Berryessa Union School DistrictMeasure L Bond Construction Program
Board of Trustees’ UpdateAugust 11, 2015
Introduction
The following presentation is intended to provide the Board of Trustees with an update on the progress of Measure L Construction Bond Projects. These are projects that are currently active throughout the District.
August 11, 2015
Current Overall Project Status (presented 7/14/2015)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Site
Education
Services
Center
Brooktree
Elementary
School
Cherrywood
Elementary
School
Laneview
Elementary
School
Majestic
Way
Elementary
School
Morrill
Middle
School
Noble
Elementary
School
Northwood
Elementary
School
Piedmont
Middle
School
Ruskin
Elementary
School
Sierramont
Middle
School
Summerdale
Elementary
School
Toyon
Elementary
School
Vinci
Elementary
School
Maintenance,
Operations
and
Transportation
Projects
Security Fencing Project
Painting Project
Paving Project
Playground Upgrades
Project
Central Kitchen Project
Campus Modernization/
Flexible Instruction Space
Technology Wireless
Infrastructure Project
Energy
Conservation
Project
Design Bidding Construction Closeout
LegendAugust 11, 2015
Projects Across The District
August 11, 2015
Current Overall Project Status1 2 3 4 5 6 7 8 9 10 11 12 13 14
Site
Education
Services
Center
Brooktree
Elementary
School
Cherrywood
Elementary
School
Laneview
Elementary
School
Majestic
Way
Elementary
School
Morrill
Middle
School
Noble
Elementary
School
Northwood
Elementary
School
Piedmont
Middle
School
Ruskin
Elementary
School
Sierramont
Middle
School
Summerdale
Elementary
School
Toyon
Elementary
School
Vinci
Elementary
School
Maintenance,
Operations
and
Transportation
Projects
Security Fencing Project
Painting Project
Paving Project
Playground Upgrades
Project
Central Kitchen Project
Campus Modernization/
Flexible Instruction Space
Technology Wireless
Infrastructure Project
Energy
Conservation Project
Waterline Replacement
Pavement Rehabilitation
for Athletic Courts
Design Bidding Construction Closeout
Legend
August 11, 2015
Projects Across The District
August 11, 2015
Brooktree ES
August 11, 2015
Replace fiber fall material and equipment
Exterior painting
Security Fencing
Cherrywood ES
August 11, 2015
Replace waterline
Exterior painting
Replace fiber fall material and equipment
Laneview ES
August 11, 2015
Replace fiber fall material and equipment construction will be completed prior to
start of school.
Majestic Way ES
August 11, 2015
Exterior painting
Replace fiber fall material and equipment
Exterior painting
Security Fencing
Noble ES
August 11, 2015
Replace fiber fall material and equipment construction will be completed prior to
start of school.
Northwood ES
August 11, 2015
Paving
Replace fiber fall material and equipment
Security Fencing
Piedmont MS
August 11, 2015
Ruskin ES
August 11, 2015
Exterior painting
Replace fiber fall material and equipment
Morrill Middle School
August 11, 2015
Exterior painting
Sierramont MS
August 11, 2015
Paving
Summerdale ES
August 11, 2015
Replace fiber fall material and equipment
Paving
Toyon ES
August 11, 2015
Replace fiber fall material and equipment
Paving
Vinci Park ES
August 11, 2015
Replace fiber fall material and equipment
Security Fencing
LAN Network Upgrade Project
Berryessa Union School DistrictMeasure L Bond Construction Program
August 11, 2015
Technology WirelessLAN Upgrade Project
August 11, 2015
District Office Data Center
Technology WirelessLAN Upgrade Project
August 11, 2015
BeforeAfter
District Office Data Center
Technology WirelessLAN Upgrade Project
August 11, 2015
District Office cabling
Technology WirelessLAN Upgrade Project
August 11, 2015
Sierramont MS cabling
LAN Network Upgrade Project - Phase I
The prior Megabits Per Second (mbps) was approximately 10 mbps with the equipment replacement it went to approximately 94 mbps. With the work completed at the Data Center and throughout the
District Office, we are now realizing approximately 213 mbps.
August 11, 2015
Energy Conservation Project
Present Recommendation to Board of TrusteesSeptember 15,2015
August 11, 2015
Current Overall Project Status1 2 3 4 5 6 7 8 9 10 11 12 13 14
Site
Education
Services
Center
Brooktree
Elementary
School
Cherrywood
Elementary
School
Laneview
Elementary
School
Majestic
Way
Elementary
School
Morrill
Middle
School
Noble
Elementary
School
Northwood
Elementary
School
Piedmont
Middle
School
Ruskin
Elementary
School
Sierramont
Middle
School
Summerdale
Elementary
School
Toyon
Elementary
School
Vinci
Elementary
School
Maintenance,
Operations
and
Transportation
Projects
Security Fencing Project
Painting Project
Paving Project
Playground Upgrades
Project
Central Kitchen Project
Campus Modernization/
Flexible Instruction Space
Technology Wireless
Infrastructure Project
Energy
Conservation Project
Waterline Replacement
Pavement Rehabilitation
for Athletic Courts
Design Bidding Construction Closeout
Legend
August 11, 2015
Projects Across The District
August 11, 2015
August 11, 2015
Measure L Bond Signage
Berryessa Union School District - Bond Measures
Measure L Bond Program Web Site
is active but under
Continuous Improvement
August 11, 2015
August 11, 2015
Berryessa Union School DistrictMeasure L Bond Construction Program
Thank You
August 11, 2015