Bond Update August 14, 2017

Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Bond Update August 14, 2017

Page 2: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Bond Summary: Total Expenditures to Date • $71,320,000 Budget

• $66,391,555 Encumbered

• 93% Of Total

Schedules • Package A (Jones, RR, CTE, & Ag.)

• $37,744,240 Contract

• Complete

• Package D (HVAC Junior High West / Schultz) • $8,579,736 Contract

• Complete

• Package E 1(Re-Roof Junior High School East) • $780,130 Contract

• Ahead of Schedule

• Complete by Spring 2018

• Package E 2(Junior High School East HVAC) • $2,136,334 Contract

• On Schedule

• Complete by Fall 2017

Page 3: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

• Budget Review • $37,744,240 Contract Amount

• $34,393,467 Billed to Date (91%)

Package A: (Jones, Roberts Road, CTE/Ag)

Page 4: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

High School CTE & Ag: • Project Update

• Painting complete

• Flooring prep underway

• HVAC complete

• Ceiling grid complete

• Electrical near complete

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/24

• Look Ahead • Flooring

• Electrical

• Paint booth

• Move-in

Page 5: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Jones Elementary School: • Project Update

• Substantial Completion

• Furniture installed

• Teacher’s items moved in

• Playground being installed

• Faculty In-service August 8, 2017

• Schedule • 25 rain delays claimed (as of 3/2/17)

• Finished on schedule (with delays)

• Look Ahead • Books to be installed 8/15

• Final clean underway

• Punch list items ongoing

Page 6: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Jones Elementary School: • Project Update

• Substantial Completion

• Furniture installed

• Teacher’s items moved in

• Playground being installed

• Faculty In-service August 8, 2017

• Schedule • 25 rain delays claimed (as of 3/2/17)

• Finished on schedule (with delays)

• Look Ahead • Books to be installed 8/15

• Final clean underway

• Punch list items ongoing

Page 7: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Jones Elementary School: • Project Update

• Substantial Completion

• Furniture installed

• Teacher’s items moved in

• Playground being installed

• Faculty In-service August 8, 2017

• Schedule • 25 rain delays claimed (as of 3/2/17)

• Finished on schedule (with delays)

• Look Ahead • Books to be installed 8/15

• Final clean underway

• Punch list items ongoing

Page 8: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Jones Elementary School: • Project Update

• Substantial Completion

• Furniture installed

• Teacher’s items moved in

• Playground being installed

• Faculty In-service August 8, 2017

• Schedule • 25 rain delays claimed (as of 3/2/17)

• Finished on schedule (with delays)

• Look Ahead • Books to be installed 8/15

• Final clean underway

• Punch list items ongoing

Page 9: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Jones Elementary School: • Project Update

• Substantial Completion

• Furniture installed

• Teacher’s items moved in

• Playground being installed

• Faculty In-service August 8, 2017

• Schedule • 25 rain delays claimed (as of 3/2/17)

• Finished on schedule (with delays)

• Look Ahead • Books to be installed 8/15

• Final clean underway

• Punch list items ongoing

Page 10: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

High School CTE & Ag: • Project Update

• Painting complete

• Flooring prep underway

• HVAC complete

• Ceiling grid complete

• Electrical near complete

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/24

• Look Ahead • Flooring

• Electrical

• Paint booth

• Move-in

Page 11: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

High School CTE & Ag: • Project Update

• Painting complete

• Flooring prep underway

• HVAC complete

• Ceiling grid complete

• Electrical near complete

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/24

• Look Ahead • Flooring

• Electrical

• Paint booth

• Move-in

Page 12: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

High School CTE & Ag: • Project Update

• Painting complete

• Flooring prep underway

• HVAC complete

• Ceiling grid complete

• Electrical near complete

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/24

• Look Ahead • Flooring

• Electrical

• Paint booth

• Move-in

Page 13: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

High School CTE & Ag: • Project Update

• Painting complete

• Flooring prep underway

• HVAC complete

• Ceiling grid complete

• Electrical near complete

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/24

• Look Ahead • Flooring

• Electrical

• Paint booth

• Move-in

Page 14: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

High School CTE & Ag: • Project Update

• Painting complete

• Flooring prep underway

• HVAC complete

• Ceiling grid complete

• Electrical near complete

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/24

• Look Ahead • Flooring

• Electrical

• Paint booth

• Move-in

Page 15: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

High School CTE & Ag: • Project Update

• Painting complete

• Flooring prep underway

• HVAC complete

• Ceiling grid complete

• Electrical near complete

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/24

• Look Ahead • Flooring

• Electrical

• Paint booth

• Move-in

Page 16: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

High School CTE & Ag: • Project Update

• Painting complete

• Flooring prep underway

• HVAC complete

• Ceiling grid complete

• Electrical near complete

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/24

• Look Ahead • Flooring

• Electrical

• Paint booth

• Move-in

Page 17: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

High School CTE & Ag: • Project Update

• Painting complete

• Flooring prep underway

• HVAC complete

• Ceiling grid complete

• Electrical near complete

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/24

• Look Ahead • Flooring

• Electrical

• Paint booth

• Move-in

Page 18: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Roberts Road: • Project Update

• HVAC complete

• Carpet 85% complete

• Painting complete

• Ceiling grid complete

• Furniture installed

• Prepping for gym floor

• Working on new drives

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/16

• Look Ahead • Fire Marshall Review 8/15

• Install gym flooring

• Pour new entry drives

• landscaping

Page 19: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Roberts Road: • Project Update

• HVAC complete

• Carpet 85% complete

• Painting complete

• Ceiling grid complete

• Furniture installed

• Prepping for gym floor

• Working on new drives

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/16

• Look Ahead • Fire Marshall Review 8/15

• Install gym flooring

• Pour new entry drives

• landscaping

Page 20: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Roberts Road: • Project Update

• HVAC complete

• Carpet 85% complete

• Painting complete

• Ceiling grid complete

• Furniture installed

• Prepping for gym floor

• Working on new drives

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/16

• Look Ahead • Fire Marshall Review 8/15

• Install gym flooring

• Pour new entry drives

• landscaping

Page 21: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Roberts Road: • Project Update

• HVAC complete

• Carpet 85% complete

• Painting complete

• Ceiling grid complete

• Furniture installed

• Prepping for gym floor

• Working on new drives

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/16

• Look Ahead • Fire Marshall Review 8/15

• Install gym flooring

• Pour new entry drives

• landscaping

Page 22: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Roberts Road: • Project Update

• HVAC complete

• Carpet 85% complete

• Painting complete

• Ceiling grid complete

• Furniture installed

• Prepping for gym floor

• Working on new drives

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/16

• Look Ahead • Fire Marshall Review 8/15

• Install gym flooring

• Pour new entry drives

• landscaping

Page 23: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package D: (Junior High School West HVAC / Schultz HVAC)

• Project Update • Both projects complete

• Budget Review • $5,724,633 JHSW

• $112,528.55 CO#1 JHSW

• $2,855,103 SJHS

• Look Ahead • Complete move-in

• Punch list

• Final clean

• Demonstrations

Page 24: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package D: (Junior High School West HVAC / Schultz HVAC)

• Project Update • Both projects complete

• Budget Review • $5,724,633 JHSW

• $112,528.55 CO#1 JHSW

• $2,855,103 SJHS

• Look Ahead • Complete move-in

• Punch list

• Final clean

• Demonstrations

Page 25: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package D: (Junior High School West HVAC / Schultz HVAC)

• Project Update • Both projects complete

• Budget Review • $5,724,633 JHSW

• $112,528.55 CO#1 JHSW

• $2,855,103 SJHS

• Look Ahead • Complete move-in

• Punch list

• Final clean

• Demonstrations

Page 26: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package D: (Junior High School West HVAC / Schultz HVAC)

• Project Update • Both projects complete

• Budget Review • $5,724,633 JHSW

• $112,528.55 CO#1 JHSW

• $2,855,103 SJHS

• Look Ahead • Complete move-in

• Punch list

• Final clean

• Demonstrations

Page 27: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package D: (Junior High School West HVAC / Schultz HVAC)

• Project Update • Both projects complete

• Budget Review • $5,724,633 JHSW

• $112,528.55 CO#1 JHSW

• $2,855,103 SJHS

• Look Ahead • Complete move-in

• Punch list

• Final clean

• Demonstrations

Page 28: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package D: (Junior High School West HVAC / Schultz HVAC)

• Project Update • Both projects complete

• Budget Review • $5,724,633 JHSW

• $112,528.55 CO#1 JHSW

• $2,855,103 SJHS

• Look Ahead • Complete move-in

• Punch list

• Final clean

• Demonstrations

Page 29: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package D: (Junior High School West HVAC / Schultz HVAC)

• Project Update • Both projects complete

• Budget Review • $5,724,633 JHSW

• $112,528.55 CO#1 JHSW

• $2,855,103 SJHS

• Look Ahead • Complete move-in

• Punch list

• Final clean

• Demonstrations

Page 30: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package E1: (Junior High School East Roof Replacement)

• Project Update • Framing 100% complete

• Roof panels being installed on gym

• Budget Review • $780,130 Contract

• Schedule • Finish January 2018

• Look Ahead • Panel installation to resume 8/15

Page 31: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package E1: (Junior High School East Roof Replacement)

• Project Update • Framing 100% complete

• Roof panels being installed on gym

• Budget Review • $780,130 Contract

• Schedule • Finish January 2018

• Look Ahead • Panel installation to resume 8/15

Page 32: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package E2: (Junior High School HVAC Replacement/Relocation)

• Project Update

• HVAC system complete

• Move-in underway

• Budget Review • $2,136,334 Contract

• Schedule • Summer 2017

• Look Ahead • Door hardware

• HVAC balancing/controls

• Final clean

Page 33: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package E2: (Junior High School HVAC Replacement/Relocation)

• Project Update

• HVAC system complete

• Move-in underway

• Budget Review • $2,136,334 Contract

• Schedule • Summer 2017

• Look Ahead • Door hardware

• HVAC balancing/controls

• Final clean

Page 34: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package E2: (Junior High School HVAC Replacement/Relocation)

• Project Update

• HVAC system complete

• Move-in underway

• Budget Review • $2,136,334 Contract

• Schedule • Summer 2017

• Look Ahead • Door hardware

• HVAC balancing/controls

• Final clean

Page 35: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package E2: (Junior High School HVAC Replacement/Relocation)

• Project Update

• HVAC system complete

• Move-in underway

• Budget Review • $2,136,334 Contract

• Schedule • Summer 2017

• Look Ahead • Door hardware

• HVAC balancing/controls

• Final clean

Page 36: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Package E2: (Junior High School HVAC Replacement/Relocation)

• Project Update

• HVAC system complete

• Move-in underway

• Budget Review • $2,136,334 Contract

• Schedule • Summer 2017

• Look Ahead • Door hardware

• HVAC balancing/controls

• Final clean

Page 37: Board Update October 21, 2015 - Waller ISD · • Project Update • Framing 100% complete • Roof panels being installed on gym • Budget Review • $780,130 Contract • Schedule

Thank You . . .