City of Bishkek & European Bank for Reconstruction & Development (EBRD)
Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final
Final | 9 November 2016
This report takes into account the particular
instructions and requirements of our client.
It is not intended for and should not be relied
upon by any third party and no responsibility
is undertaken to any third party.
Job number 246385-00
Ove Arup & Partners International Ltd
The Arup Campus
Blythe Gate
Blythe Valley Park
Solihull B90 8AE
United Kingdom
www.arup.com
ESAP/Final | | 9 November 2016
Document Verification
Job title Bishkek Solid Waste Management Project Job number
246385-00
Document title Environmental and Social Action Plan File reference
Document ref
Revision Date Filename Bishkek ESAP_26_02_2016.docx
Draft 1 26 Feb
2016
Description First draft
Prepared by Checked by Approved by
Name Olga Skotareva
Chris Stocks Colette Curran
Signature
Draft 2 31 Aug
2016
Filename Bishkek SWP ESAP Draft 2_31_08_2016.docx Description Second draft
Prepared by Checked by Approved by
Name Olga Skotareva Colette Curran -
Signature
Final 9 Nov
2016
Filename Bishkek SWP ESAP Final_8_11_2016.docx Description Final
Prepared by Checked by Approved by
Name Olga Skotareva Colette Curran Helen Davis
Signature
Issue Document Verification with Document
City of Bishkek & European Bank for Reconstruction & Development
(EBRD)
Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Contents
Page
Abbreviations 1
1 Introduction 2
2 Environmental and Social Action Plan 3
City of Bishkek & European Bank for Reconstruction & Development
(EBRD)
Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016 Page 1
Abbreviations
BADS Bishkek Authorised Disposal Site
EBRD European Bank for Reconstruction and Development
ESAP Environmental and Social Action Plan
ESIA Environmental and Social Impact Assessment
ESMS Environmental and Social Management System
ESMMP Environmental and Social Management and Monitoring Plan
FS Feasibility Study (for the proposed Bishkek Solid Waste
Management Project)
KPIs Key Performance Indicators
LRP Livelihood Restoration Plan
MBT Mechanical Biological Treatment
PIU Project Implementation Unit
PRs Performance Requirements
SEP Stakeholder Engagement Plan
SPV Special Purpose Vehicle ‘Bishkek Sanitary Landfill’
City of Bishkek & European Bank for Reconstruction & Development
(EBRD)
Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016 Page 2
1 Introduction
The City of Bishkek (the ‘City’) seeks to improve its municipal solid waste
(‘MSW’) management system and has been working with the European Bank for
Reconstruction and Development (the ‘EBRD’ or the ‘Bank’), to invest in a viable
development project. The proposed Bishkek Solid Waste Management Project
(the ‘Project’) comprises a sovereign loan of EUR 11 million and a grant of EUR
11 million to the Kyrgyz Republic to be on-lent to the City for the benefit of the
municipal solid waste management company Tazalyk (‘Tazalyk’) and a Special
Purpose Vehicle ‘Bishkek Sanitary Landfill’ (the ‘Company’ or ‘SPV’). The loan
agreement was signed in 2013. The Project will support priority investments in
the waste management segment – primarily in waste collection and disposal.
The Bank commissioned a Feasibility Study (the ‘FS’) that was completed in
2013, alongside the Environmental and Social Impact Assessment (ESIA) and an
Environmental and Social Action Plan (ESAP). The FS determined a priority
investment programme (the ‘PIP’), evaluated its benefits, and assessed a proposed
site for the new landfill, including assessing its environmental and social impacts.
Since then, the City has taken a decision to use a different site for the new landfill
to the north of the existing dumpsite, rather than the site assessed in the FS.
To support the Project, Ove Arup and Partners International Ltd. (the ‘Consultant’
or ‘Arup’) have been appointed by the City to undertake an Environmental and
Social gap analysis for the newly proposed site, and update the necessary
technical, environmental, and social studies and plans where practicable.
This document provides an updated Environmental and Social Action Plan for
mitigation of the environmental and social impacts and to move the Project
towards compliance with EBRD’s Environmental and Social (E&S) Policy (2014)
and its Performance Requirements (PRs).
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 3
2 Environmental and Social Action Plan
The following environmental and social actions are required to fulfil the requirements of the EBRD’s E&S Policy (2014), within the timescale
indicated.
Responsibility for discharging ESAP actions will lie with the City of Bishkek supported by the Project Implementation Unit (PIU), Talazyk,
Contractor and the Landfill Operator, and will be passed to the relevant sub-contractors, if appropriate. The PIU (with support of consultants)
will also be responsible for monitoring actions discharged to contractors, and for ensuring completion within the agreed timescale.
All actions, documents and plans required by this ESAP will need to be agreed with the Lender. The PIU will be required to report compliance
with the ESAP to the EBRD through an Annual Environmental and Social Report (AESR). The AESR template is to be provided by the
EBRD.
Additionally, compliance with the ESAP will be assured through independent checks and audits undertaken on behalf of the Lenders.
When relevant requirements from the ESAP previously developed in 2012 are included in the table below, they are marked as such in ‘Status’
column.
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
PR1 Assessment and Management of Environmental and Social (E&S) Impacts and Issues
1.1 Finalise the transfer of land
ownership and re-
categorisation of the
proposed site to be
appropriate for the
Legislative
compliance
Kyrgyz
regulations
EBRD PR1
Department of
Architecture and
Masterplanning of
Bishkek City,
Prior to
commencement of
construction
works
Land transfer completed.
Documents confirming land
ownership are in place.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 4
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
construction of a landfill and
be under the ownership of
the Municipal Council of
Bishkek. (Appropriate
changes are to be included in
the City Masterplan.).
PIU
1.2 Obtain necessary
construction, environmental
and sanitary permits prior to
rehabilitation of the
dumpsite, construction of the
new landfill and
development of associated
sorting and MBT plants as
well as additional
composting of green waste.
Among others, these to
include:
(i) formal approval by the
Chief Sanitary Officer of the
SPZ compliance for the new
landfill location;
(ii) approval of the State
Ecological Expertise for the
new landfill location.
Legislative
compliance.
Kyrgyz
regulations
EBRD PR1
Contractor Prior to
commencement of
construction
works
A list of required and obtained
approvals and permits is in place
alongside the physical evidence of
permits obtained.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 5
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
1.3 If required for the State
Ecological Expertise for the
new landfill location,
prepare an Addendum to the
FS in addition to the
prepared updated ESIA
documents, and undertake
public hearings in
accordance with the law.
Legislative
compliance.
Minimise impact on
environment and
community by
identifying and
implementing
adequate mitigation
measures.
Kyrgyz
regulations
PIU with PIU
support
consultants
Q3 2016
Prior to
commencement of
construction
works
Assessments and documentation
required to obtain the State
Ecological Expertise for the new
landfill location is in place.
Evidence of conducted public
hearings.
Approval by the State Ecological
Expertise is in place.
1.4 Secure necessary operational
permits and permissions for
all new operations.
Compliance with
local regulations.
Local
regulations
EBRD PR1
PIU with PIU
support
consultant,
Landfill Operator
Prior to
commencement of
operation
A list of required and obtained
permits is in place alongside the
physical evidence of permit
applications, and permits granted.
Conditions of permits incorporated
into operational plans and tender
requirements.
2012 ESAP
requirement
1.5 Review existing
environmental, Health &
Safety and social practices to
ensure they are fit for
purpose and aligned with
legal requirements and
EBRD standards.
Minimise H&S risk
to workers.
Effective
management of
environmental and
social issues.
EBRD PR1,
In line with
recognised
E&S
management
systems (e.g.
ISO 14001
and OHSAS
18001).
Tazalyk own
resources
By Q4 2016 Record of changes implemented as
a result of E&S review.
Evidence of the E&S review
having been undertaken.
.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 6
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
1.6 Develop and implement an
E&S Management System.
Effective
management of
environmental and
social issues.
EBRD PR1,
EBRD PR2.
EBRD PR4.
In line with
EBRD PR1,
ISO 14001
and OHSAS
18001
requirements
Contractor own
resources
Develop ESMS 4
months prior to
construction
works.
ESMS based on the pertinent
requirements of ISO14001 and
OHSAS 18001 in place and
operational.
Policy, required procedures and
plans are in place and implemented.
A clear commitment from senior
management in the Environmental
Policy to ensure adequate resource
is provided to enable staff to deliver
requirements.
An organisational chart clearly
shows lines of ESMS
responsibility, and reporting.
Job descriptions with clear Roles
and Responsibilities.
Evidence of ESMS monitoring.
Evidence of training provided.
ESMS Audit Reports.
1.7 Implement the
Environmental and Social
Management and
Monitoring Plan (ESMMP)
developed as part of the
2012 ESIA.
Minimise impact on
environment and
community by
identifying and
implementing
adequate mitigation
EBRD PR1
Contractor own
resources,
PIU with PIU
support
consultants
As per the
ESMMP
Plans and procedures required by
the ESMMP are in place.
Evidence of implementation is in
place.
Record of monitoring of ESMMP
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 7
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
ESMMP should be seen in
conjunction with the
Addendum to ESIA
prepared by Arup.
Should any Project
documents be reviewed or
any conditions to the Project
design and implementation
added the ESMMP should
be reviewed and amended
accordingly.
measures.
implementation is in place.
1.8 Include appropriate clauses
to tender documentation,
ESMS and contractor
documentation to ensure that
national and Lender
requirements regarding
environmental, social and
health and safety are
imposed on to the
construction, rehabilitation
and, if relevant, operation
Minimise impact on
environment and
community by
identifying and
implementing
adequate mitigation
measures.
EBRD PR1,
Best Practice1
PIU with PIU
support
consultants,
Contractor own
resources
Prior to
construction
Relevant contract clauses in tender
and contractor-related
documentation.
1 The term Best Practice refers to non-legislative procedures and guidelines (may also be legal requirements in other countries) that are internationally recognised and
accepted as being correct or most effective.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 8
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
contractors.
Contract clauses for all sub-
contractors should ensure all
relevant management and
monitoring requirements
included in the ESMMP are
binding and enforced.
1.9 Implement actions related to
technical requirements for
landfill design presented in
Appendix A of this ESAP.
Safe design,
compliance with
EU requirements.
EBRD PR1,
PR3,
EU
Directives :
EU Waste
Directive
2008/98/EC,
EU Landfill
Directive
99/31/EC,
EU Industrial
Emissions
Directive
(integrated
pollution
prevention and
control)
2010/75/EU.
PIU support
consultants as
necessary,
Designer,
Contractor
During design
stage and prior to
commencement of
construction
works.
Completed design.
Record of design checks against
actions recommended in technical
requirements.
Relevant procedures and records of
implementation and monitoring are
in place.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 9
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
1.10 Develop and implement a
system of waste transfer and
acceptance recording
allowing information on the
waste collected and received
at the landfill to be gathered
and reported.
Effective system of
waste transfer and
acceptance.
Minimise impact on
environment.
EBRD PR 1
EBRD PR 3
Best practice
EU Waste
Directive
2008/98/EC,
EU Landfill
Directive
99/31/EC
Contractor own
resources,
Landfill Operator
Prior to start of
operation
A system is in place.
Reports on waste collected and
received.
1.11 As a part of ESMMP,
develop landfill
environmental monitoring
system including additional
groundwater monitoring.
The information collected
should be in line with the
recording and monitoring
requirements of the EU
Waste and Landfill
Directives.
Prevent
environmental
pollution incidents
and accidents
EBRD PR1,
EBRD PR3,
EU Waste
Directive
2008/98/EC,
EU Landfill
Directive
99/31/EC
PIU support
consultant
Prior to
commencement of
operation
Environmental monitoring plan is
in place.
Records of monitoring.
1.12 Develop and implement an
Operational Management
Plan (OMP) and procedures
for its implementation.
Effective and
compliant
management
Clear operational
procedures enable
EBRD PR1
Best Practice
PIU and PIU
support
consultant,
Landfill Operator
Prior to
commencement of
operation.
Draft OMP and Operation manuals
and plans and procedures
completed.
Manual and plans linked to job
descriptions and necessary training
2012 ESAP
requirement
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 10
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
individual staff
members to deliver
good quality work
and achieve desired
goals for a new
system with limited
environmental and
social impacts.
requirements.
1.13 Document and rank existing
waste collection points for
improvement measures.
Identify new collection
points in areas not served at
present.
Development of
improvement plan for
collection points in the city
and monitoring system
Development of
maintenance and
replacement plan for
containers and collection
points.
Effective waste
collection system
Reduce waste
deposits around
collection bins and
in other non-
designated
locations in the city
Best Practice Tazalyk.own
resources with
PIU support
consultant as
necessary.
Commence
immediately,
Develop by end of
2016.
Initial assessment of priority sites
for investment in new containers
and repair work completed.
Annual report assessing status of
sites and maintenance work
undertaken.
Quarterly report of inspections, and
complaints, if relevant.
2012 ESAP
requirement
1.14 Develop and implement Mitigation of Best practice. PIU own Preliminary Draft Draft Plan is in place.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 11
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
landfill closure plan for the
proposed landfill.
Disclose the Plan publicly
and to local community prior
to implementation.
landfill closure and
impacts on local
environmental and
communities.
resources during
operation,
supporting
consultant if
necessary.
Landfill Operator.
to be developed
no later than 1
year prior to
closure.
Final version – no
later than 6
months prior to
closure.
Final Plan is in place and disclosed
for comments.
Evidence of implementation.
PR2 Labour and Working Conditions
2.1 Ensure appropriate human
resources management
system is in place, including
procedures and processes
related to human resource
policies and procedures,
non-employee workers,
worker grievance
mechanism, security
personnel and supply chain.
Management of
human resources in
accordance with the
law and best
practice
EBRD PR2
Kyrgyz
regulations
(Kyrgyz
Labour Code
etc.)
Own resources of
Contractor,
PIU support
consultants
Landfill Operator
Prior to
commencement of
works.
Evidence of Human Resources
system is in place, i.e. relevant
policies, procedures, assigned staff,
etc.
Human Resources and/or
procurement procedures with
respect to non-employee workers,
worker grievance mechanism,
security personnel and supply
chain.
2.2 Incorporate provisions for
working conditions
compliant with national laws
and EBRD requirements in
tender documentation and
contracts for contractors and
Risk management
and ensuring
adequate labour
conditions of
contractors and
EBRD PR 2,
Best Practice
Own resources of
Tazalyk, Landfill
Operator and
Contractor with
PIU support
consultants as
Prior to
commencement of
works.
Tender documentation and
contractual clauses contain
requirements for operating health
and safety management system,
compliance with requirements on
child labour, forced labour,
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 12
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
suppliers.
Undertake periodic internal
labour conditions checks and
audits against EBRD
Requirements.
suppliers. necessary
provision of equal opportunities,
Kyrgyz Labour Code etc.
Records of compliance checks of
contractors’ and suppliers.
2.3 Review salary scales against
job requirements.
PIU to collect baseline
information on conditions
and salary levels of workers
in comparable industries in
public sector.
PIU consultant and Tazalyk
to review salary scales
required for staffing needs.
Ensuring salaries
reflect experience
and responsibility
and are at the level
satisfying average
living standards to
discourage
personnel from
undertaking waste
unauthorised
recycling activities.
Ensure that there is
no discrimination
regarding gender,
i.e. equal pay for
work of equal
value.
Best practice PIU with support
of PIU
consultants, HR
department of
Tazalyk.
Prior to
commencement of
operation of the
new landfill.
PIU, Tazalyk to
collate data before
Q4 2016.
Evidence of analysis of salaries
which considers gender differences
and avoids discrimination.
Job descriptions at the new landfill
complex are attached to a salary
scale.
Evidence of completed reviews by
company directors.
2012 ESAP
requirement
2.4 Include equal opportunity
recruitment policy for staff
and contract conditions for
sub-contractors; and training
Promote and
facilitate equal
opportunities (e.g.
diversity and
Best Practice PIU with PIU
support
consultant,
Landfill Operator
By end 2016 for
Tazalyk.
Prior to
commencement of
The Equal Opportunity Policy is
developed.
The Policy as well as job
advertisements, job descriptions for
2012 ESAP
requirement
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 13
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
for HR personnel on
procedures to implement the
policy.
gender equality)
and relevant
technical skill mix
in each of
management,
contract
management and
operational roles.
and Tazalyk top
management and
HR.
(Development of
policy and
procedures
undertaken as part
of Technical
Assistance from
EBRD Phase 3
prior to tendering
as it forms part of
the tender
documentation.
Initial Training
modules are to be
delivered using
EBRD Phase 3
budget.)
BADS
rehabilitation.
all personnel, and contract
conditions for sub-contractors
clearly state commitment to
ensuring the equal opportunity.
Recruitment procedures include
relevant clauses.
Relevant training undertaken.
Job descriptions are developed.
Annual report showing staffing
levels demonstrating gender
equality, diversity in relation to
remuneration and recruiting.
2.5 As a part of HR MS,
develop and implement a
worker Grievance
Mechanism (GM) available
to direct employees and non-
employee workers during
BADS rehabilitation, Project
Management of
worker
relationships.
EBRD PR 2 Own resources of
PIU support
consultant,
Landfill Operator
and Contractor.
Prior to
commencement of
construction and
reorganisation
works on Project.
Grievance mechanism procedure is
developed.
Records of grievances and their
resolution are maintained and
reported to management.
Records of communication with
Labour Union, where relevant.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 14
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
construction and operation. GM is communicated to sub-
contractor employees. Records are
in place.
2.6 If a dedicated worker
accommodation is required
during construction phase,
arrange its facilities in
accordance with legal
requirements and a guidance
note by IFC and the EBRD.
Ensuring adequate
accommodation for
workers.
Kyrgyz
regulations,
EBRD PR2,
Workers'
accommodatio
n: processes
and standards
- a guidance
note by IFC
and the
EBRD2
Contractor Prior to the use of
worker
accommodation
Evidence of assessment in
accordance with the EBRD/IFC
guidance note.
Respective regulatory approvals.
PR3 Resource Efficiency and Pollution Prevention and Control
3.1 Implement pollution
prevention measures
described in the ESMMP
(covering air emissions,
noise pollution, dust, waste
water, hazardous substance
Effective
environmental
management.
Minimise impact on
environment, local
community, and
EBRD PR 3,
EU Industrial
Emissions
Directive
(integrated
pollution
Own resources of
Contractor,
PIU and PIU
support
consultant,
Prior to
commencement of
construction
works
The reviewed ESMMP is approved
and implemented.
All sub-Plans, Procedures and
Protocols required by the ESMMP
are in place.
Record of checks on implementation
2 http://www.ebrd.com/downloads/about/sustainability/Workers_accomodation.pdf
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 15
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
and materials, pesticide use
and management).
workers. prevention and
control)
2010/75/EU,
Best practice
(for example Inspections, Audits
reports).
3.2 Develop and implement
BADS Rehabilitation Plan,
showing final profiles to
shed surface water.
Develop and implement
technical specifications for
final capping of BADS.
Rehabilitation plan to
include:
Develop and implement
Leachate Management Plan.
Develop and implement
Leachate and Water
monitoring programme.
Effective BADS
rehabilitation,
leachate and surface
water management.
EBRD PR3,
EU Landfill
Directive
99/31/EC,
Best practice
PIU and PIU
support
consultant.
BADS Rehabilitation Plan showing
final contours required to achieve
these.
Technical specifications for BADS
capping (after reaching new
profiles).
Leachate and Surface Water
Management Plan is in place.
Leachate and Water Monitoring
programme is in place.
Water quality monitoring reports.
Number of overflow discharges to
river meeting discharge consent
standards.
2012 ESAP
requirement
3.3 Develop specifications for
landfill gas management
system for BADS and new
landfill.
The system should include:
Minimise risk of
incidents and
accidents related to
gas emission, and
gas migration.
EBRD PR3,
EU Landfill
Directive
99/31/EC
PIU and PIU
support
consultant,
Contractor,
Landfill Operator
Prior to
commencement of
construction
Landfill gas collection system
installed and connected to
flarestack.
Monthly gas monitoring results,
and record of actions taken in
response.
2012 ESAP
requirement
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 16
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
Sealed cells in the new
landfill with gas
migration layer under
the seal;
Porous layer beneath
final restoration soils in
rehabilitated landfill.
Install gas collection system
according to the
specification.
Monitor gas emissions at
frequency required by
developed specification.
3.4 Develop and implement
fungal spores control plan to
reduce its spreading from
MBT plant and from new
composting plants for green
waste in the town.
The plan should include,
among others, monitoring
programme, and
requirements:
To make appropriate
Minimise risk of
health impacts on
workers and
community.
EBRD PR 3,
UK Best
Practice,
Directive
2000/54/EC -
biological
agents at work
Own resources of
PIU and PIU
support
consultant,
Contractor
Prior to
commencement of
construction
Fungal spores control plan is in
place
Transmission bunds are constructed
and maintained
Results of monitoring programme,
and record of action undertaken (if
relevant).
All operational phase actions to be
part of the detailed Operational
Management Plan
2012 ESAP
requirement
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 17
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
dust masks available for
site workers.
To locate windrows
more than 300 metres
from residential areas
with soil bunds or
maturation heaps to
form barrier to
transmission.
To dampen windrows in
dry weather.
3.5 Develop and implement
pesticide control
programme, including
monitoring requirements for
construction and operational
phase.
Ensure that there is
compaction of waste in old
and new landfill areas to
limit availability of burrows
for rats and snakes and that
all wastes are covered with a
metre of other waste or soils
within one week to prevent
hatching of fly larvae.
Minimise risk of
spreading diseases.
Reduce risk of pests
dispersing into the
city during the
construction and
rehabilitation
works.
EBRD PR 3,
Best practice
Directive
2009/128/EC,
Directive
2012/18/EU
PIU and PIU
support
consultant,
Landfill Operator.
Prior to
commencement of
construction and
operation phases.
Pest control programme in place
Quarterly review of complaints
Monitoring results and record of
action undertaken (if relevant)
Number of sites with traps or baits
for rats.
2012 ESAP
requirement
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 18
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
3.6 Implement bird control
measures at new sorting,
MBT and landfill facilities.
Reduce health
impact on local
community relating
to pathogens
transferred by birds.
EBRD PR 3,
Best practice
PIU and PIU
support consultant
through
procurement
contract.
Landfill Operator.
Upon completion
of construction of
sorting and MBT
plant
Procurement contract includes
requirement for netting the new
windrows of high organic waste
until degradation is well advanced
to control birds.
Netting are installed prior to
commencement of operation.
2012 ESAP
requirement
3.7 As a part of Operational
Management Plan, develop
procedures for water
management and cleaning
process of MBT and the
sorting plant(s).
To ensure these procedures
are implemented, include
relevant requirements for
sump installed at the
sorting/MBT site and
pumping system, hoses and
sprays to enable cleaning of
the hardstanding and
spraying the windrows in the
procurement contracts.
Maintenance of the
effective
degradation process
Best practice PIU and PIU
support consultant
through
procurement
contract.
Landfill Operator.
Prior to
commencement of
operation
Relevant requirements included in
the procurement contracts.
Relevant procedures are in place
and implemented.
Procedures to include requirement
for regular cleaning and spraying
and to monitor water levels in the
sump and top up as necessary.
Sump and pump system installed
prior to commencement of
operation
Record kept of water levels in
sump.
2012 ESAP
requirement
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 19
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
PR4 Health and Safety
4.1 Appoint Health and Safety
personnel proportionately to
the scope and scale of works
within the Project.
Effective
management of
occupational H&S
issues
Best Practice,
EBRD PR1,
EBRD PR2.
EBRD PR4.
Own resources of
Tazalyk, Landfill
Operator,
Contractor and
PIU and PIU
support
consultant.
Prior to first
disbursement List of H&S personnel,
including their qualification,
and job description.
4.2 Ensure OHS management
system applies to the works
of their sub-contractors by
incorporating health and
safety provisions in
tendering documentation and
contracts for contractors and
suppliers.
Effective
management of
occupational H&S
issues
Best Practice,
EBRD PR1,
EBRD PR2.
EBRD PR4.
Own resources of
Tazalyk, Landfill
Operator,
Contractor and
PIU and PIU
support
consultant.
Prior to
construction
works
commencing
Tender documents include relevant
requirements relating to provision
of OHS management system.
Relevant clauses in the contracts
with contractors and suppliers.
4.3 Develop and implement
maintenance programme for
waste collection points.
Reduce nuisance
and risk of safety
incidents to
residents and users
at waste collection
points.
EBRD PR4,
Best Practice
Developed and
implemented by
Tazalyk
Sanitary
Ecological
Inspectorate to
monitor
During operation Maintenance programme is
developed, included in the annual
budget and implemented.
2012 ESAP
requirement
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 20
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
implementation.
4.4 As a part of ESMS establish
and implement noise
monitoring requirements and
mitigation measures to
control noise problems
relating to collection system
and to operations at the
landfill complex including
construction noise and noise
through rehabilitation of the
old landfill.
Mitigation measures to
include:
Time restriction for
noisy activities during
construction and
operation
Location of permanent
sources of noise to be as
far away from
residential areas as
possible (sorting plant,
composting plant, gas
flare, site entrance area
with weighbridge and
Compliance with
local and EU
regulation
Minimise risk of
grievances.
Kyrgyz
regulations,
EU Directive
2002/49/EC
(EU Noise
Directive),
EBRD PR3,
EBRD PR 4
Own resources of
Contractor,
Tazalyk,
PIU and PIU
support
consultant,
Landfill Operator.
Mitigation
measures and
monitoring
requirements are
identified prior to
commencement of
construction
works.
Implementation
during the whole
construction and
operational phase.
Limited
monitoring
programme
during
preconstruction
phase to establish
background
concentrations
Mitigation measures included in the
ESMMP.
Record of monitoring.
Record of grievances.
2012 ESAP
requirement
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 21
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
wheel cleaner);
Noise screening bunds
and screen planting to
be planned in advance
of the installation of
equipment.
4.5 Develop and implement
programme to identify
sources of special and
hazardous municipal waste
and arrange future separate
collection system.
Effective pollution
prevention.
Minimise impact of
exposure to
hazardous
substance by
community.
EBRD PR3
EBRD PR4
Best practice
PIU and PIU
support
consultant,
Contractor,
Landfill Operator.
Upon introduction
of a new waste
system.
Sources of hazardous waste are
identified by inspectors.
Amount of this waste is quantified,
and arrangements for collection are
in place.
2012 ESAP
requirement
4.6 Develop a detailed
construction traffic
management plan (CTMP).
Construction arrangement
should ensure that the
passing of construction
vehicles through informal
settlements is avoided.
Management of
EHS risks to
workers, road users
and communities
from construction
traffic.
Local
regulations,
Best practice,
EBRD PR 2,
EBRD PR 4.
Own resources of
Contractor
Prior to
commencement of
construction
works.
The CTMP is in place, approved by
the respective authority,
appropriately disclosed and
implemented.
Evidence of relevant information
being distributed to the drivers.
Evidence of relevant information
being distributed to the community.
Evidence of internal inspections
checking implementation.
4.7 Develop and implement
safety and security
Management of
EHS risks during
EBRD PR 4,
Best practice
Own resources of
PIU support
Prior to
commencement of
Relevant procedures are in place
and implemented.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 22
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
procedures for constructions
and phased access to the
BADS by waste pickers
during its rehabilitation,
including fencing.
BADS
rehabilitation and
security during
construction.
(e.g.
Voluntary
Principles on
Security and
Human rights:
http://www.vo
luntaryprincipl
es.org/ )
consultant,
Contractor
construction and
rehabilitation
works.
Record of monitoring / checks
carried out.
4.8 Develop Emergency
Preparedness and Response
Plan for Project construction
and operation.
Contractor should obtain
approvals from respective
authority and emergency
services.
Engage affected
communities and agencies
about these plans and any
subsequent changes made to
these.
Minimise impact on
workers,
community and
environment arising
from emergency
situations.
EBRD PR4,
Best practice
Own resources of
the Contractor,
PIU and PIU
support
consultant,
Landfill Operator.
Prior to
commencement of
construction work
Emergency Preparedness and
Response Plan in place and
implemented.
Record of consultation with local
authorities.
Record of approvals by the
respective authority.
Record of information provided to
the community.
Record of drills.
4.11 Follow design specification
to ensure that all equipment
as well as the landfill
infrastructure will be
designed to meet Kyrgyz
Compliance with
EU and Kyrgyz
standards
EBRD PR4,
Kyrgyz
regulations,
EU Waste
Directive
PIU with PIU
support consultant
to arrange for
competent design
checkers.
Design phase Record of design checks.
Record of approvals from local
regulators.
Issuance of permits.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 23
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
and EU Standards.
This should include
considerations of seismicity
of the area.
2008/98/EC,
EU Landfill
Directive
99/31/EC,
EU Industrial
Emissions
Directive
(integrated
pollution
prevention and
control)
2010/75/EU,
Best practice
PR5 Land Acquisition, Involuntary Resettlement and Economic Displacement
5.1 Through the Detailed Project
Design, avoid the potential
for resettlement impact from
construction and operation
of the access road, if
feasible. Should this not be
possible, prepare and
implement a Resettlement
Action Plan (RAP) and
conduct stakeholder
engagement for PAPs in
Mitigation of
resettlement
impacts
EBRD PR 5 Own resources of
Designer (detailed
design),
PIU and PIU
support
consultant,
Contractor
Detailed design
phase
Design drawings demonstrating that
resettlement is avoided.
Developed RAP (if impact is
unavoidable) and evidence of its
communication/disclosure and its
implementation.
Communication records (if
relevant).
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 24
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
accordance with the Project
Resettlement Framework.
5.2 In case of any additional
land acquisition and access
needs (permanent or
temporary) for the Project,
undertake assessment of
land acquisition and
resettlement impacts and be
compliant with resettlement
principles set in EBRD PR5.
Assessment and
mitigation of land
acquisition,
resettlement
impacts.
EBRD PR 5 Own resources of
Contractor,
PIU and PIU
support consultant
On-going
before/during
construction
Details of affected land or access
(e.g. cadastral records).
Communication records.
Transfer, approval, permit records.
Assessment/survey and inclusion
into the LRP or RAP, or
development of an addendum to
LRP/RAP.
Records of
mitigation/implementation.
5.3 Review if residents of the
dormitory may face any
impacts following the
detailed design
specifications, particularly in
terms of access to their
living areas, or in relation to
project construction
activities.
Establish the residents’
socio-economic profile and
vulnerability in relation to
above issues.
Mitigation of
livelihood impact
Mitigation of major
health risks from
construction/rehabil
itation activities.
EBRD PR 5
EBRD PR 10
PIU and PIU
support consultant
3-4 Q 2016 Survey records.
Records of assessment and
mitigation measures if such are
necessary.
Appropriate clauses in a
Construction Management Plans
and health and safety management
procedures.
Communication and grievance
records, including with PAPs.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 25
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
5.4 Update the LRP once the
assessment and socio-
economic survey of waste
pickers is complete to
include:
(i) provision of training to
waste pickers related to
accessing finance and
business advice to establish
SMEs, with a particular
focus on such training and
programmes tailored for
women and young people;
(ii) updated stakeholder
engagement and grievance
mechanism for PAPs
(considering the updated
SEP);
Mitigation of
livelihood impact
and build positive
and effective
relationship with
PAPs.
Best practice PIU and PIU
support
consultant,
3Q 2016 Updated LRP inclusive of specified
provisions.
Reviewed specific stakeholder
engagement plan.
5.5 Implement the updated LRP. Mitigation of
livelihood impact.
Compliance with
the EBRD
requirements.
EBRD PR5 Own resources of
PIU and PIU
support
consultant,
Contractor
and relevant City
Departments.
Prior to first
disbursement and
as per agreed
implementation
schedule
(scheduled from
4Q 2016.)
Updated implementation
programme.
Developed/reviewed
implementation targets and KPIs,
budget, resources and
responsibilities.
Stakeholder engagement log.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 26
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
Grievance/feedback records.
5.6 Implement monitoring and
evaluation provisions of the
updated LRP, including
independent completion
audit and monitoring of
stakeholder engagement
activities.
Effective
implementation of
the LRP.
EBRD PR 5 Independent
consultant,
PIU and PIU
support
consultant,
relevant City
Departments as
necessary.
As per agreed
Monitoring and
evaluation
schedule.
Monitoring schedule.
Monitoring reports.
Mid-term evaluation report (if
deemed appropriate).
Completion Audit report.
PR6 Biodiversity and Living Natural Resources
6.1 Consult with ecologist on
the best measures to mitigate
impacts on migratory birds,
should there be a potential
for impacts, and include
them in the ESMMP.
Protect nesting
colony of bee eaters
at North east corner
of current dumpsite.
EBRD PR6
Best practice
Own resources of
PIU and PIU
support consultant
Mitigation
measures
identified prior to
commencement of
construction
works.
Implementation
throughout
construction and
operation.
If applicable, detailed mitigation
measures included in the ESMMP
and operation stage plans and
demonstrable evidence of their
implementation.
2012 ESAP
requirement
6.2 When possible enhance
biodiversity, through
planting and restoration
Increase
biodiversity values
in the area
EBRD PR6
Best practice
Own resources of
PIU and PIU
support
The Restoration
Plan is prepared
prior to
Detailed planting / restoration Plan
is in place, and includes measures
to enhance biodiversity in the area.
2012 ESAP
requirement
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 27
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
schemes.
Consult with the ecologist
about the proposed
solutions.
Consider inclusion in the
Restoration Plan a high
proportion of local vascular
plants to enhance the river
corridor and increase
biodiversity.
consultant,
relevant City
Departments
commencement of
construction
work.
PR7 Indigenous People – NOT APPLICABLE
PR8 Cultural Heritage
8.1 Implement archaeological
survey requirements of
ESMMP. Any findings of
this survey will need to be
appropriately recorded,
reported and further action
completed.
Adequate and
effective
management of
archaeological and
cultural heritage
issues.
EBRD PR8
Best practice
Own resources of
PIU and PIU
support
consultant,
Contractor
Prior to
commencement of
construction
works
Record of surveys undertaken.
Archaeological finds report (if
relevant)
Implementation of findings (if
relevant)
8.2 Obtain community feedback
on any areas of cultural
value within the Project
Adequate and
effective
management of
EBRD PR8
Best practice
Own resources of
PIU and PIU
support consultant
Prior to
commencement of
construction
Record of communication with
community.
Information obtained from the
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 28
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
area, in conjunction with the
recommended
archaeological survey or as
part of the socio-economic
survey for the LRP.
archaeological and
cultural heritage
issues.
works community is adequately
interpreted by the expert, and when
relevant survey requirement are
amended.
8.3 Obtain confirmation from
the Ministry of Culture
confirming that there is no
known cultural heritage on
the new landfill location.
Adequate and
effective
management of
archaeological and
cultural heritage
issues.
EBRD PR8
Best practice
Own resources of
PIU
Prior to
commencement of
construction
works
Written record of confirmation
from the Ministry of Culture.
8.4 Develop and implement a
Chance Finds Procedure, in
coordination with
appropriate authority.
Adequate
Management of
accidental
archaeological
finds.
EBRD PR 8
Best practice.
Contractor and
Landfill
construction sub-
contractor.
Procedure is
developed prior to
commencement of
construction
works.
Implementation –
during
construction.
Chance Finds Procedure is in place.
Annual report of any archaeological
finds.
PR
10 Information Disclosure and Stakeholder Engagement
10.1 Implement the updated SEP.
Ensure its regular review
and update.
Compliance with
the EBRD
requirements.
EBRD PR 10 PIU and PIU
support
consultants,
Once approved,
then on-going.
Communication log.
Updated information on the
website.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016
Page 29
No. Action
Environmental &
Social Risks
(Liability/Benefits)
Requirement
(Legislative,
EBRD PR,
Best Practice)
Resources,
Investment
Needs,
Responsibility
Timetable Target and Evaluation Criteria
for Successful Implementation Status
Proactive
stakeholder
engagement.
Relevant City
Departments,
Contractor.
Update on SEP implementation in
the Annual Environmental and
Social Report.
Up-to-date SEP.
10.2 Establish and implement a
public grievance mechanism
in compliance with the
EBRD and best practice
requirements.
Proactive
stakeholder
engagement and
management of
impacts to public.
EBRD PR 10,
Best Practice
Contractor and
sub-contractors,
PIU and PIU
support
consultant.
Establish prior to
activities/
operations.
Implementation is
on-going
Evidence of grievance mechanism
is approved.
Contractor: GM procedure is
disseminated to PAPs.
PIU: GM procedure is publicly
available.
Workers are trained on how to
handle/pass public grievances.
Grievance records.
City of Bishkek & European Bank for Reconstruction & Development (EBRD) Bishkek Solid Waste Management Project
Environmental and Social Action Plan
ESAP/Final | | 9 November 2016