary measures,to the fullest extent feasible, Contractor to meet Tier 1 requirements  but encouragedto meet Tier 2 requirements.  These requirements are, however, superseded byMetro sustainability and environmental related policy requirements, as applicable. Please refer to Volume IV "Other Contract Documents" or go towww.metro.net/ecsd for copies of Metro's sustainability and environmental policy andplans.

10.08.13

198 09.27.13 MRDC 2.3.2.2 indicates the ventilation system shall be designed meeting certainperformance criteria when the 'most critical fan will be assumed out of service'. Oneperformance criteria for HRT is a FHRR of 86.5MBtu. The PE Tunnel and StationVentilation Report, para 4.3.7 'Performance Criteria' states the 'one fan out' appliesonly to a single car fire (FHRR of 43.6MBtu). Is a deviation report expected forthe MRDC 2.3.2.2? NOTE: MRDC in 8.1.4.D does indicate the 'one fan out of servicefor one car fire'.

The MRDC (Mechanical 8.1.4.D) and PE Tunnel and Station Ventilation Report weremodified as stated in the “Fire Life Safety Basis of Design” report (03-27-2012),paragraph 1.1 Design Fire Properties. This change was agreed upon by the FLSCfor this project since the stations have fire sprinkler systems that will prevent thespread of the fire from one car to the next. Changes to the criteria are reflected in theMechanical Criteria (8.1.4.D). Section 01 11 01, Project Design Build Requirementswill be revised to include a single car fire with the most critical fan out of serviceduring a station fire. The Metro Fire Life Safety Committee will modify MRDC 2.3.2.2to reflect “one fan out with a single car fire with FHRR of 43.6MBtu”, as is currentlystated in the MRDC (Mechanical 8.1.4.D), and the PE Tunnel and Station VentilationReport and the Fire Life Safety Basis of Design Report of 03-27-2012 as part of theirnext update to the FLS Criteria.

10.11.13

199 09.27.13 Spec section 14 31 00 Escalators (warranty starts at Substantial Completion) seemsto conflict with GC-23 Warranty (warranty starts at Final Completion, or 12 monthsafter SC). Thus, Escalator warranties could expire 12 months prior to the Project'sother standard warranties. Confirm if the Escalator spec is an exception and theconflict is not to be reconciled with Art I Precedence. Also, GC 23.2.1 states:'Subcontractor’s, manufacturer’s or Supplier’s Warranty Periods shall be for thelonger of the above stated Warranty Period or the Warranty Period specified in theparticular Warranty'. To what does 'particular warranty' refer? The manufacturer'sstandard commercial warranty? A Technical Requirement special warrantyrequirerment? Something else?

The Escalator and Elevator Warranties are an exception to GC-23 and will start atSubstantial Completion.  At Substantial Completion the 1 year Warranty as well asthe 1 year Preventive Maintenance period will commence. The “particular warranty”refers to the specific warranty that is provided by the subcontractor, manufacturer, orsupplier.  So the warranty period for these warranties will be the longer of the periodset forth in GC-23 or the period set forth in the subcontractor’s, manufacturer’s, orsupplier’s warranty. If escalator and elevator supplier warranty in in excess of the 1year, the longer warranty will apply as per GC-23.

10.03.1310.09.13

200 09.27.13 It is not clear by reading the paragraphs dedicated to the Integrated Interior Glass'Tile/Panels' if the design product supplied to the contractor for installation will be afinished assembly (tiles adhered to a backing of an approximate overall size) orindividual artist tiles to be installed thin set (according to Section 09 30 00 'Floor andTile') in the field. Please elaborate. If the design product is to be a panel, pleaseestimate approx size of the panels.

Design product to be supplied to the contractor for installation will be finished panels.Each panel will measure 48” x 120

10.02.13

Revision 1812/13/2013

32 OF 62

Page 33: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

201 09.27.13 In item 46 of the Schedule Of Quantities And Prices Form (Schedule-A) we need tosubmit a unit price for incremental costs associated with contaminated soils up to500,000 Tons. In item 10.07 of the Schedule Of Quantities And Prices Form(Schedule-C) we need to submit a unit price for incremental costs associated withcontaminated materials over 625,000 Tons. There appears to be a gap of125,000 Tons of contaminated material that the contractor would not get paid for.Please revise.

The Schedule of Quantities and Prices will be clarified in the next Amendment. 11.08.13

202 09.27.13 Specification 31 71 19 Part 2.03 A.7 indicates, Use EPB TBM or slurry TBM capableof controlling face pressure to within +/- two psi of the desired pressure at all times.Typically Slurry TBMs are able to achieve this level of control, whereas EPB pressurecontrol ranges are +/- 7.25 psi (0.5 bar). Please clarify controlled face pressureranges for both Slurry and EPB TBMs.

Referenced Specification Section has been revised in Amendment 3: +/- 5 psi forEPB.

10.18.13

203 10.02.13 SP-07 States that: "LACMTA will provide Contractor with one electronic set of allContract Documents in PDF as listed in the following table." The table lists theAgreements between LACMTA and The City of Los Angeles, County of Los Angeles,and The City of Beverly Hills. However, we are only in receipt of the agreement withThe City of Los Angeles. Are there copies available of the agreements with theCounty of Los Angeles and The City of Beverly Hills?

The referenced MCA with the County of Los Angeles is not applicable to ContractC1045 and the MCA with the City of Beverly Hills is currently under development andwill be provided when it has been executed by the City of Beverly Hills and LACMTA.

11.21.13

204 10.02.13 Section B. 1. refers to a narrative description of the approach to work items a)through f) described as "Civil Works". Section B. 8. d) requires a narrative describingthe "...approach to coordinating the civil design with the systems elements."  Wewould like to reply accurately to this section, but it is not clear how "civil design" isdefined and consequently, how "civil design" and "system elements" would thereforeintersect and what coordination is to be described. It is also not clear how this isrelated to the “multiple interfaces involved in the design and construction of theProject” in the second sentence of B. 8. d).  In order to accurately respond to thisSection, we respectfully request clarification on the “civil design” that is referred to inSection B. 8. d) and clarification of the specific subject being referenced in thesecond sentence.

“Civil design” as defined in Section B.8.d refers to design of all the Fixed Facilitiesreferenced in Section B.1, which includes Civil Works, Structures, Architecture andUrban Design, Emergency Ventilation System, Fixed Facilities, Geotechnical andUtility Relocation. The proposer is required to describe the approach to coordinatingthis Civil Design with the Systems elements described in Section C of Volume III.

11.27.13

205 10.02.13 Section 01 11 01, 3.03 A. 5. b. states that a raised decking concept has beenapproved by the City of Los Angeles (DOT) for Wilshire/Fairfax Station area and isavailable upon request. IFB No. C1055 also indicates a deck structure raised aboveexisting grade. However, if this occurs, Contract C1045 will encounter difficultieswith grading to match the side streets, problems with handicap access, a potentialnecessity of stairs at bus stops, and other potential complications that won’t becomeknown until after construction has begun. Can the work under IFB C1055 be donesuch that the C1045 temporary decking at the Fairfax Station can be installed atstreet elevation?

The extent of raised decking allowed at Fairfax Station is now limited to a particulararea necessitated by an existing utility that is to be protected in place. Generalrequirements sections 01 11 01, Project Design-Build Requirements para. 3.03 A.5.b. and 01 50 35, Temporary Decking 3.02 C, have been revised in Amendment 4to require flush decking at all locations with the exception of a short section atWilshire/Fairfax Station.

11.21.13

Revision 1812/13/2013

33 OF 62

Page 34: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

206 10.02.13 Can this manhole be moved closer to the sidewalk and rotated on the south side sothe depth will not interfere with the top of the station? This will allow placement of themanhole between the deck beams. The existing electrical line may be in conflict but itcan be moved so this manhole can be moved.

Fairfax Station has been lowered to provide space for manhole without need torotate it. Also, please refer to the answer to question no. 208.

11.22.13

207 10.02.13 Can LACMTA provide design elevations for the bottom of the four proposed electricalvaults within the station excavation footprint?

Fairfax DWP Vault Invert Elevations are shown on the Composite Existing ActiveUtility Plans issued in Amendment 4.

11.22.13

208 10.02.13 Advanced Utility Relocations Contract No. C1055, 12H5059 Sheets 2 of 5 and 4 of 5,shows electrical manholes and Vaults VL 6100, MH 6050, VL 6040, and VL 6012installed with the longest dimension longitudinal to the station. With the vaults andmanholes referenced above having dimensions of 9’-4” x 17’-6” x 12' 4" as shown onSheet U-379, there is a strong potential for the deck beams to conflict with thestructures. Would it be possible to turn the structures 90 degrees so that the longestsection of structures are perpendicular to the station and re-orient the duct banksaccordingly? This would eliminate the potential conflict with deck beam installation.The same condition would be a potential issue to consider for all stations.

Vaults must be constructed with the long axis parallel to the street centerline tomaintain maximum space for other utilities in Wilshire Blvd. Wilshire/Fairfax Stationhas been lowered in Amendment 4 to provide space for vaults between the deckbeams and top strut.

11.21.13

209 10.02.13 Advanced Utility Relocations Contract No. C1055, 12H5059 Sheet 1 of 5 shows 30"to 42” minimum cover of electrical conduits, which may pose a potential problemwhile installing the temporary decking for the stations, since the utility cross sections(Sheets U-415 to 422 and UW 402) show the bottom of the beams for the stationdecking approximately 5’ below the original grade. We would need clearance toexcavate due to the crown. To eliminate potential conflicts with the electrical ductbanks, we suggest a minimum cover of 60” for all electrical duct banks that arerelocated as part of advanced contracts.

30 inch to 40 inch minimum cover is a general note in the C1055 Contract. Actualutility profiles in have been designed to clear the underside of deck beams.

11.21.13

Revision 1812/13/2013

34 OF 62

Page 35: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

210 The Standard Operating Procedures for public outreach, stakeholdercommunications and construction impact mitigation are as follows:

· DB hires 1 full time Public Information Coordination to serve as the counterpart ofthe Metro Construction Relations Officer. This person is responsible for ensuringtimely, accurate communications to Construction Relations relative to constructionschedule, impacts and mitigations and is on call 24/7 to respond to projectemergencies.

· Construction Notices are approved, translated and disseminated a minimum of 72hours prior to the commencement of any work in the public right of way, on Metro’sprivate property where work will take place for extended periods of time and activitiesthat may have some sort of public impact.

· Renderings are created in high resolution, topographically correct electronicrenderings that depict final configuration of street lanes, landscaping and lighting.

· Maps and Construction Notices are created using Metro’s style guide

· Field Reports are evaluated and resolved within 90 days.

• Street/lane closures are provided twice daily to Construction Relations for thatevening and next morning’s commutes.

Following these SOPs will ensure we have an informed, prepared communitythrough the construction phase. These SOPs will be included in a futureAmendment.

211 10.02.13 As referenced in Section 01 35 95, Part 1.07, please define full-time person? Is thecontractor required to hire the PIC on its staff or can the full-time person be asubcontractor?

The full-time person can be a direct hire on the Contractor’s staff or be employed asa subcontracted consultant. This is a full-time position. If the full-time person is asubcontracted consultant, the person is to be fully integrated into the Contractor’sproject management structure such that they will be able liaise successfully betweenthe Contractor’s team and Metro Construction Relations.

10.04.13

212 10.02.13 In the RFP, Section E, List of Certified Firms, there is no list of certified communityoutreach firms. Can you provide the list of communications firms that are certified forthis project and the NAICS codes required?

The List of Certified Community Outreach firms will be included in the nextamendment. The NAICS code codes to be used is are 541611 and 541820.

10.18.13

10.18.1310.02.13 Section 01 35 95, Part 1.01, B mentions Construction Relations’ Standard OperatingProcedures (SOP). Can you provide a copy of the SOPs or direct us to where wemight obtain a copy? Additionally, can we get access to the environmentalcompliances also referenced in this section?

Revision 1812/13/2013

35 OF 62

Page 36: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

213 10.07.13 Are all the relocated utilities named hereon upsized per the governing agenciesrecommendations? For Wilshire/La Brea Station:1) Existing 18" concrete SS (COLA, between Detroit St. & La Brea Ave.), upsized toa 20" HDPE SS.2) Existing 24" VCP SS (COLA, between La Brea & Sycamore Ave.), upsized to a26" HDPE SS.3) Existing 33" VCP SS (COLA, between Orange Dr. & Sycamore Ave.), upsized to a36" HDPE SS.4) Existing 36" VCP SS (COLA, on Sycamore Ave.), upsized to a 42"/48"HDPE SS.5) Existing 42" RCP storm drain (COLA, crossing Wilshire Blvd.), upsized to a 60"RCP SD.For Wilshire/La Cienega Station:1) Existing 30"/33" RCP storm drain (COBH, from Gale Dr. to La Cienega Blvd.),upsized to a 60" RCP.

Proposed sections for temporary relocations are equivalent sections that will matchthe existing capacity. These are not upsized sections, DB to finalize and coordinaterelocation design with utility owners. Per Metro design criteria, permanent relocationsrequire to restore facilities to match the capacity of the original facility.

10.18.13

214 10.07.13 Reference drawing U-426, shows existing 138 KW DWPPS (E) line profile. Per allthe utilities plans the line is shown as a supported in place, but ref.dwg. U-427 showsthe same line as 138 KW DWPPS relocated line; Please clarify if this linewill be supported in place or a relocated utility.

Existing 138 KW DWPPS (E) line is to be protected and supported in place. 10.18.13

215 10.07.13 Previous versions of AQMD Rule 1166 allowed exemptions for excavation andhandling of soils with regard to VOC emissions occurring from natural sources. Themost current version of this rule has removed the exemptions for soil which iscontaminated through natural seepage of VOC from oil and gas wells and othernatural sources. Would a variance or amendment be allowed to the current Rule1166? If not, would Metro consider a provisional sum item to comply with Rule 1166with regard to natural occurring sources?

No and No. 11.13.13

216 10.14.13 What is the tolerance on Cab Signal Code Rates? - Section 34 42 13.49 - AUDIOFREQUENCY TRACK CIRCUITS, 45.2.4 2.05 Cab Signal Commands states:"Design track module to provide the following cab signal modulated code rates. Theduty cycle for each modulation rate shall be 50 percent plus/minus one percent." Notolerance for Rate provided.

Paragraph 2.05 of the referenced specification section provides the tolerance levels.For the carrier frequency, refer to paragraph A. For each frequency associated witheach speed command, refer to Table 2.

10.23.13

217 10.14.13 Are Program Station Stop markers commercially available for this application andcan the ordering information for the existing PSS markers be provided (ref. 55Section 34 42 13.83 PROGRAM STATION STOP)?

To our knowledge Program Station Stops are not commercially available. As such,the “Program Station Stop Manual” will be provided for the Contractor’s use to designthe same product. This will be issued in future amendment as an attachment toSection 34 42 13.83.

10.23.13

218 10.14.13 TC&C Room Rack Seismic Testing: Is any testing is required to demonstratecompliance of the Equipment Racks/Mounting comply with the codes called out inthe Title 24 CCR and the Los Angeles Building Code (Ref.34 42 13.56 47.2.2 2.02) ?

Design and installation of all ATC equipment on structural components must be ableto resist and withstand earthquake regulations set forth in title 24, CAC and City ofLos Angeles Building Code for essential hospital facilities within Seismic HazardZone 4. Contractor to demonstrate compliance by analysis, and/or by manufacturer’scertification, testing, and/or by inspection. The Contractor shall select the method(s)to demonstrate compliance.

10.23.13

Revision 1812/13/2013

36 OF 62

Page 37: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

219 10.14.13 Is seismic testing of switch machine layouts required per Title 24, CAC and City ofLos Angeles Building Code for essential hospital facilities within Seismic HazardZone 4 per SECTION 39.2.9 2.09 ENVIRONMENTAL REQUIREMENTS (Ref.SECTION 34 42 13.73 - SWITCH MACHINE LAYOUTS)?

Please refer to the answer to question no. 218 above. 10.23.13

220 10.14.13 Is seismic testing of signal layouts required per Title 24, CAC and City of LosAngeles Building Code for essential hospital facilities within Seismic Hazard Zone 4per SECTION 39.2.9 2.09 ENVIRONMENTAL REQUIREMENTS (Ref. SECTION 3442 13.76 - SIGNAL LAYOUTS)?

Please refer to the answer to question no. 218 above. 10.23.13

221 10.16.13 Line 13a. has been added for this Project to PRO FORM 132, which had not beenincluded in previous forms for LACMTA's RFPs. Since this is not a design/bid/buildproject, the design will not be done at the time the Proposal is due and,consequently, we may not have an accurate subcontractor quote at this time. Wetherefore request that the line be removed for this design-build Proposal.

All subcontractors that can be identified at time of Proposal are required to be listedon Pro Form 132. All other subcontractors as design progresses will be identified ata later date.

11.14.13

222 10.16.13 Q44 submitted on 7/29/13 inquired about Section 01 71 43 Table 1, where LACMTAidentified an "After Hours Construction Permit" and asked about the status of theseMetro Obtained Permits and their validity throughout the period from NTP to FinalCompletion. The answer stated that this would be clarified in a future amendment.Since the allowable work hours are critical to assembling an accurate schedule andProject cost, we respectfully request clarification on the allowable work hours.

The work hours will be addressed in the next Amendment. 11.13.13

223 10.16.13 Q137 asked if there's been any approval for the raised decking concept for the otherstations besides Wilshire/Fairfax. LACMTA responded that no approval has beenobtained for Wilshire/La Brea or Wilshire/La Cienega raised decking. However, theAdvanced Utility Relocation contract for La Brea appears to be based on a raiseddecking concept. Please clarify.

Advanced Utility relocations at Wilshire/La Brea are based on flush decking. Deckbeam design must consider the available space between utilities and the streetsurface.

11.21.13

224 10.16.13 Excavation at the Wilshire/Fairfax Station has to be carried carefully under thesupervision of a paleontologist. In order to estimate the number of crews to utilize forthis work, can LACMTA advise how many paleontologists would be available in a 24hour period?

Metro will provide the appropriate paleontological staff to support the Contractorscheduled work shifts and work locations at Wilshire/Fairfax Station. Please notethat the paleontologist must be able to clearly witness the excavation, which requiresadequate Contractor provided lighting at all times. Should adequate lighting not beprovided by the Contractor, the work location will be shut down at the expense of theContractor.

10.23.13

Revision 1812/13/2013

37 OF 62

Page 38: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

225 10.16.13 The Geotechnical Baseline Report (Vol. II, 05) provides pH design values in TablesC-1, C-2, and C-3 lower than 4.2 (except for 3 soil types). These values aresignificantly lower than report 4.02 Corrosion Control Measures TM (Final) (2-14-2012) (Vol. IIIa,0,4) which states “2.1.1 Soil pH ranged from neutral to moderatelyalkaline and was not indicative of corrosivity. Page 28 of 115 states ‘Soil pH valuesvaried from 6.7 to 8.4’ ”. Note that the low GBR pH design values indicate a highlycorrosive environment and requires external protection to the precast segmental linerand the segment gaskets to ensure a 100-year design life, which does not appear tobe included in the reference design. Please clarify this apparent discrepancy andconfirm if the GBR values are correct.

The Corrosion Control Measures TM is a Reference Document. Additional data hasbeen gathered and reported in the Contract Geotechnical Data Reports.

11.15.13

226 10.16.13 Regarding archaeological and paleontologic requirements for the Purple Line project,it appears that the RFP, MOU, and MMP requirements are not consistent with eachother. There are only a few paleontologic firms that know how to work in the soilsnear the Tar Pits and that are approved by the George C. Page Museum of La BreaDiscoveries. Since Metro has a standard 5-year contract with an environmentalcompany that fulfills standard archaeological and paleontological services as part ofthe contract, is this firm to provide paleontologic services on the Purple Line or is aspecialized firm to be hired for this work under a project specific contract?Additionally, does Metro hire the specialty firm or does the Design/Build team?

A specialized firm, currently under contract to Metro for the Purple Line Extension, isproviding archaeological and paleontological work. Also, Please refer to the answerto question no. 177 above.

10.24.13

227 10.16.13 Thank you for responding to my Q&A about who will be hiring thepaleontological/archaeological firms for this Project. Since it is Metro and coincideswith the Section 1 Contract C1045, General Requirements-Division 1:

PA-3 - Retain the Services of a Qualified Principal Paleontologist Metro will retain theservices of a qualified principal paleontologist (minimum of graduate degree, 10years of experience as a principal investigator and specialty in vertebratepaleontology) to oversee execution of mitigation measures. Will Metro be putting outa separate bid for the paleontological services? Please advise how we can go aboutbidding on the paleontological portion of the work.

A specialized firm, currently under contract to Metro for the Purple Line Extension, isproviding archaeological and paleontological work. Also, Please refer to the answerto question no. 177 above.

10.24.13

228 10.23.13 We’ve  observed that on most Metro construction projects there is usually  a 24 hour-customer complaint line to track all construction-related complaints.  Will a similarservice be installed for the Westside Subway Extension, and if so, will it be paid forand operated by Metro or the Contractor?

A similar service will be installed for the Purple Line Extension. It will be paid for andoperated by Metro. The Contractor’s scope of work regarding 24 hour complaintsare specified in Division 1 Section 01 35 95.

10.31.13

229 11.02.13 Amendment 3 includes significant changes to the appendages of the three proposedstations. In order to evaluate these changes, we respectfully request a copy of therevised Revit model and CAD files that incorporates them.

CADD files including Revit model were made available to the pre-qualified teams onNovember 5, 2013 as per LOI-RFP pg 1-4.

11.08.13

Revision 1812/13/2013

38 OF 62

Page 39: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

230 11.02.13 We have reviewed the Traction Power Simulation Report and from our analysis ofthe proposed reference design, this will meet the operational requirements with bothSections One and Two of the Westside Extension complete. However, with onlySection One in operation, the reference design will not support the requiredoperational performance, requiring an additional TPSS to be added until Section Twobecomes operational. Please advise if the additional TPSS is required for this interimperiod while Section One is operating without Section Two.

No additional TPSS is required for this interim period while Section 1 is operatingwithout Section 2 as Metro Operations is not planning to operate 6 car train / 4-minute headway during Section 1 operation. Two-4000 kW rated substations at theindicated locations on the TP Load Flow Simulation report of RFP Volume III, areadequate for the Section 1 system operation.

11.08.13

231 11.02.13 On page 7-10 of the amended GBR (Amendment 3 October 15, 2013) there is areference in Para. 7.6 to Technical Requirements 31 23 43 Shaft and StationExcavation.  This section has not been provided.  Please provide the referencedsection.

Reference should have been to Section 31 50 00 – Excavation Support Systems.This will be revised in next amendment.

11.08.13

232 11.02.13 The Triennial DBE Goal referenced in Amendment 3, Page 3-14 #105 cannot befound in the RFP documents. Does LACMTA plan to provide this goal?

Please refer to LOI Supplement Design Build (RC-FTA), PRO FORM 031A pg.1-23

11.08.13

233 11.02.13 Section  3.01 E of 01 31 31 indicates all work needs to be performed by the utilityowner or a contractor approved by the utility. This effectively precludes the Biddersfrom self performing this work. This is not a typical requirement of other similarcontracts in the past because it is a requirement of only certain utilities. Pleasereconsider this restriction or identify the specific utilities that it is applicable to.

Requirements will be amended to clarify that Utility relocation work shall beperformed by the utility owner or the Contractor as shown in the Third Party UtilityContacts and Responsibility Table. Contractor-performed work shall comply with theutility owners’ standards and specifications. However, Work on LADWP (W)waterlines and Third Party telecommunication lines must be performed by acontractor that is pre-approved by the respective utility owner.

11.08.13

234 11.02.13 In Technical Requirement 31 74 16, 1.05.D.4, ASTM C1202 Chloride IonPenetrability is required. Would test results on the segmental lining for 90 and 180days aged concrete specimens be considered to be in compliance as it has beenshown that age has significant effects on the test results stated in the standard?

Metro would consider results on 56 and 90 day tests. 11.08.13

Revision 1812/13/2013

39 OF 62

Page 40: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

Please clarify the party responsible for the oil/gas well investigation.Contractor's scope of work on oil/gas wells per General Requirement 01 35 29 is "Closure, drainage, sealing, excavation, removel, transport or disposal of oil or gaswells or casings (Gas Casings)...". Also, "Party Responsible for ImplementingMitigation" for "Further Research on Oil Well Locations" is Metro according toAttachment A Mitigation and Monitoring Reporting Plan after Section 01 35 44.

Indicating seven wells within the tunnel alignment, however, the GeotechnicalBaseline Report says, "In the area where abandoned oil wells could potentially beencountered, probe holes ahead of the face and geophysical survey to detectobstructions will be required. If an abandoned oil well is detected underground aheadof the face, and evaluation of its condition and its abandonment must be carried outin accordance with appropriate regulations." and "All seven well locations must beinvestigated to establish which are within the construction work. Investigations shouldcontinue until all sites are fully explored even if abandoned wells are identified."

These sentences seems to mean that Contractor should do well casing survey.Please clarify

236 11.02.13 GC-25, Section 25.2 Repair and Replacement stated that: “Unless otherwiseprovided, Contractor shall repair or replace all existing structures, equipment, andvegetation damaged or removed by Contractor. Repairs and replacements shall be atleast equal to the existing structures, equipment, or vegetation, and shall match...”Section 25.3 Costs stated that: “All costs for protecting, removing and restoringexisting structures, equipment, and vegetation shall be the sole expense ofContractor. If Contractor fails or refuses to make timely repairs, restoration orreplacement LACMTA may make the repairs, restoration or replacement. All costsincurred by LACMTA, as determined by LACMTA, for such repairs, restoration orreplacement shall be repaid.”Would these two Sections GC 25.2 and 25.3, especially Section 25.3, be applicablefor adjacent building damage, if any, due to building settlement and distortion lessthan the maximum allowable defined in the Technical Requirements?

GC-25 is applicable for (but not limited to) adjacent building damage due to buildingsettlement and distortion less than the maximum allowable as a result of the work asdefined in the Technical Requirements. Contractor's caused damage of all typesand extent is covered by GC-25.

11.13.13

237 11.04.13 Due to the magnitude and complexity of the Project, we respecfully request theProposal due date be extended by eight weeks, to February 13, 2014.

LACMTA is not granting an extension to the RFP proposal deadline date at this time. 11.08.13

11.08.1311.02.13235 Yes, Contractor to survey for oil wells as stated in Section 31 71 19, Excavation byTunnel Boring machine, Paragraph 3.02 B,” Probe ahead of TBM as required byCal/OSHA and when with 200 ft of an oil well identified in the GBR. Performmagnetometer surveys in probe holes to detect metal casings.

Revision 1812/13/2013

40 OF 62

Page 41: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

238 11.08.13 Per Metro Rail Design Criteria, 2.1.3.3, page 2-2, whichstates “Construct all newfacilities and projects, including new transit corridor projects, using energy-efficiencyand conservation strategies. For buildings or structures over 10,000 square feet,projects must be constructed to achieve Leadership in Energy and EnvironmentalDesign (LEED®) Silver certification, at minimum.” Please clarify if the Silvercertification provision is applicable to underground facilities like underground stationsand underground guideways? Or which particular facilities within the project aresubject to the Silver certification requirement?

Per Metro policy, each new Metro facility greater than 10,000 square feet must bebuilt to achieve LEED-Silver certification. Metro seeks justification and would reservethe right to grant variance to Metro policy if LEED is not achievable for anyinfrastructure or building greater than 10,000 square feet that is built for the project.Related sustainable features and best practices are to be identified in the requiredSustainability Plan submittal and implemented during the project, regardless of LEEDcertification.

11.15.13

239 11.08.13 Amendment 3 depresses both Wilshire/La Brea station and Wilshire/La Cienegastation TOR elevation by 1ft, but without explanation. Can Metro share the reasoninformation with us?

To provide additional space for the crossover ventilation plenum. 11.21.13

Please reference schedule of quantities and prices form schedule A, bid item 46“Incremental Cost for Excavation, Segregating, Hauling and Disposing ofContaminated (nonhazardous) Soils to Class II Landfill above cost for cleansoils” with an estimated quantity of 500,000 tons. In addition, please referenceGeneral Requirements, Section 01 35 43, Paragraph 3.03.E. which states, “Unlessotherwise directed, all tar contaminated soils shall be disposed of in aClass II landfill.” This bid item indicates that we may only provide pricing for aClass II Landfill. Please note the Class designations developed by the State ofCalifornia are not correlated with the threshold levels of acceptance. For example,the TPH threshold levels of acceptance at some Class III landfills arehigher than the TPH threshold levels at available Class II landfills.There is data and language contained within the Environmental Data Report datedMay 22, 2013, which supports that some of the tar sands or contaminated soilswould fall within the thresholds limits and thus be acceptable for disposal at a ClassIII Landfill.

Furthermore, there is data that shows TPH limits will exceed the thresholdsacceptable at either Class II or Class III landfills. As such, it appears the tar impactedsoils material may require disposal at a Class I landfill or its out-of-stateequivalent of a Subtitle D Landfill. Note: Classification of landfills such as the ECDClandfill does not fall within the classification guidelines established by the State ofCalifornia and are referred to as Subtitle D Landfills. The inference that disposal mayonly occur at a Class II Landfill severely limits the disposal options.Please clarify if disposal and payment for this item could include: Class I Landfills,Class II Landfills, Class III Landfills within California and/or Subtitle D FederallyRegulated Landfills located outside the state of California. We would suggestcreating separate bid items for disposal at Class I landfills, Class II landfills, Class IIIlandfills and Subtitle D Landfills.

240 11.08.13 In Amendment 4, General Requirements Section 01 35 43, EnvironmentalProcedures for Contaminated and Hazardous Materials, paragraph 3.03 E. has beendeleted, and Schedule A of the Quantities and Prices Form has also been modifiedto reflect this change.

11.22.13

Revision 1812/13/2013

41 OF 62

Page 42: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

Reference the Environmental Data Report dated May 22, 2013, starting on page 4-21 last paragraph under Wilshire/Fairfax station and continuing on to top of page 4-22 which states, “Based on the results of analytical testing, 91%of the tarimpactedsoils from the Wilshire/Fairfax Station were initially considered to be Non-RCRAHazardous Waste (California Hazardous Waste) per California Regulations, but laterclassified to be non-hazardous for disposal purposeswhen they passed the Bioassay Fish Kill Test. However, due to the presence of tar inthe soil, most of the excavated materials may require disposal at a Class II Landfillfacility such as McKittrick Landfill (located west of Bakersfield). It is anticipated, that aportion of the excavated material from this location can also be disposed off at aClass III Landfill facility, provided favorable test results from Bioassay test areestablished during station excavation operations and noexcessive tar balls are encountered.

If the Bioassay results are unfavorable then the excavated material will requiredisposal to a Class II Landfill facility such as McKittrick Landfill.” Reference resultsshown for TPH shown on page 3-36 for borings E-115, E-115A, E-115B, E-116(Fairfax Station); several of these results exceed the thresholds for acceptance at aClass II Landfill such as McKittrick. Based on review ofMcKittrick’s Landfill current threshold limits for TPH and other regulations it isunderstood the only way McKittrick Landfill would accept this material would be if theBioassay test results are favorable which conflicts with the statementquoted from the Environmental Data Report above which states “unfavorable”. Inconclusion, materials such as those shown in the borings at Fairfax Station thatexceed thresholds and do not pass the Bioassay test results for a Class II Landfillsuch as McKittrick would only be able to be disposed of at a Class I landfill inCalifornia or Subtitle D landfill outside of the State of California. Furthermore, eventhough thresholds may exceed the limits prescribed for McKittrick Landfill such material would not necessarily be considered hazardous.

Please clarify bid item 46 which limits disposal just to a Class II landfill? We wouldsuggest creating separate bid items for disposal to: Class I landfills, Class II landfills,Class III landfills and Subtitle D Landfills.

242 11.08.13 Please clarify which type of rail lubricators should be provided such as technicalspecifications, sizes, etc.

Rail lubricators are not required in C0145. 11.13.13

243 11.08.13 Will Metro be finished with the exploritory shaft prior to the RFP deadline to allow thedesign-build teams to investigate?

The Exploratory Shaft will not be completed prior to receipt of the proposals, but theProposers have been invited to review the progress at the shaft on 11/22/13 and willbe invited to the site for future reviews.

11.22.13

241 11.08.13 Please refer to the answer to question no. 240 above. 11.22.13

Revision 1812/13/2013

42 OF 62

Page 43: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

244 11.08.13 As specified in Addendum 3 cover letter, pages 5 and 6, the Street Works sheets C-2443 and C-2445 have been revised to update median landscape requirements. It isnoted in these drawings show to “Protect existing traffic island, if disturbed duringconstruction, reconstruct at project completion.” These addendum plans are in directconflict with the Worksite Traffic Control Plan sheets TF-1127, TF1130 and TF-1133showing the median being affected at Cloverdale and Wilshire near the proposed LaBrea Station. The same applies for sheet TF-1128 at Spaulding and Wilshire nearthe proposed Fairfax Station. Please clarify.

The median islands are now shown to be removed and replaced in Amendment 4. Please see improvements shown on Drawings C-2434 through C-2450 and drawingsTI-1011 and TI-1021.  Also see Note 16 on Drawing C-2434.

11.26.13

245 11.08.13 Due to the number of pages in the QA/QC Sample Plan and Injury and IllnessPrevention Plans (potentially 100+ pages each), can proposers submit thesedocuments as part of the electronic submittal only and not with the hard copies?

LACMTA will revise the requirement to allow electronic submission of the QA/QCSample Plan and Injury Illness Prevention Plans.

12.05.13

246 11.11.13 Has LACMTA provided the RFP Project Definition Drawings to the affected ThirdParty agencies and utilities?

The appropriate Project Definition Drawings have been provided to the 3rd PartyAgencies and Utilities. The drawings provided are associated with the infrastructureowned and maintained by these same parties.

11.21.13

247 11.11.13 In the GBR (page 10-1) the following reports are referenced:1. Clean Slurry Technology Inc. 2011, Testing of Tar Sands for Compatibility withSlurry Separation Equipment, Letter Report.2. Boduszynski, M.M., C.E. Rechsteiner, A.S.G. Shafizadeh and R.M.K. Carlson,1988, Composition and Properties of Heavy Crudes, UNITAR Center of Heavy Crudeand Tar Sands.3. City of Los Angeles, 2004, Bureau of Engineering, Department of Public Works,Methane and Methane Buffer Zones.4. Keller E., and M. Crow, 2004, Tunneling through an operational oil field and activefaults on the ECIS Project, Los Angeles CA, USA. Proceedings of the NorthAmerican Tunneling Conference, Atlanta, Georgia, pp 441-448.We could not find these reports in the Reference Documents. Are these documentsavailable for review?

The references requested were provided in Amendment 4. The City of Los AngelesMethane and Methane Buffer Zones map is available on the City’s web site.

11.22.13

248 11.11.13 Special Provisions Clause SP-06 A. 8. c. states that LA Metro may elect to obtainearthquake insurance.  Please confirm that if LA Metro decides not to obtain suchinsurance, LA Metro still bears the cost for repair per General Conditions 26.2.2which states that Contractor has no risk for loss from Force Majeure events.

Metro would bear the cost of the repair as specified in GC 26.2.2 provided theContractor has met their contractual obligations, as stated in that section, should wenot purchase earthquake insurance.

11.14.13

249 11.11.13 This clause states that "If a Delay arises out of more than one cause, to the extentthat the Delay is Excusable or Compensable, subject to all the requirements of thisArticle, Contractor will be entitled to only one extension of Contract Time for thecumulative Change to the Critical Path Schedule." In light of the phrase "subject toall the requirements of this Article," please confirm that the Contractor is entitled tothe referenced extension of contract time in the event of an Inexcusable Delay that isconcurrent with an Excusable Delay.

In the event of a delay that is excusable and/or compensable and inexcusable delayoccurs concurrently the contractor, subject to all requirements of this Article may beentitled to an extension of time.

11.15.13

Revision 1812/13/2013

43 OF 62

Page 44: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

250 11.11.13 Spec Section 26 32 13.13 covers the Standby Generator(s) and calls for load banksin Paragraph 2.01 M. Article 2.13 further specifies the load bank shall bepermanently installed and sized for full load rated capacity of the standby generator.However, there are no additional features or performance specifications provided.

Drg E-2040 (Standby Power Single Line Diagram) also agrees with this for both theLa Brea and La Cienega Stations, with a similar description in Reference Note 13.

However, the Typical Generator Enclosure Drawing E-0021 does not allocate aspace for this load bank. A typical freestanding 2000 kVA load bank is about 4 footby 7 foot and requires 34,000 cfm of airflow with appropriate clearances. If the intentof the specifications is that the load bank be internal to the genset package withradiator airflow as the cooling medium, the maximum radiator-cooled load bank thatcan be used will only be 50% of the generator full load rating.

Spec Section 26 05 05-14 describes the Standby Power Supply (SPS) System inParagraph 1.08 B, but there is no mention of a load bank.

A permanently installed load bank is to be provided for each standby generator andhave the capability of testing the full load capacity of the standby generator asspecified in Section 26 32 13.13 Standby Generator – Articles; 2.01-M., and 2.13-A.The load bank is to be located in the exterior walled areas surrounding the generatorsound attenuating housing, located in the station entrance area. Its exact location willdetermined in the Contractor’s Final Design.

11.15.13

251 11.11.13 Please confirm if the generator enclosure, panel, and fuel tank arrangement can bemodified from the reference design.

This will depend on the type of modification. The generator layout design shown isconsistent with the contract specification Section 26 32 13.13 - Standby Generators,with a prefabricated stand alone generator housing with sound attenuated enclosure,a fuel oil system, and a skid mounted fuel tank located below the generator that willbe pre-tested at the factory as a single generator unit prior to delivery. The reasonsfor this design configuration are two-fold:

1. To provide standby generator design that can pre-fabricated and tested at an off-site facility prior to delivery to minimize field testing problems.

2. To provide a standby generator design that can be upgraded and/or serviced as acomplete unit.

Designs that comply with these specifications are acceptable. Designs that include anon-integrated pre-fabricated fuel oil supply and delivery system as part of thefactory pre-fabricated generator unit will not be acceptable.

252 11.11.13 Referring to Addendum #3, additional dampers have been included for Crossoverstations. Please advise as to the size of the dampers, or issue drawings withdimensions for measurement.

The dimensions of the dampers were not given as part of the contract and finaldesign shall be by the Design Build engineer.

11.15.13

Revision 1812/13/2013

44 OF 62

Page 45: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

253 11.11.13 Please confirm if emergency fan dampers, tunnel dampers and bypass dampershave to fulfill UL555s Smoke Damper requirements.

Yes. All dampers associated with the emergency ventilation system must meet therequirements of UL555s.

11.15.13

254 11.11.13 NEMA 12 type electrical equipment enclosures have been specified for all ancillaryelectrical equipment, except those in emergency fan rooms and other similar plenumspaces. Most US major switchgear and MCC suppliers could not supply NEMA 12switchgear. Please confirm if NEMA 1 is acceptable for indoor installation.

Provide Nema 12 type Unit Substation and MCC enclosures as specified. This isMetro’s Standard.

11.15.13

255 11.11.13 Has SCE reviewed this Design Criteria Deviation and agree that the deviation will notimpact Third Parties?

This requirement for Wilshire/La Cienega Station Dual Power Feeds wascoordinated with SCE.

11.13.13

256 11.11.13 Would it be possible for the owner to make available the contents of the After Hourswork permit for the City Of Beverly Hills? Does it guarantee the contractor the right towork at all other times outside the standard work hours?

See Revised General Requirements Section 01 71 43, Permits, Licenses andAgreements. Section 1.08 defines work hours for the City of Los Angeles and theCity of Beverly Hills.

11.21.13

257 11.11.13 The peak hour exemption which Metro has obtained from the City of LA Bureau ofEngineering covers M-F from 3:30pm to 7:00pm. The Night Time Noise Varianceobtained by Metro from the LA Police Commission pertains to activities between9:00pm and 7:00am M-F. Please advise if the Design-Builder is responsible forobtaining a required permit for the hours of 7:00pm to 9:00pm M-F.

General Requirement section 01 71 43 will be revised in the next amendment toclarify which permits will be provided by Metro and those to be obtained by theContractor as well as the allowable work hours. Hours between 7:00 pm and 9:00 pmM-F in the City of Los Angeles are normal work hours and do not require Peak HourExemptions or Night Time Noise Variances

11.21.1311.15.13

258 11.11.13 Please provide copies of permits listed in Table 1: Metro Obtained Permits fromsection 01 71 43 - 1.08.

Section 01 71 43 will be revised in next amendment and will include all availablepermits/variances/exemptions that are available at this time

11.15.13

Revision 1812/13/2013

45 OF 62

Page 46: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

259 Refer to Specification Section 26 05 19 Insulated Wires and Cables Article 2.01.AGeneral Requirements and Article 2.03 Cables regarding cable assemblycomponents (including conduits) for fire/life safety system conduits and non fire/lifesafety system conduits. Fire life/safety system cable assemblies shall be compliantwith UL 2196 listing requirements for 1 hour and 2 hour rated cable assembliesbased on its application and location.

GRS conduit can be used for exposed non-life/safety system conduits.

GRS conduit cannot be used for exposed life/safety system conduits that require aUL 2196 1 hour and 2 hour listing, per the recent UL 2196 Standard for 1 hour and 2hour cable ratings.

All exposed conduits and cable assembly components shall comply with Metro’scorrosion control requirements, which is equivalent to a minimum NEMA 4X rating.

To comply with NFPA 130 requirements for exposed 1 hour rated egress lighting andLife safety system communication conduits and cable assembly components, analternate to GRS conduit must be provided that is compliant with the UL 2196 1 hourand 2 hour listing requirements.

Fiberglass “Phenolic” FRE heavy wall conduit may be acceptable alternative to GRSconduit for 1 hour and 2 hour UL 2196 listed cable assemblies. In addition Fiberglass“Phenolic” FRE Nema 4X boxes may be acceptable alternative to Stainless SteelNema 4X boxes for 1 hour and 2 hour UL 2196 listed cable assemblies. However,the specific cable assembly components would require certified UL testing to verifythe cable assembly compliance. In addition it should be noted that Fiberglassphenolic FRE boxes will not provide protection from EMI.

The only current UL 2196 1 hour listed compliant option for station and tunnel lightingbranch circuiting is metal clad cable 1 hour rated per current UL 2196 listingrequirements.

Embedding GRS conduits in 2 inches of concrete with RHW cable will comply withUL 2196 1 hour and 2 hour cable assembly listing requirements, will protect conduitsfrom being crushed, and will provide protection from EMI. In addition, all componentsof cable assemblies that require a 1 hour or 2 hour UL 2196 listing, includingembedded pull/splice boxes where the cable assembly transitions from embedded tosurface mounted.

The Contractor’s cable assembly design components shall comply with applicableUL 2196 listing requirements for 1 hour and 2 hour cable assemblies based on thecable assembly classification as ‘life/safety’ or ‘non-life/safety’, metro corrosioncontrol requirements and Metro’s EMI protection requirements.

11.11.13 Metro Rail Design Criteria 7.10.1 States that Rigid Steel Conduit shall be used for allexposed work in dry areas not likely to present corrosion problems. These conduitsshall be embedded in slabs where protection against EMI is required and in slabssubjected to high impact. The review of the reference documents also shows the useof GRS conduits at exposed and embedded locations in the stations and tunnels.Please clarify that is the intent of Metro to use GRS conduits in embedded concretewithin stations and tunnels.

11.21.13

Revision 1812/13/2013

46 OF 62

Page 47: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

260 11.11.13 The Crenshaw/LAX Corridor contract as well as the Regional Connector contractissued amendments wherein the cap on liquidated damages was reduced from$35,000,000 to $15,000,000. Will the same reduction be applied to this contract(C1045)? The reduction will lessen contractor contingency.

The liquidated damages cap amount in SP-11 to remain unchanged. 11.26.13

261 11.11.13 General Conditions 32.8.1 states: "LACMTA will not pay any mark up to Contractoron Changed Work performed by Subcontractors." Please be advised this goesagainst Metro's traditional method and places undue risk on the contractor whichmay lead to an increase in price. Please confirm there will be no mark ups of anykind paid to the general contractor on subcontractor change work.

Confirmed. There are no markups paid to the Contractor for changed workperformed by Subcontractors.

11.26.13

262 11.11.13 Please confirm that Metro will bear the cost, or has agreements in place to bear thecost for any 3rd party/stakeholder design reviews.

Section 01 31 31 h will be revised in next amendment and will include a new Roles &Responsibilities matrix that details the responsibility for all costs associated withdesign reviews by 3rd party agencies. Metro will pay for Design Reviews by the Cityof Los Angeles and City of Beverly Hills only.

11.15.13

263 11.11.13 Generally, projects within the City of Los Angeles are required to provide positivepressure shoring when excavating for utility work such as a trench. Shoring plans arerequired to be approved by COLA BOE showing the exact location of shoring. Pleaseconfirm COLA BOE will require positive pressure shoring for the Westside SubwayProject.

Yes. Assume City of Los Angeles requirements will apply. 11.22.13

264 11.11.13 Please confirm that LADWPWS will replace any cathodic protection required for allthe steel water lines for which they have responsibility. For example, if a steel waterline is required to be supported from the deck, DWPWS will be the responsible partyfor re-installation of any cathodic protection durng the backfill operation.

Contractor is to be responsible for any re-installation of cathodic protection. includingall testing. See Section 26 42 13 for responsibilities regarding testing and activationof cathodic protection.

11.21.1311.15.13

265 11.11.13 Per Section 01 35 43 1.06.C.7 "Contaminated Soils are...all tar contaminatedmaterials including excavated materials from tunnels, stations and shafts, muckremoved from within sumps, holding tanks, construction wastes; including theexisting abandoned foundation piles." This definition does not include quantifiablelimits and therefore any material with detectable tar (based on EPA Test Method8015B TPH3ORO analysis) would be considered contaminated. Please providequantifiable limits which define when material will be considered "contaminated."Also, please provide baseline quantities for contamination.

Soils with low tar contents may be acceptable at Class III landfills, and therequirement to dispose of tar contaminated material has been revised. Seeresponse to question No 240. It is the contractors responsibility to provide theanalytical lab data that supports where they intend to dispose of materials based onthe disposal facilities acceptable limits.

11.22.13

266 11.11.13 Section 01 35 43 3.03.E specifies that material with detectable tar must be disposedof at a Class II landfill. Q&A response to #187 gave contractor the ability to sendmaterial to a class III facility if the TPH level of material was acceptable by facility.Please revise specification 01 35 43.3.03.E to be consistent with RFI response.

Please refer to the answer to question no. 240 above. 11.22.13

Revision 1812/13/2013

47 OF 62

Page 48: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

267 11.11.13 The disposal of Gasoline range Hydrocarbons (Section 01 35 43 1.06 C.2), gasolineconstituents BTEX (Section 01 35 43 1.06.4), or other VOCs is not defined in thedocuments. Class II landfills are specifically designed with liners and leachatecollection for wastes that have leachable contaminants. Tar is generally notleachable whereas the other contaminants formally mentioned are leachable. Ourassumption is that disposal location options presented in the document "SoilDisposal Facilities Options Summary" are approved facilities (Section 01 35 433.03.D "Dispose of all contaminated materials at a Metro approved Waste DisposalFacility") Please confirm this assumption is correct.

Disposal of waste at a “METRO Approved” facility is required so Metro will havesome control over where the Contractor proposes to dispose of the generated wastestreams.

The Contractor can either use one of the pre-screened facilities Metro has providedin the Waste Disposal Fact Sheet , or should the Contractor wish to use a facility noton that list, the Contractor needs to submit the pertinent information on the wastestream, the proposed facility’s permits and criteria for acceptable waste, etc.information to Metro for approval.

11.22.13

In Metro Rail Design Criteria, section 9, 9.20 EMI/EMC Control, it is stated that "Foreach new rail line extension, a comprehensive EMI/EMC (ElectromagneticInterference/Electromagnetic Compatibility) study shall be performed to identifyinterferences between the various electrical/electronic subsystems including vehiclesystems that may adversely affect the operation, reliability, and safety of the system.The study shall also consider interference with any adjacent facilities commercialbroadcasting stations including radio, television and mobile phone networks as wellas other facilities that may be susceptible to EMI effects such as hospitals, recordingstudios, airports and emergency call/dispatch centers . Mitigating measures shall beimplemented to eliminate the interferences, including in the design and test of theimpacted systems. A complete EMI/EMC plan including study, testing and mitigationmeasures shall be developed by a professional who is knowledgeable andexperienced in the field, andsubmitted for Metro’s approval." Please verify the extent to which Metro will requireeach of the DB teams to develop this EMI/EMC study for the proposal.

The cost of the scope of work for the specified EMI/EMC plan, testing and study is tobe included in the Contractor’s Proposal. The scope of work (plan, testing andstudy) is not required to be included as part of technical submission when theProposal is due.

The Proposal shall Include the cost for, but not be limited to, performing the followingscope of work;

The monitoring and determination of the existing EMI/EMC influences at the existingWilshire/Western station to determine mitigation measures to be implemented fornew and extended existing electrical, communication, train control and traction powersystems at the Wilshire/Western Station.

The monitoring and determination of existing EMI/EMC influences along the transitsystem station and tunnel alignment to determine mitigation measures to beimplemented for new station and tunnel electrical, communication, train control andtraction power systems.

Will access to existing Metro underground and surface facilities be made available toall teams to install monitoring equipment that will log and map existing EMI/EMCinfluences if these are required to develop these comprehensive reports? Significantadditional time would be required to perform this study. Please issue a ProvisionalSum for this scope of work as it is not realistic for the proposers to perform acomprehensive study pre-bid and thus extra, potentially unnecessary riskcontingency would need to be carried.

The determination and study of the new EMI/EMC influences between electricalpower, lighting, traction power, train control and communication system equipmentwithin the station and tunnel transit system design to determine mitigation measuresto be implemented for new station and tunnel electrical, communication, train controland traction power systems.

Access to the in service revenue tunnels will be limited to the Non-Revenue Hours ofSunday-Thursday 12AM to 3AM, Friday and Saturday 2AM to 3AM. Access to otherunderground and surface facilities will be made available for longer durations andduring normal work hours. The cost of these restrictions are to be included in theProposal.

11.26.13268 11.11.13

Revision 1812/13/2013

48 OF 62

Page 49: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

269 11.11.13 The Final Supplemental Traction Power Load Flow Study Task No. 3.06.050(Deliverable No. 3.06.050.3C) evaluates the operation of the WSE in two stages with43car or 63 car train consists. The report recommends that 4MW substations beimplemented under the build3out of Stage 1 to Wilshire / La Cienega Station in orderto meet 43minute headways with 63car consists under this intermediate Stage 1build3out. However, the report also describes this operating scenario as analternative option. Please clarify whether the traction power system must meet Metroperformance criteria while operating 63 car consists at 43 minute headways at thecompletion of Stage 1.

Traction Power System for Stage 1 shall be designed for the ultimate 4-minute, 6-cartrain operations.

11.22.13

270 11.11.13 Metro Tech Requirement 26 05 19, section 2.03 B requires 1 hour rated cables UL2196 listed. Metro Rail Criteria section 7, 7.10.1A requires rigid hot dippedgalvanized steel conduit (GRS) to be used for all exposed work in dry areas.Currently there is no cable in the market that is UL 2196 listed and can be installedwithin GRS conduit. Will Metro allow the use of strut mounted MC cables withoutconduits?

Yes, metal clad cable that is listed for 1 hour per current UL 2196 listingrequirements is an acceptable compliant cable assembly option for station andtunnel emergency egress lighting. See question-259 response for additionalinformation.

11.22.13

For tunnel lighting branch circuiting provide both redundant wiring (separate UPSsourced branch circuits to each fixture) and UL 2196 1-hour listed cable assemblies,as specified in project definition drawings, Technical Requirements and MetroDesign Criteria. Refer to the approved project Design Criteria Deviation RequestPLE-2013-011 for additional information regarding the approved tunnel lightingbranch circuiting design. See the following Design Criteria references.

For station egress lighting branch circuiting provide UL 2196 1-hour listed cableassemblies for compliance with NFPA 130 egress lighting branch circuitrequirements, as indicated on Project Definition Drawings, Technical Requirementsand Metro Design Criteria. Also see the following Design Criteria references.

Project Definition Drawing E32034, Reference Note 6 states that the lighting racewaysystem is to comply with the NFPA3130 requirement for fire rating AND UL32196conformance. However, NFPA3130, section 6.3.3.2.8 indicates a choice betweendiversity in system routing(such as redundant or multiple circuits separated by a13hour fire barrier)or UL3 2196. Please confirm whether NFPA3130 or ProjectDefinition Drawing take precedence.

11.22.13271 11.11.13

Revision 1812/13/2013

49 OF 62

Page 50: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

Metro Design Criteria references:

Metro Fire Life Safety Design Criteria - Article 1.8 - Codes and Standards - requirescompliance with NFPA 130 requirements (which requires 1 hour UL 2196 listing ofcable assemblies or redundancy for egress lighting in tunnels and stations).

Metro Fire Life Safety Design Criteria Electrical Requirements - Article 2.4.1.1 –‘Materials for conduits, raceways, ducts, boxes, cabinets, equipment enclosures, andtheir surface finish materials shall be capable of being subjected to temperatures of932⁰F for 1 hour, and shall not support combustion under the same temperaturecondition.’ This requirement is equivalent to the UL 2196 Standard 1 hour cableassembly listing requirements, and shall be applied to life safety system branchcircuits as identified in Contract Specification Section 26 05 19 Insulated Wires andCables – 2.03.B Life Safety Branch Circuit Cables.

Metro Electrical Design Criteria - Article 7. 13.7 - Tunnel Lighting - requires eachtunnel light fixture to be sourced from a separate UPS power source (redundantwiring).

Metro Electrical Design Criteria – Basic Electrical Materials – Conduit - Article7.10.1.J - ‘For underground station and tunnel, feeder and branch circuitconduits shall be in compliance to NFPA 130 and Metro Fire LifeSafety Criteria.’

272 11.11.13 Specification Section 01 11 00 Summary of Work Section 1.04.C.1 says: "Metro willbe undertaking work at the existing Division 20 Yard including the construction ofturnback platforms and tracks , new trackwork and expansion of Maintenance of WayFacilities." Please provide schedule for this work including anticipated bid date, NTPand completion date.

See the rail welding site drawing for the infrastructure improvements that can beexpected when access to the rail welding site is made available per SP Appendix B.

11.21.13

273 11.11.13 Due to the changes made in amendments 1 through 3, answers to Q&A responsesindicating future amendments, and anticipated reports from advanced utilityrelocation contracts, exploratory shaft contract, and ti-back boring investigations ourteam respectfully requests a 12 week extension to the bid/proposal due date. The 12week duration considers the holiday season and will give all teams sufficient time toanalyze, price, and include changes in the proposal.

The Proposal due date has been extended to Friday, January 3, 2014. 11.22.13

Revision 1812/13/2013

50 OF 62

Page 51: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

274 11.11.13 Metro’s response to Q184 can have a significant impact on the SOE design. Theimpacts are two fold. The first is we need sufficient time to adequately analyze priorto bid submission. The second is there is substantial cost, MOT and scheduledifferences between a soldier pile and lagging support system and a more rigid,impermeable wall system (e.g. slurry wall or secant pile). We respectfully requestMetro provides its clarification as soon as possible such that the contractors canproperly consider the requirements, and avoid the circumstance of addingcontingency to our bid.

Clarified in Amendment #4. See General Requirements, Project Design-BuildRequirements Section 01 11 01, 3.02.D

11.26.13

275 11.11.13 Ethernet switches seem to be required but are not mentioned in this section or under2.02 Major Equipment. Can you provide a model number for the equipmentrequired?

Ethernet switch and router are mentioned in section 2.01.C.1.b. Contractor shallselect the equipment and submit for Metro approval.

11.15.13

276 11.11.13 This section lists the following equipment to be provided by LACMTA: “TransitVueContent Management Server, TransitVue Media Players, Liquid Crystal Display(LCD), LCD Display Enclosure, VGA/DVI Video Extenders”.There are several places in drawings CN-2908 and CN-2922 where LED (VMS)signs are indicated but there is no related specification. Are these also be includedas part of the “Metro Furnished” parts? If not please provide specification.

All LCD (VMS) signs required for TPIS will be provided by Metro as specified. LEDsigns are not required.

11.15.13

277 11.11.13 SONET Add-Drop Multiplexers (Metro furnished)

1. Fiber Optic SONET ADM node shall be Fujitstu Flashwave 4500. TheFLASHWAVE 4500 is a multiservice broadband transport element that provides avariety of advanced transport, add/drop, and switching capabilities within singlecompact shelf. The FLASHWAVE 4500 shelf fits in a standard 23-inch rack.

Does the SONET ADM model Flashwave 4500 provided include all additionalequipment such as cards, GBICs and associated hardware such as the referencedshelf? Additionally is the programming of the SONET ADM also included or is this tobe provided by the contractor?

The SONET ADM model Flashwave 4500 provided by Metro will be equipped withthe optical cards (GBICs), Ethernet card and associated cards required for theProject. The contractor is to provision without connecting to the live system, MetroRail Comm will review the contactors work and make any needed changes asnecessary, and then Metro Rail Comm will make the final connections to theoperating system.

11.15.13

278 11.12.13 Amendment 3 includes significant changes to the appendages of the three proposedstations. The revisions to the Wilshire/Fairfax Station were not included in the Revitmodel and CAD files that LACMTA distributed after Amendment 3. We respectfullyrequest a copy of the revised Revit model and CAD files that incorporates therevisions to the Wilshire/Fairfax Station.

The Wilshire/Fairfax Revit model was provided to the Pre-Qualified Teams withAmendment 4 issued 11.20.13.

11.22.13

Revision 1812/13/2013

51 OF 62

Page 52: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

279 11.12.13 Amendment 3 includes Architectural drawings showing a new tunnel ventilation ductconnecting the Fan Room with a ventilation plenum on the tunnel side of thecrossover at La Cienega and La Brea Stations. The new ducts appear to extendfrom the Fan Room across the top of the back of house spaces at concourse level tothe vertical plenum connecting them to track level. No information is includedindicating the size of the duct, although the revised MEP Revit models appear toshow plant has been moved to accommodate a duct.It appears that the intent is to improve the effectiveness of the tunnel ventilationsystem when it is extracting smoke from the bored tunnels on the cross-over side ofthe station, but no information is given as how the system will actually achieve thatgoal or the operational requirements. Please provide a description of the operationalrequirements of this duct (i.e. is it intended that only one tunnel at a time will beserved) as well as the size of the duct and the airflow required.

The new plenum will extend from the existing fan plant shown in the RFP Submissionto a shaft at the end of the back of house spaces to extract air and/or smoke fromeither tunnel without affecting the crossover. These requirements described inAmendment #3, 01 11 01 - Project Design-Build Requirements, paragraph 2.02Performance Criteria H.1.b and c. The final size of the plenum and associateddampers shall be determined by the final designer through calculations and analysisbased on the final design.

(For example, if there is a fire in one tunnel with evacuation away from the crossover,smoke would be extracted from the crossover/tunnel interface thereby confining thesmoke to one side while keeping the crossover free of smoke.)

11.22.13

280 11.19.13 In reference to specification:  SECTION - 01 43 10 PROJECT QUALITY PROGRAMDESIGN BUILD, 3.22 Certification of Work Elements, A. Certify quality, this sectiondoes not contain any information and does not reveal any requirements on how to“Certify Quality”.  Requesting clarification of this section.

The General Requirements Project Quality Program Requirements- D/B (01 43 10)Sub-Section 3.22 has been included in error and is to be disregarded.

11.22.13

281 11.19.13 The Q&A Log as of November 15, 2013, contains a large number of unansweredquestions from Proposers, as well as an indication of future amendment(s) that willclarify certain responses to Proposer questions. In order to reduce risk in theproposals and cost to LACMTA, we respectfully request an additional eight weeks toprepare and submit our Proposal. Please note that the maximum benefit to LACMTAwill be realized by the earliest possible notification of extension of time.

The Proposal due date has been extended to Friday, January 3, 2014. 11.22.13

282 11.19.13 The current signaling system will achieve a two minute headway as required by thespecification. However, when the constraint that no more than one train perventilation zone is added to the design this parameter of a two minute headwaycannot be achieved between La Brea and Western.  This was also confirmed in yourRail Operations Simulation Report (Final-Rev 1) Task No. 5.2.7 (Deliverable No.5.2.7.B), recently issued, which indicated that an additional vent zone must becreated if an 18 trains per hour (TPH) schedule was required.  Given that thereference design does not include the additional vent shaft, are we to presume thatan extended headway for train operations of 4 mins (15TPH) is acceptable.

Yes, the requirement is for a 4 minute headway on the branches, 2 minutes in the“trunk” between Wilshire/Vermont and Union Station.

11.21.13

283 11.21.13 Requesting the complete Book of Plans (to include all wayside and communicationsfor Train Control, systems & circuitry) for the existing Wilshire/Western equipmentroom.

Metro will provide information when available and/or after Contract Award. 12.04.13

Revision 1812/13/2013

52 OF 62

Page 53: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

284 11.22.13 Cal/OSHA Title 8 Regulations, Chapter 4, Subchapter 20, Article 12, Section 8437has an exception which states: “The lineal velocity of air flow in tunnels or chambersmore than 30 feet in diameter may be reduced to 30 feet per minuteprovided that air quality is maintained.” After discussions with Cal/OSHArepresentatives and because the entire project has been classified as gassy, the 60feet per minute lineal velocity will be enforced in the station excavations.Furthermore, General Requirements Section 01 35 23 Paragraph 1.08 A.1. states,“The underground soil conditions for the Work under this Contract have beenclassified by Cal/OSHA, Mining and Tunneling Unit as Gassy. Specific Classificationnumbers for specific portions of Section One are still under review and developmentby the Mining and Tunneling Unit, California Division of Occupational Safety & Healthand will be updated by amendment.” Will we receive this amendment prior to bidsubmission?

The Underground Classification document(s) will be provided when they becomeavailable from the Mining & Tunneling Unit, Ca. Division of Occupational Safety &Health. Per a conversation between Metro Construction Safety Management andthe Senior Engineer, Van Nuys Mining & Tunneling Unit, Ca. Division ofOccupational Safety & Health regarding the ventilation of the station box facilitiesunder the road deck structures: Until the entire excavation within the station orstation/crossover box is excavated to a depth of ten (10) feet below the bottom of thedeck support system, the 60 LFM requirement of Ca. Title 8, §8437 will apply. Oncethe entire excavation within the station or station/crossover box is excavated to adepth of greater than ten (10) feet below the bottom of the deck support system, the30 LFM requirement of Ca. Title 8, §8437 will apply. This is based on thenorth/south cross sectional area being less than or greater than the cross section ofa thirty (30) foot diameter tunnel.

11.26.13

285 11.22.13 Due to the size/complexity of Amendment 4 and the current RFP due date's proximityto the holidays, we respectfully request to extend the RFP due date 4 weeks(01/31/14).

Please refer to the answer to question no. 273 above. 11.26.13

286 11.22.13 Certain SES Scenarios are tabulated in 3 6 that depend on Wilshire/Western andWilshire/Normandie air handling infrastructure in order to attain critical air flows.Please confirm the existing stations' fan units, power, and control wiring may bedepended upon without modifications for use as part of the Project's EVS (Thisexcludes SCADA revisions that are inherently required to allow a coordinated EVSresponse to a fire). We believe this corresponds to the reading of NFPA 130paragraph 1.3.1.

The air handling infrastructure at Wilshire/Western and Wilshire Normandie issufficient to provide the necessary emergency ventilation for those existing stations.Their capacity for use on the PLE project will need to be assessed as part of the finaldesign. SCADA interfaces will be needed and the control systems at those stationswill require to be upgraded if they become part of the emergency scenario conditionsof the PLE. Refer to Technical Requirement Sections 23 32 40 and 27 01 01 forfurther details .

11.27.13

Revision 1812/13/2013

53 OF 62

Page 54: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

·Items 62 will be paid as a single lump sum item once the Contractor provides the120 day schedule in compliance with the general requirements.

·Item 63 will be paid as a single lump sum item once the contractor provides theBaseline Contract schedules in compliance with the general requirements.

·Item 64 will be paid at the rate of $25,000 per month provided that the contractorsatisfactorily provides monthly reports and schedule updates.

·Item 66 will be paid as a single lump sum once the Contractor has submitted andMetro has approved all As-Built Drawings and the As- Built BIM Model.

·Item 67 will be paid as a single lump sum once the Contractor has submitted andMetro has approved all Operation and Maintenance Manuals.

·Item 68 will be paid according the schedule of payments described in SpecialProvisions Paragraph SP-24.

·Schedule A Items 69 and 70 have been deleted and replaced by items 20 and 21 inSchedule B.

·Item 20 in Schedule B will be paid in accordance with GC-35 paragraph 35.3 orSP64 Paragraph F if applicable. The amount of the provisional sum ($700,000)represents MTA’s monies to reimburse the Contractor for MTA’s portion (50%) of theADR or DRB costs. There is no payment item to specifically reimburse the Contractorfor its portion of the ADR or DRB costs.

·Item 21 in Schedule B will be paid in accordance with SP30.B.3. The amount of theprovisional sum ($500,000) represents MTA’s monies to reimburse the Contractor forMTA’s portion (50%) of the Partnering costs. There is no payment item to specificallyreimburse the Contractor for its portion of the Partnering costs.

288 11.22.13 Please provide date bidders can anticipate receiving as builts of the advance utilitywork at the Wilshire/La Brea station (C 1048) allowing us to incorporate this work intoour proposal and avoid pricing undue risk.

Metro will provide information when available and/or after Contract Award. 11.26.13

289 11.22.13 Please provide anticipated date of NTP, Project Completion, and issuance of asbuilts for the advance utility work at the Wilshire/Fairfax station (C1055) allowing usto incorporate this work into our proposal and avoid pricing undue risk.

Please refer to the answer to question no. 288 above. 11.26.13

290 11.22.13 Please provide anticipated date of Bid Solicitation, Bid Date, NTP, ProjectCompletion, and issuance of as builts for the advance utility work at the Wilshire/LaCienega station (C1056) allowing us to incorporate this work into our proposal andavoid pricing undue risk.

Please refer to the answer to question no. 288 above. 11.26.13

Please provide payment provisions for Schedule A Bid Items 62, 63, 64, 66, 67, 68,69 and 70. These items are listed as "PS" which indicates "Provisional Sums". Arethese items to be treated as lump sum, percent complete by contract time (per diemor per month), percent complete by progress or cost reimbursable? Is the Contractorentitled to full payment of the Schedule A provisional sum items?

11.26.13287 11.22.13

Revision 1812/13/2013

54 OF 62

Page 55: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

291 11.22.13 Section D.3 of the Project Management Portion of the written proposal states:"Provide a Project Implementation Plan (PIP)..." This plan will be very long and wouldnot be able to be provided within the constraints of the page limitations.Please confirm a description of what the plan will cover (answering sections D.3.athrough D.3.m) is what is required and not the actual plan.

Volume II Project Management Submittal Section D.3 Project Implementation Plan(PIP) is to be excluded from the 120 page limitation for this section.

12.11.13

292 11.22.13 Section D.4 of the Project Management Portion of the written proposal states:"Provide a Community Outreach and Construction Mitigation Plan..." This plan will bevery long and will be developed by the Design Builder in coordination with Metro afterthe award of the project. Please confirm a description of what the plan will cover iswhat is required and not the actual plan.

Volume II Project Management Submittal Section D.3 Community Outreach andConstruction Mitigation Plan is to be excluded from the 120 page limitation for thissection.

12.11.13

293 11.22.13 Please provide date bidders can anticipate receiving the final report on the findingsof the excavation of the exploratory shaft (C1034) allowing us to incorporate thesefindings proposal and avoid pricing undue risk.

Please refer to the answer to question no. 288 above. 11.26.13

294 11.22.13 Please provide the date bidders can anticipate receiving the results from theenvironmental surveys at the buildings to be demolished within the ConstructionStaging Areas allowing us to incorporate these findings into our proposal and avoidpricing undue risk.

Please refer to the answer to question no. 288 above. 11.26.13

295 11.26.13 Environmental Impairment Liability Site Coverage: We recommend amending therequirements for a policy term of not less than 15 years from the inception ofcoverage. Current market conditions support a 10 year term period for this type ofcoverage.

We concur. LACMTA will revise the requirement to a policy term of not less than tenyears.

12.05.13

296 11.26.13 Professional Liability: Would LACMTA entertain a "Linked Limited" program structurein which an insurer issues separate policies for the Design/Builder and the Designerthen share the required $50M aggregate limit?

No. The limits and terms of the project professional liability policy are intended topreserve the full $50 million in limits for the LACMTA and Third-Parties.

12.05.13

297 11.26.13 Builders Risk: Please advise if coverage is required for the Tunnel Boring Machines,or if self insurance for the TBM’s is allowed.

Coverage is required for the Tunnel Boring Machines. 12.05.13

298 11.26.13 Builders Risk a.: For tunneling exposures, Munich Re 101 is required to provide120% of the replacement cost. 135 % is frequently provided, and higher limits arerecommended due to the costs associated with restoration after a collapse. WillLACMTA revise the requirement to 135% or higher to provide consistency amongbidders?

No. LACMTA will not agree to revise the requirements. 120% of the replacementcost is the minimum requirement. Proposers may choose to self-insure or to insurethis exposure in excess of the minimum limits at their discretion.

12.05.13

299 11.26.13 Builders Risk b.: A loss limit of $200 million is required. Please confirm LACMTAretains the risk of loss in excess of the $200 million loss limit.

The Builders Risk loss limit of $200M is the minimum requirement. Proposers maychoose to self-insure or to insure this exposure in excess of the minimum limits attheir discretion. In general, MTA does not retain the risk of loss in excess ofinsurance proceeds, except in limited cases such as force majeure.

12.05.13

300 11.26.13 Builders Risk b.: What is the desired period of indemnity for "soft costs expensecover"?

Twelve (12) months. The contract provision will be revised to reflect the period. 12.05.13

301 11.26.13 Builders Risk b.: The maximum delay deductible for "soft cost expense cover" of 30days may not be commercially available. Will the LACMTA consider changing thisrequirement to 60 days?

LACMTA confirmed with reputable insurance brokers that a 30 day deductible isreadily available.

12.05.13

Revision 1812/13/2013

55 OF 62

Page 56: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

302 11.26.13 Builders Risk c.: Can the LACMTA provide a definition of exactly what is meant by"bona fide earthquake" or a sample endorsement? This would be useful in carvingthe coverage out of the requested earth movement coverage.

Insurance companies use a variety of definitions for what constitutes an earthquake.Generally these definitions do not conform to the definition in statute as “earthquakesin excess of a magnitude of 3.5 on the Richter Scale” (California Public ContractCode Section 7105). The intent of this language is to ensure that ALL earthmovement is a covered peril EXCEPT for an earthquake. The statutory definitioncan certainly be used by proposers to define the earthquake exclusion for theBuilder’s Risk coverage. If proposers do so, the policy then would state that all earthmovement would be a covered peril except for an earthquake in excess of magnitude3.5 on the Richter Scale.

12.05.13

303 11.26.13 Verification of Coverage a.: Copies of all policies are required within 90 days of NTP.Many of the policies may not be issued by that point. Will the LACMTA considerchanging this requirement to 180 days?

LACMTA will change the requirement to 180 days. The contract provision will berevised to reflect the period.

12.05.13

304 11.26.13 Will the exploratory shaft test tie-back report be available to the design-build teamsprior the RFP due date?

Please refer to the answer to question no. 288 above. 12.05.13

305 11.26.13 Many DBE and non-DBE subcontractors and suppliers will not be working over theholiday season. We anticipate minimal pricing from subs and suppliers for theJanuary 3rd deadline. We respectfully request the RFP deadline beextended.

LACMTA is not granting an extension to the RFP proposal deadline date at this time. 12.05.13

306 11.26.13 Reference Technical Specification Section 01 78 43: List “A” Spare Parts -Trackwork Item 7 “Frog” 2 each. Please clarifythe 2 types.

The requirement is for 2 spare frogs of each type installed. Required number ofspares will be determined by the Contractor’s trackwork design. If more than onetype of frog is installed, then the Contractor is to provide two spares for each typeinstalled. If only one type of frog is installed per the Contractor’s design, then therequirement is for only two spare frogs.

12.04.13

307 11.26.13 Reference Technical Specification Section 01 78 43: List “A” Spare Parts - ContactRail Item #6 and Item #8; anchor assemblies. There are 2 anchor assembly itemswith different quantities, please clarify.

Do not include in the Proposal the price for Technical Specification Section 01 78 43:List “A” Spare Parts - Contact Rail Item #8; anchor assemblies.

12.04.13

308 11.26.13 Reference Technical Specification Section 01 78 43: List “A” Spare Parts - ContactRail Item 7 Support Insulators. What are the types? Are they Porcelain/Fiberglass?

To match what was approved and installed. 12.03.13

309 11.26.13 Will the LACMTA consider an alternative structure to a Project Professional Liabilitypolicy naming the DB Contractor and all Contractor Related Entities?The alternative structure is Design Team Project Professional Liability policy with a$25 million limit and a Contractor Protective Professional Indemnity Project policywith a $25 million limit. This would provide $50M in Professional Liability limits to theproject, as required by the contract. The primary advantage of this structure over thestructure required in the insurance specifications is that if claims made by theContractor against the Contractor Related Entities’ Project Professional Liabilitypolicy will not be excluded via an “Insured versus Insured Claims” exclusion.

No. The limits and terms of the project professional liability policy are intended topreserve the full $50 million in limits for the LACMTA and Third-Parties.

12.05.13

Revision 1812/13/2013

56 OF 62

Page 57: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

1. LACMTA will revise the requirement to a policy term of not less than ten years.

2. Phase I and Phase II environmental assessments. Phase II where the site isaccessible. Ground water and boring data is available and has already beensupplied. Additional Phase I’s and Phase II’s will be provided when available.

3. Some assessments have been completed and some are in progress. MTA’sProcurement Team can be asked for additional copies and will distribute newdocumentation when it becomes available.

4. Completed reports are currently available and distribution is pending. Reportscan be provided to carriers.

5. The Environmental Indemnification in the contract language limits the ProjectTeam’s liability. LACMTA does not carry environmental liability insurance coverageor construction coverage and does not maintain a brokerage relationship to placethis coverage. Contractors have better access, knowledge and relationships toleverage to affect placement with better terms and pricing.

6. LACMTA understands that the degree of Environmental coverage will depend onthe environmental information available. Negotiations and discussions during thechange order process should result in appropriate coverage.

311 11.26.13 Amendment #4 contained an updated set of Metro Architectural Directive Drawingsthat includes a reduced Portal Canopy and glass partition around the entrance stairsand escalators consistent with the current Kit Of Parts. Atthe same time the Project Definition drawings included in Amendment #4 do notseem to address revisions to the station entrance plazas consistent with the newDirective Drawings. How should we proceed? Are we to follow thedefinition drawings or the Directive Drawings?

Proposal is to reflect the scope of work as shown in the Project Definition Drawings. 03.04.13

312 12.02.13 The current proposal due date provides insufficient time to adequaltely review themost recent amendment, initiate and develop design requirements, and competitivelyprice a project of this magnitude without considering and including significantcontingency. Given the magnitude and importance of the Westside SubwayExtension Project, we respectfully request a minimum six (6) week postponement ofthe current proposal due date of January 3, 2014.

LACMTA is not granting an extension to the RFP proposal deadline date at this time. 12.05.13

12.05.13310 11.26.13 Regarding the Site Specific Environmental we have the following questions:1. A fifteen year policy term is not commercially available. The longest available termis ten years. Please advise.2. What type of due diligence will be performed?3. When will it be performed?4. If it has already been performed, can carriers be provided with the reports?5. It is interpreted that the Environmental Indemnification in the General Conditions ofthe RFP to limiting the Project Team’s liability to those environmental conditionswhich they create or exacerbate associated with their work. Why the LACMTA isrequiring the Contractor to secure a policy on their behalf when LACMTA is retainingthis liability and also paying for the policy via a change order?6. The extent of coverage available from the marketplace will be dependent on thequality and extent of the environmental documents provided by LACMTA. If theinformation is not thorough or if there is widespread contamination, some of therequirements may not be commercially available. Please advise.

Revision 1812/13/2013

57 OF 62

Page 58: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

313 12.02.13 The Good Faith Effort advertisement requirment is 21 days prior to the bid due date,requiring advertisiment in three publications soliciting DBE quotes. That 21daywindow now occurs between December 13, 2013 and Jan. 3, 2014, severelyhindering our ability to outreach with DBE firms and follow-up due to the holidays,and their ability to respond. Consequently, we respectfully request that the January3, 2014 date be extended a minimum of six (6) weeks to February 13, 2014, as wehave previously requested.

LACMTA is not granting an extension to the RFP proposal deadline date at this time. 12.05.13

314 12.02.13 Amendments No.3 and No.4 have also greatly impacted our design engineringstudies, requiring a lot of revisions to work that had been finished. Accordindly, wesuggest that it is appropiate to increase the stipend amount forseen in the RFP, andrespectfulllu request that LACMTA increade the stipend to $2,500,000.

Stipend limits were established by LACMTA Board. 12.05.13

315 12.03.13 Referring to Technical Requirement 21 00 00 Fire Protection Systems, isolationvalves shall be installated at every other crosspassage, but no farther apart than1600 feet.

Although NFPA 130 is not referenced in this section, it seems to be the appropriatestandard. In NFPA 130, Clause 6.5.2.1.2, isolation valves shall not be more than800 feet apart.

Please kindly confirm if we should follow the Technical Requirements.

The Proposal is to include the cost of, and is to be in compliance with, NFPA 130,Clause 6.5.2.1.2.

12.12.13

316 12.03.13 Referring to Metro Rail Design Criteria Section 08 Mechanical, Article 8.1.5. B. 1. -UPE System, the fans shall not be high temperature rated. Please confirm if thesound attenuator follows the same requirements and please issue technicalrequirements for non-emergency ventilation sound attenuators for the UPE systemand ancillary ventilation systems.

Revision 1812/13/2013

58 OF 62

Page 59: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

Refer to previous Question No. 240. The solution adopted by LACMTA inAmendment No. 4 only deleted the reference to Class II landfills in GeneralRequirements Section 01 35 43 3.04.E and Bid Item 46, but did not resolve the issuethat presents a risk of millions of dollars. According to the largest operator of landfillsin this area, the various Regional Water Quality Control Boards that ultimately governand permit the landfills in this area are not willing to commit at this time to letting thelandfills accept “Naturally Occurring Tar Sands”.  This issue could cause all the tarcontaminated material to either be hauled to the central valley landfills or out of state,but the Proposers cannot determine that at this time.  We request that LACMTAestablish separate Bid Items, similar to Bid Item 46, for the incremental costsassociated with disposal of contaminated soils at Class I landfills, Class II landfills,Class III landfills, and Subtitle D landfills in order to reduce the cost of risk that wouldotherwise be put into the Price Proposals.

As an alternative, please provide a bid basis to estimate how much excavatedmaterial will go to a Class II versus a Class III landfill.

318 12.03.13 Has a wheel/rail interface or similar/vehicle track interface study been undertaken forthe existing system and, if so, can it be made available?

A wheel/rail interface or similar vehicle/track interface study is not available. 12.10.13

319 12.03.13 Please confirm the make/manufacturer of the standard Direct Fixation Fasteners forthe existing system and what alternatives, such as LVT (low vibration track) orfloating slab track, are used elsewhere on the system.

Metro currently procures direct fixation replacement fasteners from L. B. Foster orAmsted RPS. Metro has not procured any replacement Type 3 (egg) fasteners.Metro has not procured any replacement Resiliently Supported Block Ties (RSBT) ofLow Vibration Track (LVT) used on the Metro Gold Line Eastside Extension (lightrail) originally provided by The Permanent Way Corp. Please note that theContractor is to design and submit for approval all track materials regardless ofprevious Metro use or approval.

12.10.13

320 12.03.13 Please confirm if it is planned to operate more than one type of rail vehicle in normalservice and what specific vehicles they will be.

Metro plans to operate more than 1 type of rail vehicle during normal service. Thoseplanned vehicles are: A650 base buy, A650 option cars and a forthcomingprocurement.

12.10.13

321 12.03.13 Amendment 4, Division 1 Section 01 11 01, Article 3.02 D. 2 states that a soldier pilesystem is allowable at the Wilshire/Fairfax Station if shotcrete lagging is installed asthe excavation is advanced. However, Article 3.02 B. 1. a) 1 states that the followingexception should be made to Metro Rail Structural Standard Drawing SS-002: “DoNot Use 'Semi-rigid wall systems include tangent or secant pile wall or similarsystems.'” Is the word "include" meant to be "including"? Does this clause mean thattangent and secant pile walls are not allowed for excavation support on any of thestations? How is “semi-rigid” and "similar systems" defined in Article 3.02 B. 1. a) 1?Please confirm the type of excavation support systems that will be allowed at thestations.

Amendment 3, Division 1 Section 01 11 01 Article 3.02 B 1 a 1 states not to use thenote regarding design of semi rigid wall system on Structural Standard Drawing SS-002. The tangent pile and secant pile wall systems maybe be used. The lateralpressure diagrams are for flexible and rigid wall systems only. Tangent pile wallsystem would fall under flexible wall system while secant pile wall system would fallunder rigid wall system.

12.10.13

317 1.Base proposal on disposal of contaminated soil at site(s) of proposer’s preference.The site must be approved by Metro

2.A provisional sum has been established for payment of the incremental cost(above clean soils) for excavation, segregation and transport of Cal Hazardous andRCRA hazardous soils.

3.All material not falling into items 1 or 2 above are the sole responsibility of theContractor

12.03.13 12.13.13

Revision 1812/13/2013

59 OF 62

Page 60: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

322 12.03.13 According to Section 2, Clause SP-58 / SP-58 A., it seems that there is no cap onContractor's liability to the LACMTA for costs incurred by LACMTA, itsrepresentatives and contractors in completing or correcting the work.  Werespectfully request your consideration of the fact that the completion costs for aproject this size could be very large, thereby substantially reducing the total limit onliability.  We respectfully propose that SP-58 reads: “The Contractor’s Liability to theLACMTA for damages arising out of its performance of the Contract (or failure toperform hereunder) shall be limited to the sum of the following: A) all [40% of] costsreasonably incurred by LACMTA, its representatives or contractors in completing orcorrecting the Work…”

323 12.03.13 In the event of termination for convenience or default, the Contractor shall givewaiver of consequential damages towards LACMTA under Section 2, Clauses GC-37.6 and GC-38.7.  But, it doesn't seem that there is any clause specifyingLACMTA's waiver of consequential damages towards the Contractor.  We would liketo respectfully suggest adding the following language: “No Party shall be liable to theother Party for loss of business reputation, loss of opportunity, loss of revenue, lossof profit, loss of any contract, cost of capital or for any indirect, incidental, special orconsequential loss or damage which may be suffered by the other Party inconnection with this Contract.”

324 12.03.13 Article 3.01 B. 3 states that construction photographs shall be taken monthly. Article3.01 C. states that no less than 100 photographs shall be submitted each week.Article 3.01 D. states that progress photos shall be submitted monthly with thenumber of photos adequately depicting the construction activities. Please confirmhow often and how many construction photos are required to be submitted.

Regarding the requirement for monthly construction photos (only); the Contractor isto submit construction photographs monthly. The number of photos submitted are toadequately depict the construction activities. As construction activities ramp up andconstruction is occurring at multiple locations the number of photos needed tocomply with the requirement to adequately depict the construction activities will needto increase.

12.13.13

325 12.03.13 Structural Standard Drawing SD-011 shows part of the suggested connection detailbetween the bored tunnel and the station.  In Note 3 it states: "Installation of seal …for detail see the Tunnel Directive Drawings". We cannot find a directive drawingthat shows the connection between a segmental lining and station end wall. Can therelevant drawing be supplied?

The question refers to drawing SD-11 as “Structural Standard Drawing”, however it isa Structural Directive Drawing. Structural Directive Drawings are provided forguidance to the Contractor and may not meet all the Contract requirements. TheContract requirement is as follows from Technical Requirement Section 07 10 00,Water and Gas Protection Systems, Section 2.01 A.4.b: Tunnel to Station andTunnel to Crosspassage Interface – As a minimum provide the following: 1) A doublesealed connection capable of rotational and translational movement of sufficientmagnitude to accommodate the combined effects of differential non-seismic andseismic movement between the two structures. Design the connection to permitfuture injection sealing behind the structures that is readily accessible from within thestation or tunnel should a leak occur, together with the replacement of the secondaryseal. Both primary and secondary seals are to allow joint movement in combinationwith water pressure.

12.13.13

Revision 1812/13/2013

60 OF 62

Page 61: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

326 12.03.13 Paragraphs F.2 and F.3 of Article 01 71 43 1.08 indiacte that no work will be allowedduring holiday periods. We assume that "no work" is defined as "no work withinpublic right of way that could require lane closures or create obstructions to vehicularor pedestrian traffic." Please confirm.

During the week of Thanksgiving and the week between Christmas and New Years(in the City of LA) and during the City of Beverly Hills holidays listed in Section 01 7143 generally no work at or above grade within the public right of way is allowed.Work beneath the decking system (which is within the public right of way) will beallowed. However, it should be noted that the Contractor may be allowed to performsome at grade work within the public right of way within these periods provided theyare working with an approved Traffic Control Plan (TCP) / Traffic Management Plan(TMP) and have obtained a Holiday Moratorium Exemption. An example of thiswould be work in the public right of way that is behind the K-Rail. Contractor will berequired to work with both cities each holiday season to determine specificrequirements and specific days of work during the week of Thanksgiving and theweek between Christmas and New Years.

12.13.13

327 12.03.13 2.01.E of Section 01 52 13 says that Metro offices are to be designed for floor load of100 psf, while 2.01.G indicates 125 psf. Please confirm which is correct.

Proposal is to reflect the cost to comply with Section 01 52 13, 2.01.E, which statesthat Metro offices are to be designed for floor load of 100 psf.

12.10.13

328 12.03.13 Article 2.02.B of Section 01 52 13 indicates that the Design-Builder is to provide twooffices, presumably for LACMTA, in its Construction Management offices, along withtwo desktop computers. Article 2.01.D indicates that Metro would provide desktopcomputers for its staff. Since the Design-Builder will provide office trailers forLACMTA adjacent to its own offices at each site, would you clarify the intent of Article2.02.B?

As the location of the Contractor’s Design Office and the Contractor’s ConstructionField Office or single Construction Management Office is unknown at this timerelative to the proximity to the planned Metro Construction Field Office, theContractor is to provide 2 offices in the Design Office and in the Construction FieldOffice or in the single Construction Management Office for Metro’s use. TheContractor is to provide 2 desktop computers with internet access and phones forMetro use.

12.13.13

329 12.03.13 The requirement to submit Delay Compensation Prices refers to Schedule E. Weassume that this should refer to Schedule D. Please confirm.

Yes, the reference will be corrected to reflect Schedule D. 12.13.13

330 12.03.13 The evaluation criteria for Delay Compensation Prices refers to Schedule E. Weassume that this should refer to Schedule D. Please confirm.

Yes, the reference will be corrected to reflect Schedule D. 12.13.13

331 12.09.13 As we have previously explained in prior communications, with the extent of thechanges made by LACMTA to the RFP documents to date, the 21-day DBEnotification requirements over the holiday season, the schedule delays to the AURcontracts, and the price risk involved in many of the answers to the questions orunanswered questions (specifically question nos. 240, 279, and 371), the currentProposal Submittal daye of January 3, 2014 is at this point unrealistic. Werespecfully request that the January 3, 2014 date be extended a minimum of 4 weeksto January 31, 2014.

The Proposal due date has been extended to Thursday, January 30, 2014. 12.13.13

Revision 1812/13/2013

61 OF 62

Page 62: C1045 RFP Westside Subway Extension QA Log as of 12.13.13

RFP NO. C1045

No.Date of

Question

Date

Answer

Issued

AnswerQuestion

332 12.11.13 This is in follow up to Q&A 286 response. There are current NFPA 130 and/or MetroRail Design Criteria (MRDC) requirements as to the nature of Emergency VentilationSystem (EVS) equipment. One example of many, according to NFPA 130 7.3.1.1, istheir ability to 'achieve their full operating speed in no more than 30 seconds from astopped position'. As noted by Metro, should the PLE Design Build contractordetermine the capacity (air volume) for use on the PLE project, is the EVS equipmentrequired to be upgraded to current NFPA 130 and/or MRDC requirements?According to NFPA 130 paragraph 1.3.1, and except for the SCADA interfacesalready noted, we believe no such further equipmentupgrades are required. Please confirm our understanding is correct.

333 12.11.13 Reference Section 34 11 16B, part 1.01.B: This paragraph says "thermite welds arenot allowed in the tunnels for this project": If the Trackwork Contractor does not startwork until after the tunnel and invert are complete and the tunnel is sealed at thattime, will thermite welds be allowed? Thermite welds are an industry wide applicationfor connecting CWR strings and are equivalent to in track welds.

NOTE: the answers to the questions identified above are not binding. Only

written amendments revise the RFP document.

Questions regarding this RFP must be submitted in writing to LACMTA’s

Contact Person. In order to be considered, all questions must be received by

3:00pm, Pacific Standard Time twnety-one (21) calendar days before the RFP

due date.

Revision 1812/13/2013

62 OF 62