1 BUILDING STANDARDS DIVISION Building Standards Verification Key Performance Outcomes Handbook (from May 2012) This electronic document will be published on the Scottish Government website and will be reviewed and updated as necessary. This is a .pdf version of the handbook, and also includes the templates for: KPO Reporting, National Customer Charter, Balanced Scorecard, and Continuous Improvement Plan

Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

1

BUILDING STANDARDS DIVISION Building Standards Verification

Key Performance Outcomes Handbook (from May 2012)  

 

This electronic document will be published on the Scottish Government website and will be reviewed and updated as necessary. This is a .pdf version of the handbook, and also includes the templates for:

KPO Reporting,

National Customer Charter,

Balanced Scorecard, and

Continuous Improvement Plan

Page 2: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

Table of Contents

1. Introduction 2. How to use this guidance 3. Key performance outcomes     3.1 Professional Expertise & Technical Processes 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency  Annex A KPO4 template – national customer charter Annex B Balanced Scorecard template (including Continuous Improvement Plan templates) Annex C Key Performance Outcomes 1, 2, 3, 6 returns template Annex D Quarterly summary reports VERSION RECORD Version Number Amendments Made Date 1.0 Inclusion of references to the

ScotXed web platform for the quarterly reporting of performance and annual return data and details of the new approach to the reporting of Continuous Improvement Plans and Balanced Scorecards.

20 August 2014

Page 3: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

1

1. Introduction 

 

The building standards system in Scotland was established as a result of the Building (Scotland) Act 

2003.  The remit of the building standards system is to protect the public interest by setting out the 

standards to be met when building or a conversion takes place, to the extent necessary to meet the 

building  regulations.    The  public  interest  is  a  critical  success  factor  ‐  ensuring  compliance with 

regulations and above all – keeping the public safe. 

 

The  Act  provides  for  the  appointment  of  verifiers  by  Scottish Ministers.    At  present  the  only 

appointed verifiers are the 32 Scottish local authorities, each covering their own geographical area. 

 

The main  function  for  local authorities  in  their verification  role,  is granting building warrants and 

accepting completion certificates.  This work is central to the delivery of the following key objectives 

contained in the 2003 Act: 

 

To  secure  the  health,  safety, welfare  and  convenience  of  persons  in  and  about 

buildings and others who may be affected by buildings or matters connected with 

buildings 

Furthering the conservation of fuel and power and 

Furthering the achievement of sustainable development. 

 

The current verification system was launched on 1 May 2005.  A requirement of their appointment 

is  for verifiers  to submit an annual  ‘balanced scorecard’  to  the Building Standards Division of  the 

Scottish Government.   

 

Local  authorities were  re‐appointed  on  1 May  2011  for  a  further  six‐year  period.    The  Scottish 

Government’s  re‐appointment  of  local  authorities  as  building  standards  verifiers  was  on  the 

understanding  that  a  new  performance  framework  be  put  in  place  to  improve  the  quality, 

compliance, consistency and predictability of verification activities. 

 

Building  Standards  services  have  been  operating  a  balanced  scorecard  performance  framework 

approach  since  2005.    This  new  advanced  performance  framework  for  building  standards 

introduced  in  2012 builds on what  has  already been  achieved  and  aims  to drive  forward better 

compliance with  the  building  regulations,  particularly  during  construction.    This  is  supported  by 

introducing a revised balanced scorecard, continuous improvement plans and is underpinned by the 

introduction of a range of new Key Performance Outcomes (KPOs) (9 in total).  This framework has 

been developed by the Building Standards Division of the Scottish Government and the approach is 

supported by Local Authority Building  Standards Scotland (LABSS).  

 

The  balanced  scorecard  approach  has  also  been  taken  forward  by  the  Local Authority Heads  of 

Planning who introduced a new Planning Performance Framework in 2012 that addresses the issues 

and  recommendations made by Audit Scotland  in  their  recent  review of  the planning  services  in 

Scotland.    Part  of  this measure  was  to  introduce  a  balanced  scorecard  approach  of  gathering 

information for the first time.   

 

As a result of the balanced scorecard performance framework for 2005‐2011, all verifiers have now 

Page 4: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

2

embedded into their service the following:  

 

Risk management protocols that determine the management of work on building 

warrant and completion certificates 

Customer  charters  that  encompass:  guidance  to  stakeholders;  accessibility  of 

service; measurable performance targets;  and customer views 

Formal plan for internal business since September 2005 

Since 2005, a rolling 3‐year strategy for continuous improvement 

Since 2007,  systems have been  in place  to  record costs and  the management of 

costs against income streams for the verification process. 

 

This new building standards performance framework was introduced from the 1 May 2012 and was 

measurable  from  1 October  2012.    It  seeks  to  address  a wide  range  of  actions  and  behaviours 

which, between them, demonstrate a strong customer‐focused service.  It allows the assessment of 

building standards performance outcomes over a range of key national objectives, including: 

 

Overall time taken in the decision making process 

Certainty of timescales  in respect of decision making, the assessment process and 

the provision of advice 

Delivery of compliant development 

Management and assessment of building warrants and completion certificates 

Clear communications and open engagement 

Sharing of best practice 

An overall ‘open for business’ attitude. 

 

Continuous  improvement embedded  in  the  culture of an effective building  standards  service  is a 

critical  success  factor  in  relation  to  raising  the  bar  for  compliance  and  consistency.    Continuous 

improvement may look towards: 

 

Delivery (customer valued) processes which are  constantly evaluated and improved 

in the light of their efficiency, effectiveness and flexibility 

Changes to and demands from the business environment 

Incremental  improvements  over  time,  with  a  focus  on  the  ongoing  changing 

business environment 

Peer review, benchmarking and sharing best practice.  

 

Continuous  improvement  is  a  dynamic  evolving  process  which  continually  seeks  to  respond  to 

customer needs.  As well as incremental improvements, there may be breakthrough improvements 

in  specific priority areas.   For example  they may be directly  linked  to each verifier’s  readiness  to 

implement the new performance framework over the next year or so.  

 

This  framework  ties  performance  assessment  to  specific  improvement  actions  through  the  local 

authorities’  balanced  scorecards,  quarterly  continuous  improvement  plan  updates  and  quarterly 

national statistical KPO returns.  This handbook and the associated templates set out the aspects of 

performance  that will be measured.   The Scottish Government  intends  to collate  the  information 

taken  from  all  building  standards  returns  and  produce  a  Scotland‐wide  annual  report  on  the 

Page 5: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

3

performance  of  the  building  standards  verification  system.    This  may  include  a  statement  of 

ministerial priorities for future improvements. 

 

The  introduction of  the balanced  scorecards  in 2005  resulted  in positive progress and a  stronger 

focus on customer service in particular, but this did not enable a consistent approach to monitoring 

and measuring performance.   Subsequently during 2011  research was  conducted  to develop and 

test a robust set of national KPOs that will form part of the new performance framework for  local 

authorities responsible for building standards verification.  The KPOs will contribute towards wider 

changes to the performance framework for building standards verification and will ensure that the 

activities of local authorities can be better compared to ensure consistency and quality in terms of 

outputs and overall service. 

 

The  research  sought  the  views  of  all  32  local  authority  verifiers  and  key  stakeholders  in  the 

construction  industry  so  that  KPOs  were  developed  collaboratively.    This  has  resulted  in  the 

development of three core perspectives for the outcomes: 

 

Professional Expertise & Technical Processes The aim of this perspective is to ensure that verifiers possess the necessary professional expertise to efficiently and effectively undertake all technical aspects of building standards verification. This is expected to be underpinned by on-going training and development and a commitment to delivering streamlined and transparent technical processes that meet customer needs and are compliant at all times with relevant legislation.

Quality Customer Experience The aim of this perspective is to ensure that verifiers provide high quality standards and services to customers, underpinned by clear and transparent communications, and an understanding of different customer and stakeholder types and their differing needs. These insights and actions taken in response to them are intended to bring about continuous improvement of the customer experience, which will be regularly measured and assessed.

Operational & Financial Efficiency

The aim of this perspective is to ensure that verifiers are managing the building standards verification operations and finances in the most efficient and effective way possible, underpinned by efficient utilisation of funds and resources, high levels of productivity and fit-for-purpose infrastructure such as IT systems.

 

These perspectives  are  supplemented by  two  themes which  are  cross‐cutting  and  span  all  three 

perspectives.    They  cover  all  aspects  of  building  standards  verification  including  strategy, 

operational delivery, internal and external relationships: 

 

Public Interest The aim of this theme is to ensure that all actions taken by verifiers in alignment with the three perspectives outlined above are in the best interest of the general public. Also, that building standards verification is undertaken in a consistent way regardless

Page 6: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

4

of verifier organisation or region and that will always protect the public interest through compliance with building regulations.

Continuous Improvement The aim of this theme is to encourage an on-going culture of commitment to ‘raising the bar’ and ensuring that there is a consistent effort to improve building standards verification across all of the three core perspectives as outlined above.

 

The framework for the KPOs is therefore summed up in the following diagram: 

 

PUBLIC INTEREST

PROFESSIONAL EXPERTISE &TECHNICAL PROCESSES

 

QUALITY CUSTOMER EXPERIENCE

OPERATIONAL & FINANCIAL EFFICIENCY

CONTINUOUS IMPROVEMENT

 

 

 

 

 

 

 

 

 

 

Page 7: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

1

 

2. How to use this guidance 

 

The  purpose  of  this  guidance  is  to  give  a  clear  understanding  of  each  of  the  Key  Performance 

Outcome perspectives and what  they are designed  to achieve  in supporting  the building standards 

system. 

 

Section 3 of this handbook describes each KPO in a standard template as set out below: 

 

Title i.e. the desired outcome   Purpose 

Requirements of verifiers 

Measurement (targets) and reporting  

Implementation date  

 

General principles Continuous  improvement  is  a  critical  success  factor  in  relation  to  ‘raising  the  bar’  for  customer 

service,  compliance,  and  in  particular  ‐  consistency.    KPOs  have  been  developed with  a  view  to 

embedding a  culture of  continuous  improvement underpinned by a greater  focus on peer  review, 

benchmarking and sharing of best practice. 

 

KPOs  should  be  adopted  by  all  verifiers  and  reviewed  after  a  period  of  2  years  (when  fully 

implemented)  to ensure  they  remain  fit  for purpose, with any necessary  changes  to KPOs,  targets 

and/or timescales implemented in order to maintain continuous improvement.   

 

Verifiers should report accurate and evidence based information on performance against KPOs to the 

Scottish Government  (generally on  a quarterly basis).    This will  enable  issues  to be  identified  and 

actioned on an on‐going basis, and trigger targeted interventions such as audit or peer review where 

poor performance is flagged up as a concern.  Poor performance will be expected to be improved. 

 

KPOs 1‐3 are segmented by building type and value.   This  is to gain a greater understanding of the 

type  of  building  warrants  and  how  they  are  treated  as  they  flow  through  the  system.    The 

segmentation  is  intended  to  cover  all  building  types  (new  buildings,  extensions  and  alterations).  

Mixed  building  types,  demolitions  and  conversions  should  be  reported  in  the  most  appropriate 

segment. 

 

The performance framework was launched in May 2012 consisting of 9 KPOs in three broad perspectives. Reporting by verifiers under the framework started from 1 October 2012 and applies to those applications for building warrants and amendments to building warrants received on or after that date.

Verifiers should ensure they refer to the latest version of this KPO handbook for quarterly reporting 

templates, dates and targets as it may be updated periodically.  The Scottish Government will provide 

information about updates as they are published.   

 

Page 8: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

2

Since 2009, the Scottish Government has requested annual returns from all local authorities covering 

the numbers of building warrant applications; completion certificates; fees; costs; certificates 

(certification, energy performance; sustainability and enforcement cases).  This information gives an 

insight into the trends affecting building standards services across Scotland.  It also provides key 

information to keep Ministers and local authorities informed of the significant contribution building 

standards is making to Scotland’s economy.  From April 2014 these returns have been integrated into 

the quarterly KPO reporting cycle to make use of the web platform and any duplication has been 

removed.  Therefore the last annual return in the ‘annual’ format covers 2013‐14. 

 

Unless  otherwise  specified,  quarterly  returns  will  be  for  each  three  monthly  period.    Quarterly 

reporting provides a means to calculate cumulative performance and a quarterly and yearly summary 

will be published.   The annual  return data  requested  in  recent years has been embedded  into  this 

process.  

 

From April  2014  all  returns  to  the  Scottish Government  are made  via  the  ScotXed web  platform, 

available at: https://procxed.scotxed.net/ProcXed/Security/Logon.aspx?ReturnUrl=%2fProcXed 

 

It was  recognised  that  not  all  verifiers would  be  at  the  same  starting  point  and  so  it was  to  be 

expected that there may be differing timescales for adoption.  However, all verifiers were expected to 

have systems and KPOs in place by the agreed implementation dates and these are explained within 

the  handbook.    Construction  Compliance  and Notification  Plans  should  be  issued  for  all  buildings 

under  KPO2  from  October  2012.    However  the  risk‐based  methodology  underpinning  it  was 

introduced  in  two  phases.    Initially  the  methodology  for  domestic  buildings,  followed  by  the 

methodology  for non‐domestic buildings once  fully developed.   The methodology  for non‐domestic 

buildings was introduced from 1 October 2013.  

 

Key Performance Outcomes (KPOs)

Professional Expertise & Technical Processes

KPO1 Year-on-year reduction in the average time taken to grant a building warrant

KPO2 Increased quality of assessment and compliance during the construction processes

Quality Customer Experience

KPO3 Commitment to meeting customer expectations

KPO4 Adherence to service commitments of a National Customer Charter

KPO5 Improvement of the customer experience

Operational & Financial Efficiency

KPO6 Financial governance

KPO7 Improved partnership working underpinned by engagement with a National Forum

KPO8 Development of and adherence to objectives outlined in balanced scorecard

KPO9 Commitment to continuous improvement  

Page 9: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

3

3. Key Performance Outcomes

  

3.1 Professional Expertise & Technical Processes 

 

KPO1

Year-on-year reduction in the average time taken to grant a building warrant1

Purpose Research indicates that speed of turnaround is important for the majority of customers seeking a building warrant, as this allows them to start work.  

The intention of this KPO is to minimise the time taken for customers to obtain a building warrant whilst importantly, maintaining the appropriate levels of competent plan assessment.  

It is recognised that the average time includes, in addition to the assessments by the verifier, other influencing factors such as performance of customers (applicants and agents) and the quality of submissions.   

Requirements of verifiers

1. Maintain records of the time taken to grant a building warrant. 2. Have mechanisms in place to record the breakdown of time taken by verifier 

and by customer (applicant or agent).  3. Seek to minimise the time taken to grant a building warrant whilst maintaining 

high standards of verification.

Measurement and reporting

The trigger for KPO1 is the issue of a building warrant (or amendment to warrant) within the reporting period.  Quarterly reporting to the Scottish Government commenced on 1 October 2012 using the template.  Reporting from 1 April 2014 is by the ScotXed web platform.  

Data reporting:  

Total number of building warrants granted  

Total number of working days from receipt of a valid2  application to granting the building warrant3 

 

Context reporting (if deemed necessary): 

Commentary on any significant changes from quarter to quarter 

Implementation date

For all applications for building warrants and amendments to building warrants received on or after 1 October 2012 (domestic and non‐domestic).  

Notes 1 For the purpose of this KPO, “building warrant” includes associated amendments to warrant for design changes or for building warrant stages. 2 For the purpose of this KPO, a valid application is one that has sufficient information for the verifier to undertake a substantive technical check and be able to issue a first report if one is necessary. 3 Reporting from April 2014 includes average time taken by the verifier for use by verifiers who can provide further breakdown of the time taken to grant the building warrant.

Page 10: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

1

 

KPO2

Increased quality of compliance during the construction processes

Purpose The development of safe and compliant buildings is of paramount importance to building standards verification.  This means protecting the public interest by minimising the occurrence of non‐compliance with building regulations.  The “relevant person” (usually the building owner or the developer) is responsible for complying with building regulations.  When the work is finished, they must sign the completion certificate confirming compliance with building regulations.  The verifier is responsible for accepting or rejecting the completion certificate submission but only after they have made reasonable inquiry.  The verifier will carry out site visits or other means of inspection to satisfy themselves that the work carried out has been satisfactorily completed.  A key aspect of the relevant person’s role is to notify the verifier at the necessary stages of work.  This will enhance the likelihood of compliance by assisting the verifier to carry out their inspections as work progresses.  It is hoped that this approach will promote partnership working on the project between the relevant person and the verifier.  It should also give the relevant person a better understanding on both their and the verifiers roles and responsibilities.  The intention of this KPO is to promote quality and consistency of compliance assessment by undertaking timed and proportionate reasonable inquiries using a risk‐based approach to inspection and other forms of assessment e.g. photographic evidence.  

Requirements of verifiers

1. Embed the risk assessment methodology into normal working practices for reasonable inquiry and: 

apply to “domestic buildings” from 1 October 2012 

apply to “non‐domestic buildings” from 1 October 2013.  2. Issue Construction Compliance Plans (CCNP) with all building warrants1 applied 

for on or after 1 October 2012 (domestic and non‐domestic buildings2).  3. Record the numbers of CCNPs for “accepted” completion certificates, and of 

these, how many were fully achieved in terms of: 

notification by the relevant person 

inspection by the verifier. Provide reasons why CCNPs were not fully achieved. 

 4. Record aspects of construction non‐compliance3 locally and report issues with 

a national impact to drive forward improvements in the verification system.  Escalate construction non‐compliance trends to the National Forum for discussion. 

 

Page 11: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

2

Measurement and Reporting

The trigger for KPO2 is the acceptance of a completion certificate within the reporting period.  Quarter reporting to the Scottish Government commenced on 1 October 2012 using the template.  Reporting from 1 April 2014 is by the ScotXed web platform.  Data Reporting: 

Number of CCNPs4 for “accepted” completion certificates 

The number of these CCNPs fully achieved5  

Context reporting (if deemed necessary): 

The main reasons why CCNPs were not fully achieved (prioritised) 

The main aspects of construction non‐compliance3 found through reasonable inquiry (prioritised) 

 

Implementation date

For all applications for building warrants and amendments to building warrants  received on or after 1 October 2012:  a) CCNPs to be issued with all building warrants (domestic and non‐domestic)   b) Risk assessment methodology to be applied to: 

all domestic buildings from 1 October 2012 

all non‐domestic buildings from 1 October 2013  

Notes 1 For the purpose of this KPO, “building warrant” includes associated amendments to warrant for design changes or for building warrant stages. Staged warrants may require review of the CCNP at each stage as the design progresses.

2 CCNPs should be issued for all building types from 1 October 2012. CCNPs for non-domestic buildings should be based on current practices until the methodology for non-domestic buildings is developed for implementation from 1 October 2013. This approach will promote partnership working on each project between the relevant person and the verifier for all buildings. The methodology for non-domestic buildings was introduced from 1 October 2013. 3 “Construction non-compliance” in this context is a reference to the failure of a building to meet a minimum building standard. The intention being that these areas of non-compliance are recorded for use locally or for escalation to the National Forum – see KPO7. 4 Building warrants covering multiple dwellings need a completion certificate for each dwelling. Therefore, CCNP achievement should be reported for each completion certificate, not for the building warrant.

5 Reporting from April 2014 includes the number of CCNPs fully achieved by the relevant person and the number of CCNPs fully achieved by the verifier for use by verifiers who can provide further breakdown.

Page 12: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

1

 

3.2 Quality Customer Experience  

 

KPO3

Increased commitment to meeting customer expectations

Purpose The current system does not allow customers an alternative option if they are dissatisfied with the level of service provided.  The purpose of this KPO is to provide an “escape route” for any customers that are dissatisfied with the agreed processing time of building warrant and amendment to building warrant applications.   

Requirements of verifiers

1. Meet key performance targets for the time in working days from receipt of a valid1 building warrant2 application to the time to issue “first report3” (20 working days or as detailed in the customer agreement). 

 2. Customer Agreements4 can apply to building warrant applications and be used 

when the standard 20 working days target is not appropriate.  They should be agreed between the verifier and the applicant for the building warrant and include a project specific first report target. 

 3. Provide the “escape route” for customers who are dissatisfied with service 

provision regarding the time taken to process a building warrant.   

4. Identify and record the reasons targets have not been met and why customers have chosen the escape route. 

 5. Utilise customer reasons for choosing the escape route to identify and embed 

process and customer experience improvements.   

Measurement and reporting

The trigger for KPO3 is the issue of a first report for a building warrant (or amendment) within the reporting period (or if the building warrant or amendment can be granted immediately, the trigger is the granting of the building warrant or amendment).  Quarterly reporting to the Scottish Government commenced on 1 October 2012.  First report target and backstop are measured in working days.  Reporting from 1 April 2014 is by the ScotXed web platform.  Data reporting: 

a) The number of first reports issued (without Customer Agreement) 

number within customer target (1 ‐ 20 working days) 

number within the 15 day backstop period (21 – 35 working days)  

number after backstop period (35 days) but within statutory 3 month5 period  

 b) The number of first reports issued (with Customer Agreement) 

number within customer target (as set out in CA)  

number after customer target but within statutory 3 month5 period  Context reporting (if deemed necessary) : 

Commentary on any significant changes from quarter to quarter (as KPO1) 

The main reasons why building warrant first report targets not met 

The main reasons why the escape route trigger not met 

Commentary on any issues arising from Customer Agreements  

Page 13: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

2

Implementation date

For all applications for building warrants and amendments to building warrants received on or after 1 October 2012 (domestic and non‐domestic).  The escape route needs to fully address customers concerns.  To allow the concerns to be fully understood, from 1 October for a trial six month period, all building warrant applicants will be able to report any dissatisfaction of a verifier failing to meet the appropriate level of service for their building warrant first report response time.  The outcome of this trial will be used to inform future development of the escape route.  Reporting will be through the Scottish Government Building Standards Division, who will contact both the local authority concerned and Local Authority Building  Standards Scotland.  The key  stages are set out below:  

1. Customer notifies Scottish Government Building Standards Division (BSD) at: [email protected] or 01506 600400 

 2. BSD contacts the local authority concerned (and informs Local Authority 

Building Standards Scotland (LABSS))  

3. Local authority investigates the case  

4. Local authority notifies the customer of expected issue date for first report (and informs BSD and LABSS) 

 5. Local authority issues the first report within the timescale (and  informs 

BSD and LABSS)   

Notes 1 For the purpose of this KPO, a valid application is one that has sufficient information for the verifier to undertake a substantive technical check and be able to issue a first report if necessary. 2 For the purpose of this KPO, “building warrant” includes associated amendments to warrant for design changes or for building warrant stages. 3 If the verifier, following a full technical assessment of the application, cannot grant the warrant, they will issue the “first report”. This report indicates any failures to comply or areas requiring further clarification and should provide a level of detail sufficient to identify clearly which standards must be addressed or what further information is required. When a first report is not needed and the warrant can be granted immediately, the date the building warrant is granted should be used for reporting. 4 A Customer Agreement for a project is likely to cover a range of aspects from pre-application through to completion on site. The first report target is only one aspect. 5 The statutory 3 month “deemed refusal” period can be extended.  

Page 14: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

1

 

KPO4

Adherence to service commitments of a National Customer Charter

Purpose Local customer charters have been embedded in all verification services since 2007.    A national customer charter will complement the local charter and will demonstrate the shared commitment to service levels and a consistent standard of quality across all verifiers. 

Requirements of verifiers

1. Incorporate local information into the national customer charter template (see Annex A).  

2. Ensure the national customer charter is published on verifier’s website and is clearly accessible for customers online and in printed form.  

 3. Ensure the requirements of the customer “escape route” are detailed in the 

customer charter.  

4. Publish data on performance against national KPOs within the national customer charter on an annual basis (with rolling 3 years data entered beginning with year 2012/13). 

 5. Maintain checks on localised information to ensure contact details and 

appropriate website links are kept up‐to‐date on an on‐going basis.   

6. BSD and LABSS to carry out an annual review of customer charter at national and local level and update the charter where appropriate. 

 

Measurement and reporting

Quarterly reporting through the continuous improvement plan should note when the national customer charter is changed or updated and for what reasons.  

Implementation date

Verifiers to have national customer charter published by 1 October 2012 

 

 

 

Page 15: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

2

 

KPO5

Improvement of the customer experience

Purpose Ensuring customer satisfaction is an essential part of building standards verification.    The purpose of this KPO is for verifiers to gain a more detailed understanding of their different customer groups and to be able to respond most appropriately to their needs. 

Requirements of verifiers

1. To assist the Scottish Government Building Standards Division to supply customer data for research purposes. 

 2. Inform customers that they may be contacted for research purposes.   3. Use findings from the national survey for the purpose of customer 

segmentation.  

4. Use survey findings to identify and make improvements to the customer experience.  

 5. Develop an improvement plan in relation to customer experience and 

monitor/report progress.   

Measurement and reporting

Progress in relation to improving the customer experience should be reported on a quarterly basis through the continuous improvement plan and outcomes from the survey findings, if appropriate. 

 

Implementation date

First survey to be carried out by Scottish Government spring 2013 and annually thereafter.  Initially the survey will be funded by the Scottish Government. 

 

Page 16: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

3

 

3.3 Operational & Financial Efficiency 

 

KPO6

Financial governance

Purpose It is vital that resources including funds, employees, IT and other infrastructure are fully harnessed to ensure efficiencies are maximised.    The purpose of this KPO is to monitor verification fee income compared with the costs of running the service:  a) to identify where efficiencies can be improved and  b) to determine whether verification fees are of a sufficient level to ensure a high   quality service can be offered. 

Requirements of verifiers

1. Provide data on the income received from building warrant and related statutory fees and the expenditure incurred (staff costs only) to run building standards verification services. 

 2. Have in place systems to support the accurate and timely collection of these 

data.  

3. Ensure that time recording systems identify the percentage of time spent on verification activity, and thus enable direct staff costs required to run the verification system to be calculated. 

 4. Undertake regular reviews of income and cost streams in order to inform and 

embed efficiency savings where possible.  

5. Adhere to the national approach for identifying staff1  costs:   

Identify total staff costs which are: wages and salaries; social security costs; pension costs and temporary staff costs 

Identify time spent on verification work from the time recording system   

The example below is for a verifier with 6 staff and verification time of 75%.  

EXAMPLE: VERIFIER A COSTSTotal staff costs for all activity (6 staff) £200,000 

Total Verification staff costs (75% of all activity) £200,000 x 75% 

TOTAL VERIFICATION STAFF COSTS £150,000  

Measurement and reporting

Verifiers will be required to report data on verification fee income and staff costs. Quarterly reporting to the Scottish Government commenced on 1 October 2012. Reporting from 1 April 2014 is by the ScotXed web platform.  

Implementation date

All financial data to be recorded from 1 October 2012   

Notes 1Staff costs are the costs for technical and support staff directly involved in the verification service. 

Page 17: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

1

 

KPO7

Improved partnership working underpinned by engagement with a National Forum

Purpose To develop a national construction forum within Scotland that will bring together key stakeholders in the construction industry and encourage collaborative partnership working.  This approach will underpin greater consistency and seek solutions to issues in the public interest.    

Requirements of verifiers

1. Attendance by Local Authority Building Standards Scotland (LABSS), and individual verifiers when appropriate, at national forum meetings with peers and industry stakeholders to discuss key issues. 

 2. Gain a better understanding of stakeholders’ priorities, ensuring that 

partnership working realises benefits and minimises areas of potential conflict. 

 3. Utilise through LABSS and individually the forum and other forms of 

communications to share best practice with peers and industry stakeholders.  

4. Initiate ideas for improving the performance of those involved in the construction industry. 

 5. Work towards the improvement of key business processes.  

Measurement and reporting

Full meetings to be held twice yearly through a systematic, flexible agenda in response to issues raised by forum members.  Regular meeting reports to be published for dissemination.   

Implementation date

First meeting to be arranged by Scottish Government to take place in spring 2013. 

 

Page 18: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

2

 

KPO8

Development of and adherence to objectives outlined in balanced scorecard (Business Plan)

Purpose The balanced scorecard approach introduced for the period 2005‐2011 enabled verifiers to report performance to Scottish Ministers across five key areas.    Research into the development of KPOs has identified three core perspectives with two cross‐cutting themes underpinning them – therefore balanced scorecards need to be refined to take this into account.  The balanced scorecard template will enable a consistent approach to reporting that has not been delivered in previous years.   

Requirements of verifiers

1. Produce a new balanced scorecard using the relevant template covering the following: 

 Core perspectives: 

Professional expertise & technical processes 

Quality customer experience 

Operational & financial efficiency  Cross cutting themes: 

Public interest 

Continuous improvement  

2. Submit balanced scorecard to the Scottish Government by 30 September 2012. 

 

Measurement and reporting

Verifiers to submit annual balanced scorecard using the template.  The template is available as a separate document.    From April 2013, verifiers to publish their balanced scorecards on their website, instead of submitting to the Scottish Government.    From April 2014, verifiers to update their balanced scorecards to incorporate the Continuous Improvement Plan summary updates in section 4 (see KPO9), and review quarterly.   

Implementation date

Verifiers to submit balanced scorecards to cover the period  April 2012‐ March 2013 by 30 September 2012.   

 

Page 19: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

3

 

KPO9

Increased commitment to continuous improvement

Purpose The introduction of a Continuous Improvement Plan will enable verifiers to demonstrate their commitment to continuous improvement which cuts across all aspects of their balanced scorecards.  Although initially focussing on the implementation of the performance framework, verifiers can still be creative in their pursuit of improvements without concentrating solely on the data reporting aspects, such as response times.   The plans will allow the Scottish Government to assess the current position of verifiers and see both their business ambitions, and their progress.  Also initially, to understand how close verifiers are to implementing the new framework and achieving KPO targets, and the actions planned in order to meet the implementation and the targets. 

Requirements of verifiers

1. Produce a Continuous Improvement Plan using the relevant template, outlining achievement time; current level of distance from KPO and plans in place to meet the KPO targets.  

2. Identify and include key milestones within the Continuous Improvement Plan. 

 3. Allocate responsibility to members of the verification team for monitoring 

and reporting progress against the targets outlined in the Continuous Improvement Plan. 

 4. The template highlights the baseline information required for the framework. 

Verifiers may include more advanced or creative improvement actions as they see appropriate to their business. 

 

Measurement and reporting

Verifiers will be required to report progress against the Continuous Improvement Plan.  Quarterly reporting to the Scottish Government commenced on 1 October 2012.    From April 2014, a simplified reporting approach to focus on the key improvements was introduced using updated Continuous Improvement Plan Templates.  Verifiers to migrate to the “Detailed CIP“ template, and provide quarterly “Summary of CIP” updates.  Quarterly reporting to Scottish Government should be made using the “Summary of CIP” template.   

Implementation date

Verifiers to develop their first Continuous Improvement Plan by 30 September 2012 and return to BSD by 31 October 2012.  Quarterly reporting will be required from 1 October 2012.  

Page 20: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

ANNEX A: KEY PERFORMANCE OUTCOME 4 - National Customer Charter Template Purpose of a National Customer Charter:  

A National Customer Charter for Building Standards Verification provides information about the minimum standards of service that all local authority 

verifiers should meet.  This gives customers the reassurance that a consistent, high quality service will be delivered no matter which local authority 

provides the service.   

 

Our Aims:   To grant building warrants and accept completion certificates: 

To secure the health, safety, welfare and convenience of persons  in and about buildings and others who may be affected by buildings or 

matters connected with buildings 

Furthering the conservation of fuel and power and 

Furthering the achievement of sustainable development. 

Our vision/values: To provide a professional and informative service to all our customers. 

 

Our Commitments: Nationally all local authority verifiers will: 

1. Seek to reduce the average time it takes for customers to obtain a building warrant 

2. Ensure continuous improvement around the robustness of our verification assessments to ensure compliance 

3. Meet and seek to exceed customer expectations  

4. Carry out local customer satisfaction surveys 

5. Address feedback obtained through a National Customer Satisfaction Survey to improve the customer experience  

6. Provide accurate financial data that is evidence‐based  

7. Engage with our peers and stakeholders through a National Forum that will identify and embed service improvements at a national level  

8. Develop and adhere to a Balanced Scorecard approach outlining our objectives and targets 

9. Fully adhere to the commitments outlined in this Charter (including information regarding the escape route* process for dissatisfied customers 

in relation to building warrant processing timescales. 

10. Provide a consistent format for our continuous improvement plans 

Page 21: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

Information: National information on verification performance can be found at the Scottish Government website www.scotland.gov.uk/bsd 

 

Locally:  ADD YOUR OWN LOCAL CUSTOMER CHARTER TO THIS TO COMPLETE 

* Each local authority should include details of the trial for customers to report dissatisfaction in the level of service for their first report response time. 

Page 22: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

ANNEX B: BALANCED SCORECARD TEMPLATE (INCLUDING CONTINUOUS IMPROVEMENT PLAN TEMPLATES)

Local Authority name and logo to be inserted here

Building Standards Verification Service

Balanced Scorecard Template 2014-2015

Page 23: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

Table of Contents

1.   Introduction to the Local Authority  

 

2.   Building Standards Verification Service Information  

 

3.   Strategic Objectives 

 

4.   Key Performance Outcomes 

 

5.   Building Standards Additional Data 

 

 

 

 

Page 24: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

1. Introduction  

As part of  the new performance  framework,  it has been agreed  that all verifiers must produce an 

annual balanced  scorecard on  the agreed  template.    It  should  then be published on  their website.  

The  following  sections  detail  the minimum  information  and  standard  paragraphs  that  should  be 

included throughout the balanced scorecard. 

 

The information on each of the bullets listed below should also be included in the introduction 

section. 

Include balanced scorecard standard statement (see below for wording) Size of the local authority by population and geographical size Insert a map of the area Describe the physical environment – mainly rural, urban, mixture of both and concentration of

population in urban vs. rural areas State the major employers and main employment sectors Detail the full range of responsibilities the local authority building standards service delivers Organisational chart of the Local Authority (CEO to BSM level see example below)

Standard balanced scorecard statement. (All balanced scorecards should contain the following paragraph in the introduction section)  

The  balanced  scorecard  is  a  strategic  planning  and  management  tool  that  is  used  in  business 

organisations  to  align  business  activities  to  the  vision  and  strategy  of  the  organisation,  improve 

internal and external communications, and monitor performance against strategic goals.  

 

Building standards verifiers  in Scotland are required to utilise the balanced scorecard as a means to 

manage, monitor,  review and develop  strategies  for  their business with a  focus on  the  three  core 

perspectives listed below and the public interest and continuous improvement cross‐cutting themes: 

Professional Expertise & Technical Processes  Quality Customer Experience  Operational & Financial Efficiency  

Service Director 

Head of Planning 

Head of Environment

Head of Infrastructure

Building Standards Manager

Chief Executive

Page 25: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

2. Building Standards Verification Service Information  

This section should include the following information:  

Location of office (if the department is located in one office or across separate offices, if so a description of allocation of provision is required here) 

Detail verification services and functions delivered  Include public interest statement (listed below)  Include organisation chart (BSM and below) which should include vacant and occupied

positions and job titles. Chart should include links into other departments that work closely with building standards verification e.g. planning (see example below)

Public Interest Statement (to be included in all balanced scorecards) The purpose of the building standards system  is to protect the public  interest.   The system sets out 

the essential standards that are required to be met when building work or conversion of a building 

takes place in order to meet building regulations.  

 

The building standards system checks that proposed building work or conversion of a building meets 

standards;  inspections are  limited  to a minimal necessary  to ensure  that  legislation  is not avoided.  

The control of work on site is not down to the system but is a matter for contracts and arrangements 

in place between a builder and client.  

 

Verifiers,  appointed  by  Scottish  Ministers  are  responsible  for  the  independent  checking  of 

applications for building warrants to construct or demolish buildings, to provide services, fittings or 

equipment in buildings, or for conversions.  

 

 

 

 

 

 

Building Standards Manager 

Team Leader  Team Leader  Team Leader 

Surveyor Inspector Surveyor Inspector  Admin Admin

Page 26: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

 

3. Strategic Objectives 

 

This section should include a short narrative covering the following bullets under each of the headings

The overarching goal/vision of the service Departmental issues to be addressed in the coming year The key strategic objectives for the coming year (should align with continuous improvement

plan)  

 

 

4. Key Performance Outcomes –(Professional Expertise & Technical Processes, Customer Experience & Operational & Financial Efficiency)  

This section should include a narrative covering the following bullets under each of the headings

Professional Expertise & Technical Processes Protocols for dealing with work Performance management systems Training and development/CPD  Benchmarking/shared services/partnership work  Commitment to work together on technical issues  Succession planning

Quality Customer Experience

Customer communication strategies Charter (local/national) Engagement (national and local forums) Customer feedback (local and national)/analysing and changes systems. Accessibility of service Escape route Recognised external accreditations

 

Operational & Financial Efficiency Team structures e.g. (area splits/specialist teams) Time recording system Financial monitoring/governance IT systems Finance systems Internal communication strategies

This section should include a summary of the Continuous Improvement Plan.

 The Continuous Improvement Plan (CIP) Summary template is provided below.  (A suggested detailed CIP template is also provided however it should be noted that the detailed CIP does not form part of the balanced scorecard and is intended to be retained at local authority level.) 

Page 27: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

Key actions from previous quarter (Q_ 20__):

Relevant to KPO1-2 (from list):

Target completion date: Status (from list): Outcomes:

12345 etc.

Key actions planned for next three quarters:

Relevant to KPO1-2 (from list):

Target completion date: Priority level (from list): Proposed outcomes:

12345 etc.

Key actions from previous quarter (Q_ 20__):

Relevant to KPO3-5 (from list):

Target completion date: Status (from list): Outcomes:

12345 etc.

Key actions planned for next three quarters:

Relevant to KPO3-5 (from list):

Target completion date: Priority level (from list): Proposed outcomes:

12345 etc.

Key actions from previous quarter (Q_ 20__):

Relevant to KPO6-9 (from list):

Target completion date: Status (from list): Outcomes:

12345 etc.

Key actions planned for next three quarters:

Relevant to KPO6-9 (from list):

Target completion date: Priority level (from list): Proposed outcomes:

12345 etc.

Professional Expertise and Technical Processes

Commentary: (This is an important requirement and should include a narrative summary of progress, as well as the context and rationale for any changes to current and planned actions.)

CONTINUOUS IMPROVEMENT PLAN - SUMMARY (PART 4 OF BALANCED SCORECARD)

Commentary (optional): (This could look at longer term priorities (one to three years)):

Commentary (optional): (This could look at longer term priorities (one to three years)):

Commentary: (This is an important requirement and should include a narrative summary of progress, as well as the context and rationale for any changes to current and planned actions.)

Operational and Financial Efficiency

Commentary (optional): (This could look at longer term priorities (one to three years)):

Commentary: (This is an important requirement and should include a narrative summary of progress, as well as the context and rationale for any changes to current and planned actions.)

Quality Customer Experience

Page 28: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

Actions from previous quarter (Q_ 20__):

Relevant to KPO1-2 (from list):

Target completion date(s): Status (from list): Owner (e.g. individual): Reasons if behind schedule/not yet started:

Outcomes (progress, outputs and impact):

1

2

3

4

5 etc.

Planned actions for next three quarters:

Relevant to KPO1-2 (from list):

Target completion date(s): Priority (from list): Owner (e.g. individual):

1

2

3

4

5 etc.

Actions from previous quarter (Q_ 20__):

Relevant to KPO3-5 (from list):

Target completion date(s): Status (from list): Owner (e.g. individual): Reasons if behind schedule/not yet started:

Outcomes (progress, outputs and impact):

1

2

3

4

5 etc.

Planned actions next three quarters:

Relevant to KPO3-5 (from list):

Target completion date(s): Priority (from list): Owner (e.g. individual):

1

2

3

4

5 etc.

Actions from previous quarter (Q_ 20__):

Relevant to KPO6-9 (from list):

Target completion date(s): Status (from list): Owner (e.g. individual): Reasons if behind schedule/not yet started:

Outcomes (progress, outputs and impact):

1

2

3

4

5 etc.

Planned actions next three quarters:

Relevant to KPO6-9 (from list):

Target completion date(s): Priority (from list): Owner (e.g. individual):

1

2

3

4

5 etc.

Coverage of continuous improvement relating to: Efficient utilisation of funds and resources (including people); high levels of productivity; fit-for-purpose infrastructure (including IT); effective partnership working with key stakeholders.

SECTION 2: Quality Customer Experience

Proposed outcomes:

SECTION 3: Operational and Financial Efficiency

SECTION 1: Professional Expertise and Technical ProcessesCoverage of continuous improvement relating to: Appropriate levels of competent plan assessment; quality and consistency of compliance assessment; streamlined and transparent

technical processes; effective performance management; commitment to training and development; partnership working.

Proposed outcomes:

CONTINUOUS IMPROVEMENT PLAN - DETAILED (RETAINED AT LOCAL AUTHORITY LEVEL)

Coverage of continuous improvement relating to: Providing high quality customer service; understanding and meeting customer needs; delivering clear and transparent communications; adhering to the national customer charter.

Proposed outcomes:

 

Page 29: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

 

5. Building Standards – Additional Data (Local Authority Return)    

The Scottish Government requested annual returns from all local authorities from 2009 until 2013.  These 

covered the numbers of building warrant applications; completion certificates; fees; costs; certificates 

(certification, energy performance; sustainability); enforcement cases.   

 

From April 2014 these returns have been integrated into the quarterly KPO reporting cycle on the newly 

introduced web based data collection platform.  The last annual return in the ‘annual’ format covers 2013‐14. 

Below is the new quarterly report template. 

 

 

  

Page 30: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

ANNEX C: KEY PERFORMANCE OUTCOMES 1, 2, 3, 6 Returns

Local Authority name and logo to be inserted here

Building Standards Verification Service

Key Performance Outcomes 1, 2, 3 and 6 Returns Template

2014-2015

Page 31: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

 

  

 

 

 

 

 

Page 32: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

 

KEY PERFORMANCE OUTCOMES - QUARTER PERIOD (Insert Q1, Q2, Q3, Q4) - 2014-15

Local Authority:

Contact details:Breakdown into "days taken by verifier provided"

CATEGORY (by building type and value of work)

Number of CCNPs for "accepted"

completion certificates

Number of CCNPs fully achieved

(OPTIONAL FOR 2014-15)

Number of CCNPs fully achieved by

"Relevant Person"

(OPTIONAL FOR 2014-15)

Number of CCNPs fully achieved by

"Verifier"

0 - £10,000£10,001 - £50,000£50,001 - £250,000£250,001 - £1,000,000£1,000,001 and above

0 - £10,000£10,001 - £50,000£50,001 - £250,000£250,001 - £1,000,000£1,000,001 and above

0 - £10,000£10,001 - £50,000£50,001 - £250,000£250,001 - £1,000,000£1,000,001 and above

0 - £10,000£10,001 - £50,000£50,001 - £250,000£250,001 - £1,000,000£1,000,001 and above

0 - £10,000£10,001 - £50,000£50,001 - £250,000£250,001 - £1,000,000£1,000,001 and above

KPO2 Total ALL CATEGORIESProvide Verifier's view of the main reasons why CCNPs were not fully achieved

Provide Verifier's view of the main aspects of technical non-compliance identifed through reasonable inquiry (prioritised)

Other comments on CCNPs

KPO2 - COMPLIANCE DURING CONSTRUCTION

KPO2 - DOM1 - Domestic New Build - MULTIPLOT

KPO2 - DOM2 - Domestic New Build - OTHER

KPO2 - DOM3 - Domestic Existing Building- EXTENSION

KPO2 - DOM4 - Domestic Existing Building - ALTERATION

KPO2 - NDOM5-9 - Non Domestic building - ALL

 

Page 33: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

 

 

Page 34: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

 

 

 

 

Page 35: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

 

  

 

 

 

 

 

Page 36: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer

ANNEX D: QUARTERLY SUMMARY REPORTS

 

Page 37: Building Standards Verification Key Performance Outcomes ... · 3.2 Quality Customer Experience 3.3 Operational & Financial Efficiency Annex A KPO4 template – national customer