Upload
prajwal
View
217
Download
0
Embed Size (px)
Citation preview
7/23/2019 BE Distribution 3rd slide
1/24
Factors affecting Distribution LossLoss dependence on Transformer Size
Suppose demand: 20 KW
Monthly energy sell : 4320 unit
The minimum standard size transformer required is 2!"#
Transformer $oss %ariation &ith transformer size
Transformer'ating(!"#)
*o $oad$oss(!W)
'ated $oad$oss (!W)
Monthly*o $oad+nergyloss(!Wh)
Monthly$oad $oss(!Wh)
Total +nergyloss (!Wh)
,er-entage+nergy $oss
2 0./0 0.30 2.00 2.1 .1 2.3/
0 0./ 0.0 /22.40 //.2 /33.2 3./0
/00 0.30 0. 2/1.00 4.0 220.0 .//
/10 0.44 /.30 3/1.0 2.3 3/.3 .40
200 0.10 /.10 432.00 2.30 434.30 /0.0
7/23/2019 BE Distribution 3rd slide
2/24
Loss dependence on Load center Size
7/23/2019 BE Distribution 3rd slide
3/24
5eeder &ise po&er loss
7/23/2019 BE Distribution 3rd slide
4/24
$oss Summary
7/23/2019 BE Distribution 3rd slide
5/24
Loss dependence on Load pattern
Suppose for the same load -enter &ithmonthly energy demand same as forpre%ious -ase i.e. Monthly energy sell :/2 unit
6ut the all energy is7 consumed in 3 hours
7 consumed in 6 hours
7 consumed in 12 hours
7 consumed in 24 hours
$oss %ariation &ith demand pattern
7/23/2019 BE Distribution 3rd slide
6/24
LT loss scenario
7/23/2019 BE Distribution 3rd slide
7/24
Loss dependence on feeder unbalancing
S-enario one all phase ha%e equal loading: 20 #
S-enario one feeder loading7 ,hase ': /0 #
7 ,hase 8: 20 #
7 ,hase 6: 30 #
S-enario three feeder loading7 ,hase ': /0 #
7 ,hase 8: /0 #
7 ,hase 6: 40 # 9f the loss in s-enario / is 1
The loss in s-enario 2 is aout .
The loss in s-enario 3 may e around /0
7/23/2019 BE Distribution 3rd slide
8/24
;ther 5a-tors
The loss also depends on -ondu-tor size
7 Thi-! -ondu-tor: less loss
7 Thin -ondu-tor: more loss
7 +.g the loss &ith dog -ondu-tor is aout /
7/23/2019 BE Distribution 3rd slide
9/24
Summary
Transformer should e appropriately installed tominimized transformer loss. 9t should not e o%ersized.
The load -enter size should e as small as possile.The feeder should e -onfigured so that the -onsumers
should e as -lose to the sour-e ( transformer). To redu-e the per-entage loss its required to in-reasethe other a-ti%ities than lighting only.#s far as possileminimize other use during pea! hours.
While -onne-ting -onsumers to supply phase alan-ingshould e !eep in mind.
Thi-! -ondu-tor -ause less loss ut high -ost-ompromise is done to sele-t appropriate -ondu-tor
7/23/2019 BE Distribution 3rd slide
10/24
Distribution Transformer Size & Location
In urban area go for maximum Transformer size and are
usually higher due to high load density as far as the LT
conductor capacities permits (No & size!
In "ural the maximum size of LT is limited by #o$er
Loss & %oltage drop (its recommended limit is around 'm! and Transformer size are usually smaller due to lo$
density and load coincident beha%ior
ut
This choice is also reflected by the utilization )oltage
le%el and the transformer %oltage ratio (The abo%e is for
*+,)!
7/23/2019 BE Distribution 3rd slide
11/24
Location of transformer
-s far as possible the Distribution transformer must be
located at the center of gra%ity the Load center In rural areas some times a single transformer is used to
ser%e ./* or more small %illages located in proximity
In such case follo$ing theoretical approach may be used to
locate approximate transformer location
Ta'e a reference point on the x/ y coordinate/ The location
0/ 1 is then find using/
7/23/2019 BE Distribution 3rd slide
12/24
In the selection of LT line routethe follo$ing criteriashould be ta'en into consideration2
3 The routing of the lines (radial length! has been made asshort as possible so as to minimize the %oltage drop andline loss
3 The LT lines are mostly routed along the feasible roads/foot trail4hilly road so that
The transportation of lines4construction materials to site is easier
This also facilitates the maintenance of lines
3 The line routing is done in such a $ay that maximum
number of households could be co%ered3 -%oids placing poles in flooded or land 3 sliding areas
3 5inimizes deforestation as much as possible
3 5inimizes $idth of ri%er crossings
7/23/2019 BE Distribution 3rd slide
13/24
,rimary >istriution 5eeder >esign
? @onfiguration
The primary distriution system design
in-ludes the routing and -ondu-tor sele-tion to
ser%e the distriution transformers from
Sustation. The optimization pro-edure usually used for
-ondu-tor and routing sele-tion is one of the
follo&ing:
7 minimizing the length of -ondu-tor
7 minimizing the -ost
7 minimum po&er transfer and distan-e approa-h.
7/23/2019 BE Distribution 3rd slide
14/24
$etAs -onsider fi%e different distriution transformers of same size and same
numer of -ustomers are desired to e -onne-ted from the sustation
through a radial distriution feeder of similar -ondu-tor. ;ut of pra-ti-ally
feasile feeder layout options t&o are sho&n in 5ig.(a) ? ().
S4S-
6
D
7(a! 8ption9-
. 'm
. 'm
. 'm
. 'm
. 'm
S4S-
6
D
7(b! 8ption9
. 'm
. 'm . 'm
. 'm
. 'm
*ote that:7 The load to e ser%ed in oth the -ases same
7 @ondu-tor length same
6ut it -an e sho&n that the losses in option 7# is aout /. times
greater than optionB6
7/23/2019 BE Distribution 3rd slide
15/24
Suppose the transformer size at ea-h of the node is S !"#.
Then the po&er flo& through the ran-hes -an e easily
-omputed and is sho&n in 5ig. elo&.
S4S -
6
D
7(a! 8ption9-
. 'm
. 'm
. 'm
. 'm
. 'm
:S
;S
*S
.S
S
S4S -
6
D
7
(b! 8ption9
. 'm
. 'm . 'm
. 'm
. 'm
:S *S
SS
S
7/23/2019 BE Distribution 3rd slide
16/24
9t is to e noted that this differen-e in losses are only due
to the fa-t that the ran-h po&er for the same load are
signifi-antly different in t&o options.
#lternati%ely it -an e said that the node po&ers ha%e to
tra%el larger distan-e in optionB# than optionB6.
Summarized in Tale elo&:
7/23/2019 BE Distribution 3rd slide
17/24
9t -an e sho&n that the -ondition for &hi-h po&er loss is
minimum "oltage >rop is also minimum.
#lso for the same -ase 'eliaility is also ma=imum Ta!e an e=ample &ith /00 -onsumers at ea-h node
7 5ailure rate 0.04
Node Tra%elingdistance
#robabilityoffailure4yr
#robable No ofconsumer notgetting supply4yr
- 2 0.0
4 0./1 /1
6 1 0.24 24
D 4 0./1 /1
7 1 0.24 24
7/23/2019 BE Distribution 3rd slide
18/24
7/23/2019 BE Distribution 3rd slide
19/24
'ea-ti%e ,o&er 5lo&:
7/23/2019 BE Distribution 3rd slide
20/24
&,, ')-,+ pf lag
&,, ')-,+ pf lag
&,, ')-,+ pf lag
&,,, ')-
**4&&')
SS -
6
&
7/23/2019 BE Distribution 3rd slide
21/24
A!A S"#STAT$%& S!L!'T$%&
Ser%i-e area
9nput
7/23/2019 BE Distribution 3rd slide
22/24
Sustation sitting
-%ailability of land for the %arious necessary e>uipment of there>uired capacity and re>uired number of distribution feeders forthe identified ser%ice area of the substation
The cost of land
8pportunity for ?eeder geta$ay
The cost of preparing the site (slope/ drainage/ underlying soil androc'!
The cost of transporting material
7sthetic re>uirements (fencing/ landscaping!
-%ailable options for expanding the substation capacities/ additionof distribution feeder and extension of sub transmission line for thene$ substation that may come in future
"ight of $ay for transportation of substation e>uipments
7/23/2019 BE Distribution 3rd slide
23/24
Ser%i-e #rea identifi-ation ? Sizing
The expected substation ser%ice area has to be fixed asserting the
follo$ing@
The area $here the reach of the distribution feeder is acceptableThis is to assure that the entire load $ithin the ser%ice area isade>uately ser%ed (%oltage/ reliability!
No e>uipment is o%er loaded considering the constraint in the plansuch as limitations on the size of transformers/ circuit brea'ers etc
Distribution feeder costs and its losses are $ithin the acceptablelimit considering the social/ geographical/ political and othersimilar scenarios
7xisting substations are utilized $here%er possible That is theareas that can be ser%ed by this proposed substation but at highercost or loss in comparison to the existing surrounding substation(s!ha%e to be discarded
7/23/2019 BE Distribution 3rd slide
24/24
Sele-tion of su transmission line route
#ossibly a%oiding any crossing of proposed sub transmission lineroute $ith another high (**') and abo%e! or 5edium (')!%oltage line this increase the cost due to high to$er
5inimizing the length of line
"eliability of the system $ithin the acceptable limit
5aintaining the %oltage profile and line loss (as from thepreliminary assessment! in the proposed and effected existing subtransmission line $ithin the standard limit
8%erall in%estment and running cost to be minimum
Nearest possible motor able road or ma=or trac's
-%oiding of proposed alignment crossing through the rural4urbansettlements
-%oiding of deforesting and long ri%er crossing
5inimizing the Land ac>uisition problem