BETTER SOLUTIONS 6-1. Installation Press equipments & schedule item Equipment name qty wt(Ton) KIA Site arr. instal l trial #1 Press 5,400ton Press 1 2,071.0 2005.12 2005.1 2 ~ 2006.0 1 2006.01 ~ 2006.04 T/F unit 1 20.1 Destacker 1 141.5 Auto Palletizer 1 154.6 Aux. 2,400ton T/O Press 1 643.2 50Ton D/S 1 82.5 B.T.O 1 11.5 600ton Blanking press 1 275.7 Coil line 1 285.9 #2 Press 5,400ton Press 1 2,071.0 2006.03 2006.0 3 ~ 2006.0 5 2006.05 ~ 2006.07 T/F unit 1 20.1 Destacker 1 141.5 Auto Palletizer 1 154.6 total 13 6,073.

BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

Embed Size (px)

Citation preview

Page 1: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-1. Installation Press equipments & scheduleitem Equipment name qty wt(Ton) KIA Site arr. install trial

#1 Press 5,400ton Press 1 2,071.0

2005.12

2005.12

~

2006.01

2006.01

~

2006.04

T/F unit 1 20.1

Destacker 1 141.5

Auto Palletizer 1 154.6

Aux. 2,400ton T/O Press 1 643.2

50Ton D/S 1 82.5

B.T.O 1 11.5

600ton Blanking press 1 275.7

Coil line 1 285.9

#2 Press 5,400ton Press 1 2,071.0

2006.03

2006.03

~

2006.05

2006.05

~

2006.07

T/F unit 1 20.1

Destacker 1 141.5

Auto Palletizer 1 154.6

total 13 6,073.2

Page 2: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-2. Installation working scope1. General

(1) Schedule Management (2) Safety Management (3) Management of Works (4) Inevitable condition, Disaster (5) Investigation and Technical advise for abnormal condition during installation, assembling and start up. (6) Working time (A) Seven(7) days / week Two shift should be done if not to keep the installation schedule (B) One(1) shifts / days or Two(2) shift / days (C) Eleven(11) hours / shift

2. Unloading and Packaging

(1) Checking quantities and condition (2) Protection cover from rain, flood and snow fall at outdoor (3) Transportation from storage area to erection site (4) Unpacking at installation site (5) Disposal of crate, case, skid and steel, and rubbish to the outside of the plant (6) Removing rust preventives and cleaning

Page 3: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-2. Installation working scope3. Preparation of foundation

(1) Checking of dimension of level and center in accordance with drawings and manuals

4. Installation of press equipments and fixture

(1) Base plate (2) Foundation Bolt for Bed (3) Press Proper (Including Crown, Upright, Bed, Die Cushion, Slide, Moving bolster, Platform, Covers, Coil line eqipment, B.T.O ETC) (A) Installation and assembling (including level and center adjust) (B) Assembling of electrical motor and centering (4) Fixture (Auxiliary) * Air tanks * Oil Hydraulic unit with tank * Moving boister and rails, Cable Guides * Safety guards (5) 2,400 Ton Crown Assembly * Assembly work (Refer Packing list) (6) Welding & Cutting work for installation of equipments (7) Welding work for pipe connection between balancer cylinders and air tanks, cushion cylinders and air tanks

Page 4: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-2. Installation working scope5. Mechanical pipings

(1) Assembling pipes between press and fixtures (2) Installation and connection of air pipes between air tanks and CTB cylinders (3) Flushing work after piping installation (4) The cutting, bending, welding and etc. for piping work of presss, coil line and etc.

6. Installation of electrical equipment

(1) Drive panel for main motor (2) Control panels (3) Terminal boxes (4) Cable racks & ducts (Cutting, assembly, installation at site) (5) Conduit pipes (6) Wiring (A) Wiring and termination * From panels to termina boxes (TB) * From TB to sensors / actuators * Between each panels (7) The welding, bending, cutting work for electrical pipe installation

Page 5: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-2. Installation working scope

8. Installation of scrap chute Carrier railway

9. Installation of the cover for coil line

10. Preparation for Machine Adjustment

(1) Charging of grease to each points (2) Filling up the oils to tanks (3) Cleaning and oil sprinkling to Crown inside and Slide (4) Pickling, cleaning and Flushing of the pipes fabricated at site after inspection of Rotem S/V (5) Air blow cleaning of intemediate air pipes (6) Disposal of dirty and/or used oil (7) Wiring check (Continuity) (8) Power on (9) I/O check for electrical

11. Machine adjustment (1) Assistant Workers during the running test & after running test refer the working schedule (2) Responsibility for bad installation work

Page 6: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-3. Organization chart6-3. Organization chart

Main Facility (Rotem)

Press Mechanical Specialist

Press Electric Specialist

PM

Chief PM : Press Specialist (1)

Vice PM : Industrial Facility Specialist (1)

Auxiliary Facility (WIA)

Press Mechanical Specialist

Press Electric Specialist

Installation Master

Specialist Installation Comissioning

Mechanical 20 3

Piping 10 2

Electrical 15 4

Helpers 10 2

Total 55 11

Installation Master

Specialist Installation Comissioning

Mechanical 10 3

Piping 10 2

Electrical 10 4

Helpers 10 4

Total 40 13

Page 7: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-4. Installation equipment

Four(4) Point Hydraulic lifter : 400 Tons 1 unit

Mobile Hydraulic crane : 100 Tons 1 unit

Page 8: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

1-5. 1-5. 설비 장비설비 장비

Mobile Hydraulic crane : 50 Tons 1 unit

Fork lifter : 10 ~ 20 Tons 4 units

Remarks : KIA Over-Head Crane (30~50 Tons)

Page 9: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-5. Installation basetool list

INSTALLATION BASETOOL LISTNo Machine Name Specification Quantity Remarks

1 Hand tool set      

2Arc welder and all necessary welding equipment

     

3 Helmet for Welding      

4 Glove for Welding      

5Cutting gas torch and bulbs with all necessary equipment

     

6 Eye bolt

M8 X 1.25 mm Pitch    

M10 X 1.5 mm Pitch    

M12 X 1.75 mm Pitch    

M16 X 2.0 mm Pitch    

M20 X 2.5 mm Pitch    

M24 X 3.0 mm Pitch    

M30 X 3.5 mm Pitch    

7 Shackle

1 ton    

2 ton    

2.5 ton    

5 ton    

10 ton    

20 ton    

Page 10: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-5. Installation basetool list6-5. Installation basetool list

INSTALLATION BASETOOL LIST

8 Ratchet lever hoist

0.5 ton    

1.0 ton    

1.5 ton    

9 Chain hoist

1 ton    

1.5 ton    

3 ton    

10 Hydraulic jack

10 ton x 50mm Strok    

10 ton x100mm Strok    

10ton x 200mm Strok    

15ton x 150mm Strok    

11 Hand pump for Hydraulic jack      

12 Hydraulic jack and distance blocks 50ton    

13 Distance block or tube for jack / 15ton /each

Dia 50 - 70mm    

Length 1 m    

15ton / each    

14 Sling for lifting(or Wires)

1 ton x 1 m    

1.5 ton x 1 m    

3ton x 1 m    

3 tons x 2 m    

3 tons x 4 m    

5 ton x 1 m    

5 tons x 2 m    

5 tons x 4 m    

Page 11: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-5. Installation basetool list

INSTALLATION BASETOOL LIST

15 Dial indicator0.01mm / div    

0.01 - 10mm    

16 Magnet stands for Dial Indicator      

17 Oil stone(Fine)      

18 Washing Oil(Degreasing equipment)      

19 Waste clothes(Scrap rags)      

20 Fire extinguisher      

21 Fire Blanket      

22 Hand saw      

23 Craw bar      

24 Angle(Disc) grinder Dia 120mm    

25 Safety Glasses      

26 Hand lamp      

27 Garage lamp      

28 Extension electric cable 20A, 30m Cable    

29 Cold chiselSmall    

Medium    

Page 12: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-5. Installation basetool list6-5. Installation basetool list

INSTALLATION BASETOOL LIST30 Large hammer (Sledge Hammer)      

31 Hammer      

32 Copper hammer

Small    

Medium    

Large    

33 Rubber hammer      

34 Files 10"      

35 Open end spanner

6mm,8mm,10mm, 12mm,14mm,15mm, 17mm,18mm,19mm, 20mm,22mm,24mm,27mm,29mm,30mm,32mm,36mm,46mm,50mm,55mm.

   

36 Ring Spanner

6mm,8mm,10mm, 12mm,14mm,15mm, 17mm,18mm,19mm, 20mm,22mm,24mm,27mm,29mm,30mm,32mm,36mm,46mm,50mm,55mm.

   

37 Sledge Spanner24mm, 30mm, 36mm,41mm,50mm,55mm.

   

38 Ring Spanner

M30    

M36    

M41    

M46    

M55    

Page 13: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-5. Installation basetool list

INSTALLATION BASETOOL LIST

39 Socket & Socket wrenct 8mm - 55mm    

40 Tie-Rod Jack      

41 Torque Wrenches 60kg/m    

42 Hexagon Wrenches MAX 27mm    

43 Hanger Metal      

44 Combination Spanner      

45 Adjustable Wrench      

46 Chain Clamp      

47 Grip Plier      

48 Screwdriver      

49 Super Lift      

50 Heavy Equipment

- Hydro Crane 500t 이상 or hydro gantry Crane 300t 이상(Rail type)

   

- Hydro Crane 200T    

- Hydro Crane 80T    

- Hydro Crane 50T    

- Hydro Crane 25T    

- Fork lift 10 ton    

- Fork lift 20 ton 이상    

- Hydro Gentry Crane    

(Tire Type)    

Page 14: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-5. Installation basetool list6-5. Installation basetool list

INSTALLATION ELECTRICAL BASETOOL LIST

1 Heart maker     Numbering type

2 Hydraulic pusher 250SQ    

3 Hydraulic puncher      

4 Testor     Digital type

5 A Meter      

6 Drill      

7 Hand welder      

8 Pipe bender      

9 Hole maker      

10 Mega ring testor      

11 O-ster      

12 Laptop & PLC programmer      

13        

14        

15        

Page 15: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-5. Installation basetool list6-5. Installation basetool list

정도 측정 공구1 Cylinder gauge      

2 Dial gauge      

3 Fineness gauge      

4 Oxygen cutter      

5 Laser thermamometer      

6 Level reader      

7 Torque gauge      

8 Bolt doubler      

9 Oil injector      

10 Flatness finder      

11 Piano wine, turn buckle      

12        

13        

Page 16: BETTER SOLUTIONS 6-1. Installation Press equipments & schedule itemEquipment nameqtywt(Ton)KIA Site arr.installtrial #1 Press5,400ton Press12,071.0 2005.12

BETTER SOLUTIONS

6-6. Spare Parts & maintenance6-6. Spare Parts & maintenance

Spare part : Rotem

location : BMI Slovakia s.r.o in Rosina, Slovakia (8km from KIA site) Mlynska  813, 013 22 Rosina capa. : 1,500m2, Yard 5,000m2

scope : Press equipment Spare Parts