Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs Madhya Gujarat Vij Company Ltd (MGVCL) Page 1 of 15 Request for Proposal Under GoI’s R-APDRP Volume I Purchaser: Madhya Gujarat Vij Company Ltd,Baroda On behalf of: Madhya Gujarat Vij Company Ltd, Baroda (MGVCL) Uttar Gujarat Vij Company Ltd, Ahmdabad (UGVCL) Paschim Gujarat Vij Company Ltd, Rajkot(PGVCL) Dakshin Gujarat Vij Company Ltd, Surat (DGVCL) RFP Identification No: MGVCL/RAPDRP/SIA/1140 Single Stage – Single Envelope Two stage Selection Procedure Last date for submission of Proposal is 28.09.2011 (This document is meant for the exclusive purpose of RFP and shall not be transferred, reproduced or otherwise used for purposes other than that for which it is specifically issued.) (This section is part of the bid)

Bid Document for Appointment of SCADA/DMS Implementation ... Office/030520… · Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs Madhya Gujarat

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 1 of 15

Request for Proposal

Under GoI’s R-APDRP

Volume I

Purchaser: Madhya Gujarat Vij Company Ltd,Baroda

On behalf of:

Madhya Gujarat Vij Company Ltd, Baroda (MGVCL)

Uttar Gujarat Vij Company Ltd, Ahmdabad (UGVCL)

Paschim Gujarat Vij Company Ltd, Rajkot(PGVCL)

Dakshin Gujarat Vij Company Ltd, Surat (DGVCL)

RFP Identification No: MGVCL/RAPDRP/SIA/1140

Single Stage – Single Envelope Two stage Selection Procedure

Last date for submission of Proposal is 28.09.2011

(This document is meant for the exclusive purpose of RFP and shall not be transferred, reproduced or otherwise used for purposes other than that for which it is specifically issued.)

(This section is part of the bid)

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 2 of 15

Volume-I

General Information

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 3 of 15

Table of Contents

1. Background ................................................................................................................................... 4

2. About utility .................................................................................................................................. 4

3. Utility Vision ................................................................................................................................. 6

4. RFP Structure ................................................................................................................................ 7

4.1. Volume I –General Information ................................................................................................. 7

4.2. Volume II – RFP _SIA (Commercial) ........................................................................................ 7

4.3. Volume III – Technical Specifications and BOQ ....................................................................... 7

4.4. Volume IV- Utility Information .................................................................................................. 7

5. General Information ...................................................................................................................... 7

6. Proposed SCADA/DMS solution .................................................................................................. 8

APPENDIX-A -Bidder Query response format ........................................................................... 15

List of Tables

Table 1: Utility Statistics ....................................................................................................................... 5

Table 2: Major Offices in the project area ............................................................................................. 6

Table 3: RFP Structure ........................................................................................................................... 7

Table 4: Minimum band width requirement ........................................................................................ 10

List of Figures

Figure 1:SCADA/DMS System connectivity envisaged by DISCOM ................................................. 9 Figure 2: Reference architecture .......................................................................................................... 11

Figure 3: Control centre architecture ................................................................................................... 12

Figure 4: DR Centre Architecture ........................................................................................................ 14

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 4 of 15

1. Background

Ministry of Power, Govt. of India, has launched the Restructured Accelerated Power Development and Reforms Programme (R-APDRP) in the XI Five year Plan. Under Part A of R-APDRP SCADA/DMS shall be installed in eligible urban areas which are towns and cities with population of more than 4,00,000 and annual input energy of 350MUs . In Gujarat 6 towns falling under four DISCOMs have met above qualification criteria and it has been decided to implement the SCADA/DMS at these towns. The eligible towns are Baroda(MGVCL),Ahmdabad Peri(UGVCL),Rajkot,Jamnagr,Bhavnagr(PGVCL) and Surat peri(DGVCL).

Major Scope envisaged under the implementation are the following.

• Establishment of SCADA/DMS Control Centre in each town

• Integration/Upgrading of existing SCADA at Baroda

• Disaster Recovery (DR) Centre at Baroda for SCADA/DMS of all the 6 towns.

• RTUs at all primary substations and FRTUs at RMUs, Sectionalizers on HV Distribution network.

• SCADA/DMS system to supervise primary substations and HV Distribution network including Information Storage & Retrieval (ISR) Functions

• Distribution Management Systems(DMS) with following main functions

o Network Connectivity Analysis (NCA)

o State Estimation (SE)

o Load Flow Application (LFA)

o Voltage VAR control (VVC)

o Load Shed Application (LSA)

o Fault Management and System Restoration (FMSR)

o Loss Minimization via Feeder Reconfiguration (LMFR)

o Load Balancing via Feeder Reconfiguration (LBFR)

o Operation Monitor (OM)

o Distribution Load forecasting (DLF)

• Dispatcher training simulator (DTS)

2. About utility

Gujarat state power distribution network was unbundled into four regional distribution companies namely Madhya Gujarat Vij Company Ltd, Baroda (MGVCL) , Uttar Gujarat Vij Company Ltd,

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 5 of 15

Ahmadabad (UGVCL) ,Paschim Gujarat Vij Company Ltd, Rajkot (PGVCL) and Dakshin Gujarat Vij Company Ltd, Surat (DGVCL) .

MGVCL is feeding electricity in 5 Districts, 49 Taluks covering 4,426 Villages of Gujarat. For better administration and consumers' conveniences, administrative area of company is divided into 89 Sub Division and 17 Division Offices throughout its operational area which is divided into four Circles.

UGVCL feeds power to 6 districts in northern region of Gujarat and three part districts in western and central areas. The consumers under residential, commercial, industrial, agricultural categories are served by 127 Sub Division and 20 Division Offices throughout its operational area which is divided into four Circles. The business affairs are taken care of by Corporate Office presently headquartered at Mehsana.

PGVCL covers 8 districts of Gujarat namely Rajkot, Jamnagar, Junagadh, Porbandar, Bhuj, Bhavnagar, Surendranagar and Amreli with a total of 83 Talukas. For better administration and consumers' conveniences, administrative area of company is divided in to total 11 and out of which 6 circles are under direct control of Corporate Office and 4 circles are under the control of Bhavnagar Zonal Office and 1 circle under the control of Bhuj Zonal Office.

DGVCL is feeding electricity in 7 districts namely Bharuch, Narmada, Surat (except part of Surat City), Tapi, Dangs, Navsari and Valsad in South Gujarat. For better administration and consumers' conveniences, administrative area of company is divided in to total 3 Circles,17 Division Offices and 87 Subdivisions

In Gujarat state Baroda, Ahmdabad Peri, Rajkot, Jamnagar, Bhavnagar and Surat Peri towns met the eligibility criteria defined by the nodal agency for R-APRDP Part A SCADA/DMS scheme. The geographical areas, energy consumption in the project area are given in Table-1

Discom Project Area Name

Population

(In millions)

Total Energy (In MUs)

Project Coverage Area (In Sqkm)

MGVCL Baroda 1.49 1321 447.08

UGVCL Ahmdabad Peri 0.45 421.436 314

PGVCL Rajkot 1.30 1050.020 150 Jamnagar 0.56 455.910 150 Bhavnagar 0.52 453.228 90.16

DGVCL Surat Peri 2.80 664.030 197.41

Table 1: Utility Statistics

Functionally Sub divisions are the lowest operational unit which provides information and maintains the power distribution network. For the managerial and administration purpose, the utility is divided into Divisions, circles with corporate officeat the top. Following table provides information on the structure and size of each DISCOM.

Discom Project Area Name Head Circle Divisional Sub

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 6 of 15

office office offices divisional offices

MGVCL Baroda 1 1 4 18 UGVCL Ahmdabad Peri 1 1 3 8

PGVCL Rajkot 1 1 3 20 Jamnagar 0 1 2 7 Bhavnagar 0 1 2 8

DGVCL Surat Peri 1 1 4 18 Table 2: Major Offices in the project area

All the DISCOMs supply electricity to all categories of users including domestic, commercial, industrial (small, medium and large) and agricultural consumers. The power distribution system has large & complex distribution network infrastructure which carries the energy from the power sub stations (66/11lkV) through the HT and LT lines up to the consumers’ premises. For the day to day operation ,DISCOM has huge human capital that works round the clock. Technical and commercial losses occurring due to various reasons affect the financial health of the DISCOM severely. All the four DISCOMS in Gujarat have already taken various initiatives in order to improve its operational efficiency and for delivering enhanced services to the consumers under their jurisdiction. The distribution companies are in the process of implementing various IT systems under RAPDRP part-A for which contracts are already been awarded.

3. Utility Vision

The Company has the vision of providing customer satisfaction through service excellence. Company is committed to achieve the goal of providing reliable and quality power at competitive cost and to reach global standards in reducing distribution losses.

In order to meet the objectives and go upward in the value chain, DISCOMs of Gujarat have taken various initiatives like enabling IT systems in all the business process, installing supervisory, remote monitoring and enterprise resource planning tools along with investments in communication , IT and modernization of distribution networks.

With the proposed SCADA/DMS systems under R-APDRP PART-A scheme along with planned investments under R-APDRP PART-B, it is expected to deliver highly reliable & improved quality supply to its consumers meeting various mandatory Standards of Operation(SOP) proposed by state regulatory board. During contingencies with help of real time monitoring and analysis functions remedial actions shall be taken by SCADA/DMS either by self designated rules or intelligence-in- response to system state at different operational constraints. The systems to be implemented shall have necessary scalability and adaptation to the future standards and regulations and shall be a step towards Smart Grid.

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 7 of 15

4. RFP Structure

This request for Proposal (RFP) has been issued for selectingSCADA/DMS Implementation Agency (SIA) by Gujarat distribution companies (DISCOM) for implementation of SCADA/DMS systems under Restructured APDRP Part A

The Request for Proposal (RFP) document is structured in four volumes as below:

Volume Section

RFP Volume-I General Information RFP Volume-II RFP_SIA(Commercial) RFP Volume-III Technical Specifications and BOQ RFP Volume-IV Utility Information

Table 3: RFP Structure

4.1. Volume I –General Information

This document provides the bidder a brief introduction about the Project objectives and the Utility. The document explains the overall structure of the bid document and General terms and conditions applicable to each bidder.

4.2. Volume II – RFP _SIA (COMMERCIAL)

This document provides all commercial information to the bidder which include Instructions to the bidders General and specific conditions of the contract, eligibility criteria, Scope of work and it provides all relevant data sheets and bidding forms.

4.3. Volume III – TECHNICAL SPECIFICATIONS AND BOQ

This volume contains the Model Technical Specification (MTS) released by the Nodal agency (PFC) and modifications applied to selected clauses of MTS. It is mandatory to comply to the given technical specification..

4.4. Volume IV- Utility Information

Utility specific information like existing SCADA/DMS system, IT system and ERP are elaborated in this document.

5. General Information

The RFP document specifies the terms and conditions in detail in the sections of GCC, SCC and ITB in the bid document (Volume-II). Bidder shall compulsorily quote for all the 6 eligible towns under 4 DISCOMS in the state. Towns are Baroda(MGVCL),Ahmdabad Peri(UGVCL),Rajkot,Jamnagr,Bhavnagr(PGVCL) and Surat peri(DGVCL).

a. Any queries on this bid document likely to be discussed during Pre-bid Conference should be emailed to : [email protected] in the specified format given the Appendix-A

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 8 of 15

b. The bid cost is Rs. 10,000/- only (Rupees Ten Thousand Only) and need to submitted along with the bid in the form of Demand Draft in favor of Madhya Gujarat Vij Co. Ltd. Payable at Vadodara. Bidder can download the bid document from the utility website( www.mgvcl.com.) .The bid cost in the form of Demand Draft will be deposited along with the bid submission in a separate envelope highlighting as “Bid Cost”.Any tender without bid cost will be rejected

c. Bidder has to quote for 1 year communication link charges. However the charges will be applicable only after the operational acceptance testing. Any link charges before the Operation acceptance test shall be in bidder’s scope.

d. Number of signals from the FPI will be as per the requirement and minimum of 3 status signals(o/c,e/f,reset) can be conidered.

e. The actual location of RMU,FPI will be Provided after award of contract.

6. Proposed SCADA/DMS solution

This section gives details of proposed SCADA/DMS system under R-APDRP, the communication networks, system architecture and integration with other systems within DISCOMs. The proposed SCADA/DMS system shall be designed to operate & monitor distribution substations and the network from a designated centralized location of each project area/town. The communication backbone for the envisaged SCADA/DMS system consists MPLS-VPN/MLLN and 3G/CDMA/GPRS across the project area. The below figure depicts typical connectivity envisaged by the DISCOMs for its towns.

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 9 of 15

Figure 1:SCADA/DMS System connectivity envisaged by DISCOM

Divisional offices, Circle office are identified as the functional area of DISCOMs for SCADA/DMS implementation, the monitoring should be possible from the proposed system for any remote VDU locations. SIA has to do site study of the project area and define the interface requirements for SCADA/DMS system and for necessary connections with switchgears including protection relays/controlling equipments (mechanical/numerical/microprocessor). The site study team shall include all necessary experts to understand and identify the above requirements. Proposed system envisages the following key functions at minimum and SIA has to strictly comply with all international and national standards and codes while implementing.

i. The proposed system consists of RTU, FRTU and FPI Modems at field and SCADA/DMS at Control Centre.

ii. DMS functions at control centre should enable automatic and manual operations of the network devices and monitor all the power meters of interest.

iii. All the data pertaining to substation shall be collected by RTU and the same shall be send to control centre via MPLS-VPN network. If MPLS-VPN is not feasible at a specific location alternate options like leased line, broad band shall be considered by the SIA.

iv. Status and indications data from 11 KV distribution assets like Ring Main Units (RMUs), Fault Passage Indicators and Sectionalizers are acquired by FRTU communicating to

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 10 of 15

control centre over wireless mobile network(3G/CDMA/GPRS). Stand alone FPIs are to be communicated to control centre using 3G/CDMA/GPRS modems. The communication media shall be 3G and if 3G is not available in any particular city area bidder can go for the CDMA or GPRS. But then, the used equipments shall be easily upgradable to 3G without any additional cost.

v. The modems attached with the FRTU shall be capable of adapting latest wireless transfer technology including 3G, CDMA&GPRS. SIA should ensure all types of data quality, reliability and security over desired communication links as per the model technical specification (MTS). The Modem shall support 3G with backward compatible for CDMA/GPRS.

vi. Remote Visual Data Units (VDU) and Local Data Monitoring Systems(LDMS) at all functional offices should allow monitoring of the distribution assets depending upon user privileges defined. Connectivity to the offices shall have necessary bandwidth for the data exchanges.

vii. GIS and network model information are to be fetched from upcoming IT system using middleware or interface adapters.

viii. Minimum band width requirement estimated for the MPLS-VPN connection at all towns is given in below table, however all bandwidth requirements shall be estimated by SIA in order to attain the desired level of system reliability and availability specified in the MTS. Minimum bandwidth for all the MPLS-VPN at a typical SCADA/DMS control Center shall be as shown below:

Sl.No Node(s) to be linked Minimum bandwidth

1 Control Center to RTU 2 Mbps

2 Data Recovery Centre 2 Mbps

3 SLDC 2 Mbps

4 Head office, Divisional office,Circle Office

2Mbps

5 IT customer care/Cell 2 Mbps

6 IT Data Center 2 Mbps

Table 4: Minimum band width requirement

Data flow between devices/systems and proposed SCADA/DMS system, communication protocols and integration standards has to be followed with respect to Model Technical Specifications (MTS)

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 11 of 15

document. SIA shall ensure closely coupled integration for every possible point and it shall be in line with MTS.

Figure 2: Reference architecture

All data integrations shall be based on following general approach.

i. Tag database changes at any node shall be updated at other applicable nodes and manual configuration shall be minimal.

ii. Data point mapping and configurations shall be done using graphical tools and taking lesser engineering effort.

iii. Every new addition/deletion of the data points shall be automatically updated throughout system rather than defining at every point of integration.

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 12 of 15

Figure 3: Control centre architecture

A detailed control centre architecture in line with Model Technical Specification(MTS) is depicted in the figure-06 above. The proposed system consists communication equipments, application servers (ISR, DMS, NMS, DTS and COM.), mass storage device, work stations and intrusion prevention systems all connected together over a dedicated dual redundant Gigabits local area network(LAN).The different SCADA/DMS functions at control centre are identified as critical and non critical functions as below:

Critical Functions:

i. All SCADA functions

ii. Information Storage and Retrieval (ISR)

iii. All DMS functions

iv. Data exchange among the contractor supplied SCADA/DMS system,existing SCADA/DMS system and IT system established under R-APDRP.

v. Web server and Security functions

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 13 of 15

vi. Network Management system (NMS)

vii. Data recovery function (DR)

Non-Critical functions:

i. Dispatcher Training Simulator (DTS)

ii. Database modification and generation

iii. Display modification and generation

iv. Report modification and creation

v. Data exchange with VPS and remote VDUs ,if any.

The entire critical functions should have redundancy in hardware and connectivity; non critical functions should be supported with backups and storage options. Failure of non critical functions should not interrupt any normal operation of critical functionalities including DMS functions.

Major DMS functions envisaged as a part of system are the following:

i. Network Connectivity Analysis (NCA)

ii. State Estimation (SE)

iii. Load Flow Application (LFA)

iv. Voltage VAR control (VVC)

v. Load Shed Application (LSA)

vi. Fault Management and System Restoration (FMSR)

vii. Loss Minimization via Feeder Reconfiguration (LMFR)

viii. Load Balancing via Feeder Reconfiguration (LBFR)

ix. Operation Monitor (OM)

x. Distribution Load forecasting (DLF)

All operator actions shall be recorded in the SCADA/DMS system with time stamp. Authentication and privileges shall be in such way that secured operations of the equipments are possible from the control centre. It is also envisaged that the system complying with statutory codes and security guidelines of IEC/NERC/CE/EMI/EMC .

Ahmdabad,Rajkot,Jamnagr,Bhavnagr,Surat will have independent SCADA/DMS control centre at its dedicated utility area with above functionalities except dispatch training & simulator (DTS) and Data Recovery(DR) facility. Baroda city will have the DTS, which is a common dispatch training facility for the whole state. Power system models of all the 6 towns shall be incorporated at DTS server

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 14 of 15

located at Baroda Control Centre for simulation , testing and training required for all three DISCOMs.

DTS function shall have ability to establish the following training functions as a minimum:

i. Normal steady state

ii. Disturbed network conditions for distribution network

iii. High & Poor Voltage conditions

iv. Poor VAR conditions

v. Indiscriminate tripping

vi. Islanding

vii. System blackout

viii. System restoration

ix. Conditions/functions included for SCADA/DMS real time system

Figure 4: DR Centre Architecture

Data recovery centre (DR) for 6 towns shall be located under MGVCL at Baroda. All the towns shall be connected to Baroda Data recovery system over MPLS-VPN. The DR should have routine backups of SCADA/DMS, ISR as described in MTS. It shall be possible to recover entire SCADA/DMS application of each town from the DR backups.

Bid Document for Appointment of SCADA/DMS Implementation Agency by Gujarat DISCOMs

Madhya Gujarat Vij Company Ltd (MGVCL) Page 15 of 15

APPENDIX-A -Bidder Query response format

SL No SIA Name

Volume

No

Page

Number

Reference

Section

Existing

Clause

Question

regarding

the

Clause Description Comments

*********************************End Of Document*** ******************************