Upload
trinhkhanh
View
221
Download
0
Embed Size (px)
Citation preview
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: For Proposal DATE: August, 2013
BC-4341 rev 2011 09 14 B - 1
SPECIFICATION FOR
FGD SYSTEM - STRUCTURAL STEEL FABRICATION FOR RUTENBERG POWER STATION - UNITS 1 AND 2
1. PURCHASER: The Israel Electric Corporation Limited. 2. NAME OF PROJECT: Emissions Control in existing coal fired Power Stations. 3. LOCATION OF PROJECT: Rutenberg Power Station, Near Ashkelon on the Mediterranean Sea Shore. 4. SCOPE OF WORK: The scope of work includes engineering, fabrication and supply of steel structure
and on-site supervision services for various steel structures (pump houses, pipe bridges, sheds) required as an integral part of the emission control project (installation of FGD Systems) in Rutenberg Power Station.
The scope of work shall include, but shall not be limited to the following: 4.1 Scope of Engineering and Supply: Contractor’s scope of engineering and supply shall include preparation of
complete structural shop and erection drawings (detail design based on Purchaser’s conceptual design), fabrication of structural steel and cladding in categories, and delivery of structural steel and cladding for Rutenberg Power Station, Units 1 and 2, as follows:
4.1.1 Basic scope of Engineering and supply, subdivided as follows:
a. FGD circulating Pump House b. Pipe Bridge no. 17 - PB-17 c. Pipe Bridge no. 19 - PB-19 d. Pipe Bridge no. 20 - PB-20 e. Pipe Bridge no. 55 - PB-55 [Hold]
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 2
The estimated Structural Steel weights for all above structures are given in the breakdown in Annexure “C1”, which is subject to additions/deletions per Purchaser’s final conceptual design.
4.1.2 The Categories of Steel and works forming part of the scope of work:
(Hebrew translation) a. Light Shapes and Plates ( ים קל ופלטותיםפרופיל ) b. Medium Shapes and Plates )ים בינוני ופלטותיםפרופיל( c. Heavy Shapes and Plates ( ים כבד ופלטות יםפרופיל( d. Trusses מסבכים( ) e. Girders Welded Sections and plates ( ( ופלטותקורות פחיםf. Base Plates פלטות בסיס( ) g. Grating ( סבכות( h. Handrails (מעקות) i. Stair treads (מדרגות) j. Bolts, Nuts and Washers (ברגים אומים ודסקיות) k. Reserved l. Reserved m. Painting and Delivery צביעה ואספקה( ) n. Galvanizing, Painting and Delivery צביעה ואספקה, גילוון( )
4.1.3 The Scope of Work includes: 4.1.3.1 Preparation of complete structural steel Shop and Erection Drawings, and
submittal of all documentation as specified in Article 8 below. 4.1.3.2 Preparation of Material Source lists based on the design drawings. 4.1.3.3 Fabrication of the structural steel members in accordance with the last edition of
the AISC manual and AWS-D.1.1 – last edition welding Specification and/or IEC welding procedure 17/745/03/01-08 (supplement 5.1.13 to the Specification).
4.1.4 The structural steel shall meet the following essential requirements: 4.1.4.1 The Structural Steel including protective coatings shall meet Purchaser’s
conceptual design and shall be designed, fabricated and supplied to form a COMPLETE, RELIABLE AND SAFE CONSTRUCTION.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 3
4.1.4.2 High Strength Bolts, Nuts and Washers shall be ASTM A325 Type 1, shall be hot dip galvanized and shall be supplied by the Contractor in accordance with Contractor’s Bills of Materials (specifying lengths, quantities and locations) with at least 5% spare.
4.1.4.3 All Structural Steel Members shall be corrosion protected as per 11.5 below. 4.2 Special Equipment, Tools and Instruments Contractor shall provide all special equipment, tools and instruments required for
safe and secure transport of all components from ex works to final destination. Said equipment, tools, and instruments should be / are listed in Contractor's Proposal where it should be / is clearly stated which are provided on a loan basis and which are included in the Contract Price/Option list.
4.3 Contractor Services The Contractor shall provide the services of competent advisors to direct
Purchaser's personnel and assure proper, complete and successful erection and installation of the Steel Structure provided under this Specification.
The services shall be provided as part of the basic Scope of Work or as
Purchaser’s option, at the per diem or lump sum rates, all as stated in the Summary of Prices and Delivery Schedule, Annexure “C1”. Field personnel provided by the Contractor shall be capable and qualified to perform the required duties to the satisfaction of the Purchaser. They shall be vested with authority to make decisions that could affect the status of the Steel Structure and which are binding on the Contractor.
4.4 Work by Others (Facilities and Services to be provided by the Purchaser) 4.4.1 Purchaser shall provide and be responsible for the conceptual design of the Steel
Structure.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 4
Note: In the event that the Contractor is exceptionally requested to provide conceptual design, such conceptual design shall be prepared under the auspices of a structural engineer registered in Israel, and shall be certified by him.
4.4.2 Purchaser shall provide all the necessary labor force, tools and facilities in order
to erect and install the Steel Structure provided under this Specification, following Contractor’s instructions and according to Contractor’s plans, procedures and (if applicable) supervision.
4.5 Terminal Points and Terminal Connections Contractor shall terminate the Steel Structure provided under this Specification at
the Terminal Points depicted in Purchaser’s conceptual design with the appropriate terminal connections [Contractor shall include in the proposal a definition for all terminal points and terminal connections not specified by Purchaser].
5. SUPPLEMENTS: The following supplements are attached hereto and their requirements form an
integral part of this specification - to the extent they are consistent and conform with the requirements specifically set forth herein. In the event of a variance between the requirements of the Supplements and the particular requirements set forth in the Specification, the requirements specifically set forth in the Specification shall take precedence. In the event of inconsistent requirements set forth in the various Supplements, the Contractor shall consult with the Purchaser to verify which requirement takes precedence.
5.1 Purchaser's general documentation, quality assurance and quality control
requirements: 5.1.1 I.E.C. Painting Specification 217-000093-2011: Specification for inorganic Zinc-Silicate painting on non-galvanized surfaces. 5.1.2 I.E.C. Spec/Procedure CL-716/1600/99 Issue 5:
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 5
Specification for painting on galvanized surfaces by wet/electrostatic powder painting.
5.1.3 Standard Q-APP-02-PR R 03: Appendices for Contracts / Orders Quality Requirements 5.1.4 Form 1700: Standard Specification for Fabrication of
Structural Steel, (Structural – I.E.C). 5.1.5 Form 1703: Standard Requirements for Structural Steel
Shop Drawings and Instruction Books, (Structural – I.E.C).
5.1.6 Form 1708: Standard List of Definitions and Reference
Publications, (Structural – I.E.C). 5.1.7 Form 1737: Standard Specification for Anchor Bolts,
(Structural – I.E.C). 5.1.8 Structural Design Standards: 5.1.8.1 SDS-D27.1 Structural design standard for metal floor area and platform design. 5.1.8.2 SDS-D27.2 Structural design standard for fixed industrial stair system details. 5.1.8.3 SDS-D27.3 Structural design standard for fixed metal ladder details. 5.1.8.4 SDS-D27.4 Structural design standard for platform framing connection detail. 5.1.9 SDS-E7.: Standard for Beam, Column and Bracing
Connections for Structural Steel, (Structural – I.E.C)
5.1.10 SDS-D4.1: Standard for Girt Details (Structural I.E.C) 5.1.11 SDS-D7.1 Frames beam connection details.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 6
5.1.12 SDS-D41.0 Welding presentation. 5.1.13 17/145/03/01-08 I.E.C Welding Procedure 5.1.14 I.E.C Steel Structure Design Dwg. ZAO/C7-121-0001: Minimum Connections capacity. 5.2 Purchaser's conceptual design drawings: 5.2.1 Reserved. 5.2.2 FGD circulating Pump House: 5.2.2.1 ZAO/25-C12-3IA200-00 rev. 00 5.2.2.2 ZAO/25-C12-3IA217-00 rev. 00 5.2.2.3 ZAO/25-C12-3IA217-01 rev. 00 5.2.2.4 ZAO/25-C12-3IA217-00 rev. 00 5.2.2.5 ZAO/25-C12-3IA218-00 rev. 00 5.2.2.6 ZAO/25-C12-3IA219-00 rev. 00 5.2.2.7 ZAO/25-C12-3IA220-00 rev. 00 5.2.2.8 ZAO/25-C12-3IA221-00 rev. 00 5.2.2.9 ZAO/25-C12-3IA222-00 rev. 01 5.2.2.10 ZAO/25-C12-3IA222-01 rev. 01 5.2.2.11 ZAO/25-C12-3IA223-00 rev. 00 5.2.2.12 ZAO/25-C12-3IA224-00 rev. 00 5.2.3 Reserved. 5.2.4 Reserved. 5.2.5 Pipe Bridge no. 17 - PB-17: 5.2.5.1 ZAO/25-C12-3IA240-00 5.2.5.2 ZAO/25-C12-3IA240-01 5.2.5.3 ZAO/25-C12-3IA241-00 5.2.5.4 ZAO/25-C12-3IA242-00 5.2.5.5 ZAO/25-C12-3IA243-00 5.2.5.6 ZAO/25-C12-3IA243-01 5.2.5.7 ZAO/25-C12-3IA243-02
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 7
5.2.5.8 ZAO/25-C12-3IA244-00 5.2.5.9 ZAO/25-C12-3IA245-00 5.2.5.10 ZAO/25-C12-3IA246-00 5.2.5.11 ZAO/25-C12-3IA247-00 5.2.5.12 ZAO/25-C12-3IA248-00 5.2.5.13 ZAO/25-C12-3IA249-00 5.2.5.14 ZAO/25-C12-3IA250-00 5.2.5.15 ZAO/25-C12-3IA251-00 5.2.6 Pipe Bridge no. 20 - PB-20: 5.2.6.1 ZAO/25-C12-3IA260-00 5.2.6.2 ZAO/25-C12-3IA260-01 5.2.6.3 ZAO/25-C12-3IA261-00 5.2.6.4 ZAO/25-C12-3IA262-00 5.2.7 Front of Station: Pipe Bridge no. 55 - PB-55: 5.2.7.1 ZAO/08-C11-3IR350-00 5.2.7.2 ZAO/08-C11-3IR351-00 5.2.7.3 ZAO/08-C11-3IR351-01 5.2.7.4 ZAO/08-C11-3IR351-02 5.2.7.5 ZAO/08-C11-3IR352-00 5.2.7.6 ZAO/08-C11-3IR353-00 5.2.7.7 ZAO/08-C11-3IR354-00 5.2.7.8 ZAO/08-C11-3IR355-00 5.2.7.9 ZAO/08-C11-3IR356-00 5.2.7.10 ZAO/08-C11-3IR357-00 5.2.7.11 ZAO/08-C11-3IR358-00 5.2.7.12 ZAO/08-C11-3IR359-00 5.2.7.13 ZAO/08-C11-3IR360-00 5.2.7.14 ZAO/08-C11-3IR360-01 5.2.7.15 ZAO/08-C11-3IR361-00 5.3 Purchaser's additional requirements: 5.3.1 Source List of Raw Materials (Based on the Design Drawings) The source list is for information only “Material Report of Steel”. 5.3.2 Reserved.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 8
5.3.3 Appendix SASPI rev. 0: Requirements for operation of Steel All Structure Process in IEC (“SASPI”).
5.3.4 Standard Specification for Data Transmittal. 6. STANDARDS AND CODES 6.1 Standards and Codes referenced in this Specification and in the Supplements to
this Specification, form an integral part of this Specification - to the extent their requirements are consistent and conform with the requirements specifically set forth herein. All such Standards and Codes are to the issue, including all amendments, supplements, etc., current as of the date of the Contract, unless indicated otherwise. In the event of a variance between the requirements of the Standards and Codes and the particular requirements set forth in the Specification and the supplements, the the Contractor shall consult with the Purchaser to verify which requirement takes precedence.
6.2 The Steel Structure to be provided under this Specification, including all
appurtenances and accessories, shall be designed, fabricated, inspected, tested, stamped and preserved to the extent indicated in said referenced Standards and Codes. Where this Specification does not include such reference, The Steel Structure, or any of its components, shall be designed, fabricated, inspected, tested and preserved, as applicable, to comply with currently recognized International and/or Contractor's Standards, whichever are tighter and more restrictive.
6.3 The Contractor may propose Standards and Codes as alternates to those
specified herein. A copy of each proposed Standard and code, if any, shall be submitted (in English) for Purchaser's approval. In case Purchaser's approval is granted, the Contractor shall remain responsible for the compatibility of the design and the physical interfaces between the supplied Steel Structure and the equipment supplied by others.
6.4 The Purchaser shall assist Contractor in identification of Israeli codes and
standards applicable to the Work. In all cases Contractor shall adhere to and comply with the requirements of Israeli official standards found to be more restrictive than those specified herein.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 9
6.5 Subject to the provisions stated above, the steel structure shall be designed,
manufactured, erected, tested operated and maintained in accordance with the standards, regulations, directives and publications of the following agencies and organizations:
6.5.1 AISC: Steel Construction Manual, latest Edition, complete. This reference shall
be understood to include the specifications and codes which form a part of the Manual, including, but not limited to:
6.5.2 AISC Specification for Structural Steel for Buildings. 6.5.3 AISC Code of Standard Practice, for steel building and bridges latest edition. 6.5.4 Specification for Structural Joints using ASTM A325 or A490 Bolts (2004). 6.5.5 Israeli Standard 918: Hot Dip Zinc Coating on Steel and Cast Iron Products (In Hebrew). 7. QUALITY ASSURANCE AND QUALITY CONTROL 7.1 Without derogating from the provisions of the General Conditions, Contractor's
quality system shall meet the requirements of Purchaser's Standard Q - APP - 02-PR R 03 "Appendices for Contracts / Orders - Quality Requirements", and of the requirements of the Inspection and Test Plan, all as further detailed in Annexure "M" to the Contract. The contractor shall especially implement design control procedure and demonstrate its effectiveness to the purchaser.
7.2 The Contractor and the main subcontractors shall be certified to ISO-9001-2008
by a certification body qualified to EN-45004 levels A or C or otherwise as may be acceptable to the Purchaser.
7.3 The Contractor shall submit upon request a copy of its Quality Assurance
Manual including Quality Procedures.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 10
7.4 The choice of main subcontractors shall be subject to Purchaser's approval and the Contractor shall be responsible for assuring that their quality assurance/quality control programs, including their organizations, procedures, personnel qualifications, etc., meet Purchaser’s quality requirements.
8. TECHNICAL DOCUMENTATION 8.1 The Contractor shall submit technical documentation in accordance with the
provisions of Annexure "J" – Documentation Submission Schedule. 8.2 The procedure of handling technical documentation shall be as follows: 8.2.1 The Purchaser shall submit to the Contractor the conceptual design drawings in
a standard file format (AUTOCAD), and in hard copies (two sets). 8.2.2 Contractor’s erection drawings, shop drawings and assembly (mark) stamps
shall be numbered in accordance with the requirements set forth in Appendix SASPI.
8.2.3 The Contractor shall submit one hard copy of each shop drawing and erection
drawing to the address specified in Annexure "J” to initiate the review process. 8.2.4 The Contractor shall in parallel submit each shop drawing and erection drawing
as an electronic file in accordance with the requirements set forth in Appendix SASPI to the address specified in Annexure "J”.
8.2.5 The Purchaser shall submit its comments/approval and the Contractor shall
accordingly submit revisions to its drawings as detailed in Appendix SASPI. 8.2.6 Contractor will not start steel fabrication before the receipt of Purchaser's
approval on the shop drawings relevant for the steel to be fabricated. Purchaser's approval, however, will not relieve Contractor from fulfilling its obligations under the Contract, including direct responsibility for any errors in Bills of Raw Materials.
8.2.7 Purchaser shall not unreasonably delay approval or comments of the
Documentation. Incomplete drawings and/or drawings not accompanied by adequate detail design calculation will not be approved by Purchaser. In such
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 11
case the delay in approval shall not release the Contractor from fulfilling the Contractual Delivery Dates, and any additional charges which may occur from such a delay, shall be borne by the Contractor.
9. SHIPMENT AND HANDLING OF GOODS AND DOCUMENTATION The Contractor shall comply with the requirements for Shipment and Handling of
Equipment set forth in Annexure "R" to the Contract and additionally with the following supplementary requirements:
9.1 All components or accessories shipped detached for field mounting or field
assembly, including those items to be galvanized, shall be suitably marked by "hard stamp" so that such marking will be clearly visible after galvanizing and/or painting.
Additionally, material from one elevation shall not be crated or banded with
material from another elevation. 9.2 Unless specially designated, all Steel Structure and other items shall be
packaged for outdoor storage until erection. Where required by the nature of the Steel Structure, the Contractor shall furnish and install necessary covers to protect the Steel Structure from sand, rain, hail, wind, dust and salt spray. Steel Structure shall be adequately sealed and protected during shipment to prevent corrosion and entrance of foreign matter. All exposed machined surfaces shall be protected where required with a suitable antirust compound or covers before shipment, for shipment and storage until erection.
9.3 Upon release of erection drawing for production, the Contractor shall submit
electronically to the Purchaser the updated StruCad model as detailed in Appendix SASPI, and the Purchaser shall produce the respective Bill of Fabricated Materials (hereinafter BOFM) to enable checking and identifying of said Fabricated Materials upon receipt on Site.
9.4 Contractor shall in parallel produce said respective BOFM and submit it to the
Purchaser to enable comparison with Purchaser’s data. Upon shipment, the Contractor shall attach one set of hard copy and computer disk of the BOFM to the respective assemblies.
9.5 The Bills of Fabricated Materials shall include at least the following information:
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 12
9.5.1 Item number, consistent with Contractor's Bill of Fabricated Materials (BOFM). 9.5.2 Number of items. 9.5.3 Contractor's shop order number (if any). 9.5.4 Manufacturer and/or Supplier, if other than Contractors. 9.5.5 Shop Drawing and Erection Drawing number. 9.5.6 Theoretical weight based on approved Shop Drawing. 9.5.7 Indication of the applicable I&T plan chapters, the fabricated materials were
inspected in accordance thereto. 9.5.8 Shipping details. 9.6 After completion of Work, the Contractor shall submit to the Purchaser, for
reference and verification, all the updated Bills of Materials showing actual weights of steel delivered to Site.
10. RESERVED 11. TECHNICAL REQUIREMENTS 11.1 General Definitions: 11.1.1 Structural Steel Categories: 11.1.1.1 Light Shapes and Plates: Sections weighing up to 58 kg/m / Plates weighing up
to/ 80 Kg/sq.m. 11.1.1.2 Medium Shapes and Plates: Sections weighing between 59 to 150 kg/m / Plates
weighing between 80.1 to 200 Kg/sq.m.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 13
11.1.1.3 Heavy Shapes and Plates: Sections weighing over 150 kg/m / Plates weighing over 200.1 Kg/Sq.m.
11.1.1.4 Trusses. 11.1.1.5 Girders. 11.1.1.6 Base Plates: Plates having thickness from 1 to 8 inches. 11.1.1.7 Grating. 11.1.1.8 Hand Rail. 11.1.1.9 Stair Treads. 11.1.1.10 Bolts, Nuts and Washers. 11.1.1.11 Reserved. 11.1.1.12 Reserved. 11.1.2 Weights: 11.1.2.1 Structural Steel Estimated Tonnage shall be calculated using the conversion
factor of 1 Kg = 2.20462 Pounds. 11.1.2.2 Theoretical Weight: Weight of shapes, sheets, rods, etc. in Metric Tons, shall be in accordance with
the Code of Standard Practice for Steel Buildings and Bridges, latest edition. 11.1.2.3 Actual Weight of Steel The actual weight of Raw Material Steel should be the weight calculated for the
profile which appears on the Shipping Documents. The Weight of the fabricated Structural Steel for invoicing should be the
Theoretical Weight which appears on the Contractor's Shop Drawings duly approved by the Purchaser.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 14
11.2 Detail Design of the Steel Structure (Model, Erection Drawings, Shop Drawings,
Connections Calculations and Bills of Materials): 11.2.1 Engineering shall commence immediately after receiving final conceptual design
drawings, in conformance, as applicable, with Purchaser’s requested priorities, regardless of shipping schedule.
11.2.2 The design of the model, the erection and shop drawings, and the calculations of
all the connections shall be performed by civil engineers having proven experience in design of steel structures for industrial facilities, approved by the Purchaser.
11.2.3 Contractor shall coordinate the notation method with Purchaser, before start of
Drawings preparation. 11.2.4 Minimum connection will be used whenever reaction is not shown on Purchaser’s
conceptual design drawings. Whenever reaction has been marked on said drawings and the minimum connection capacity is exceeded, the shop drawing designer must develop a special heavier connection.
11.2.5 Shop drawing shall be made for all manufactured materials and shall include all
necessary details for manufacturing including detail drawings, tolerances, welding symbols and the specific Welding Procedure Specification (WPS) or weld map, etc.
11.2.6 Each Shop Drawing shall include the theoretical weight of the fabricated
Structural Steel. The calculation of this weight shall conform to “AISC Code of Standard Practice for Steel Buildings and Bridges”, latest edition.
11.2.7 Erection Drawings shall contain all the necessary details so as to permit
Purchaser to organize erection in an orderly and continuous manner. Erection Drawings shall also include details as to how parts are to be assembled
(Welded or Bolted), which torques are required for the high tensile bolt tightening and inspection on Site.
11.2.8 Changes in Design by the Purchaser.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 15
11.2.8.1 Without derogating from the provisions of the general Conditions, Annexure “A”, the Contractor shall be entitled to a Change Order for extra engineering work necessary to revise detail design and/or shop drawings for fabrication, when changes are necessary due to Purchaser's updated requirements.
11.2.8.2 To substantiate such Change Order the Contractor shall submit for Purchaser’s
approval a list showing weight, location and reference to shops drawing of members that are influenced by Purchaser's new requirements.
11.3 Raw Materials. 11.3.1 All the raw materials shall be ordered according to EN-10025:2004-S235JR or
S275JR or S355J2 or ASTM-A36 or ASTM-A572 Gr.50 or ASTM-A992 (W shapes) killed fine grained. All materials shall be certified to EN 10204-3.1.
All steel shall be furnished in the normalized condition. In order to assure galvanizing quality, the Silicon content of all steels intended for
galvanizing shall either be less than 0.05% or in the range between 0.15% to 0.3%.
11.4 Fabrication. The fabrication of the structural steel members shall be in accordance with the
latest edition of the AISC manual and AWS - D1.1 - Welding Specification. All Pre Welding Heat Treatment (PWHT) shall be performed by the Contractor. 11.4.1 Welding 11.4.1.1 The approved Welding processes to be applied in production are:
a. Submerged Arc Welding (SAW). b. Shielded Metal Arc Welding (SMAW). c. Flux Cored Arc Welding (FCAW).
and all welding consumables shall be of the Low Hydrogen type and shall be
subject to the approval of Purchaser’s Materials Laboratory.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 16
Any other welding process/consumable, if proposed by the Contractor, is subject
to written approval of Purchaser’s Materials Laboratory as a precondition for its application.
11.4.1.2 All Welding procedures, Welding Operators and Welders must be qualified In
accordance with - AWS D1.1. - latest edition, Structural Welding Code – Steel or IEC Welding Procedure 17/145/03/01-08.
Detailed Welding procedures shall be presented to and approved by Purchaser’s
Materials Laboratory prior to initiation of work. No prequalified WPS will be accepted for Automatic or Semiautomatic welding
processes. If requested by Purchaser, Purchaser’s representative(s) shall witness all
qualifications, prior to initiation of work. Purchaser's approval is conditioned upon verification by Purchaser’s Materials
Laboratory that the Welding Consumables conform to AWS Standards, and that the Quality Control procedures implemented during their manufacturing are adequate.
11.4.1.3 At least one month prior to initiation of Fabrication, the Contractor shall prepare
for Purchaser's review a list containing the names of its Welding personnel and the type of welding each individual shall perform. Each Welder will be examined according to the procedures of the Israel Electric Corporation, and approved for that type of welding.
The use by the Contractor of unapproved Welders, or Welders performing Welds
for which they have not been approved is strictly prohibited. Unauthorized Welders and Welds as described above shall not be accepted. Furthermore, such welds shall be removed and welded again according to requirements, at no exrtra cost to Purchaser.
11.4.1.4 All Pre Welding Heat Treatment (PWHT) and all the Non Destructive Tests (NDT)
are included in Contractor’s scope of Work and the the respective PWHT/NDT Subcontractor(s) shall be subject to Purchaser’s approval.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 17
Examination/inspection of structural steel welds shall be performed in accordance with the applicable section of AWS D1.1 – latest edition.
The structural steel welds shall be examined by NDT according to the following
methods:
a. Visual Inspection (VT). Visual Inspection (VT) for cracks and other discontinuities shall be
aided by a magnifying lens of 5X-10X power to discern indications or defects. Size and contour of welds shall be measured with suitable gauges.
b. Magnetic Particle Inspection (MT). Magnetic Particle Inspection (MT) of welds shall be performed in
accordance with the requirements of ASTM E 709.
c. Radiographic Inspection (RT). Radiographic Inspection (RT) of welds shall be performed in
accordance with the requirements of PART B, “Radiographic Testing of Groove Welds in Butt Joints”, of AWS D1.1 – last edition.
d. Ultrasonic Inspection (UT) Ultrasonic Inspection (UT) of welds shall be performed in accordance
with the requirements of PART C, “Ultrasonic Testing of Groove Welds,” of AWS D1.1 – last edition.
11.4.1.5 Levels of Examination: The levels of examination of specific welds shall comply with the requirements
set forth below or as specifically stated in the conceptual design drawings.
a. Butt Welds: The scope of examination shall be 100% visual (VT). Radiographic (RT) inspection shall be as per the applicable AWS D1.1
– last edition requirements. Where RT is required but is not practical, MT and UT of the root pass and the final surface of each weld joint shall be performed.
Each radiograph shall have the following additional information permanently included in the image:
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 18
- Weld No. (including repair cycle no.) - Drawing number. - Contract number.
b. Fillet welds: Fillet welds shall be examined by 100% visual (VT) and, if so required
by the AWS D1.1 – last edition code, by MT and/or UT inspection of the final surface of each weld joint.
c. Flanges under tensile stresses of butt-welded beams, and flanges of
extended H profiles: The scope of examination shall be 100% Radiographic Test (RT):
11.4.1.6 Acceptance Requirements: The acceptance criteria shall be as per the applicable standards. The Contractor shall provide all records of Non-Destructive Examination,
including radiographic film, to the Purchaser for approval no later than two (2) days after the examination.
The final interpretation and acceptance of all radiographs of welded joints shall
be subject to Purchaser’s approval. 11.4.2 General Requirements for Fabrication of Steel Intended for Galvanizing: 11.4.2.1 All holes in Structural Steel shall be drilled. 11.4.2.2 All threaded holes shall be protected while galvanizing by means which shall be
approved by Purchaser. 11.4.2.3 Cutting of Structural Steel shall be by flame, plasma, cutting machines or saw. Shearing of Structural Steel shall be in accordance with the requirements of
ASTM A143/A143M latest edition. 11.4.2.4 All Welded Joints shall be cleaned free of slag prior to welding.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 19
11.4.2.5 Structural members, having overlapping surfaces that are to be Hot Dip Galvanized, shall be seal welded on all contacting edges so as to prevent acid infiltration during cleaning prior to galvanization.
Note: Seal Welding shall be indicated in the drawings. 11.4.2.6 Steel structure members shall be stamped in accordance with the requirements
set forth in Appendix SASPI (numbers and direction marks). The letter size of the numbers and direction marks shall be 20mm at least and they shall be stamped deep enough to be clearly visible after galvanizing and painting.
11.4.2.7 Welder's identification: each welder should have a special identification tag. This
tag should be non perishable. For traceability purposes every welder should sign (by imprinting) his welding work with his identification tag.
11.4.3 Tolerance in Fabrication All tolerances in fabrication, dimensions, layouts etc. shall be in accordance with
the AISC 303-05 Code of Standard Practice for Steel Buildings and Bridges. 11.5 Corrosion Protection. 11.5.1 General requirements: 11.5.1.1 Structural steel shall be protected against corrosion by Duplex system
(galvanized and painted). 11.5.1.2 Surface areas of the structural steel which have been milled and for which the
milled surfaces are to be retained without coating, shall be protected during galvanization and/or painting so that they remain without a galvanized or paint layer. Varnish shall be brushed in mill area.
11.5.1.3 Connection Areas of slip critical joints shall meet the requirements of 3.2.2(c) of
Specification for Structural Joints using ASTM A325 or A490 Bolts (2004). Connection areas of painted structures shall be masked after priming before the
intermediate and top painting.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 20
11.5.1.4 In any case, fabricator shall remove the masking in the shop. If "No Paint Areas" become soiled or painted, Contractor will remove any foreign
matter at its own expense. 11.5.2 Painting Systems: 11.5.2.1 The colour of the top coat will be decided upon at a later stage, in accordance
with RAL color scale. 11.5.2.2 Hot-dip galvanized structures shall be painted according to I.E.C.
Spec/Procedure CL-716/1600/99 Issue 5 (Supplement 5.1.2 to the Specification). 11.5.2.3 Non-Galvanized structures shall be painted according to Specification 217-
000093-2011 (Supplement 5.1.1 to the Specification). 11.5.3 Scope of Galvanization: 11.5.3.1 All Structural Steel Members that can be inserted in a galvanization tube shall be
hot-dip galvanized according to Israeli Standard 918, latest edition (or equivalent standard, as approved by the Purchaser)
11.5.3.2 The corrosion protection of all Structural Steel Members that cannot be inserted
in a galvanization tube shall be subject to Purchaser’s approval. 11.5.4 Detailed Galvanization requirements. 11.5.4.1 The shop drawing designer shall design the elements to be galvanized, while
considering the peculiarities of the galvanized steel structure and ensuring that:
a. Holes to drain the excessive liquid zinc are provided. b. Fillet weld are continuous.
11.5.4.2 The general and detailed conditions for the preparation, galvanization and testing
of the galvanic coating shall be as specified in, and according to Israeli Standard 918, "Hot Dip Zinc Coatings on Steel and Cast Iron Products", latest edition, and to the following mandatory requirements:
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 21
11.5.4.2.1 All Galvanized Structural Members shall pass 100% visual examination of the coating quality. Items with defective coatings shall be repaired by Contractor according to a method approved by the Purchaser.
Non-acceptable defects are: bare spots, flux, rust, rust to welds, brittle areas.
Dripping and sharp edges are non-acceptable if they interfere with the intended use of the member.
11.5.4.2.2 Galvanized steel members shall be stored with adequate ventilation between
each member: Each member shall be separated from the other by small steel or galvanized steel spacers. Members shall be stored vertically if possible. If stored in the horizontal direction, the members shall be tilted at a small angle to the horizontal (recommended 5 degrees) so that water cannot accumulate on the surface.
11.5.4.2.3 Handling of galvanized steel shall be done with care to avoid mechanical damage
to coating. 11.5.4.2.4 Quality Control for Galvanizing The galvanizer will have a formal and documented quality system, which includes
quality control department. The quality system shall encompass at least the following items:
a. Calibrated equipment to measure zinc coating thickness. b. A procedure for identifying, tracing and recording all coated items
including a system for identifying and inspecting status of the galvanized items, either coated and tested singly or coated and tested as a batch.
c. Procedures or instructions for rejection and acceptance of coating
quality. d. Written limits on the composition of the cleaners, wash solution and
zinc bath and a system for their control and inspection. e. Written instructions and inspection forms for the acceptability of
cleaned surfaces.
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: ZC-4341 ISSUE: for Proposal
ZC-4341 rev 2013 08 22 B - 22
f. Written instructions and inspection forms for the acceptability of
visually inspected surfaces. g. Procedures and/or Instructions for in process control of the whole
galvanizing process. h. Written instructions and inspection forms for the acceptability of
coatings which have undergone thickness tests. i. Temperature control of the bath and calibration of the control
instruments. j. Inspection criteria for the suitability of welded assemblies and sub-
assemblies for galvanizing, and instructions for the clients. 11.5.4.2.5 Specification for Repair of Defects in Galvanized Coatings All galvanized parts shall be inspected after cooling to ambient temperature.
Rejected parts shall be cleaned and re-coated as follows:
a. Drippings, sharp edges, excess zinc droplets, etc., shall be removed by means of grinders or any other suitable tool, when their presence interferes with the intended use of the component.
b. Spots of flux, dirt, soot or other impurities shall be cleaned by wire
brushing. c. The weld areas of Zinc coated parts which are subsequently welded
shall be cleaned by wire brushing. d. Scratches and similar linear imperfections shall be cleaned by wire
brushing. e. Uncoated surfaces are unacceptable, and shall not be repaired.
Contractor shall re-coat such surfaces at no extra cost to Purchaser. - F I N A L -