27
© California ISO 2019 – CAISO Public © California ISO 2019 – CAISO Public Irina Green, Senior Advisor, Regional Transmission, California ISO NERC SPIDER WG, Chicago October 8-9 2019 BPS Impacts from Behind the Meter DER Reactive Power Support and Frequency Support in Different Operating Modes

BPS Impacts from Behind the Meter DER Reactive Power

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

© California ISO 2019 – CAISO Public© California ISO 2019 – CAISO Public

Irina Green, Senior Advisor, Regional Transmission,California ISO

NERC SPIDER WG, Chicago October 8-9 2019

BPS Impacts from Behind the Meter DER Reactive Power Support and Frequency

Support in Different Operating Modes

© California ISO 2019 – CAISO Public

Page 2

NERC SPIDER (System Planning Impact from DER) WG – DER_A Modeling Guideline

New DER_A dynamic model now released in all major positive sequence simulation software platforms.

NERC SPIDERWG developed guideline for how to use the DER_A model, and how to develop its parameter values

The Guideline is approved by NERC Provides detailed understanding of the

model Provides recommendations for

developing parameters for the model and values of DER_A parameters to use

© California ISO 2019 – CAISO Public

Page 3

Modeling DER in Power Flow and Dynamic Stability

U-DER transformer and feeder modeled. DER modeled as generator

R-DER is modeled as part of composite load

© California ISO 2019 – CAISO Public

Page 4

DER_A Model in Dynamic Stability

Simplified version of the second generation generic renewable energy system models (i.e., regc_a, reec_b, repc_a, lhvrt, lhfrt)

More detailed and flexible than PVD1 model used previously Currently, may represent only aggregated solar PV Standalone or part of composite load model These two models are identical Available in all widely-used software platforms The following studies are of the behind-the-meter DER,

which is a part of composite load model

© California ISO 2019 – CAISO Public

Page 5

DER_A Model Features

Constant power factor and constant reactive power control modes. Allows voltage control to be active along with PF/Q control

Active power-frequency control with droop and asymmetric dead-band - was studied

Voltage control with proportional control and asymmetric dead-band - was studied

Fraction of resources tripping or entering momentary cessation at low and high voltage, includes a timer feature

Fraction of resources restoring output following a low or high voltage or frequency condition

Active power ramp rate limits during return to service after trip or enter service following a fault or during frequency response

Active-reactive current priority options Capability to represent generating or energy storage resources.

© California ISO 2019 – CAISO Public

Page 6

DER_A Block Diagram – Active Power-Frequency Control

Freq flag = 1, control enabled

Frequency error

Frequency signal dead-band

Droop gains

Power order time constant

Also, frequency tripping logic control

© California ISO 2019 – CAISO Public

Page 7

Reactive Power-Voltage Controls Pf Flag = 0 constant Q control, = 1 – constant power factor

control, Pf Flag =1 was used

If Kqv=0, no voltage control With dynamic voltage control, SPIDER Guideline recommended

Kqv=5, Dbd1= -0.12, Dbd2=0.1

© California ISO 2019 – CAISO Public

Page 8

Active –Reactive Priority Logic

Type flag = 1 – generator (Ipmin = 0), =0 – storage (Ipmin=-Ipmax) Pqflag = 0 – Q priority, =1- P priority Inverters prior to IEEE 1547-2018 Standard not required to have

voltage control – P priorrity After the approval of IEEE 1547-2018 - voltage control, Q priority

© California ISO 2019 – CAISO Public

Page 9

CAISO Studies of DER_A Model as Part of Composite Load. Voltage and Frequency Regulation by DER

CAISO models behind the meter DER as a part of load for the last two years. Software used was GE PSLF Version 21.07

2029 Summer Peak case for voltage studies, 2029 Spring off-peak for frequency studies

The peak case has high load, thus stalling of single-phase air-conditioners with faults

The off-peak case has high dispatch from behind-the-meter DER

DER_A parameters as recommended by SPIDER Modeling Guideline, 70% new, 30% old inverters

© California ISO 2019 – CAISO Public

Page 10

Case Studied – 2029 Summer Peak, Behind the Meter DER at 20%

No DER impact in the peak case because of its low amount (280 MW in the CAISO).

Increased amount of behind-the-meter DER to 20% of the installed capacity

Behind the meter DER installed capacity 18600 MW, dispatched 3720 MW (increased from 280 MW)

PG&E (Northern California) Behind the meter DER installed capacity 9270 MW Behind the meter DER dispatched 1854 MW

© California ISO 2019 – CAISO Public

Page 11

Contingency Studied, power flow case with 20% Behind-the-Meter DER dispatched

Heavily loaded 500 kV line, Tesla –Metcalf in San Francisco Bay Area, highest loss of load in PG&E

3-phase fault on the sending end with normal clearance (4 cycles)

DER cases studied: No voltage control, P priority No voltage control, Q priority Voltage control, P priority Voltage control, Q priority Voltage control, Q priority, DER

MVAR at 0.95 lagging Cases with voltage control, kqv=5,

dead-band +0.1/-0.12

© California ISO 2019 – CAISO Public

Page 12

Loss of Composite Load and DER with Contingency

No criteria violations with this contingency 181 MW reduction in lost load if behind the meter DER

have voltage control and Q priority

© California ISO 2019 – CAISO Public

Comparison of the five cases, Two 230 kV buses close to the fault (Westley and Peabody). Voltage

Page 13

Higher recovery voltage with voltage control and Q priority Power factor of the DER in power flow doesn’t make a difference Without voltage control, P and Q priority have same voltage

© California ISO 2019 – CAISO Public

Comparison of the five cases, Westley and Peabody 230 kV buses. Net load

Page 14

Less load loss with voltage control and Q priority Power factor in power flow doesn’t make a difference Without voltage control, P and Q priority have same load loss

© California ISO 2019 – CAISO Public

Comparison of the five cases, Westley 230 kV bus. DER real and reactive output

Page 15

Higher DER loss with voltage control and Q priority in transient period

Real PowerReactive Power

© California ISO 2019 – CAISO Public

Comparison of the five cases, Peabody 230 kV bus. DER real and reactive output

Page 16

Higher DER loss with lagging power factor in transient period

Real PowerReactive Power

© California ISO 2019 – CAISO Public

Conclusions from Voltage Studies

If Behind the Meter DER control voltage, it is not during steady state conditions, but with faults, during transient voltage recovery period.

Voltage regulation on the Behind the Meter DER can help with faults ride through and may allow the induction motors not to stall.

There is a difference in the load and DER loss with different voltage control settings of the DER, but it is mainly during transient recovery period (less than 6 seconds after the fault)

There is less load reduction if DER have voltage control

Page 17

© California ISO 2019 – CAISO Public

Study of Frequency Response from Behind the Meter DER

2029 Summer off-peak case, with reduced headroom WECC generation in the case, not including pumps 133,146

MW, headroom 12,800 MW Behind the meter DER installed capacity in the CAISO –

18,600 MW, dispatch 15,048 MW Frequency droop assumed at 7.14% (1/14) as recommended

by the Reliability Guideline on DER Parameterization Studied outage of two Palo Verde nuclear units, 2750 MW Run dynamic simulation for 60 seconds

Page 18

© California ISO 2019 – CAISO Public

Frequency Response from Behind the Meter DER Settling frequency Without DER frequency response 59.906 Hz With DER frequency response 59.912 Hz Difference is insignificant

Frequency nadir Without DER frequency response 59.810 Hz With DER frequency response 59.830 Hz

With frequency control from DER DER response after 60 sec 234 MW, 1.5% of dispatch Governor response 1838 MW, 2.7% of dispatch Total 2072 MW

Without frequency control from DER Governor response 2004 MW, 3% of dispatch Net Load reduction 841 MW

Page 19

© California ISO 2019 – CAISO Public

Outage of Two Palo Verde Units 2029 off-PeakFrequency on Midway 500 kV bus

Page 20

Red – no frequency control from DER

Blue – with frequency control

© California ISO 2019 – CAISO Public

DER Output with Frequency Control. Outage of two Palo Verde Units

Page 21

Normalized DER output for SCE and SDG&E DER

Response of other DER is similar

3.25% response at nadir and 1.5% at settling frequency

Net Load reduction 1007 MW

© California ISO 2019 – CAISO Public

Impact of DER MVA Base For Type 2 DG model, the Pdgen and Qdgen values from the

load table are used in the cmpldwg model. If DGmbase is negative, the actual MVA base calculated as Pdgen / abs(DGmbase)

In the base case: "DGtype" 2 "dgdatno" -100 "dgmbase" -0.9, thus DER are loaded 90%

DER MVA base = -1.0, with frequency control Settling frequency 59.909 Hz, nadir 59.816 Hz No frequency response from DER, because DER don’t have

headroom Governor response 2004 MW, same as without frequency

control from DER

Page 22

© California ISO 2019 – CAISO Public

DER Output with Frequency Control and MVA base = 1. Outage of two Palo Verde Units

Page 23

Normalized DER output for SCE and SDG&E DER

Response of other DER is similar

No frequency response because no headroom

Net Load reduction 838 MW

© California ISO 2019 – CAISO Public

DER Output with Frequency Control and MVA base = 0.8 Outage of two Palo Verde Units

Page 24

Settling frequency 59.912 Hz Nadir 59.830 Hz Normalized DER output for

SCE and SDG&E DER Response of other DER is

similar 4.2% response at nadir and

2.0% at settling frequency Total system DER response after 60 sec 267 MW Governor response 1811 MW Total 2078 MW

Net Load reduction 1034 MW

© California ISO 2019 – CAISO Public

Outage of two Palo Verde Units. 2029 Spring off-Peak. Comparison of DER Frequency Response

Page 25

© California ISO 2019 – CAISO Public

Page 26

Conclusions from Frequency Studies

If DER have frequency control, their response to drop in frequency depends not only on the droop and dead-band, but also on their headroom, which is modeled through the MVA base

With 10%-20% headroom, DER response makes rather insignificant difference, if there is sufficient response from units with responsive governors

DER response replaces response from other frequency-responsive units

DER frequency response has impact mainly on the frequency nadir, but not on the settling frequency

© California ISO 2019 – CAISO Public

QUESTIONS?COMMENTS?

Please send your comments to Irina [email protected]

Page 27