Bond Update October 9, 2017

Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

Bond Update October 9, 2017

Page 2: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

Bond Summary: Total Expenditures to Date • $71,320,000 Bond

• $66,558,766 Encumbered

• 93% Of Total

Schedules • Package A (Jones, RR, CTE, & Ag.)

• $37,744,240 Contract

• Complete

• Package D (HVAC Junior High West / Schultz) • $8,579,736 Contract

• Complete

• Package E 1(Re-Roof Junior High School East) • $780,130 Contract

• Complete

• Package E 2(Junior High School East HVAC) • $2,136,334 Contract

• Complete

Page 3: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

• Outstanding work • HVAC pumps (Jones)

• Door locks (Jones and Roberts Road)

• Hydromulching / Weeding (Jones)

• Sound (Jones and Roberts Road)

• Spray booth (High School)

Package A: (Jones, Roberts Road, CTE/Ag)

Page 4: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

• Project Update • Painting complete

• Flooring prep underway

• HVAC complete

• Ceiling grid complete

• Electrical near complete

• Schedule • On Schedule for Fall 2017 Open

• Anticipated finish 8/24

• Look Ahead • Flooring

• Electrical

• Paint booth

• Move-in

Page 5: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work
Page 6: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work
Page 7: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work
Page 8: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work
Page 9: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work
Page 10: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work
Page 11: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work
Page 12: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work
Page 13: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work
Page 14: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work
Page 15: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

Package D: (Junior High School West HVAC / Schultz HVAC)

• Outstanding work • Replace two lights (Schultz)

• Repair cycling A/C unit (Schultz)

• Repair broken door (WJHSW)

Page 16: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

Package D: (Junior High School West HVAC / Schultz HVAC)

• Project Update • Both projects complete

• Budget Review • $5,724,633 JHSW

• $112,528.55 CO#1 JHSW

• $2,855,103 SJHS

• Look Ahead • Complete move-in

• Punch list

• Final clean

• Demonstrations

Page 17: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

Package D: (Junior High School West HVAC / Schultz HVAC)

• Project Update • Both projects complete

• Budget Review • $5,724,633 JHSW

• $112,528.55 CO#1 JHSW

• $2,855,103 SJHS

• Look Ahead • Complete move-in

• Punch list

• Final clean

• Demonstrations

Page 18: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

Package E2: (Junior High School HVAC Replacement/Relocation)

• Outstanding work • Install two lights

Page 19: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

Package E2: (Junior High School HVAC Replacement/Relocation)

• Project Update

• HVAC system complete

• Move-in underway

• Budget Review • $2,136,334 Contract

• Schedule • Summer 2017

• Look Ahead • Door hardware

• HVAC balancing/controls

• Final clean

Page 20: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

Package E1: (Junior High School East Roof Replacement)

• Outstanding work • None

Page 21: Board Update October 21, 2015 - Waller ISD...• $780,130 Contract • Complete • Package E 2(Junior High School East HVAC) • $2,136,334 Contract • Complete • Outstanding work

Thank You . . .