CONSTRUCTION COST (PLINTH ARAE BASIS )
FOR BUILDING WORKS
Item Specifications UnitsPlinth Area
Rate (Rs./Sft)
Plinth Area Rate
(Rs./Sqm)Breakup
Biology Block
Structure RCC Rs./Sft BUA 450.00 4844 20%
Finishes Rs./Sft BUA 675.00 7266 30%
Electrical wiring & fixtures Rs./Sft BUA 150.00 1615 7%
Plumbing / Sanitation Rs./Sft BUA 75.00 807 3%
A/C Central A/C Rs./Tonne 300.00 3229 13%
D.G./Backup 100% incl. A/C Rs./KVA 90.00 969 4%
UPS 70% of Lighting load Rs./KVA 0.00 0 0%
Stuctured Cabling LAN/ Datacom Rs./Sft. of BUA 90.00 969 4%
Intercom/EPABX 37.50 404 2%
Automation / Security 135.00 1453 6%
Lifts 45.00 484 2%
Sub-Station 60.00 646 3%
Fire Alarm 75.00 807 3%
Fire Fighting 45.00 484 2%
Total Cost per Sft. 2227.50 23976.61 100%
IT Block
Structure RCC Rs./Sft BUA 425.00 4575 22%
Finishes Rs./Sft BUA 500.00 5382 26%
Electrical wiring & fixtures Rs./Sft BUA 150.00 1615 8%
Plumbing / Sanitation Rs./Sft BUA 75.00 807 4%
A/C Central A/C Rs./Tonne 300.00 3229 15%
D.G./Backup 100% incl. A/C Rs./KVA 100.00 1076 5%
UPS 70% of Lighting load Rs./KVA 0.00 0 0%
Stuctured Cabling LAN/ Datacom Rs./Sft. of BUA 125.00 1345 6%
Intercom/EPABX 50.00 538 3%
Automation / Security 50.00 538 3%
Lifts 45.00 484 2%
Sub-Station 60.00 646 3%
Fire Alarm 25.00 269 1%
Fire Fighting 45.00 484 2%
Total Cost per Sft. 1950.00 20989.63 100%
Service Corridor
Computational Biology Centre
Structure RCC Rs./Sft BUA 350.00 3767 21%
Finishes Rs./Sft BUA 300.00 3229 18%
Electrical wiring & fixtures Rs./Sft BUA 125.00 1345 8%
Plumbing / Sanitation Rs./Sft BUA 75.00 807 5%
A/C Central A/C Rs./Tonne 300.00 3229 18%
D.G./Backup 100% incl. A/C Rs./KVA 100.00 1076 6%
UPS 70% of Lighting load Rs./KVA 0.00 0 0%
Stuctured Cabling LAN/ Datacom Rs./Sft. of BUA 125.00 1345 8%
Intercom/EPABX 50.00 538 3%
Automation / Security 50.00 538 3%
Lifts 50.00 538 3%
Sub-Station 60.00 646 4%
Fire Alarm 25.00 269 2%
Fire Fighting 50.00 538 3%
Total Cost per Sft. 1660.00 17868.09 100%
CONSTRUCTION COST (PLINTH ARAE BASIS )
FOR BUILDING WORKS
Item Specifications UnitsPlinth Area
Rate (Rs./Sft)
Plinth Area Rate
(Rs./Sqm)Breakup
Centre for specialised services
Structure RCC Rs./Sft BUA 425.00 4575 23%
Finishes Rs./Sft BUA 450.00 4844 24%
Electrical wiring & fixtures Rs./Sft BUA 150.00 1615 8%
Plumbing / Sanitation Rs./Sft BUA 75.00 807 4%
A/C Central A/C Rs./Tonne 300.00 3229 16%
D.G./Backup 100% incl. A/C Rs./KVA 90.00 969 5%
UPS 70% of Lighting load Rs./KVA 0.00 0 0%
Stuctured Cabling LAN/ Datacom Rs./Sft. of BUA 113.00 1216 6%
Intercom/EPABX 38.00 409 2%
Automation / Security 38.00 409 2%
Lifts 45.00 484 2%
Sub-Station 60.00 646 3%
Fire Alarm 23.00 248 1%
Fire Fighting 45.00 484 2%
Total Cost per Sft. 1852.00 19934.76 100%
Admin and Mgmt Block
Structure RCC Rs./Sft BUA 188.00 2024 26%
Finishes Rs./Sft BUA 150.00 1615 21%
Electrical wiring & fixtures Rs./Sft BUA 75.00 807 11%
Plumbing / Sanitation Rs./Sft BUA 45.00 484 6%
A/C Central A/C Rs./Tonne 75.00 807 11%
D.G./Backup 100% incl. A/C Rs./KVA 30.00 323 4%
UPS 70% of Lighting load Rs./KVA 0.00 0 0%
Stuctured Cabling LAN/ Datacom Rs./Sft. of BUA 0.00 0 0%
Intercom/EPABX 38.00 409 5%
Automation / Security 0.00 0 0%
Lifts 45.00 484 6%
Sub-Station 0.00 0 0%
Fire Alarm 23.00 248 3%
Fire Fighting 45.00 484 6%
Total Cost per Sft. 714.00 7685.43 100%
Amenity Centre
Structure RCC Rs./Sft BUA 350.00 3767 20%
Finishes Rs./Sft BUA 600.00 6458 35%
Electrical wiring & fixtures Rs./Sft BUA 150.00 1615 9%
Plumbing / Sanitation Rs./Sft BUA 75.00 807 4%
A/C Central A/C Rs./Tonne 150.00 1615 9%
D.G./Backup 100% incl. A/C Rs./KVA 100.00 1076 6%
UPS 70% of Lighting load Rs./KVA 0.00 0 0%
Stuctured Cabling LAN/ Datacom Rs./Sft. of BUA 75.00 807 4%
Intercom/EPABX 45.00 484 3%
Automation / Security 30.00 323 2%
Lifts 45.00 484 3%
Sub-Station 25.00 269 1%
Fire Alarm 25.00 269 1%
Fire Fighting 50.00 538 3%
Total Cost per Sft. 1720.00 18513.93 100%
Other Utility Services
Structure RCC Rs./Sft BUA 150.00 1615 27%
CONSTRUCTION COST (PLINTH ARAE BASIS )
FOR BUILDING WORKS
Item Specifications UnitsPlinth Area
Rate (Rs./Sft)
Plinth Area Rate
(Rs./Sqm)Breakup
Finishes Rs./Sft BUA 125.00 1345 23%
Electrical wiring & fixtures Rs./Sft BUA 75.00 807 14%
Plumbing / Sanitation Rs./Sft BUA 50.00 538 9%
A/C Central A/C Rs./Tonne 50.00 538 9%
D.G./Backup 100% incl. A/C Rs./KVA 50.00 538 9%
UPS 70% of Lighting load Rs./KVA 0.00 0 0%
Stuctured Cabling LAN/ Datacom Rs./Sft. of BUA 0.00 0 0%
Intercom/EPABX 0.00 0 0%
Automation / Security 0.00 0 0%
Lifts 0.00 0 0%
Sub-Station 0.00 0 0%
Fire Alarm 25.00 269 5%
Fire Fighting 25.00 269 5%
Total Cost per Sft. 550.00 5920.15 100%
Services Apartments
Structure RCC Rs./Sft BUA 350.00 3767 20%
Finishes Rs./Sft BUA 500.00 5382 29%
Electrical wiring & fixtures Rs./Sft BUA 125.00 1345 7%
Plumbing / Sanitation Rs./Sft BUA 125.00 1345 7%
A/C Central A/C Rs./Tonne 350.00 3767 20%
D.G./Backup 100% incl. A/C Rs./KVA 30.00 323 2%
UPS 70% of Lighting load Rs./KVA 25.00 269 1%
Stuctured Cabling LAN/ Datacom Rs./Sft. of BUA 50.00 538 3%
Intercom/EPABX 25.00 269 1%
Automation / Security 25.00 269 1%
Lifts 30.00 323 2%
Sub-Station 40.00 431 2%
Fire Alarm 25.00 269 1%
Fire Fighting 25.00 269 1%
Total Cost per Sft. 1725.00 18567.75 100%
Apartments
Structure RCC Rs./Sft BUA 350.00 3767 34%
Finishes Rs./Sft BUA 400.00 4306 39%
Electrical wiring & fixtures Rs./Sft BUA 110.00 1184 11%
Plumbing / Sanitation Rs./Sft BUA 75.00 807 7%
A/C Central A/C Rs./Tonne 0.00 0 0%
D.G./Backup 100% incl. A/C Rs./KVA 30.00 323 3%
UPS 70% of Lighting load Rs./KVA 0.00 0 0%
Stuctured Cabling LAN/ Datacom Rs./Sft. of BUA 0.00 0 0%
Intercom/EPABX 0.00 0 0%
Automation / Security 0.00 0 0%
Lifts 25.00 269 2%
Sub-Station 30.00 323 3%
Fire Alarm 0.00 0 0%
Fire Fighting 0.00 0 0%
Total Cost per Sft. 1020.00 10979.19 100%
Commercial
Structure RCC Rs./Sft BUA 450.00 4844 20%
Finishes Rs./Sft BUA 700.00 7535 31%
Electrical wiring & fixtures Rs./Sft BUA 175.00 1884 8%
CONSTRUCTION COST (PLINTH ARAE BASIS )
FOR BUILDING WORKS
Item Specifications UnitsPlinth Area
Rate (Rs./Sft)
Plinth Area Rate
(Rs./Sqm)Breakup
Plumbing / Sanitation Rs./Sft BUA 100.00 1076 4%
A/C Central A/C Rs./Tonne 400.00 4306 18%
D.G./Backup 100% incl. A/C Rs./KVA 50.00 538 2%
UPS 70% of Lighting load Rs./KVA 50.00 538 2%
Stuctured Cabling LAN/ Datacom Rs./Sft. of BUA 50.00 538 2%
Intercom/EPABX 50.00 538 2%
Automation / Security 50.00 538 2%
Lifts 50.00 538 2%
Sub-Station 50.00 538 2%
Fire Alarm 50.00 538 2%
Fire Fighting 50.00 538 2%
Total Cost per Sft. 2275.00 24487.90 100%