Budget Summary

Linac-4 Instrumentation review

CERN, 18.10 2011

Uli Raich BE/BI

Page 2: Budget Summary Linac-4 Instrumentation review CERN, 18.10 2011 Uli Raich BE/BI

EVM, EDH, budget codes …

• EVM: stands for Earned Value Management– The project is subdivided into workpackages– Work package “Beam Instrumentation” has workpackages which

correspond to types of sensors: BCT, BPM, SEM …– Progress must be reported each month– Used by the project management to follow progress

• EDH: Electronic Document Handling– Contains all orders, workshop jobs …

• Budget Codes– Expenditures are assigned to budget lines. The budget codes

are “filled” yearly

10/18/2011 CERN Linac-4 instrumentation review Uli Raich BE/BI

2

Page 3: Budget Summary Linac-4 Instrumentation review CERN, 18.10 2011 Uli Raich BE/BI

Budget review

• At the beginning of the projects non-instrumentation expenditures have been put onto instrumentation budget codes

• EVM work packages do not map onto budget codes• One budget code for several instruments (work

packages)• Initial budget is assigned to work packages

-> Difficult to get an overview

-> Go through all EDH orders since 2007 to assign expenditure to correct work package

10/18/2011 CERN Linac-4 instrumentation review Uli Raich BE/BI

3

Page 4: Budget Summary Linac-4 Instrumentation review CERN, 18.10 2011 Uli Raich BE/BI

Budget Summary

Instrument 2007 2008 2009 2010 2011 Still to be paid

Totalspent

Grand total

foreseen

Faraday Cup 20947 19944 0 40891 40891 61000

BCT 1428 38052 111710 145187 200000 296378 500000 390000

BPMs 11148 23249 117208 313165 200000 453623 1 MCHF 800000

BSM 198500

15408 15128 40000 229037 270000 270000

Emittance M 47108 163374 2633 598 173971 60000 387685 450000 480000

BLMs 63680 75000 150000 63680 133000

BTVs Will be replaced by SEMGrids

Profile 15300 77630 73192 77629 373300 660000 754751 1.4 MCHF

1610000+200000 BTV

10/18/2011 CERN Linac-4 instrumentation review Uli Raich BE/BI

4

Page 5: Budget Summary Linac-4 Instrumentation review CERN, 18.10 2011 Uli Raich BE/BI

Budget Summary (2)

• Emittance Meter oversprends by 80 kCHf(initial estimation 400kCHF for 2 instruments, later corrected to 480 kCHF for 1 ½ instruments

• BCTs will overspend by 110 kCHF (390 kCHF -> 600 kCHF) (more different types than initially foreseen)

• BPMs will overspend by 200 kCHF (800 kCHF -> 1000 kCHF)

• There will be no BTVs but these will be replaced by SEMGrids (which are more expensive)

10/18/2011 CERN Linac-4 instrumentation review Uli Raich BE/BI

5

Page 6: Budget Summary Linac-4 Instrumentation review CERN, 18.10 2011 Uli Raich BE/BI

Budget Summary (3)

• BLMs: The budget was already been reviewed in March 2011. Very little or no overspending is foreseen

• SEMGrids, Wire Scanners and TV screensThe budget was overestimated (fortunately!)– Old electronics used 1 electronics card + 1 cable per channel

and the cost estimate was based on this– New electronics uses 1 multi conductor cable + 1 electronics

card per sensor plane.

Globally: We need to reshuffle budgets internally but should be able to stay within the allocate budgets. We will however also not under spend!

10/18/2011 CERN Linac-4 instrumentation review Uli Raich BE/BI

6