Roads and Maritime Services I September 2019
Berry to Bomaderry Princes Highway upgradeProject Update
Looking north along the newly-constructed carriageway between Jaspers Brush Road and Wileys Creek which will soon be opened to traffic.
Use U-turn facilities to access properties
Lateral traffic shifts during construction
Speed limits in place during construction 60
Right turn intoLamonds Lanepermitted
Right turn intoBoxsells Lanepermitted
Right turn into Strongs Road permitted
Right turn intoCroziers Roadpermitted
Right turn intoMullers Lane
permitted
Right in/right outpermitted at Meroo Road
Andersons Lane
Mullers Lane
Croziers Road
Jaspers
Brush Road
Turners Lane
Mor
sche
lls L
ane
Dev
itts
LaneBoxsells Lane
Lamonds Lane
Mer
oo R
oad
Pestells LaneAbernethys Lane
See i
nset
for d
etail
Cambew
arra
Road
Strongs
Ison
Road
LaneSilos Estate
Broughton Cre
ek
To Berry
Bomaderry
MerooMeadow
JaspersBrush
Wileys C
reek
Princes Highway
To N
owra
Tandingulla Creek
The intersection at Meroo will be a new (standard) one which deviates from in front of the �rst house on the Northern side of the road to a point just to the south of the existing. It basically overlays the new overpass. This is a small lateral shift to get tra�c o� the existing Meroo intersection so we can work in that area.
KEY
Abernethys Lane
Pest
ells
Lan
e
Mer
oo R
oad
Lamonds Lane
Boxsells Lane
Abernethys
Creek Tullia
n Creek
Stron g
s
Roa d
Princes Highway
Princes Highway
See inset for detail
Ison
Lan
e
Silos Estate
350,000m3 of earth moved
10 of 11 bridges underway
23,000m2 of paving laid
2.1km of 15 kilometreof drains now in place
Roads and Maritime Services Berry to Bomaderry - Princes Highway upgrade
Traffic movements - during construction
Upcoming traffic changesThe Berry to Bomaderry project team is preparing for a series of traffic switches which will happen between now and the end of 2019.
We will have three separate “lateral shifts” where traffic is moved from the existing road onto sections of the newly-constructed southbound carriageway.
Motorists should follow the directional signage and directions of traffic controllers during these lateral shifts.
This allows the project team to begin work on demolishing and rebuilding the existing highway.
These shifts will occur through September and October 2019 and include shifting traffic to the east between: • Jaspers Brush Road and Silos Estate• Tandingulla Creek and Meroo Road• Meroo Road and Abernethys Lane.
Privacy: Roads and Maritime Services (“RMS”) is subject to the Privacy and Personal Information Protection Act 1998 (“PPIP Act”) which requires that we comply with the Information Privacy Principles set out in the PPIP Act. All information in correspondence is collected for the sole purpose of assisting in the assessment of this proposal/ delivering this project. The information received, including names and addresses of respondents, may be published in subsequent documents unless a clear indication is given in the correspondence that all or part of that information is not to be published. Otherwise RMS will only disclose your personal information, without your consent, if authorised by the law. Your personal information will be held by RMS. You have the right to access and correct the information if you believe that it is incorrect.
September 2019RMS. 19.1366
DSWJV foreman Rob Usher shows Flagstaff employees how it’s done
Berry to Bomaderry project teams up with local workers with disabilitiesThe Berry to Bomaderry project team has partnered with Flagstaff Group to offer work opportunities to local people with a disability.
The team at Flagstaff will be filling sand bags for use across the project for a variety of purposes including weights for traffic signage, erosion and sediment control on site and temporary retaining walls.
The Flagstaff Group provides employment, life skills and training for people with a disability across the Illawarra and Shoalhaven. The Shoalhaven site has 86 employees working in diverse roles including lawn maintenance, woodwork, light engineering, laundry, packaging and assembly and recycling.
Contact us:If you have any questions or would like more information on the Berry to Bomaderry upgrade please contact our project team:
1800 506 976 (press 3)
rms.nsw.gov.au/bbu
PO Box 309 Berry NSW 2535
Have your say
If you need help understanding this information, please contact the Translating and Interpreting Service on 131 450 and ask them to call us on 1800 506 976, option 3.131 450