Beam Dump Upgrade Planning. Keith Welch 2/5/13. Drivers for Upgrade. Historical Problems Hardware failures Helium system Windows, diffusers Dehumidifiers Ion chambers Uncertainties in beam transport Vulnerable hardware in “zone of death” - PowerPoint PPT Presentation

Citation preview

Page 1: Beam Dump Upgrade Planning

Beam Dump Upgrade Planning

Keith Welch2/5/13

Page 2: Beam Dump Upgrade Planning

Drivers for Upgrade• Historical Problems

– Hardware failures• Helium system• Windows, diffusers• Dehumidifiers• Ion chambers

– Uncertainties in beam transport– Vulnerable hardware in “zone of death”– ALARA – 1/3 of all dose collected since 2009 involved dump work (> 3

person-rem)• Goals for Upgrade

– Ensure dumps are ready for operations in 12 GeV era– Simplify maintenance– Reduce downtime– Provide robust dump protection and diagnostics– Reduce operational cost and dose

Page 3: Beam Dump Upgrade Planning

Dump Upgrade Scope• Upgrade beam transport hardware

– Replace helium tubes and upgrade helium blanket system– Semi-static, pressure demand helium system– Vacuum-to-helium interface modification

• Upgrade dump protection hardware– Be diffusers redesigned for 12 GeV – looking at possible passive cooling– Ion chambers – CERN design, retrievable– Beam position monitor to replace “burnthrough detector”

• Replace dump cave air treatment systems with dry nitrogen inerting systems– N2 generator(s)– Improved atmospheric isolation (wall integrity)

• Upgrade beam transport diagnostics– Viewer system with tune and CW operation capability– Upgrade camera mechanical mounting and shielding package– Ion chamber test apparatus

Page 4: Beam Dump Upgrade Planning

Dump Upgrade Scope• Other scope

– Evaluate shielding in isolation wall– Install “trolley” system for insertion of

inspection/measurement equipment into caves– Replace dump entrance windows– Inspect dump internals– Test and reconfigure (if necessary) H2 sensors

Page 5: Beam Dump Upgrade Planning

Conceptual Design Overview

• Tunnel dehumidification system eliminated• Hall A ion chamber test rig standardized• Radiation hard ion chambers, cables, position monitor• Viewers for pulsed and CW beam

Replace burnthrough monitor with position

monitorUpgrade diffuser

Move isolation wall, ion chamber test plate

Extend vacuum pipe, add diagnostics

Replace dump window

N2 purge

Upgraded ion chambers

Replace helium line, upgrade supply system

Page 6: Beam Dump Upgrade Planning

Status• Engineering underway

– Diffuser modeling– Helium line design– Position monitor– New ion chamber evaluation

• Scheduling– Strawman schedule– Input from most resource providers

• Initial visual inspection of tunnel completed

Page 7: Beam Dump Upgrade Planning

Dump Upgrade Timeline (preliminary guess)• Hall A is the critical path• First beam is scheduled mid-March, 2014

- How much of the installation can/must be complete by then?- More runs to Hall A scheduled later in 2014 (August, December?)

Hall A Milestones (assuming no hall work until late March ‘14)

Task Upgrade done by July ‘14

Design/Engineering complete 9/13

Major hardware procurements 10/13

Hardware onsite 1/14

Beam pipe tearout 3/14

Dump inspection/test 4/14

He/vac pipe install 4/14

Tunnel atmospheric controls, helium system, etc. 5/14

Diagnostics, monitoring hardware, etc. 6/14

Page 8: Beam Dump Upgrade Planning
Page 9: Beam Dump Upgrade Planning
Page 10: Beam Dump Upgrade Planning
Page 11: Beam Dump Upgrade Planning
Page 12: Beam Dump Upgrade Planning
Page 13: Beam Dump Upgrade Planning