58
Bunbury Outer Ring Road Southern Community Reference Group 4 September 2018

Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

Bunbury Outer Ring RoadSouthern Community Reference

Group

4 September 2018

Page 2: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

Prepare Ultimate Planning Design

and environmental referral

documents Obtain approvals, develop Project Case Design

and Business CaseCRG #1 JULY 2018

Project overview, planning

options criteria, key project

issues and opportunities

CRG #2 SEPTEMBER 2018

Alignment, planning options

and analysis, key project issues

CRG #3 DECEMBER 2018

Ultimate planning design

concept, landscaping, urban

design, environmental referral,

key project issues

CRG #4 MARCH 2019

Project criteria and objectives,

key project issues

CRG #5 MAY 2015

Project options and staging,

key project issues

CRG #6 AUGUST 2019

Key project issues, final

summary and next steps

Page 3: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

3

5.45 Arrival – light refreshments available

6:00 Welcome – meeting purpose and process Linton Pike

6:10 Previous Workshop Summary and actions arising All

6:25 Project update (both sections) Padraic Murphy

6:35 Questions and answers All

6:45 Southern section – main alignment, connectivity and interchange options Padraic Murphy

7:00 Questions and answers All

7:10 Consultation and engagement update Tammy Mitchell

7:20 Questions and answers All

7:30 CRG member comment CRG members

7:55 Next steps Tammy Mitchell

8:00 Close

Page 4: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

4

• Dominic Boyle

• Padraic Murphy

• Hannah Ruprecht

• Bruce Walker

• Tammy Mitchell

• Chris Mitchell

Page 5: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

Previous Workshop

Summary and

Actions Arising

Page 6: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

Project UpdatePadraic Murphy - BORR Team

Services Delivery Manager

Page 7: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

7

• Preferred northern main alignment refinement

• Network connectivity considered further

• Directly affected landowner contact

• Continued investigative work

• Met with various stakeholder groups:

– Local Government Advisory Group

– Freight and Road User Group

– Project Enabling Group

– Steering Committee

• Considered interchange options

Page 8: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

8

Geotechnical

• Completed 27 monitoring wells with data loggers

Traffic

• 25 classified traffic count sites

• 15 turning video counts

• 2 x 17 hour Origin Destination surveys at 11 key locations

Environmental

• Western Ring Tail Possum Spotlighting and Distance survey

along southern GBRS corridor (July)

• Site Investigation Management Plan completed

• Forrest Highway Cockatubes Review issued to Main Roads

Page 9: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

Sourthern Section Project Development WorkPadraic Murphy - BORR Team

Services Delivery Manager

Page 10: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

10

Page 11: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

11

EXISTING

NO BORR

EXISTING

NO BORR

2,500

14,000

6,500

24,000

4,000

20,000

13,500

31,000

4,500

19,000

19,000

45,000

7,000

16,000

18,000

53,000

N/A

18,000

N/A

8,000

4,000

14,000

13,500

39,000

4,500

7,000

19,000

37,500

7,000

15,000

6,500

15,000

18,000

54,000

2,500

14,000

N/A

34,000

N/A

9,000

Page 12: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

12

Willin

ge

Dr

Ex

tv

Willin

ge

Dr

Ex

tv

3,000

6,0003,000

13,000

16,000

40,000

3,000

13,000

21,000

36,000

29,000

40,000

2,500

14,000

2,000

14,000

7,000

8,000

16,000

34,000

EXISTING

NO BORR

EXISTING

NO BORR

16,000

37,000

7,000

9,000

2,000

2,000

3,000

6,000

29,000

30,000

21,000

25,000

16,000

36,000

2,500

14,000

NA

37,000

Page 13: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

13

• Drainage Strategy

• Material Sourcing Strategy

• Waterways Investigation

• Utility Consultation

• Freight Planning

Page 14: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

14

Page 15: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

15

Section 1: Forrest Hwy to Collie

River Crossing

Section 2: Collie River Crossing to Rail

Crossing (south of South Western Hwy)

Section 3: Rail Crossing (south of South

Western Hwy) to BORR Central

Page 16: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

16

Environmental & Ecology Community & Social Local Economy Network Efficiency & Safety Engineering/ Project Cost

Native vegetation (area and

fragmentation)Land Acquisition (area)

Property access/

connectivity

Road length (vehicle operating

costs and vehicle travel times)

Water Infrastructure (irrigation

and drainage)

Rare Flora SitesProperty severance

(fragmentation)

Resource Use (mining

tenements)Road capacity & LOS Utilities

Fauna habitat and TECs Noise and Visual Amenity Facilities developmentRoad Safety (construction and

operation)

Constructability (incl.

connectivity to other sections)

Rare Fauna Aboriginal Heritage Whole of Life Cost

Wetlands (area) Non-indigenous Heritage

Waterways (crossing impact)

Page 17: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

17

EATON

PROPOSED

WANJU FUTURE URBAN

DEVELOPMENT

Preferred Alignment

Page 18: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

18

Page 19: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

19

Page 20: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

20

• Key Objectives

– Free flow access to Bunbury

– Paris Road to be connected to Clifton Road

– Not preclude the future Perth to Bunbury Fast Rail

The interchange is treated as a split interchange between Paris

Road/Clifton Road and Raymond Road

Page 21: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

21

Page 22: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

22

Page 23: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

23

Page 24: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

24

Page 25: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

25

Page 26: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

26

ST HELENA ROAD

HARRIS ROADWIR

EL

ES

S R

OA

D

WA

TE

RL

OO

RO

AD

WA

TE

RL

OO

RO

AD

Possible future roundabout

Future connection

RIN

G R

OA

D

Page 27: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

27

Page 28: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

28

Page 29: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

29

Page 30: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

30

Page 31: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

31

Page 32: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

32

Page 33: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

33

Page 34: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

34

Page 35: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

35

Page 36: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

36

Page 37: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

37

Page 38: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

38

Page 39: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

39

Page 40: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

40

Page 41: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

41

Page 42: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

42

Page 43: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

43

Page 44: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

44

Page 45: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

45

Page 46: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

46

WOODS ROAD

CALINUP ROADLAKES ROAD

LILLYDALE ROAD

CENTENARY ROAD

JIL

EY

RO

AD

ST

RA

TH

AM

Page 47: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

47

Page 48: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

48

Page 49: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

49

Page 50: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

50

Page 51: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

Consultation and Engagement Update

Tammy Mitchell – BORR Team

Community & Stakeholder Engagement Manager

Page 52: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

52

• Initial contact for access for investigations.

• Initial landowner contact for southern alternative corridor assessment.

• Website updates.

• Reference Groups established:

– Drainage Reference Group – 1 August 2018

– Community Reference Group (2 No.) – 9 July 2018 & 10 July 2018

– Meadow Landing Working Group – 13 August 2018

– Freight and Road User Group – 22 August 2018

• Commenced initial discussions with:

– South West Development Commission

– Port of Bunbury

• Increased community interest and enquiries

• Briefings of local MP’s

• Project Enabling Group Meeting – 16 August 2018

• Local Govt Advisory Group meeting – 16 August 2018

• Steering Committee meeting – 23 August 2018

Page 53: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

53

• Next round of established group meetings

• Project Newsletter – October 2018

• Community Drop In Sessions – October 2018

• Complete landowners contact for site investigations.

Page 54: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

54

Page 55: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

55

• Liaison – personalised meetings

• Community Reference Groups

• Community information sessions

• Newsletters and electronic updates

• Project webpage

• Project information 138 138

• Surveys

Page 56: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

CRG member

comment

Page 57: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

Next Steps

Tammy Mitchell

Page 58: Bunbury Outer Ring Road - mainroads.wa.gov.au · 3 5.45 Arrival –light refreshments available 6:00 Welcome –meeting purpose and process Linton Pike 6:10 Previous Workshop Summary

58

Prepare Ultimate Planning Design

and environmental referral

documents Obtain approvals, develop Project Case Design

and Business CaseCRG #1 JULY 2018

Project overview, planning

options criteria, key project

issues and opportunities

CRG #2 SEPTEMBER 2018

Alignment, planning options

and analysis, key project issues

CRG #3 DECEMBER 2018

Ultimate planning design

concept, landscaping, urban

design, environmental referral,

key project issues

CRG #4 MARCH 2019

Project criteria and objectives,

key project issues

CRG #5 MAY 2015

Project options and staging,

key project issues

CRG #6 AUGUST 2019

Key project issues, final

summary and next steps